HomeMy WebLinkAboutM1.0.pdfRADIANT FLOOR SUPPLY
RADIANT FLOOR RETURN
NOTE: ALL SYMBOLS SHOWN ON LEGEND
ARE NOT NECESSARILY USED.
CHILLED WATER RETURN
CHILLED WATER SUPPLY
HEATING WATER RETURN
HEATING WATER SUPPLY
MECHANICAL LEGEND
MEDIUM PRESSURE NATURAL GAS
SNOWMELT RETURN
SNOWMELT SUPPLY
GAS
HWS
T
A
B
HWR
CWS
CWR
SMS
SMR
RFS
RFR
G
MPG
PIPE RISER
PIPE DROP
PIPE TAKEOFF (FROM BOTTOM OF MAIN)
PIPE TAKEOFF (FROM TOP OF MAIN)
PIP END CAP
PIPE CONTINUATION
PIPE EXPANSION GUIDE
PIPE UNION
PIPE ANCHOR
FLEXIBLE PIPE CONNECTION
PIPE EXPANSION JOINT
POINT OF NEW CONNECTION
AIR VENT
PLUG VALVE
CHECK VALVE
BALL VALVE
BALANCING VALVE
BUTTERFLY VALVE
PRESSURE REDUCING VALVE
STRAINER
PRESSURE - TEMP. TAP
PRESSURE GAUGE
2-WAY CONTROL VALVE
3-WAY CONTROL VALVE
SUPPLY GRILLE
RETURN GRILLE
EXHAUST AIR
SUPPLY AIR
RETURN AIR
OUTDOOR AIR
SUPPLY AIR DAMPER
RETURN AIR DAMPER
SUPPLY DIFFUSER
OA
RA
SA
EA
RAD
SAD
SG
RG
SD
RETURN DIFFUSER
RD
TRANSFER GRILLE
TG
TRANSFER DIFFUSER
TD
THERMOSTAT
FIRE/SMOKE DAMPER
FIRE DAMPER
MOTOR OPERATED DAMPER (MOD)
MANUAL BALANCING DAMPER
7851,1*9$1(6,1(/%2:
??x??
DUCT SIZES ARE NET FREE AREA
1ST NO. IS DUCT WIDTH.
2ND NO. IS DUCT DEPTH.
SECTION THRU SUPPLY AIR DUCT
SECTION THRU RETURN/EXHAUST AIR DUCT
SUPPLY DUCT TURN DOWN
RETURN/EXHAUST DUCT TURN DOWN
CHANGE OF ELEVATION
FLEXIBLE DUCT CONNECTION
R/D
(D) DROP (R) RISE
SENSOR (CALL OUT ON DRAWINGS)
SUPPLY REGISTER/DIFFUSER/LOUVER
NECK SIZE
CFM-S
RETURN REGISTER/DIFFUSER/LOUVER
NECK SIZE
CFM-R
OUTSIDE AIR REGISTER/DIFFUSER/LOUVER
NECK SIZE
CFM-O.A.
EXHAUST REGISTER/DIFFUSER/LOUVER
NECK SIZE
CFM-E
U
DOOR UNDERCUT
CFM
(A) SECTION CUT LINE
(B) SHEET SHOWN ON
S
SECTION THRU ROUND DUCT
ROUND DUCT TURN DOWN
4-WAY CONTROL VALVE
FLOW REGULATOR VALVE
DIFFERENTIAL BYPASS VALVE
NATURAL GAS PRESSURE REGULATOR
THERMOMETER
MECHANICAL SPECIFICATIONS:
1. GENERAL:
a. FURNISH ALL LABOR, SUPERVISION, MATERIALS, EQUIPMENT AND FACILITIES NECESSARY TO FURNISH, FABRICATE, DELIVER,
STORE AND INSTALL ALL WORK NOTED ON THE DRAWINGS AND/OR SPECIFIED HEREIN.
b. THE CONTRACTOR SHALL FURNISH AND INSTALL ALL WORK NECESSARY TO MAKE A COMPLETE SYSTEM WHETHER OR NOT SUCH
DETAILS ARE MENTIONED IN THESE SPECIFICATIONS OR SHOWN ON THE PLANS, BUT WHICH ARE OBVIOUSLY NECESSARY TO
MAKE A COMPLETE SYSTEM, EXCEPTING ONLY THOSE PORTIONS THAT ARE SPECIFICALLY MENTIONED HEREIN OR PLAINLY
MARKED ON THE ACCOMPANYING DRAWINGS AS BEING INSTALLED UNDER ANOTHER SECTION OF THE SPECIFICATIONS.
2. WORKMANSHIP:
a. THE WORK SHALL BE ACCOMPLISHED IN A THOROUGH AND WORKMAN-LIKE MANNER SATISFACTORY TO AND MEETING THE
APPROVAL OF THE OWNER AND ARCHITECT.
3. MATERIALS:
a. ALL MATERIALS AND EQUIPMENT SHALL BE NEW AND THE BEST OF THEIR RESPECTIVE KIND, FREE FROM ALL DEFECTS AND OF
THE MAKE AND QUALITY SPECIFIED.
4. SITE INSPECTION:
a. CONTRACTOR SHALL VISIT THE SITE OF WORK PRIOR TO SUBMISSION OF HIS BID AND THOROUGHLY FAMILIARIZE HIMSELF WITH
THE WORKING CONDITIONS & EXACT NATURE OF THE WORK.
b. SUBMISSION OF A BID ACKNOWLEDGES FULL RESPONSIBILITY FOR FURNISHING A COMPLETE AND FUNCTIONAL SYSTEM.
c. NO CHANGES IN CONTRACT WILL BE MADE TO ACCOMMODATE OR ALLOW EXTRA FUNDS FOR ANY OMISSION WHICH RESULTS
FROM A FAILURE TO THOROUGHLY MAKE THE EXAMINATION.
5. CODES AND PERMITS:
a. ALL MECHANICAL EQUIPMENT, INSTALLATION, ETC., SHALL CONFORM TO THE 2012 INTERNATIONAL MECHANICAL CODE (IMC), 2012
INTERNATIONAL ENERGY CONSERVATION CODE (IECC) AND ORDINANCES AS INTERPRETED BY THE TOWN OF VAIL BUILDING
DEPARTMENT.
b. CONTRACTOR SHALL OBTAIN AND PAY FOR ALL PERMITS AND INSPECTIONS.
c. COPIES OF ALL PERMITS AND INSPECTION REPORTS SHALL BE SUBMITTED TO THE ARCHITECT.
6. AS-BUILTS:
a. CONTRACTOR SHALL PROVIDE A COMPLETE SET OF AS-BUILT DOCUMENTS WITH ALL CHANGES NOTED THEREON AT THE
COMPLETION OF THE PROJECT AND PRIOR TO FINAL ACCEPTANCE AND PAYMENT.
7. GUARANTEE:
a. CONTRACTOR SHALL UNCONDITIONALLY GUARANTEE ALL LABOR AND MATERIALS ON ALL WORK AGAINST DEFECTS IN
WORKMANSHIP AND MATERIALS FOR A PERIOD OF ONE YEAR AFTER COMPLETION.
8. SUBMITTALS:
a. CATALOG INFORMATION AND CUTS OF ALL EQUIPMENT AND DEVICES (WITH ALL OPTIONS CLEARLY MARKED) SHALL BE SUBMITTED
TO THE ARCHITECT FOR REVIEW (SIX COPIES OF EACH). ELECTRONIC SUBMITTALS PREFERRED.
9. COORDINATION:
a. THE DRAWINGS ARE DIAGRAMMATIC AND INTENDED TO SHOW SCOPE.
b. THE CONTRACTOR SHALL COORDINATE HIS WORK WITH OTHER TRADES TO PROVIDE BEST ARRANGEMENT OF ALL DUCTS, PIPES,
CONDUIT, ETC.
10. CUTTING AND PATCHING:
a. ALL CUTTING AND PATCHING REQUIRED OF THE STRUCTURE (NEW OR EXISTING) SHALL BE PROVIDED UNDER OTHER SECTIONS
OF THE WORK.
b. PROVIDE NECESSARY REQUIREMENTS TO THE PROJECT SUPERINTENDENT.
c. X-RAY SLABS PRIOR TO CORING.
11. CLEANUP:
a. UPON COMPLETION OF THE WORK UNDER THIS SECTION, THE CONTRACTOR SHALL REMOVE ALL SURPLUS MATERIALS,
EQUIPMENT AND DEBRIS INCIDENTAL TO THIS WORK AND LEAVE THE PREMISES CLEAN AND ORDERLY.
12. MECHANICAL IDENTIFICATION
a. EQUIPMENT NAMEPLATES: METAL, WITH DATA ENGRAVED OR STAMPED, FOR PERMANENT ATTACHMENT ON EQUIPMENT.
b. PIPE MARKERS: PREPRINTED, COLOR CODED, WITH LETTERING INDICATING SERVICE, AND SHOWING DIRECTION OF FLOW.
c. VALVE TAGS: STAMPED OR ENGRAVED WITH 1/4" LETTERS FOR PIPING SYSTEM ABBREVIATION AND 1/2" NUMBERS, WITH
NUMBERING SCHEME. PROVIDE 5/32" HOLE FOR FASTENER.
d. VALVE TAG SCHEDULE: PREPARE A VALVE TAG SCHEDULE TO BE SUBMITTED TO THE MAINTENANCE ENGINEER FOR RECORD.
13. DUCTWORK:
a. DUCTWORK SHALL BE FABRICATED AND INSTALLED IN ACCORDANCE WITH THE 2012 IMC AND SMACNA STANDARDS.
b. DUCTWORK SHALL BE GALVANIZED STEEL GAUGES TO MEET SMACNA STANDARDS. DUCTWORK SIZES INDICATED ARE FREE
CLEAR DIMENSIONS.
c. ALL DUCT JOINTS SHALL BE SEALED AIR TIGHT WITH RCD CORP. # 6 MASTIC ADHESIVE WITH VERSA GRIP OR MESH.
d. ALL FINAL CONNECTIONS TO SUPPLY GRILLES SHALL BE COMPLETED WITH ACOUSTICAL FLEXIBLE DUCT UNLESS OTHERWISE
NOTED ON THE PLANS.
e. FLEXIBLE DUCT USED FOR CONDITIONED AIR SHALL BE UL APPROVED, VINYL COATED, WIRE REINFORCED FIBERGLASS, WITH
MAXIMUM THERMAL CONDUCTIVITY OF 0.30 BTU-IN/HR-FT2-F AND A MAXIMUM LENGTH OF FIVE FEET.
f. DUCTWORK SHALL BE SIZED AT A MAXIMUM VELOCITY OF 1,000 FPM/.08" PRESSURE DROP PER 100 FEET.
g. EACH MECHANICAL VENTILATION SYSTEM (SUPPLY AND/OR EXHAUST) SHALL BE EQUIPPED WITH A MEANS OF SHUT-OFF WHEN
VENTILATION IS NOT REQUIRED, AND BACKDRAFT DAMPERS WHICH CAN BE CLOSED ON FAN SHUTDOWN SHALL BE PROVIDED FOR
AIR INTAKES AND/OR DISCHARGES.
h. CLEAN OUT ALL DUCTS PRIOR TO SUPPLY AND RETURN GRILLE INSTALLATION
i. '28%/(7+,&.1(667851,1*9$1(66+$//%(86('21$//'8&7785162)
14. REFRIGERANT PIPING:
a. REFRIGERANT LINE SETS SHALL BE FURNISHED BY THE CONDENSING UNIT MANUFACTURER AND BE PRE-INSULATED.
b. REFRIGERANT PIPING CONNECTIONS SHALL BE BRAZED WITH 15% SILL FLOSS. PURGE PIPING WITH NITROGEN WHILE BRAZING.
c. PROVIDE HANGERS, SUPPORTS AND INSULATION SADDLES AS REQUIRED AND PER ANSI REQUIREMENTS. PLUMBERS TAPE AND
WIRE ARE NOT ACCEPTABLE.
d. REFRIGERANT PIPING INDICATED IS SCHEMATIC ONLY. SIZE PIPING AND DESIGN THE ACTUAL PIPING LAYOUT, INCLUDING OIL
TRAPS, DOUBLE RISERS, SPECIALTIES, AND PIPE AND TUBE SIZES, TO ENSURE PROPER OPERATION AND COMPLIANCE WITH
WARRANTIES OF CONNECTED EQUIPMENT.
e. EVACUATE THE ENTIRE REFRIGERANT SYSTEM WITH A VACUUM PUMP TO A VACUUM OF 500 MICROMETER FOR A PERIOD OF 12
HOURS PRIOR TO CHARGING.
15. DUCTWORK INSULATION:
a. ALL DUCTWORK SHALL BE INSULATED CONSISTENT WITH THE REQUIREMENTS PER SECTION 604 OF THE 2012 IMC.
b. INSULATION SHALL BE UL LISTED IN COMPLIANCE WITH A FLAME-SPREAD INDEX NOT MORE THAN 25 AND SMOKE DEVELOPED
INDEX NOT MORE THAN 50, PER THE 2012 IMC. INSTALLATION SHALL BE IN ACCORDANCE WITH IMC REQUIREMENTS.
c. RECTANGULAR SUPPLY, RETURN & TRANSFER DUCTWORK SHALL BE INTERNALLY LINED WITH A VAPOR RESISTANT DUCT LINER OF
THICKNESSES SPECIFIED BELOW.
d. CONCEALED ROUND, CONCEALED OVAL & OUTDOOR AIR DUCTS SHALL BE EXTERNALLY WRAPPED WITH FIBERGLASS INSULATION
WITH AN EXTERNAL VAPOR BARRIER. REQUIRED R-VALUES ARE SPECIFIED BELOW.
e. ALL SUPPLY, RETURN & TRANSFER DUCTWORK LOCATED WITHIN THE BUILDING ENVELOPE SHALL BE INSULATED TO A MINIMUM OF
5ߛ´/,1(5ߜ81/(6663(&,),('27+(5:,6(217+(3/$16
f. $//6833/<ߙ5(7851'8&7:25.6+$//%(,168/$7('72$0,1,0802)5ߛ´/,1(5ߜ:+(1/2&$7(',181&21',7,21('
63$&(6$1'6+$//%(,168/$7('72$0,1,0802)5ߛ´/,1(5ߜ$1':($7+(53522)(':+(1/2&$7('2876,'(7+(
BUILDING.
g. ALL OUTDOOR AIR DUCTS SHALL BE INSULATED TO A MINIMUM OF R-6 WITH A VAPOR BARRIER.
16. TEMPERATURE CONTROL DEVICES:
a. CONTRACTOR SHALL PROVIDE STAND-ALONE CONTROLS CAPABLE OF MEETING THE SEQUENCE OF OPERATION DESCRIBED ON
SHEET M1.2.
b. THE HVAC SYSTEM SHALL BE PROVIDED WITH 7-DAY PROGRAMMABLE AUTOMATIC SPACE TEMPERATURE CONTROL DEVICES
(THERMOSTATS) AS SHOWN ON THE PLANS. THE THERMOSTATS SHALL BE CAPABLE OF SCHEDULING OCCUPANCIES AND
3529,',1*6(7%$&.&$3$%,/,7,(6720$,17$,1=21(6(732,176'2:172)258372)
c. &21752/66+$//%(&$3$%/(2)3529,',1*$'($'%$1'2)$7/($67)%(7:((1+($7,1*$1'&22/,1*
d. 7+(50267$766+$//+$9(180(5,&6(732,176,1)$'-867$%/(6(732,1767236$1'6+$//%(02817('$7$%29(
FINISHED FLOOR ADJACENT TO THE ROOM'S LIGHT SWITCH.
e. COORDINATE CONTROL TIE-INS WITH CONTROLS CONTRACTOR AS NECESSARY.
17. WATER QUALITY:
a. HEATING AND CHILLED WATER CONDITIONS SHALL BE WITHIN HARDNESS AND PH RANGE SUITABLE FOR MECHANICAL EQUIPMENT
(PER MANUFACTURER). CONTRACTOR TO TEST CONDITIONS PRIOR TO SYSTEM FILL. WATER SOFTENERS OR OTHER DEVICES
MAY BE REQUIRED TO IMPROVE WATER QUALITY.
18. BEFORE STARTING ANY WORK, THE CONTRACTOR FOR THIS SECTION OF THE WORK SHALL EXAMINE A COMPLETE SET OF DRAWINGS FOR
ALL TRADES, INCLUDING ARCHITECTURAL, STRUCTURAL, HVAC, ELECTRICAL, FIRE PROTECTION AND PLUMBING. DIMENSIONS, SPACE
REQUIREMENTS AND POINTS OF CONNECTION TO ALL EQUIPMENT SHALL BE VERIFIED, AND ANY MINOR ADJUSTMENTS NECESSARY TO
AVOID CONFLICT WITH THE BUILDING STRUCTURE AND THE WORK OF THE OTHER TRADES SHALL BE MADE. CONTRACTOR SHALL NOTIFY
ARCHITECT IMMEDIATELY IF ANY MAJOR CONFLICTS OCCUR.
19. COORDINATE LOCATIONS OF ALL ROOF AND EXTERIOR WALL OPENINGS WITH ALL RELEVANT TRADES, AND PROVIDE WATERTIGHT
FLASHINGS WHEREVER PENETRATIONS OCCUR. EXACT LOCATIONS AND SIZES MAY BE DEPENDENT UPON EQUIPMENT SELECTIONS;
COORDINATE SIZES AND LOCATIONS OF ALL OPENINGS WITH APPROPRIATE EQUIPMENT REQUIREMENTS.
20. PERMANENT ACCESS TO EQUIPMENT SHALL BE PROVIDED, AND A MINIMUM OF 30" CLEAR WORKING SPACE IN FRONT OF ACCESS PANELS
TO THE COMPRESSOR, BLOWER ASSEMBLY AND AIR FILTER SECTION OF THE EQUIPMENT SHALL BE PROVIDED BY GENERAL CONTRACTOR.
21. ALL EQUIPMENT SHALL BE SECURELY FASTENED TO THE BUILDING STRUCTURE WITH CODE APPROVED VIBRATION ISOLATORS.
22. EACH PIECE OF EQUIPMENT AND ALL SYSTEMS SHALL BE ADJUSTED AND RE-ADJUSTED TO INSURE PROPER FUNCTION OF ALL CONTROLS,
MAINTENANCE OF TEMPERATURE, ADEQUACY OF FLOWS AND CAPACITIES, ELIMINATION OF NOISE AND VIBRATION, AND SHALL BE LEFT IN
PROPER OPERATING CONDITION.
23. TEST & BALANCING:
a. THE ENTIRE HEATING AND VENTILATING SYSTEM SHALL BE BALANCED BY AN INDEPENDENT CERTIFIED TEST AND BALANCE
COMPANY.
b. 5 COPIES OF THEIR BALANCE REPORTS SHALL BE SUBMITTED TO THE ENGINEER FOR REVIEW AND APPROVAL. ELECTRONIC
DISTRIBUTION PREFERRED.
c. ALL REQUIRED RE-SHEEVING AND ADJUSTING OF EQUIPMENT SHALL BE MADE BY THE TEST & BALANCE CONTRACTOR.
d. ALL FINAL MEASURED CAPACITIES SHALL BE WITHIN 10% OF THOSE INDICATED ON THE PLANS.
24. FINAL LOCATION OF GRILLES, REGISTERS & DIFFUSERS SHALL BE PER THE ARCHITECTURAL PLANS, ELEVATIONS OR AS PER FIELD
REQUIREMENTS (UPON ACCEPTANCE BY ARCHITECT).
25. THE GENERAL CONTRACTOR SHALL FURNISH & INSTALL ALL OF THE REQUIRED ACCESS PANELS IN THE DRYWALL CEILINGS TO GAIN
SERVICE ACCESS TO THE EQUIPMENT. EQUIPMENT WITH MANUFACTURER MANDATED SERVICE REQUIREMENTS INSTALLED WITHIN
CRAWLSPACES MUST BE A MAXIMUM OF 20 FEET FROM AN ACCESS PANEL.
26. ALL EQUIPMENT SHALL BE INSTALLED ACCORDING TO THE MANUFACTURER'S INSTALLATION, OPERATION & MAINTENANCE MANUAL'S
RECOMMENDATIONS ESPECIALLY FOR SERVICE CLEARANCES.
27. FILTERS:
a. SHALL BE UL RATED AND APPROVED.
b. PRESSURE DROPS SHALL NOT EXCEED .10" STATIC PRESSURE.
28. ELECTRICAL CONNECTIONS:
a. UNLESS OTHERWISE INDICATED ALL MAGNETIC MOTOR STARTERS, THERMAL OVERLOADS, LOW VOLTAGE THERMOSTATS,
CONTROL RELAYS, CONTROL TRANSFORMERS AND SOLENOID VALVES SHALL BY FURNISHED BY THE MECHANICAL CONTRACTOR.
b. PROVIDE MOTORS AND EQUIPMENT FOR ONLY THOSE CURRENT CHARACTERISTICS INDICATED ON THE DRAWINGS.
c. IT IS THE INTENT OF THIS DIVISION TO REQUIRE A COMPLETE SYSTEM PER THE CONTRACT DOCUMENTS.
d. COORDINATE ALL EQUIPMENT REQUIRING ELECTRICAL POWER, REGARDLESS OF VOLTAGE, WITH OTHER TRADES, SO THAT ALL
SYSTEMS ARE COMPLETE AND OPERATIONAL.
e. ALL THREE PHASE MOTORS SHALL BE PROVIDED WITH PHASE LOSS PROTECTION.
f. ALL SINGLE AND THREE PHASE MOTORS, STARTERS AND DISCONNECTS PROVIDED BY MECHANICAL CONTRACTOR AND WIRED BY
THE ELECTRICAL CONTRACTOR.
29. TEMPORARY HEATING DURING CONSTRUCTION:
a. MECHANICAL EQUIPMENT SHALL NOT BE UTILIZED FOR TEMPORARY HEATING.
b. GAS FIRED TEMPORARY HEAT SHALL BE PROVIDED BY THE GENERAL CONTRACTOR.
W
DUCT RADIUS ELBOW DETAIL
NO SCALE
R
WHENEVER POSSIBLE R=W
IN AREAS OF TIGHT CLEARANCE, R=W/2 IS ACCEPTABLE
INSULATED RIGID DUCT
AIR FLOW
CLAMP
MANUAL DAMPER,
HANDLE, & LOCK NUT
WORM DRIVE S.S.
7:,67,1),77,1*:
ROUND DUCT TAKE-OFF
NO SCALE
INSULATED
RIGID DUCT
AIR
FLOW
CLAMP
MANUAL
DAMPER,
HANDLE,
& LOCK NUT
WORM
DRIVE S.S.
7:,67,1),77,1*:
ROUND DUCT TAKE-OFF
NO
SCALE
FAN COIL DETAIL
NO SCALE
FC
HANGER ROD,
SECURE TO
STRUCTURE (TYP.)
VIBRATION
ISOLATOR (TYP.)
DUCT TRANSITION (TYP.)
FLEXIBLE DUCT
CONNECTION (TYP.)
RETURN DUCT
SUPPLY DUCT
FAN COIL WITH OUTSIDE AIR DETAIL
NO SCALE
FC
FLEXIBLE DUCT
CONNECTION (TYP.)
RETURN DUCT
HANGER ROD,
SECURE TO
STRUCTURE (TYP.)
VIBRATION
ISOLATOR (TYP.)
WRAPPED
OUTSIDE AIR
DUCT
M
MOTOR OPERATED
DAMPER (TYP.)
DUCT LINER (TYP.)
DUCT TRANSITION (TYP.)
SUPPLY DUCT
DUCT LINER (TYP.)
SEQUENCE OF OPERATION:
VENTILATION:
HRV-1, FC-1:
DURING OCCUPIED HOURS, OUTDOOR AIR DAMPER SHALL OPEN, & HRV-1 & FC-1
BLOWER SHALL OPERATE CONTINUOUSLY TO PROVIDE VENTILATION THROUGHOUT
BUILDING & EXHAUST TO BATHROOMS & KITCHEN.
DURING UNOCCUPIED HOURS, OUTDOOR AIR DAMPER SHALL CLOSE, HRV-1 SHALL
REMAIN OFF, & FC-1 SHALL ONLY OPERATE WHEN THERE IS A CALL FOR HEATING.
SPACE HEATING:
FC-1, CU-1, EDH-1:
UPON A CALL FOR HEAT, FC-1 & CU-1 SHALL OPERATE TO PROVIDE FORCED AIR HEATING
TO MEET THE SETPOINT ON THE MANUFACTURER SUPPLIED THERMOSTAT /
&21752//(5,)7+(63$&(7(03(5$785(,6)/2:(57+$17+(6(732,17FC-1
SHALL SIGNAL EDH-1 TO OPERATE (USING CN24 RELAY KIT). DURING EDH-1 OPERATION,
FC-1 & CU-1 SHALL CONTINUE TO OPERATE & EDH-1 SHALL STAGE & CYCLE TO MAINTAIN
)ߛ$'-ߜ',6&+$5*($,5%$6('2))$'2:1675($06(1625
FC-2:
UPON A CALL FOR HEATING, FC-2 SHALL OPERATE TO MAINTAIN A MINIMUM SPACE
7(03(5$785(2))ߛ$'-ߜ
BASEBOARD HEATERS:
BASEBOARD HEATERS SHALL BE CONTROLLED OFF WALL MOUNTED THERMOSTATS.
SEE ELECTRICAL PLANS FOR MORE INFORMATION ON BASEBOARD HEATERS.
SPACE COOLING:
FC-1, CU-1:
WHEN COOLING IS ENABLED ON THE MANUFACTURER SUPPLIED THERMOSTAT /
CONTROLLER & THERE IS A CALL FOR COOLING, CU-1 SHALL OPERATE TO MEET THE
SETPOINT. COOLING SHALL BE LOCKED OUT DURING UNOCCUPIED HOURS.
&RS\ULJKWE\=HKUHQߙ$VVRFLDWHV,QF