HomeMy WebLinkAboutHelical Pier Report.pdf H-P KU mAR5020 County Road 154
\. Glenwood Springs, CO 81601
Geotechnical Engineering I Engineering Geology Phone: (970)945-7988
Materials Testing I Environmental Fax: (970)945-8454
Email: hpkglenwood@kumarusa.com
Office Locations: Denver(HQ), Parker, Colorado Springs, Fort Collins, Glenwood Springs, Summit County, Colorado
December 27, 2017
Paul Graf
528 Potato Patch Drive
Vail, Colorado 81657
Pgraf32 @ gmail.com
Project No. 17-7-784
Subject: Observation of Excavation and Review of Helical Pier Installation, Proposed
West Deck Addition to Existing Residence, 758 Potato Patch Drive, Vail,
Colorado
Dear Paul:
As requested, a representative of H-P/Kumar observed the excavation at the subject site on
October 26, 2017 to evaluate the soils exposed for foundation support. We have also reviewed
the helical pier install records for partial foundation support of the deck. The findings of our
observations and recommendations are presented in this report. The services were performed in
accordance with our agreement for professional engineering services to you dated October 23,
2017. We previously observed the foundation excavation for a new driveway retaining wall at
the site and submitted our findings in a report dated November 6, 2017, Project No. 17-7-784.
The deck will be attached to the west side of the residence and be supported on isolated columns.
The columns were originally designed to be supported entirely on helical piers with working
design axial capacities of from 5 to 8 kips for the individual columns. Based on our observations
of the soils exposed in the open excavations prior to the helical pier installation, we
recommended spread footing pads be used to support most of the columns away from the
residence where natural coarse granular soils were exposed at excavation grade. The footing
pads were sized using an allowable soil bearing pressure of 2,000 psf.
At the time of our October 23 site visit, the foundation excavations for the thirteen column
support areas for the deck had each been cut one level from about 21/to 5 feet below the
adjacent ground surface. The soils exposed in the bottom of the excavations consisted primarily
of relatively dense, silty sand and gravel with cobbles. In the three excavations nearest the
residence and at the one at the northwest, existing foundation backfill consisting of generally
medium dense, silty sand and gravel with cobbles was exposed at subgrade. Depth of the fill
Paul Graf
December 27, 2017
Page 2
was not determined but estimated to be down to existing residence footing bearing elevation,
about 4 to 5 feet. No free water was encountered in the excavations and the soils were slightly
moist to moist.
Subsequently, Great Divide Corporation installed helical piers consisting of single helix, 11
square shaft Heli-piles in about half(six) of the excavations nearest the residence. Based on
information provided by Great Divide Construction, the pier depths ranged from about 2 to 71/2
feet below the bottoms of the excavations with the deeper piers typically in the fill areas nearest
the residence. The piers achieved either torque (4 to 7 pin) shear refusal, or penetration refusal
likely on a large cobble or a boulder. At this time, we recommended the piers be used as well as
pier caps placed on the piers, with spread footing pads in the natural soil areas designed for an
allowable soil bearing pressure of 2,500 psf, and the pile caps/footing pads have a minimum
width of 3 feet. Based on the plans dated December 13, 2017 by KRM Consultants, this was
done.
We believe the piers as installed and the exposed soils at excavation grade in the column
excavation areas have adequate capacity to support the 5,000 to 8,000-pound individual axial
design column loadings for the deck supports. There could some differential settlement between
the deck supports and with respect to the existing residence which should be considered in the
design. Prior to the footing pad and/or pier cap construction, all loose disturbed soils should be
removed. The bearing soils should be protected against frost and concrete should not be placed
on frozen soils. The footing pads and pier caps should be provided with adequate soil cover
above their bearing elevations for frost protection.
The foundation backfill should be compacted to at least 90% of standard Proctor density (SPD)
at a moisture content near optimum (and to at least 95% SPD in pavement areas) and have the
surface graded to prevent ponding within at least 10 feet of the new deck and existing building
foundations.
The recommendations submitted in this letter are based on our observation of the soils exposed
within the foundation excavations and the information provided to us regarding the helical pier
installation, and do not include subsurface exploration to evaluate the subsurface conditions
within the loaded depth of foundation influence. This study is based on the assumption that soils
beneath the excavations have equal or better support than those exposed. The risk of foundation
H-Pk-KUMAR
Project No. 17-7-784
Paul Graf
December 27, 2017
Page 3
movement may be greater than indicated in this report because of possible variations in the
subsurface conditions. It is possible the data obtained by subsurface exploration could change
the recommendations contained in this letter.
If you have any questions or need further assistance, please call our office.
Sincerely,
fo(0
40,
H-P:KUM •' o ,3.
&loos,
7 r
is IZAT
David A. Young, P E: , ".gyp y.Z -e7�,s•
D14.
Crag
cc: KRM Consultants—Tim Fiennum(tim@krmconsultants.com)
H-P*KUMAR
Project No. 17-7-784