Project: West Vail Sewer Main Improvements
Pre-PreConstruction Meeting (District Office 846 Forest Road)
☒ Meeting Minutes ☐ Construction Observation Report
To:
Eagle River Water & Sanitation Dist.Date:4/9/2018 MonAttn:Jeff SchneiderSite Visit No:N/A
Contractor:Western PipewayTime:3:00-6:00 PMProject Name:West Vail SewerWeather:Mostly SunnyContract No:18.15.018Temp Range:50 °F
Attendees:
Harry Baum (WPW)
Jeff Schneider (ERWSD)
Romeo Baylosis (High Country Engineering, Inc.)
Topics:
Award
Insurance and final amounts
Harry to contact bonding company
Contracting. Separate agreements for District and Casa. Notice of Award by District Tues/Wed.
Staging
Use Kinnickinnick Road as loop
Conoco. Meet with Peter and Randy.
Casa north of tennis court to be evaluated (quantity not included in bid docs; verify per Conoco service redesign). West side of parking lot 30’x40’ approx.
VR cat facility 10 parking spots near District office. Truck and trailer.
Dewatering at end of Intermountain west guardrail. 4” trash pump and weir. CDPHE >1.0 ac; Adler
Schedule. Startup 5/21. Approximate 4 month duration. Goal to be complete by Labor Day.
PreConstruction Meeting Date
Set up meeting with Conoco & TOV for Fri 4/13
Precon TBD
Potholing before milling
Badger from Rifle. Need surveying. Is 36 hours $12,000 enough for all?
Conoco I-70 main
(2) Raw water locations. 3’ horizontal separation.
Intermountain 36” & 24” CMPs
West Gore Creek Drive water main
Bypass pumping will be allowed overnight. 4” trash pumps, diesel sound attenuated pump. Aspen 4 MGD 8” & 12” pumps.
Mh0475 PR 6’ dia. manhole. Substitute 5’ or 4’. Need 10’x10’ shoring box, water stops, plugs, stub out pipes, flowfill.
WPW using HP Kumar. JS in contact with HP.
Equipment
55 ton excavator, 366, 430, 11’ wide, 10’x10’ bedding box, 54” and 30” buckets w/ quick coupler, vibratory plates, stack (2)-8’ boxes.
TOV
Need Leonard input on Traffic Control and Staging. Flaggers, 2 traffic signals. HB contact ongoing.
RB to reach out to Chad and Gregg
Chad questions
Electric undergrounding, flowfill quantity (timing for hydration), ¾” screened rock allows compaction/chocking.
Vault location field fit with Holy Cross
IGA
Gregg questions
RPM Gore Valley Trail schedule. Roby Forsythe and Marie Christine.
TOV buses. JS and Diana preparing public relations.
Additional Remarks & Follow Up Items:
Bond certificates
TOV Public Way Permit
Project: West Vail Sewer Main Improvements
Early coordination meeting, Conoco, District Office 846 Forest Road)
☒ Meeting Minutes ☐ Construction Observation Report
To:
Eagle River Water & Sanitation Dist.Date:4/13/2018 FriAttn:Jeff SchneiderSite Visit No:1Contractor:Western PipewayTime:9:00 AM-12:00 PMProject Name:West Vail Sewer
Main ImprovementWeather:Mostly SunnyContract No:18.15.018Temp Range:28 °F
Attendees:
Harry Baum (WPW)
Jeff Schneider (ERWSD)
Chad Salli, Leonard Sandoval (TOV)
Peter, Randy (Conoco)
Romeo Baylosis (High Country Engineering, Inc.)
Topics:
Conoco
Sewer pipe replacement, new asphalt.
Staging area, temp staging for Class 6 and pipe bedding.
VR pipes and manholes
Processing and screening in work area
Vehicle circulation/deliveries/loader. Backing in. Cars can be moved.
Inspection/location of service line. JS evaluating PSI locating.
Sunday flaggers likely needed.
Conoco closed 5-10 days per Randy; dispenser upgrade. Electric work through building.
Late June trenching; pave later. MH0980 PR to MH0497 PR and Conoco service 1 week duration.
Peter: Asked about drainage improvements, additional asphalt, how many people? 7 person crew plus flaggers. Provide fleet diesel rate.
Vail Garage & Conoco additional insured.
Casa del Sol trenching/staging/access to buildings
LS & CS open to access through western trench corridor near bike path.
Far northwest corner of parking lot has light pole not on survey.
Intermountain - S. Frontage Rd traffic control, CIP MH to next MH
Coordinate water main depressurize with VR and District. WSU installed 25-30 years ago.
Milling with drum roller to maintain millings, windrow. Millings against guardrail with erosion control.
Temp paving will be needed for vehicles and bike path.
JS evaluating extra mobe.
Dewatering tank proposed at pull off at western end guardrail.
Conoco/West Gore Creek section traffic control and closure.
Flaggers during daylight, traffic signals otherwise.
MH0980 1 day duration. Queue to WV Roundabout. Evaluate night work.
WGC Drive 3 day duration. Close far side of bridge for reroute.
General schedule
Potholing
Milling
Start Intermountain first
SS sewer
Shallows west. CS to allow field adjustments to vaults per HC/JVroom.
Shallows east
Complete Intermountain around 6/21
Conoco – West Gore creek closures
Casa Del Sol Sewer mid-July. Storm sewer and paving to follow.
Completion Labor day
Public Relations – notification
Diane working with Suzanne
Letters to all accounts in intermountain
Newspaper/radio
Message boards/timing?
Other: Postal, trash
Notify 2005 WGC Dr residents
LS will need:
CDOT SUPermit.
CDPHE stormwater permit. RB estimates 55000+12000+6000 SF=74000 SF=1.7 ac. State enforcing more TOV projects this year.
Need to send TOV Planning John Spence 2 trees to be removed/replaced at Casa.
CDOT
District will remain Permittee.
HB proposing Type 4 barriers. Type 7 typical on interstate and ramps. 35 mph posted, 15-25 operating.
CS emailed traffic counts to JS from August.
Need to send signal spacing and timing to CDOT Joel (likely Brian Killian review in Traffic Dept.) 250’ possible. Modify as needed, consult CC Enterprises.
IGA
General bid items items separated for mobe and traffic control. HB one survey line item.
RB to revise Exhibit A for Intermountain cost sharing of Items 16, 17, 19, 20 & 21 related to earthwork and paving. Estimated 80/20% split. Approx. $46K back to District.
Other
HP Kumar contract in progress.
HB and Jim Boyd in the Village 30’ deep sewer Village Center Dr. in front of La Tour.
HB 3 water quality vaults in bike path from Matterhorn to Conoco; ~9-10 years ago.
Additional Remarks & Follow Up Items:
Set up meeting Tues/Wed with LS to review WPW revised MHT. RB out on family leave Tues afternoon for 1.5-2 weeks.
HB needs overall paving exhibit.
Bypass pumping.
Set up meeting with Casa for WPW introduction and project scope. Gutter/downspout connections to storm with coordination for electrical/heat tape scope.
Follow up with Gregg Barrie for Gore Valley Trail PreConstruction Meeting. Estimated 4/18-4/20 for early May construction start.
RB to issue stamped CDs and compile Project Manual.