HomeMy WebLinkAboutRB-draft West Vail Sewer Main Construction Meeting Minutes 5-23-2018.docxERWSD – West Vail Sewer Main Improvements Project
Weekly Meeting Minutes 5/23/2018
ACTION ITEMS
WPW will pothole retaining wall geogrid in Holy Cross trench area using conventional excavation methods.
Harry will provide 3-week schedules for review/discussion at subsequent meetings.
Romeo will provide and maintain submittal log.
Jeff will add Leonard to future progress meeting invites.
Jeff will set up materials testing.
Romeo to notify Peak about minor design changes for re-staking.
Jeff to follow up on painting Manholes
Jeff to locate Conoco service line
Jeff to coordinate with ECO Transit
1. ATTENDANCE
Harry, Jeff, Romeo, Chad
Anyone else? Add Leonard to subsequent meetings
2. APPROVAL OF PREVIOUS MINUTES: Final Preconstruction Meeting Minutes sent out.
RB Observation Report from 5/17 site visit.
3. CONTRACTOR'S SCHEDULE STATUS REPORT
3a. DETAILED DISCUSSION OF THE PRESENT WEEK CONSTRUCTION SCHEDULE
Intermountain asphalt cut today
Will cut HCE asphalt tomorrow, need to verify extent at west end. East end is dependent on retaining wall. Possible pohtholing to verify geogrid. Conventionally excavate test pit
to 4’ depth. Will pothole two locations to determine geogrid location
Asphalt removal today, excavate for MH0475 PR tomorrow. Need 5-10’ of pipe with bell. Cast in place concrete base and reinforcement discussed with Jesus. Rebar to be bent on site.
Flow fill 8am Tuesday morning, 5’ of flowfill. Install first barrel section and start backfilling Tuesday.
Material appears to be suitable, screen out > 4”.
Traffic control for the weekend – flaggers during the day, shorten closure at night.
Manholes to be delivered Thursday. Pipe is coming from Nevada.
3b. REVIEW AND DISCUSSION OF THE CURRENT 3-WEEK LOOK AHEAD SCHEDULE
Pipe and manholes as production allows.
Harry will bring 3 week schedules
Talked about backfilling MH475 area and narrowing the barricaded area, Harry agreed that we could do that once road base is completed. Current approximate 1200’ length.
Haul from JP Trucking yard in Wolcott primarily, Plan B is Western Slope aggregate in Silt.
Potential for structural material needed at Hospital and Lionshead Parking Structure.
4. SUBMITTALS/SHOP DRAWING STATUS REPORT
Asphalt, concrete complete yesterday
Pipes/MHs yesterday
Romeo will provide/maintain submittal log
5. MATERIALS TESTING
Proposed off site import proctor – import seems acceptable, provided that rocks > 4” are screened/crushed
On site proctor – Thursday
Concrete Testing – Friday – Class D, 8 cy of mix. Jeff will set up testing.
Next week? - Plan on Tuesday next week compaction testing of import material.
6. CHANGES IN THE WORK
Redesign based on potholing
24” SS conflict at approx. 5+51. Lower inverts in MH 0700 to 83.55 in and 83.35 out. Romeo notify Peak, no change in rim elevation grade.
West Gore Creek Dr. proposed 8” sewer should cross above existing 8” water. Raise MH 0435 invert 1.05’ to 7925.55 (pipe slope change from 3.4% to 2.5%)
Conoco area – possibly omit MH 0495, cast in place at 2+00. Eliminate bypass pumping.
Identify/pothole existing 12” DIP sewer going north out of MH 0520.
HCE trench location/retaining wall conflict
Other issues? – asphalt thickness considerably higher than plan, asphalt replacement quantity stays the same.
Relocate HCE vault at approx. 10+54
Discussed asphalt replacement. Possibly reduce limits to exclude north lane line. Mill and overlay out of wheel path.
Comcast may add conduit to trench.
Unclassified Excavation load counts for end dump and tandem. 1.8 tons/CY assumed.
Import Suitable material per ton. Need weight tickets, will only be for Class 6, will not have weight tickets for other class 2 material.
7. AS-BUILTS STATUS
Surveyed as-builts required per specs
8. PAY REQUESTS
Assume one pay request per month, Engineer has 10 days to review, Owner has 10 days to pay. Refer to General Conditions Section 15.01.
5% retainage withheld on all pay applications.
9. OLD BUSINESS
Manhole Coatings – 475 lined in situ, other MHs lined in GJ.
Jeff S. to circle back with Jake on painting. Consider quicker curing alternative.
Action items from Preconstruction Meeting:
Jeff S. to set up recurring bi-weekly construction progress meetings at ERWSD offices - COMPLETE
Harry B. to set up construction water with ERWSD customer service – COMPLETE
Jeff S. set up all testing with Lena at HP Kumar – COMPLETE; ONGOING
Jeff S. arrange to locate Conoco service from cleanouts - OUTSTANDING
Chad S. will look at overnight traffic counts on Frontage Rd - COMPLETE
Jeff S. talk to Leonard about emergency services coordination - COMPLETE
Jeff S. coordinate with ECO Transit - OUTSTANDING
Romeo B. to complete submittal reviews –COMPLETE
Jeff S. follow up with Flowfill testing requirements – COMPLETE, NO TESTING REQUIRED
10. NEW BUSINESS
Memorial Day Weekend – will shorten lane closure length, flaggers during the day, lights at night.
Rebar at MH 0475 – jeff talked to Jesus today, some details in pipe penetrations to work out.
Pipeline/MH testing – will be Manhole to Manhole. Jesus will work with Jeff directly, jeff to involve ERWSD field inspectors.
JS schedule next week. RB to coordinate with District field personnel for observation, daily logs, and reports.
11. SAFETY
ERWSD Safety Coordinator, Dan.
Traffic Control
Trench shoring/access
12. OTHER BUSINESS
Casa staging – not for now. RB coordinating with Western Pipeway and Holmes Murphy.
ERWSD staging – keep what is coned off.
Gore Valley Trail open this weekend with roadbase surface. Gregg Barrie and Elam anticipating paving next week.