HomeMy WebLinkAboutMicropilesReport(18-6523.Micropiles.0025).pdf Client: Chad Salli
Town of Vail
GROUND 1309 El 81rn Drive
ENGINEERING
Red Sandstone Parking Garage
Report Date: Aug 2,2018 Work Order No.: 18-6523.Micropiles.0025;ver: 1
Work Order Date: Aug 1,2018 Reviewed by: Shane Sorensen
Micro•files
General Contractor: Haselden Performed by: Chris Leeper
Installation Contractor: Schnabel
Installation Equipment: 2 x Hi tte HBR 604 Crawling Hydraulic Drilling Machine
Placement Location: Micropiles for Group A,B,and D
On-Site Notifications
Name Company
Tom Highsmith Haselden Construction
Locations and Plan Dimensions
Micropile Plan/Contractor Micropile Location Plan Diameter(in) Min.Length(ft) Min.Bedrock Plan Top of Pile
No. Micropile No. Penetration(ft) Elevation(ft)
14 A64 A.212.1 6 41 - 8196.7
15 A82 A.2/5.4 6 41 - 8196.7
16 A17 A.0/4.2 6 41 - 8196.7
17 B1 A.711.9 6 41 - 8196.7
18 B3 B.0/1.9 6 26 - 8196.7
19 A112 A.013.7 6 41 - 8196.7
20 A10 A.013.4 6 41 - 8196.7
21 D35 D.1/1.9 6 41 - 8196.7
Excavation Measurements (ft)
%Vertical Reinforcing Micropile Existing Top of Overburden Top of Excavation Bottom Depth in Pile
Top of Footing p Ground Pile Bedrock of Pile
N4 No. Elevation Elevation Depth Elevation Depth Elevation Bedrock Length
/
T Y 14 8196.2 8196.7 - - 41.3 8154.9 - 41.8
IF•
15 8196.2 8196.7 - - 41.1 8155.1 - 41.6
Bottom of Footing- 16 8196.2 8196.7 - - 41.0 8155.2 - 41.5
Casing
Length r 17 8196.2 8196.7 41.4 8154.8 41.9
Top of Bedrock v 18 8196.2 8196.7 - - 26.5 8169.7 - 27.0
J
i /"~ v 19 8196.2 8196.7 - - 41.1 8155.1 - 41.6
a
Casing °
1 i 20 8196.2 8196.7 - - 41.3 8154.9 - 41.8
l
Reinforcing _fr21 8196.2 8196.7 -
- 41.1 8155.1 - 41.6
Centralizer
Grout 11
I
P.,. +-Micropile Diameter
Results apply only to the specific items and locations referenced and at the time of testing, observations or special inspections. This report should not
be reproduced,except in full,without the written permission of GROUND Engineering Consultants, Inc.
www.groundeng.com
Englewood I Commerce City I Loveland I Granby I Gypsum Page 1 of 3
Client: Chad Salli
Town of Vail
GROUND 1309 El 81rn Drive
ENGINEERING
Red Sandstone Parking Garage
Report Date: Aug 2,2018 Work Order No.: 18-6523.Micropiles.0025;ver: 1
Work Order Date: Aug 1,2018 Reviewed by: Shane Sorensen
Micro•iles
Excavation Conditions
Micropile Drill Start Drill Finish Top of Casing Casing Casing Deviation Excavation Ground
No. Time Time Elevation(ft) Length(ft) Diameter(in) from Center Plumbness Cleanliness Water Depth
(ft)
14 7:21 AM 7:21 AM 8196.2 6.0 6 Conforms Conforms Conforms 18
15 8:18 AM 8:56 AM 8196.2 6.0 6 Conforms Conforms Conforms 20
16 10:20 AM 11:03 AM 8196.2 6.0 6 Conforms Conforms Conforms 15
17 10:38 AM 11:16 AM 8196.2 6.0 6 Conforms Conforms Conforms 25
18 1:20 PM 1:35 PM 8196.2 6.0 6 Conforms Conforms Conforms 18
19 1:30 PM 2:09 PM 8196.2 6.0 6 Conforms Conforms Conforms 20
20 3:29 PM 4:10 PM 8196.2 6.0 6 Conforms Conforms Conforms 15
21 3:40 PM 4:36 PM 8196.2 6.0 6 Conforms Conforms Conforms 20
Reinforcing Steel
Required Vertical Actual Vertical
Required Vertical Actual Vertical Required Splice Actual Splice
Micropile No. Reinforcement Reinforcement Reinforcement Reinforcement Length(in) Length(in)
Length(ft) Length(ft)
14 Threaded Bar/#18 Threaded Bar/#18 41 41.8 - -
15 Threaded Bar/#18 Threaded Bar/#18 41 41.6 - -
16 Threaded Bar/#18 Threaded Bar/#18 41 41.5 - -
17 Threaded Bar/#18 Threaded Bar/#18 41 41.9 - -
18 Threaded Bar/#14 Threaded Bar/#18 26 27 - -
19 Threaded Bar/#18 Threaded Bar/#18 41 41.6 - -
20 Threaded Bar/#18 Threaded Bar/#18 41 41.8 - -
21 Threaded Bar/#18 Threaded Bar/#18 41 41.6 - -
Grout Placement
Micropile No. Grout Placement Grout Placement Water Depth Before Theoretical Grout Estimated Grout Method of Grout
Start Time Finish Time Grout Placement(in) Volume(ft) Volume(ft) Placement
14 9:05 AM 9:30 AM 0 8.2 Tremmie
15 8:40 AM 8:52 AM 0 8.2 Tremmie
16 11:40 AM 10:50 AM 0 8.1 Tremmie
17 11:56 AM 12:01 PM 0 8.2 Tremmie
18 1:55 PM 2:10 PM 0 5.3 Tremmie
19 2:31 PM 2:42 PM 0 8.2 Tremmie
20 4:20 PM 3:35 PM 0 8.2 Tremmie
21 4:54 PM 5:08 PM 0 8.2 Tremmie
Results apply only to the specific items and locations referenced and at the time of testing, observations or special inspections. This report should not
be reproduced,except in full,without the written permission of GROUND Engineering Consultants, Inc.
www.groundeng.com
Englewood I Commerce City I Loveland I Granby I Gypsum Page 2 of 3
Client: Chad Salli
Town of Vail
GROUND 1309 El 81rn Drive
ENGINEERING
Red Sandstone Parking Garage
Report Date: Aug 2,2018 Work Order No.: 18-6523.Micropiles.0025;ver: 1
Work Order Date: Aug 1,2018 Reviewed by: Shane Sorensen
Micro•files
Comments
Micropile No. Description of Soil Location of Obstructions Comments
14 Silty,Clayey SAND w/Gravel - -
15 Silty,Clayey SAND w/Gravel - -
16 Silty,Clayey SAND w/Gravel - -
17 Silty,Clayey SAND w/Gravel - -
18 Silty,Clayey SAND w/Gravel - -
19 Silty,Clayey SAND w/Gravel - -
20 Silty,Clayey SAND w/Gravel - -
21 Silty,Clayey SAND w/Gravel - -
Photos
Y[
i.o.;,...._k 1 rh.4 . • ._z , .
•
l -
•
—; - I — I
•,.. ,_ . l
_, iii .: .ii-4:41,
_.....r, . . , '-#1••-- — ti
`r �* r — -
•
Micropile Micropile
Results apply only to the specific items and locations referenced and at the time of testing, observations or special inspections. This report should not
be reproduced,except in full,without the written permission of GROUND Engineering Consultants, Inc.
www.groundeng.com
Englewood I Commerce City I Loveland I Granby I Gypsum Page 3 of 3