HomeMy WebLinkAboutB16-0019 Engineers letter.pdf,_. !'_ 41
H-P3:::;KUMAR ~ l~ /
02~A~n~RoodlPO D~,1~7 ~ Silverthorne, Colorado 80498
Geotechnical Engineering I Engineering Geology Phone: (970) 468-1989
Materials Testing I Environmental Fax: (970) 468-5891
Email: hpksummit@kumarusa.com
Office Locations: Parker, Glenwood Springs, and Silverthorne, Colorado
November 2, 2016
Christoff erson Commercial Builders, Inc.
Attn: Craig Sorvald
3235 Fillmore Ridge Heights
Colorado Springs, CO 80907 Job No. 16-9-159
Subject: Construction Observation and Materials Testing Services, West Vail
McDonalds Remodel, 2171 North Frontage Road, Vail, Colorado.
Dear Mr. Sorvald:
As requested, please find the attached package of finalized reports for the West Vail
McDonalds remodel project. Kumar and Associates, Inc. (H-P Kumar) was retained by
Christofferson Commercial Builders, Inc. to provide construction observation and
materials testing services for the construction of the subject project. H-P Kumar was on
site during the period of August 8, 2016 to September 21, 2016. The services provided
under this contract included part-time observation and materials testing with site visits
requested by the contractor.
1) On site soil sampling and laboratory testing on 8/8/2016 (Attached).
2) Excavation observation on 8/15/2016 (Attached).
3) Fresh concrete testing on 8/17, 9/1, 9/13, 9/19, and 9/21/2016 (Attached).
4) Masonry wall observation on 8/23/2016 (Attached).
5) Grout Core testing on 8/26/2016 (Attached).
6) Parking lot subgrade soil observations on 9/19 and 9/21/2016 (Attached).
7) Subcontracted structural steel inspections on 919 and 9/21/2016 (Attached).
Please let us know ifthere are any questions or if we can be of further assistance.
Sincerely,
H-P Kumar
Jared Cohen
Construction Services Manager
Reviewed by:
Chad Bringle
Project Engineer
( ,_. ....
SIEVE ANALYSIS HYDROMETER ANALYSIS
CLEAR SQUARE OPENINGS U.S. STANDARD SIEVES TIME READINGS
100 8" S" 3" 1112" 3/4" 3/8" #4 #8 #16 #30 #SO #100 #200 1 MIN 4 MIN 19 MIN 60 MIN 43S MIN
~ ....__
90 '\ ..
80
70 \
I!) \ z Vi ~ 60 ............
I-
........... loo.. z w so u ......... a:: "-.. w a..
40 '"" 30
20
10
0 1000 soo 200 127 7S 37.S 19.0 9.S 4.7S 2.3S 1.18 .60 .30 .lS .o7S .037 .019 .009 .oos .002 .001
DIAMETER OF PARTICLE IN MILLIMETERS
GRAVEL SAND
COBBLES
COARSE I I CLAY(plastic) TO SILT(non-plastic)
COURSE FINE MEDIUM FINE
Grain Size (mm) Sieve Size % Passing Particle Size Distribution
200 8" 100 Cobbles: 0%
127 5" 100 Gravel: 39%
75 3" 100 Sand: 27%
so 2" 95 Silt & Clay: 34%
37.5 11/2" 92
25.0 1" 91 Classification: Gravel (GM); Silty, Sandy
19.0 3/4" 89 Location: Sample #1, Existing On-Site Fill Soils
12.5 1/2" 84 Depth: 1.5 Feet Below Grade @ Drive Thru Area
9.5 3/8" 79 Sample Date: 8/8/2016
4.75 #4 61 Liquid Limit: 29
2.35 #8 59 Plasticity Index: 4
1.18 #16 56
0.60 #30 51
0.30 #50 46
0.15 #100 40
O.Q75 #200 34
16-9-159 H-P~KUMAR WEST VAIL MCDONALDS FIGURE 1 GRADATION TEST RESULTS
i, • """
125
* -
120 I \. ,...... 'I i\... LL (.) 'f \ Cl. ......... I I\ ~ I '
(/) ' z I \ w 115 J I\ c
>-I I D 0:: c ,I,
110
5 10 15 20
MOISTURE CONTENT (%)
SAMPLE LOCATION DEPTH DATE MAXIMUM OPTIMUM PROCTOR
NO. DRY DENSITY MOISTURE METHOD
1 On Site Soils #1 -1.5' 8/8/16 *121.2 PCF *10.3% ASTM 0-698
Drive Thru Area Method C
COBBLES 0 % GRAVEL 39 % SAND 27 % SILT AND CLAY 34 %
LIQUID LIMIT 29 % PLASTICITY INDEX 4 %
SAMPLE OF: Gravel (GM); Silty, Sandy LAB NO.: 733
* The optif'.Tlum moisture and density were corrected using ASTM 0-4718 due
to oversized particles within sample.
16-9-159 H-P~KUMAR WEST VAIL MCDONALDS FIGURE 2 MOISTURE/DENSITY RELATIONSHIP
It •
SIEVE ANALYSIS HYDROMETER ANALYSIS
CLEAR SQUARE OPENINGS U.S. STANDARD SIEVES TIME READINGS
100 8" 5" 3" 111211 3/4" 3/8" #4 #8 #16 #30 #50 #100 #200 1 MIN 4 MIN 19 MIN 60 MIN 435 MIN
"'\
90 ' \ .. ,., . .. ..
80 \ , .. .
70 ' l!) z \ v; ... ..
VI 60 ~ \ -·
I-z UJ 50 u .. " a: UJ Cl.
40 ' " .
30 ' '\
20 ' "I"" ,....__
10
0 1000 500 200 127 75 37.5 19.0 9.5 4.75 2.35 1.18 .60 .30 .15 .075 .037 .019 .009 .005 .002 .001
DIAMETER OF PARTICLE IN MILLIMETERS
GRAVEL SAND
COBBLES
COARSE I I CLAY(plastic) TO SILT(non-plastic)
COURSE FINE MEDIUM FINE
Grain Size (mm Sieve Size % Passing Particle Size Distribution
200 8" 100 Cobbles: 0%
127 S" 100 Gravel: 50%
7S 3" 100 Sand: 40%
so 2" 100 Silt & Clay: 10%
37.S 11/2" 98
2S.O 1" 92 Classification: Gravel (GP-GM); Slightly Silty, Very Sandy
19.0 3/4" 8S Location: Sample #2, Existing On-Site Fill Soils
12.S 1/2" 72 Depth: At Site Grade @ Parking Area West Side
9.S 3/8" 6S Sample Date: 8/8/2016
4.7S #4 so Liquid Limit: 20
2.3S #8 43 Plasticity Index: NP
1.18 #16 35
0.60 #30 26
0.30 #SO 17
O.lS 11100 12
O.Q7S #200 10
16-9-159 H-P~KUMAR WEST VAIL MCDONALDS FIGURE 3 GRADATION TEST RESULTS
L' ,..
145
140 * ,......, ~ LL. (.) I \ a.. ............ \ >-J
t-r; ,
Cf) z 135 w I \ Cl
>-I \ e:::: Cl I~
130
5 10 15 20
MOISTURE CONTENT (%)
SAMPLE LOCATION DEPTH DATE MAXIMUM OPTIMUM PROCTOR
NO. DRY DENSITY MOISTURE METHOD
2 On Site Soils #2 Grode 8/8/16 *139.6 PCF *6.7 % ASTM D-698
Parking Area Method C
COBBLES 0 % GRAVEL 50 % SAND 40 % SILT AND CLAY 10 %
LIQUID LIMIT 20 % PLASTICITY INDEX NP %
SAMPLE OF: Grovel (GP-GM); Slightly Silty, Very Sandy LAB NO.: 734
*The optimum moisture and density were corrected using ASTM D-4718 due
to oversized particles within sample.
16-9-159 H-P~ KUMAR WEST VAIL MCDONALDS FIGURE 4 MOISTURE/DENSITY RELATIONSHIP
H-P~KUMAR
Geotechnical Engineering I Engineering Geology
Materials Testing I Environmental
.,
240 Annie Road I P.O. Drawer 1887
Silverthorne, Colorado 80498
Phone: (970) 468-1989
Fax: (970) 468-5891
Email: hpksummit@kumarusa.com
Office Locations: Parker, Glenwood Springs, and Silverthorne, Colorado
August 29, 2016
Christofferson Commercial Builders, Inc.
Attn: Colin Christofferson
3235 Filmore Ridge Heights
Colorado Springs, CO 80907 Job No. 16-9-159
Subject: Excavation Observation, West Vail McDonalds Remodel, 2171 North Frontage
Road West, Vail, Colorado.
Dear Mr. Christofferson:
As requested, a representative of Kumar & Associates, Inc. (H-P Kumar) observed the
excavation at the subject site on August 15, 2016 to evaluate the soils exposed for foundation
support. The findings of our observations and recommendations for the foundation design are
presented in this report.
Proposed Construction
The proposed construction consists of a small addition to the west side of the existing structure.
The addition will consist of a single story structure with the finished floor elevation at or above
existing grade. Grouted solid masonry block walls and continuous footings will be used below
grade and masonry block walls above grade. Ground floor will be concrete slab-on-grade. We
reviewed the Foundation Plan and Structural Notes prepared by Core States Group, Project No.
MCD-17784, dated 2/19/16. The plans indicated the structure was designed for a maximum
allowable bearing pressure of 3,000 pounds per square foot (psf).
Excavation Observation
At the time of our initial site visit, the foundation excavation had been cut in one level from about
4 to 5 feet below the adjacent ground surface. The soils exposed in the base of the excavation
consisted of loose to medium dense, silty sand with gravel fill material. The soils were generally
moist and offered little resistance when probed with a %-inch T-probe with penetrations of 18 to
24 inches. We recommended removing all fill material beneath foundations and floor slabs.
Foundations should be extended down to the undisturbed granular soils or bear on properly
placed structural fill. Slab-on-grade floors shall be placed on properly placed, moisture-
conditioned structural fill.
We returned to the site later on August 15, 2016. All fill material had been removed from below
the proposed foundations and floor slab area to a depth of approximately 9 feet below the
adjacent ground surface. The soils exposed at the base of the excavation consisted of dense
reddish brown clayey sand with gravel. The soils were moist and offered stiff resistance when
probed with a %-inch T-probe with maximum penetrations of 4 inches.
Christofferson Commercial Builders, Inc.
August29,2016
Page2
The base of the excavation measured approximately 10 feet wide and extended approximately
6 feet away from the existing basement wall. The cut slopes in the excavation consisted of silty
sand with gravel fill material and were laid back approximately 1 % horizontal to 1 vertical.
Foundation Recommendations
Considering the conditions exposed in the excavation and the nature of the proposed
construction, spread footings placed on the undisturbed natural granular soil designed for an
allowable soil bearing pressure of 3,000 psf should be adequate for support of the proposed
addition. Foundation settlements are anticipated to be relatively minor and essentially occur
during construction. Loose and disturbed soils should be moisture-conditioned and compacted.
The bearing soils should be protected from frost and concrete should not be placed on standing
water, frost, or frozen soils. Exterior footings should be provided with adequate soil cover above
the bearing elevation for frost protection. Backfill placed around the structure should be
compacted and the surface graded to prevent ponding within at least 10 feet of the structure in
accordance with the recommendations presented in the "Surface Drainage" section of this letter.
Floor Slab Recommendations
The silty sand with gravel fill material had been removed from the area under the proposed floor
slabs of the addition. The natural clayey sand with gravel observed at the base of the
excavation and structural fill is considered good for slab-on-grade construction. To reduce the
effects of some differential movement, nonstructural floor slabs should be separated from all
bearing walls and columns with expansion joints which allow unrestrained vertical movement.
Floor slab control joints should be used to reduce damage due to shrinkage cracking. Slab
reinforcement and control joints should be established by the designer based on experience and
the intended slab use.
Structural fill placed beneath slabs can consist of the onsite granular soils or a suitable imported
granular material, excluding topsoil and plus 6-inch material. Structural fill should be spread in
thin horizontal lifts not to exceed 8 inches thick, adjusted to optimum moisture content, and
compacted to at least 95% of the maximum standard Proctor dry density.
We recommend vapor retarders conform to the minimum requirements of ASTM E1745 Class C
material. Certain floor types are more sensitive to water vapor transmission than others. For
floor slabs bearing on angular gravel or where flooring system sensitive to water vapor
transmission are utilized, we recommend a vapor barrier be utilized conforming to the minimum
requirements of ASTM E1745 Class B material. The vapor retarder should be installed in
accordance with the manufacturers' recommendations.
Underdrain and Dampproofing
It is our understanding the finished floor elevation at the lowest level of the addition is above the
surrounding exterior grade. Therefore, a foundation drain system and stem wall dampproofing
is not required. We recommend below-grade construction, such as retaining walls, crawlspace
and basement areas, be protected from wetting and hydrostatic pressure buildup by an
underdrain and wall drain system.
If the finished floor elevation of the proposed structure has a floor level below the surrounding
grade or the finished grading does not meet the minimum requirements of the "Surface
H-P~ KUMAR Project No. 16-9-159
...
Christofferson Commercial Builders, Inc.
August 29, 2016
Page 3
Drainage" section, we should be contacted to provide recommendations for an underdrain
system and dampproofing. All earth retaining structures should be properly drained.
Site Grading
The following recommendations should be followed for grading, site preparation, and fill
compaction.
..
1) Where fill is to be placed, topsoil, loose or otherwise unsuitable material should be
removed prior to placement of new fill. The exposed soils should be scarified to a depth
of 6 inches, moisture conditioned and compacted to the minimum requirements of the
overlying fill. Soils should be compacted with appropriate equipment for the lift thickness
placed. Lift thickness should be no more than 8 inches compacted at the recommended
moisture content and greater than the minimum required density.
2) Permanent unretained cut and fill slopes should be graded at 3 horizontal to 1 vertical
(3: 1) or flatter and protected against erosion by revegetation or other means. The risk of
slope instability will be increased if seepage is encountered in cuts and flatter slopes
may be necessary. If seepage is encountered in permanent cuts, an investigation
should be conducted to determine if the seepage will adversely affect the cut stability.
This office should review site grading plans for the project prior to construction.
3) Slopes of 4:1 or steeper should be benched to provide a level surface for compaction.
4) All backfill should be processed so that it does not contain fragments larger than 6-
inches in diameter and placed at the recommended moisture content.
5) The following compaction requirements should be used:
TYPE OF FILL MOISTURE SOIL TYPE -Compaction Percent
PLACEMENT CONTENT (ASTM 0698 -Standard Proctor)
Foundation Wall
± 2% Optimum Processed Onsite -95%
Backfill
Below Floor Slabs ±2% Optimum Structural Fill -95%
Landscape Areas ±2% Optimum Processed Onsite -90%
Below Concrete
± 2% Optimum Processed Onsite -95%
Flatwork/Pavements
Utility Trenches As they apply to the finished area
Suitability of Onsite Soil
The onsite silty sand with gravel is suitable as common fill after moisture treatment.
Structural Fill
Structural fill used for support of the floor slabs can consist of the onsite silty sand with gravel
soils or a relatively well-graded imported granular material with no rock larger than about 6
inches in diameter and be properly placed and compacted to reduce the risk of settlement and
distress. Structural fills should be placed in accordance with the recommendations presented in
the "Site Grading" section of this report.
H-P~ KUMAR Project No. 16-9-159
Christofferson Commercial Builders, Inc.
August 29, 2016
Page4
Surface Drainage
The following drainage precautions should be observed during construction and maintained at
all times after the addition has been completed:
1) Inundation of the foundation excavations and underslab areas should be avoided
during construction.
2) Backfill in pavement and slab areas should be compacted to at least 95% of the
maximum standard Proctor dry density at a moisture content within 2% of
optimum. Exterior backfill placed in landscape areas should be compacted to at
least 90% of the maximum standard Proctor dry density at a moisture content
near optimum.
3) The ground surface surrounding the exterior of the building should be sloped to
drain away from the foundation in all directions. We recommend a minimum
slope of 12 inches in the first 10 feet in unpaved areas and a minimum slope of 3
inches in the first 10 feet in paved areas.
4) Roof downspouts and drains should discharge well beyond the limits of all
backfill.
5) Landscaping which requires regular heavy irrigation should be located at least 10
feet from foundation walls. The upper 2 feet of foundation wall backfill should
consist of relatively impervious cover soil.
Continuing Services
Placement of structural fill under floor slabs should be observed and tested by a representative
of the Geotechnical engineer to judge whether the proper placement conditions have been
achieved.
Limitations
The recommendations submitted in this letter are based on our observation of the soils exposed
within the foundation excavation and do not include subsurface exploration to evaluate the
subsurface conditions within the loaded depth of foundation influence. This study is based on
the assumption that soils beneath the footings have equal or better support than those exposed.
The risk of foundation movement may be greater than indicated in this report because of
possible variations in the subsurface conditions. In order to reveal the nature and extent of
variations in the subsurface conditions below the excavation, drilling would be required. It is
possible the data obtained by subsurface exploration could change the recommendations
contained in this letter. Our services do not include determining the presence, prevention or
possibility of mold or other biological contaminants (MOBC) developing in the future. If the
client is concerned about MOBC, then a professional in this special field of practice should be
consulted.
If there are any questions or if we may be of further assistance, please let us know.
Sincerely,
H-P Kumar
/. #~:7"'>~k~:o>
E. Stoy Streepey, E. I.
Staff Engineer
H-P~ KUMAR
Chad M. Bringle, P.E.
Project Engineer
Project No. 16-9-159
H-P~KUMAR
Geotechnical Engineering I Engineering Geology
Materials Testing I Environmental
H-P Kumar
P.O. Drawer 1887
240 Annie Road
..
Silverthorne, Colorado 80498
Phone: (970) 468-1989
Fax: (970) 468-5891
hpksummit@kumarusa.com
Report of Concrete Cylinder Test Data
Client:
Attn:
Christofferson Commercial Builders, Inc.
Colin Christofferson
3235 Fillmore Ridge Heights
Colorado Springs, CO 80907
Job No.:
Sheet No.:
Lab#:
16-9-159
1 of
497
Date:
l
08/17/2016
Project: West Vail McDonalds Remodel, 2171 North Frontage Road, Vail, Colorado.
Placement Location: West Side Footings for Drive Thru; North Side (Footing Only), South Side (Footing and Slab)
Test Location: North Side Footing
Truck: 38 Time Batch: 7:52 am Supplier: Casey Concrete
Ticket: 306960 Time Arrived: 8:45 am Yards: 5 of 5
Mix: 4000 psi % Exterior Time Placed: 9:35 am Method of Placement: Chute
Physical Pro11erties: Water/Cement: 0.41 S11ecifications:
Sample Point: End of Chute Water added: -0-Gal. Slump: 3-5 Inches
Time Sampled: 9:30 am Slump: 5.0 Inches Air Content: +/-4 %
Air Temp.: 58 op Air Content: 5.5 % Water I Cement: 0.45 Max
Concrete Temp.: 65 op Wet Unit Wt.: 141.4 pcf Design Strength: 3,500 psi@28 days
Time Cy!. Cast: 9:43 am Initial Cure: Field Field Storage: Cure Box
Diameter: 4 Inches Area: 12.57 Inches2 Max/Min: NA op to NA op
Compressive Strength Data
Age Load Compressive
Date Strength (Days) (lbs.) (psi)
7 08/24/2016 51,446 4,090
28 09/14/2016 69,748 5,550
28 09/14/2016 68,423 5,440
Hold -------------
Preliminary Observations and I or Testing Results Verbally Reported To: Craig Sorvald with Christofferson Commercial Bmlders
Progress Report:
Copies:
Andrew Mc Williams Jared Cohen
Field Observer Reviewed By
'•
H-P~KUMAR
Geotechnical Engineering I Engineering Geology
Materials Testing I Environmental
Report of Construction Activities
H-P Kumar
P.O. Drawer 1887
240 Annie Road
..
Silverthorne, Colorado 80498
Phone: (970) 468-1989
Fax: (970) 468-5891
hpksummit@kumarusa.com
Client: Christofferson Commercial Builders, Inc.
Colin Christoff erson
Job No.: 16-9-159 Date: 08/23/2016
Attn:
3235 Fillmore Ridge Heights
Colorado Springs, CO 80907
Sheet No.: of 1
Project: West Vail McDonalds Remodel, 2171 North Frontage Road, Vail, Colorado.
Weather Conditions and Temperature: Cloudy, 60° F
Major Equipment on Site: NA
Contractor's Construction Activities:
Contractor constructed 3 Masonry CMU walls; a new exterior wall for the drive-thru and two interior walls filling in
existing openings on the west side of the building. The drive-thru wall measured 48 inches high by 80 inches wide and
was constructed with 12 inch CMU blocks up to slab grade from -8 feet below grade. The north interior wall that was
constructed in an existing opening was built from the slab up to 88 inches high by 64 inches wide with 8 inch CMU
blocks. The south interior wall that was constructed in an existing opening was a "plug" and began up approximately
24 inches from the slab and measured 62 inches high, 118 inches wide, with 8 inch CMU blocks.
H-P Kumar's Site Activities:
As requested, H-P Kumar was on site to observe and document reinforcement steel placement for areas of masonry wall
construction. While on site we observed 3 Masonry CMUWalls:
Drive-Thru Wall -Observed ( 6) #5 re bars at the comer. Two bars in each cell; 3 cells. The bars were within 16 inches
of each side of the comer. There were also (2) #5 rebars at each end of the wall. On the north side, a vertical bar was
placed to maintain 40 inch on center spacing of vertical bars. No ladder or truss type reinforcement was placed.
Contractor installed two bond beams that were not on the plans with (2) #5 rebars on each face at the 36 inch level and
the 72 inch level. These bond beams were epoxied into the existing foundation wall. Contractor intends to fully grout
the wall in all cells.
North Wall -Wall was constructed with vertical bars at each end and one in the middle to maintain 40 inch on center
vertical spacing. These bars were drilled into the foundation and extended to the top of the wall. As such, they have no
lap. The (1) #5 rebar bond beam shown on the plans at the lowest course was not present, nor was the ladder/truss
horizontal reinforcement. Contractor installed two bond beams that were not on the plans with (2) #5 rebars on each
face at the 36 inch level and the 72 inch level. Contractor intends to fully grout the wall in all cells.
South (Plug) Wall -Vertical reinforcement bars extended into the existing wall down to the slab. These bars could not
be epoxied into the existing wall at the top due to a steel beam at that level. These vertical bars had 30 inches of
overlap with the bars extending from the slab. Vertical bars were only present at the wall ends, no bars in the middle
for 40" O.C. spacing. In addition there were no ladders as horizontal joint reinforcement every 16 inches as noted.
Contractor installed two bond beams that were not on the plans with (2) #5 rebars on each face at the 36 inch level and
the 72 inch level. Contractor intends to fully grout the wall in all cells.
Verbal Communication With: Craig Sorvald with Christofferson Commercial Builders, Inc.
Copies:
Andrew Mc Williams Jared Cohen
Field Observer Reviewed By
'I
H-P~KUMAR
Geotechnical Engineering I Engineering Geology
Materials Testing I Environmental
H-P Kumar
P.O. Drawer 1887
240 Annie Road
Silverthorne, Colorado 80498
Phone: (970) 468-1989
Fax: (970) 468-5891
hpksummit@kumarusa.com
Report of Grout Core Test Data
Client:
Attn:
Project:
Christofferson Commercial Builders, Inc.
Colin Christofferson
3235 Fillmore Ridge Heights
Colorado Springs, CO 80907
Job No.: 16-9-159
Sheet No.: of
Lab#: 506
West Vail McDonalds Remodel, 2171 North Frontage Road, Vail, Colorado.
Core Properties
Date:
1
08/26/2016
Placement Location: Drive Thru Exterior Masonry Wall and (2) Interior Masonry Walls on the West Side of the Building
Supplier: Casey Concrete Mix ID: 7SK20%3/81 Truck: 38 Ticket: 307127
Age When Cored: 6Days
Core Preparation: Saw cut I Cap
Core ID: Core #1
Age When Tested: 7
Date Tested: 09/02/2016
Diameter (in.) 2.75
Length (in.) 5.5
Area (in2) 5.94
Max Load (lbs) 28,073
Length I Diameter 2:1 Ratio
Correction Factor NA
Compressive 4,730 Strensrth (psi)
Age When Tested: 7 & 28 Days
Reinforcement Noted: None
Comoressive Stren2th Data
Core #2
28
09/23/2016
2.75
5.5
5.94
32,479
2:1
NA
5,470
Max. Aggregate Size: 3/8 Inches
Design Strength at 28 days: 2,000
Core #3
28
09/23/2016
2.75
5.5
5.94
33,064
2:1
NA
5,570
psi
Preliminary Observations and I or Testing Results Verbally Reported To: Craig Sorvald with Christofferson Commercial Builders
Progress Report:
Contractor filled masonry units with grout at the time of placement. H-P Kumar picked up the grout filled CMU blocks and
returned them to our Silverthorne Laboratory for coring, moist curing, and compressive strength determination.
Copies:
Christofferson
Commercial Builders
Field Observer
Jared Cohen
Reviewed By
,,
H-P~KUMAR
Geotechnical Engineering I Engineering Geology
Materials Testing I Environmental
H-P Kumar
P.O. Drawer 1887
240 Annie Road
I •
Silverthorne, Colorado 80498
Phone: (970) 468-1989
Fax: (970) 468-5891
hpksummit@kumarusa.com
Report of Concrete Cylinder Test Data
Client:
Attn:
Christofferson Commercial Builders, Inc.
Colin Christofferson
3235 Fillmore Ridge Heights
Colorado Springs, CO 80907
Job No.:
Sheet No.:
Lab#:
16-9-159
1 of
511
Date:
1
09/01/2016
Project: West Vail McDonalds Remodel, 2171 North Frontage Road, Vail, Colorado.
Placement Location: (3) Interior Pier Footings and (2) Interior Slab In-Fill
Test Location: Southwest Pier Footing
Truck: 038 Time Batch: 3:04 pm Supplier: Casey Concrete
Ticket: 307271 Time Arrived: 3:52 pm Yards: 6 of 6
Mix: 4000 psi -Interior Time Placed: 4:00 pm Method of Placement: Chute
Ph:i::sical Pro12erties: Water/Cement: 0.41 S12ecifications:
Sample Point: End of Chute Water added: -0-Gal. Slump: 3-5 Inches
Time Sampled: 4:09 pm Slump: 4 Yi Inches Air Content: NA %
Air Temp.: 75 op Air Content: 2.5 % Water I Cement: 0.45 Max
Concrete Temp.: 75 op Wet Unit Wt.: 144.9 pcf Design Strength: 3,500 psi@28 days
Time Cyl. Cast: 4:38 pm Initial Cure: Field Field Storage: Cure Box
Diameter: 4 Inches Area: 12.57 Inches2 Max/Min: NA op to NA op
Compressive Strength Data
Age Load Compressive
Date Strength (Days) (lbs.) (psi)
7 09/08/2016 53,658 4,270
28 09/29/2016 73,211 5,820
28 09/29/2016 74,975 5,960
Hold -------------
Preliminary Observations and I or Testing Results Verbally Reported To: Craig Sorvald with Christofferson Commercial Builders
Progress Report:
Copies:
Andrew Mc Williams Jared Cohen
Field Observer Reviewed By
H-P~KUMAR
Geotechnical Engineering I Engineering Geology
Materials Testing I Environmental
H-P Kumar
P.O. Drawer 1887
240 Annie Road
J •
Silverthorne, Colorado 80498
Phone: (970) 468-1989
Fax: (970) 468-5891
hpksummit@kumarusa.com
Report of Concrete Cylinder Test Data
Client: Christofferson Commercial Builders, Inc. Job No.: 16-9-159 Date:
1
0911312016
Attn: Colin Christofferson
3235 Fillmore Ridge Heights
Colorado Springs, CO 80907
Sheet No.: of
Lab#: 518
Project: West Vail McDonalds Remodel, 2171 North Frontage Road, Vail, Colorado.
Placement Location: Curb & Gutter; South Side of Drive Thru Area and Sidewalk on South Side of Building
Test Location: Southwest Comer of Drive Thru Area Curb
Truck: 992 Time Batch: 10:22 am Supplier: Casey Concrete
Ticket: 307482 Time Arrived: 11:20 am Yards: 10 of 10
Mix: 4000 psi 7'4 Exterior Time Placed: 11:40 am Method of Placement: Chute
Physical ProQerties: Water/Cement: NA SQecifications:
Sample Point: End of Chute Water added: 7 Gal. Slump: 3-5 Inches
Time Sampled: 11:41 am Slump: 5.0 Inches Air Content: +/-4 %
Air Temp.: 65 op Air Content: 6.6 % Water I Cement: 0.45 Max
Concrete Temp.: 70 op Wet Unit Wt.: 140.l pcf Design Strength: 4,000 psi@28 days
Time Cyl. Cast: 11:54 am Initial Cure: Field Field Storage: Cure Box
Diameter: 4 Inches Area: 12.57 Inches2 Max/Min: NA op to NA op
Compressive Strength Data
Age Load Compressive
Date Strength (Days) (lbs.) (psi)
7 09/20/2016 55,367 4,400
28 1011112016 68,662 5,460
28 10/11/2016 67,154 5,340
Hold -------------
Preliminary Observations and I or Testing Results Verbally Reported To: Craig Sorvald with Christofferson Commercial Builders
And Cotton with Casey Concrete
Progress Report:
Copies:
Andrew Mc Williams Jared Cohen
Field Observer Reviewed By
H-P~KUMAR
Geotechnical Engineering I Engineering Geology
Materials Testing I Environmental
Report of Construction Activities
Client:
Attn:
Christofferson Commercial Builders, Inc.
Colin Christofferson
3235 Fillmore Ridge Heights
Colorado Springs, CO 80907
Job No.: 16-9-159
Sheet No.: 1 of
Project: West Vail McDonalds Remodel, 2171 North Frontage Road, Vail, Colorado.
Weather Conditions and Temperature: Sunny, 55° F
Major Equipment on Site: Concrete Truck with 10 Yard Load
Contractor's Construction Activities:
Contractor was preparing to pour parking area and drive lane concrete slabs.
H-P Kumar
P.O. Drawer 1887
240 Annie Road
Silverthorne. Colorado 80498
Phone: (970) 468-1989
Fax: (970) 468-5891
hpksummit@kumarusa.com
Date:
2
09/19/2016
Contractor performed a proof roll of the subgrade soils on the south side parking and drive-thru area.
H-P Kumar's Site Activities:
As requested, H-P Kumar was on site to test and observe the scheduled fresh concrete placement for the south side
parking area and drive lane concrete slabs (page 2of2). In addition, while on site we were requested to observe a proof
roll of the prepared subgrade soils in these areas and document conditions. Contractor plans to pour concrete starting at
the west end of the lot and continue across to the east to approximately 15 feet past the southwest building corner today.
Contractor plans to pour the remaining approximate 95 by 35 foot section to the east on 09/21/2016. Contractor utilized
a concrete mixer truck with a 10 yard load for the proof roll. The area observed was on the south side of the parking I
drive-thru area. We were not able to observe a proofroll of the entire area as the contractor had already placed some
concrete on the north end of the southwest portion. The majority of the subgrade observed during the proof roll
appeared firm with minimal to no areas of deflection with the exception of two areas where excessive pumping was
noted. The first soft area identified extended from the southwest corner of the building, 27.5 feet west, 12.5 feet east,
and south to the end of the parking area adjacent to the newly poured curb. Recommended to the contractor to remove
and replace the softened soils prior to concrete placement. Contractor informed us that they plan to pour this area today
(09/19/2016) and will attempt to bridge the soft soils by reinforcing the concrete. Informed that they will place a rebar
mat consisting of#7 and #8 rebar running north/south and east/west as additional reinforcement. The second area
where pumping was observed was approximately 6 feet off of the southeast corner of the building and measured
approximately 7 by 14 feet. Contractor informed us that for this area they will remove and replace the moistened soils
and requested that we observe again prior to concrete placement scheduled for Wednesday, 0912112016.
Verbal Communication With: Craig Sorvald with Christofferson Commercial Builders, Inc.
Copies:
Andrew Mc Williams Jared Cohen
Field Observer Reviewed By
H-P~KUMAR
Geotechnical Engineering I Engineering Geology
Materials Testing I Environmental
H-P Kumar
P.O. Drawer 1887
240 Annie Road
Silverthorne, Colorado 80498
Phone: (970) 468-1989
Fax: (970) 468-5891
hpksummit@kumarusa.com
Report of Concrete Cylinder Test Data
Client:
Attn:
Christofferson Commercial Builders, Inc.
Colin Christofferson
3235 Fillmore Ridge Heights
Colorado Springs, CO 80907
Job No.:
Sheet No.:
Lab#:
16-9-159
2 of
525
Date:
2
09/19/2016
Project: West Vail McDonalds Remodel, 2171 North Frontage Road, Vail, Colorado.
Placement Location: Drive-Thru Slab and Western Portion of the South Parking Area Slab
Test Location: Southwest Comer of the Placement Area
Truck: 287 Time Batch: 7:52 am Supplier: Casey Concrete
Ticket: 307603 Time Arrived: 8:40 am Yards: 20 of 50
Mix: Class B/DIP CDOT 20 Time Placed: 9:01 am Method of Placement: Chute
Phxsical Pro12erties: Water/Cement: NA S12ecifications:
Sample Point: End of Chute Water added: -0-Gal. Slump: 3-5 Inches
Time Sampled: 9:04 am Slump: 5 Yi Inches Air Content: +/-4 %
Air Temp.: 55 op Air Content: 6.6 % Water I Cement: 0.45 Max
Concrete Temp.: 67 op Wet Unit Wt.: 139.l pcf Design Strength: 4,000 psi @28 days
Time Cyl. Cast: 9:17 am Initial Cure: Field Field Storage: Cure Box
Diameter: 4 Inches Area: 12.57 Inches2 Max/Min: NA op to NA op
Compressive Strength Data
Age Load Compressive
(Days) Date (lbs.) Strength
(psi)
7 09/26/2016 63,233 5,030
28 10/17/2016 67,199 5,350
28 10/17/2016 69,421 5,520
Hold -------------
Preliminary Observations and I or Testing Results Verbally Reported To: Craig Sorvald with Christofferson Commercial Builders
and Marvin with Casey Concrete
Progress Report:
Copies:
Andrew Mc Williams Jared Cohen
Field Observer Reviewed By
H-P~KUMAR
Geotechnical Engineering I Engineering Geology
Materials Testing I Environmental
Report of Construction Activities
Client:
Attn:
Christofferson Commercial Builders, Inc.
Colin Christofferson
3235 Fillmore Ridge Heights
Colorado Springs, CO 80907
Job No.: 16-9-159
Sheet No.: 1 of
Project: West Vail McDonalds Remodel, 2171 North Frontage Road, Vail, Colorado.
Weather Conditions and Temperature: Overcast, 55° F
Major Equipment on Site: Concrete Truck with 10 Yard Load
Contractor's Construction Activities:
Contractor was preparing to pour the eastern half of the south parking area slab.
H-P Kumar
P.O. Drawer 1887
240 Annie Road
Silverthorne, Colorado 80498
Phone: (970) 468-1989
Fax: (970) 468-5891
hpksummit@kumarusa.com
Date:
2
09/21/2016
Contractor performed a proof roll of the subgrade soils for the eastern half of the south parking area.
H-P Kumar's Site Activities:
As requested, H-P Kumar was on site to test and observe the scheduled fresh concrete placement for the eastern half of
the south side parking area (page 2 of 2). In addition, while on site we were requested to observe a proof roll of the
prepared subgrade soils in this area and document conditions. Contractor plans to pour concrete starting approximately
15 feet past the southwest building comer and continuing to the east to the existing parking area (approximate 95 by 3 5
foot section). Contractor utilized a concrete mixer truck with a 10 yard load for the proof roll. The majority of the
subgrade observed during the proof roll appeared firm with minimal to no areas of deflection with the exception of one
area where excessive pumping was noted. Recommended to the contractor to remove and replace the softened soils
prior to concrete placement. Contractor informed us that they plan to pour this area today and will attempt to bridge the
soft soils by reinforcing the concrete. Informed that they will place a rebar mat consisting of#7 and #8 rebar running
north/south and east/west as additional reinforcement.
Verbal Communication With: Craig Sorvald with Christofferson Commercial Builders, Inc.
Copies:
Andrew Mc Williams Jared Cohen
Field Observer Reviewed By
\~ .
H-P~KUMAR
Geotechnical Engineering I Engineering Geology
Materials Testing I Environmental
' H-P Kumar
P.O. Drawer 1887
240 Annie Road
Silverthorne, Colorado 80498
Phone: (970) 468-1989
Fax: (970) 468-5891
hpksummit@kumarusa.com
Report of Concrete Cylinder Test Data
Client:
Attn:
Christofferson Commercial Builders, Inc.
Colin Christofferson
3235 Fillmore Ridge Heights
Colorado Springs, CO 80907
Job No.: 16-9-159
Sheet No.: 2 of
Lab#: 529
Date:
2
09/21/2016
Project: West Vail McDonalds Remodel, 2171 North Frontage Road, Vail, Colorado.
Placement Location: Eastern Portion of the South Parking Area Slab
Test Location: Northwest Corner of the Placement Area
Truck: 83 Time Batch: 7:10 am Supplier: Casey Concrete
Ticket: 307664 Time Arrived: 8:15 am Yards: 10 of NA
Mix: M02462 Time Placed: 8:46 am Method of Placement: Chute
Physical Pro12erties: Water/Cement: 0.40 SQecifications:
Sample Point: End of Chute Water added: -0-Gal. Slump: 3-5 Inches
Time Sampled: 8:47 am Slump: 5.0 Inches Air Content: +/-4 %
Air Temp.: 52 op Air Content: 4.8 % Water I Cement: 0.45 Max
Concrete Temp.: 70 op Wet Unit Wt.: 142.6 pcf Design Strength: 4,000 psi @28 days
Time Cyl. Cast: 8:58 am Initial Cure: Field Field Storage: Cure Box
Diameter: 4 Inches Area: 12.57 Inches2 Max/Min: NA op to NA op
Compressive Strength Data
Age Load Compressive
(Days) Date (lbs.) Strength
(psi)
7 09/28/2016 60,539 4,820
28 10119/2016 83,729 6,660
28 10/19/2016 85,493 6,800
Hold -------------
Preliminary Observations and I or Testing Results Verbally Reported To: Craig Sorvald with Christofferson Commercial Builders
Progress Report:
Copies:
Andrew Mc Williams Jared Cohen
Field Observer Reviewed By
INDEPENDENT TESTING &
INSPECTION SERVICES INC.
12084 VASEEN CT.
CONIFER, COLORADO 80433
303-674-7560
FAX 303-674-7560
OBSERVATION REPORT
Page 1
... t ' ..
of __ 2
Client: ----~Ku=m~a=r~H~-~P _______ ITIS Job No: 090916-A Date : __ """"'9-..-19 ...... 11"""6 __
Project: ----=M=cD __ o=n-=a=ld=s ______ Location: _____ V'"""""a=il........:C;...;::O'--------
Inspector: -----=D=a...,vi=d-=L.:....;. S=t=u'"""rg=e=on'""------
This report package contains information concerning specific tests and inspections of structural steel
welding, structural bolting, structural sprayed fireproofing, and/or nondestructive testing.
The specific criteria utilized in judging the degree of conformance for each area of inspection are
contained on each individual inspection form.
Also included may be ITIS' "List of Outstanding Discrepancies" (0.D. List). The O.D. List will be
consecutively numbered for each page issued throughout the duration of the project. Each individual
item listed will also be consecutively numbered.
If there are any questions regarding the content of this report, please feel free to contact ITIS at your
convenience.
David L. Sturgeon
President
ICBO Certified Inspector #1138247-85
AWS QC-1 #82122691
Resident Level 111
·. .
INDEPENDENT TESTING &
INSPECTION SERVICES INC.
12084 VASEEN CT.
CONIFER, COLORADO 80433
303-674-7560
FAX 303-674-7560
Page -~2-
INITIAL VISUAL INSPECTION OF WELDING
FIELD REPORT FORM
of
i. I • t
2
~ Inspector: -----=D"""a,...v=id'"""L""'".""'S=tu""'rg='e=on...._ __ _ Job No. ___ 0~9~0~91~6~-A~-Date: -~9~/9~/1~6 __ _
Field Made Welds X Shop Made Welds __ _
Type of Welds Inspected: Fillet X Groove Other ___ _
Type of Component (i.e.: Column, beam girder, moment weld, etc) As Recorded
Applicable Code or Standard: A WS
AREAS OF INSPECTION
LEVEL OR ELEVATION: Roof 3 X $ X W' Reinforcing
GRID LINE LOCATON(S): Just North of A-line. Adjacent to a New Moment Frame
CONDITIONS OF NONCONFORMANCE I INSPECTION RESULTS;
The field welding was not yet completed the time of this inspection; however, the work completed
was found conforming. ITIS will follow-up with inspections when the work is comopleted.
LEVELORELEVATION: ______ R~o~o_f ______ ~9~o=f=S~3.=l _____ ~J=oi=st~R=e=in=f<=or~c=in~g
GRID LINE LOCATION(S): 2.3 and North of A-line
CONDITIONS OF NONCONFORMANCE I INSPECTION RESULTS:
At the referenced locations, three joist require point load reinforcing. The erector and G.C. were
informed
LEVEL OR ELVA TION: Roof Decking
GRID LINE LOCATION(S): Just North of A-line, Adjacent to a New Moment Frame
CONDITIONS OF NONCONFORMANCE I INSPECTION RESULTS:
The decking is in place and is screwed down per the requirements; however, the welded side
has not been completed. ITIS will Follow-up when complete.
'.· .
INDEPENDENT TESTING &
INSPECTION SERVICES INC.
12084 VASEEN CT.
CONIFER, COLORADO 80433
303-674-7560
FAX 303-674-7560
OBSERVATION REPORT
Client: ------'"K=u=m=a,,_r .:...:.H-_,_P _______ ITIS Job No: 090916-A
Project: ------'"M=c=D=o""'na=ld=s"-------Location: ____ _,V..,.a=il co
Inspector: ----'D=a=v=id:....:L=·-=S=tu"""rg:a.::e=o.:..:..n ___ _
.. J ••
Page 1 of __ 3
Date : __ _..91,,..2...:..:.11...!..:16"---
This report package contains information concerning specific tests and inspections of structural
steel welding, structural bolting, structural sprayed fireproofing, and/or nondestructive testing.
The specific criteria utilized in judging the degree of conformance for each area of inspection
are contained on each individual inspection form.
Also included may be ITIS' "List of Outstanding Discrepancies" (O.D. List). The O.D. List will be
consecutively numbered for each page issued throughout the duration of the project. Each
individual item listed will also be consecutively numbered.
If there are any questions regarding the content of this report, please feel free to contact ITIS at
your convenience.
David L. Sturgeon
President
ICBO Certified Inspector #1138247-85
AWS QC-1 #82122691
Resident Level 111
• •
INDEPENDENT TESTING &
INSPECTION SERVICES INC.
12084 VASEEN CT.
CONIFER, COLORADO 80433
303-67 4-7560
FAX 303-674-7560
Page -~2-
INITIAL VISUAL INSPECTION OF WELDING
FIELD REPORT FORM
of 3
Inspector: ----=D=av=id=L=.'-"S,_tur~ge=o=n __ _ Job No. ----=0~90=9 ...... 16=--.._.A._____ Date: -~9~/2~1/~1~6 __ _
Field Made Welds X Shop Made Welds __ _
Type of Welds Inspected: Fillet X Groove Other ___ _
Type of Component (i.e.: Column, beam girder, moment weld, etc) As Recorded
Applicable Code or Standard: A WS
AREAS OF INSPECTION
LEVEL OR ELEV A TION: Roof 5 ofS3.0 L-Bracing
GRID LINE LOCATON(S): North of A-line
CONDITIONS OF NONCONFORMANCE I INSPECTION RESULTS;
The L-bracing has been installed, and the field welding was found confonning.
LEVELORELEVATION: --~R=o=o~f _______ ~5~o=f~S=3.=0 __ ~S=tru~ctur~a~IB=o=l=re=d~C=o=nn=e=ct=io~ns
GRID LINE LOCATION(S): A-line
CONDITIONS OF NONCONFORMANCE I INSPECTION RESULTS:
The l" A-325 bolts were installed and hand tensioned. The installation was judged as confonning.
LEVEL OR ELVATION: Roof 5 of S3 .1 and 2 of S3. l Penetrations & Joist Reinforcing
GRID LINE LOCATION(S): -------------------------
CONDITIONS OF NONCONFORMANCE I INSPECTION RESULTS:
The field welding of the roof penetrations was found confonning. Three joist required web
reinforcing due to top flange point-loading. The installation and field welding were found
confonning.
.. .-.
INDEPENDENT TESTING &
INSPECTION SERVICES INC.
12084 VASEEN CT.
CONIFER, COLORADO 80433
303-674-7560
FAX 303-674-7560
Page 3
INITIAL VISUAL INSPECTION OF WELDING
FIELD REPORT FORM
of 3
Inspector: David L. Sturgeon Job No. 090916-A Date: 9/21/16
Field Made Welds X Shop Made Welds X
Type of Welds Inspected: Fillet X Groove Other __ _
Type of Component (i.e.: Column, beam girder, moment weld, etc) -----~A~s~R~ec~o~rd~ed ______ _
Applicable Code or Standard: A WS
AREAS OF INSPECTION
LEVEL OR ELEVATION: Roof Decking
GRID LINE LOCATON(S): North of A-Line
CONDITIONS OF NONCONFORMANCE I INSPECTION RESULTS:
The decking was viewed and found welded and screwed down per the specifications and was found
conforming.
LEVEL OR ELEV A TION:
GRID LINE LOCATION(S):
CONDITIONS OF NONCONFORMANCE I INSPECTION RESULTS:
LEVEL OR ELV ATION:
GRID LINE LOCATION(S):
CONDITIONS OF NONCONFORMANCE I INSPECTION RESULTS: