Review Coordinator Carolyn Godfrey ( cgodfrey@vailgov.com )
Review Cycle 1
Workflow/Activity Name Begin_Workflow / ApplicantResubmit
Activity InstructionsPlease review all sections of the eForm and drawing markups and resubmit the required
information prior to completion of task.
Current User Logon Adam Gilmer ( adam@berglundarchitects.com)
CHANGEMARKS Review Cycle:1
Filter Changemarks by Keyword: SEARCH SHOW ALL
Click Here to Load Changemarks...
Click Here to Publish Changemarks to PDF...
Sorting:
Resolved Status File Cycle Department File Markup Description Details Applicant Response
Yes | No No 1 Planning A3.3.pdf jbatcheller P001
This area counts towards GRFA, per Section 1215
3 http://sterlingcodifiers.com/codebook/index.php?
book_id=560§ion_id=841013
Yes | No No 1 Planning A2.4.pdf jbatcheller P001 Revise GRFA calcs to include the auto court.
Yes | No No 1 Public
Works A3.3.pdf lsandoval PW001 Removal of, On street parking will be required.
Show on site plan.
Yes | No No 1 Public
Works A3.3.pdf lsandoval PW002
The Public Works Department, Engineering will not
support driveway to exceed 12% grade. As shown,
currently at 16%. Revise
Yes | No No 1 Public
Works A3.3.pdf lsandoval PW003
No additional concrete pan will be required, if one
currently exist. Concrete pan shall not be heated.
Please note on plans, heated driveway within right
of way shall me on a seperate zone marked at
control box, TOV or ROW.
Yes | No No 1 Public
Works A3.3.pdf lsandoval PW004
Show a limits of disturabance fence and BMP (
Best Management Practices for Erosion Control on
site plan.
Yes | No No 1 Public
Works A3.3.pdf lsandoval PW005
A Revocable Right of Way Permit will be required
for all improvments within the Right of Way. To be
submitted at building permit submittal.
Yes | No No 1 Public
Works A3.3.pdf lsandoval PW006
Provide, Stamped approved drawing for a license
PE, for Retaining Wall, over 4 ft in height. All
disturbed grading, must return to a 2:1 grade.
Complete Save And Close
Building Process V1
DEPARTMENT REVIEW Review Cycle:1
CYCLE DEPARTMENT REVIEWED BY STATUS & NOTES
1 FIRE
MIKE VAUGHAN
MVAUGHAN@VAILGOV.COM
NO REVIEW REQUIRED
VIEW CHECKLIST
PLAN REVIEW AND/OR ASSIGNMENT COMPLETE
1 PLANNING JOE BATCHELLER
JBATCHELLER@VAILGOV.COM
CORRECTIONS REQUIRED
PLAN REVIEW AND/OR ASSIGNMENT COMPLETE
1 PUBLIC WORKS
LEONARD SANDOVAL
LSANDOVAL@VAILGOV.COM
CORRECTIONS REQUIRED
VIEW CHECKLIST
PLAN REVIEW AND/OR ASSIGNMENT COMPLETE
I have reviewed and addressed the Checklist Comments provided on the "Checklist" tab above. Please click on the tab and review each item. Each comment will be
indicated as "Met" or "Not Met". If you would like to export a list of the comments to Excel, click on the "Export to Excel" link in the upper right hand corner of the popup
window.
I have addressed all of the items listed in the Changemarks section above that were identified during the Plan Review.
I have uploaded the revised drawings into the "Drawings" folder and, if requested, uploaded any revised documents into the "Documents" folder using the SAME file name as
the original files. I am ready to complete my assigned task.
Task Instructions