HomeMy WebLinkAboutSI Report - Excavation.pdf cESARE, ,_. INC. Geotechnical Engineers&Construction Materials Consultants Inspection date December 21, 2017 Letter prepared January 9, 2018 Mr. Gary Kendall Beck Building Company P.O. Box 4030 Vail, CO 81658 Subject: Open Excavation Observation Galvin Residence Vail Rowhouses Units 9 and 10 Gore Creek Drive Vail, Colorado Cesare Project No. 14.5012 Dear Mr. Kendall: Cesare, Inc. (Cesare) personnel visited the site to conduct an open excavation observation for the proposed continuous footing foundation for the Galvin Residence renovation. The continuous footing foundation is located on the east side of the party wall for Units 8 and 9 at an elevation of 8,165.75 feet. Soils encountered at the proposed bottom of the footing elevation were native medium dense sand, with silt and gravel, with a trace of cobbles, low to no plasticity, slightly moist, and reddish brown in color. Random T-probe strikes and relative nuclear densities indicated the subgrade was medium dense. Prior to leaving the site, Cesare recommended to you that the native soils be compacted again prior to concrete placement with a jumping jack or walk behind sheepsfoot. The additional compaction will help to minimize potential settlement. Cesare also recommended the soils be covered and heated prior to concrete placement. It is Cesare's opinion, the subgrade soils exposed for the base of the continuous footing foundation will support a foundation system designed for a maximum allowable soil bearing pressure of 3,000 pounds per square foot (psf), with a low risk of movement. Refer to Photos 1 and 2. Contact us with any questions or comments regarding this information. Sincerely, .Fpv R E 4 #'0,t £0.e.4.,,... CESARE, INC. '/'yrs °'••� '�' <`' ',, ,ii.)1..,04:41L: �',, °• 1/9/2018 /c�J (7— 7 i Ian M. Cesare William H. Koechlein, P.E. Summit Office Manager Senior Geotechnical Consultant Corporate Office: 7108 South Alton Way, Building B Centennial,CO 80112 Centennial Office 0 Frederick Office Silverthorne Office Crested Butte Office Phone 303-220-0300 www.cesareinc.com CESARE,INC. 101 11 efi . i ..„-ii - ,\ Y ' N . - '4• .\ . . , ....,, ._. ,., „.,„,.. _� \ . 1. fit• • Photo 1. Overview looking north at open hole excavation and initial demolition of Unit 9, and preparation of soils for foundation footing for Units 8 and 9 party wall. R : 1t �E. - 1 , ' ' QI - , f, -- I ,,, -- • -4. _ vi : - �. . .. — ,A . . . . .. . ,,, _ , • , . _ , , . ,. • Photo 2. View looking north along party wall for Units 8 and 9. Soil elevation for continuous footing foundation is about 8,165.75 feet. 14.5012 Galvin Residence Open Excavation Observation(inspected 12.21.17)Letter 01.09.18 2