HomeMy WebLinkAboutScope of Work - CJ - TOV Building.pdf From: Rick Geddes
To: Chris Jarecki(CJ)(cjarecki(awailgov.com)
Subject: Permit for replacement of LiteTouch equipment on Beaver Dam Road
Date: Wednesday,December 27,2017 3:36:00 PM
Attachments: image001.pnq
Hi CJ,
Thanks for your explanation of when the town requires an electrical permit. Our scope of work for
this consists of the following:
• Disconnect all remote dimming conductors and remove existing dimming modules in
LiteTouch panels within the garage area.
• Install Lutron panel inserts, which are set up to separate the 120-volt lighting loads from the
low voltage control wiring entering each enclosure.
• Sort the 120-volt switch-leg conductors and terminate the existing lighting conductors on
module terminals that are based on efficient layout of loads.
• Remove LiteTouch keypads and replace these with new Lutron keypads in all locations of the
home.
• Remove and replace system processor, create programming in Lutron software and upload
into the processor.
• Test and adjust all dimmed loads. Reprogram as necessary.
Since we are competitively bidding this against a low voltage A-V contractor, I thought it may be an
advantage for us to pull an electrical permit and have the TOV inspect our work. Many of our clients
like to have this extra assurance that all work is performed to minimum NEC standards. Please let
me know if you would consider having us perform the work in this way.
Thanks,
Rick Geddes
Cell 970-376-6020
cc,iikjliElz 4,
White River Electric, Inc.
PO Box 1118
Avon, CO 81620
v. 970-949-1403
f. 970-514-7115