HomeMy WebLinkAboutC-7 - Sewer Line & Temp Facility Work Plan.pdfBUILDING CONC. WALK PRO SHOP OFFICES LO BBY DN RAMP SLOPE 1:12 MAX. RESTROOMS RAMP SLOPE 1:12 MAX. LANDING ASPHALT ST ST GRAPHIC SCALE (IN FEET) 1 inch = ft. 30 Copyright © 2015 by Zehren & Associates Inc. Sewer line work to take place between 9/21/15 and 10/2/15. Install orange 4' construction fencing around excavation area Sewer line work across driving range to take place from 10/2/15 - 10/20/15. Install orange 4' construction fencing around excavation area Temp Facility to be set during month of October. Staging for Temp Facility Work NO CONTRACTOR PARKING THIS AREA. All parking to be in main lot. Staging of materials along side of excavation, typical. Staging of materials along side of excavation, typical. Staging plan for Sewer & Temp Facility Work - 9/21/15 - 10/31/15 09/02/15