Review Coordinator Shelley Bellm ( sbellm@vailgov.com )
Review Cycle 3
Workflow/Activity Name Begin_Workflow / ApplicantResubmit
Activity InstructionsPlease review all sections of the eForm and drawing markups and resubmit the required
information prior to completion of task.
Current User Logon Mike Cuthbertson ( mcuthbertson@ranelson.com)
CHANGEMARKS Review Cycle:3
Filter Changemarks by Keyword: SEARCH SHOW ALL
Click Here to Load Changemarks...
Click Here to Publish Changemarks to PDF...
Sorting:
Resolved Status File Cycle Department File Markup Description Details Applicant Response
Yes | No No 3 Public
Works
C
110.pdf tkassmel PW001 Tress are not to be removed. These are not part of
the Town project
Yes | No No 3 Public
Works
C
120.pdf tkassmel PW001
Currently the Town is not planning on designing an
accessible walk in this area. Remove note #9 and
show replacement of existing walk as a part of this
project.
Yes | No No 3 Public
Works
C
130.pdf tkassmel PW001 See comment on Sheet C120
Yes | No No 3 Public
Works
C
140.pdf tkassmel PW001 These improvements are not approved to occur,
please remove them from the plans
Yes | No No 3 Public
Works
C
150.pdf tkassmel PW001
When will these be determined? I was told these
may have already been installed in a location not
yet approved, and using a TOV spare conduit not
approved for this use. Please confirm.
Yes | No No 3 Public
Works
C
160.pdf tkassmel PW001 These ramp improvement are not planned. Please
remove from plans.
Yes | No No 3 Public
Works
C
180.pdf tkassmel PW001 Please see comment on C120
Yes | No No 3 Public
Works
C
310.pdf tkassmel Pw001 Provide Executed lease agreement for extended soil
nails
Yes | No No 3 Public
Works L1.1.pdf tkassmel PW001 Revise landscape plan to reflect this note. Planting
cannot be planted on reconstructed walk.
Complete Save And Close
Building Process V1
Yes | No No 3 Public
Works L1.1.pdf tkassmel PW002
Show utilities on Landscape plan. Trees cannot be
planted in conflict with utilities and not planted on
top of Storm sewer, or within 5' of storm sewer, for
future maintenance.
submit fire alarm and fire sprinkler plans.
DEPARTMENT REVIEW Review Cycle:3
CYCLE DEPARTMENT REVIEWED BY STATUS & NOTES
3 BUILDING
FLORENCIO MONDRAGON
JMONDRAGON@VAILGOV.COM
CORRECTIONS REQUIRED
VIEW CHECKLIST
PLAN REVIEW AND/OR ASSIGNMENT COMPLETE
3 FIRE
MICHAEL MCGEE
MMCGEE@VAILGOV.COM
CORRECTIONS REQUIRED
PLAN REVIEW AND/OR ASSIGNMENT COMPLETE
3 PLANNING
JONATHAN SPENCE
JSPENCE@VAILGOV.COM
APPROVED
VIEW CHECKLIST
PLAN REVIEW AND/OR ASSIGNMENT COMPLETE
3 PUBLIC WORKS
TOM KASSMEL
TKASSMEL@VAILGOV.COM
CORRECTIONS REQUIRED
PLAN REVIEW AND/OR ASSIGNMENT COMPLETE
I have reviewed and addressed the Checklist Comments provided on the "Checklist" tab above. Please click on the tab and review each item. Each comment will be
indicated as "Met" or "Not Met". If you would like to export a list of the comments to Excel, click on the "Export to Excel" link in the upper right hand corner of the popup
window.
I have addressed all of the items listed in the Changemarks section above that were identified during the Plan Review.
I have uploaded the revised drawings into the "Drawings" folder and, if requested, uploaded any revised documents into the "Documents" folder using the SAME file name as
the original files. I am ready to complete my assigned task.
Task Instructions