HomeMy WebLinkAboutMicropilesReport(18-6523.Micropiles.0026).pdf Client: Chad Salli Town of Vail GROUND 1309 Elkhorn 81rn Drive ENGINEERING Red Sandstone Parking Garage Report Date: Aug 3,2018 Work Order No.: 18-6523.Micropiles.0026;ver: 1 Work Order Date: Aug 2,2018 Reviewed by: Shane Sorensen Micro•iles General Contractor: Haselden Performed by: Chris Leeper Installation Contractor: Schnabel Installation Equipment: 2 x Hiltte HBR 605 Hydraulic Crawling Drilling Machines Placement Location: Micropiles from Groups A, B,C and D Comments: On-Site Notifications Name Company Tom Highsmith Haselden Construction Locations and Plan Dimensions Micropile Plan/Contractor Micropile Location Plan Diameter(in) Min.Length(ft) Min.Bedrock Plan Top of Pile No. Micropile No. Penetration(ft) Elevation(ft) 22 All A.0/3.5 6 41 - 8196.7 23 D36 0.0/2.0 6 41 - 8195.4 24 A16 A.0/4.2 6 41 - 8196.7 25 B5 B.2/1.9 6 41 - 8195.4 26 C3 B.8/0.9 6 26 - 8195.4 27 A70 A.0/3.3 6 41 - 8196.7 28 C9 C.1/0.9 6 26 - 8195.4 29 A75 A.2/4.2 6 41 - 8196.7 30 D33 D.1/0.9 6 26 - 8195.4 Excavation Measurements (ft) Vertical Reinforcing Micro ile Existing Top of Overburden Top of Excavation Bottom Depth in Pile Top of Footing p Ground Pile Bedrock of Pile p \a No Elevation Elevation Depth Elevation Depth Elevation Bedrock Length A / 22 8196.2 8196.7 - - 41.2 8155.0 - 41.7 /* 23 8194.9 8195.4 41.8 8153.1 42.3 Bottom of Footing---/ f 24 8196.2 8196.7 - - 41.0 8155.2 - 41.5 !1 Casing Length 25 8194.9 8195.4 - - 41.3 8153.6 - 41.8 Top of Bedrock j J 26 8194.9 8195.4 - - 26.5 8168.4 - 27.0 { / i r o 27 8196.2 8196.7 - - 41.1 8155.1 - 41.6 Casing • 28 8194.9 8195.4 - - 26.2 8168.7 - 26.7 Reinforcing 29 8196.2 8196.7 - - 41.3 8154.9 - 41.8 Centralizer -___-' 30 8194.9 8195.4 - - 26.6 8168.3 - 27.1 Grout------- '41filmili I 14- r -M Micropile Diameter Results apply only to the specific items and locations referenced and at the time of testing, observations or special inspections. This report should not be reproduced,except in full,without the written permission of GROUND Engineering Consultants, Inc. www.groundeng.com Englewood I Commerce City I Loveland I Granby I Gypsum Page 1 of 3 Client: Chad Salli Town of Vail GROUND 1309 El 81rn Drive ENGINEERING Red Sandstone Parking Garage Report Date: Aug 3,2018 Work Order No.: 18-6523.Micropiles.0026;ver: 1 Work Order Date: Aug 2,2018 Reviewed by: Shane Sorensen Micro•iles Excavation Conditions Micropile Drill Start Drill Finish Top of Casing Casing Casing Deviation Excavation Ground No. Time Time Elevation(ft) Length(ft) Diameter(in) from Center Plumbness Cleanliness Water Depth (ft) 22 7:45 AM 9:15 AM 8196.2 6.0 6 Conforms Conforms Conforms 20 23 7:51 AM 8:59 AM 8194.9 6.0 6 Conforms Conforms Conforms 25 24 10:43 AM 11:31 AM 8196.2 6.0 6 Conforms Conforms Conforms 15 25 11:08 AM 11:52 AM 8194.9 6.0 6 Conforms Conforms Conforms 20 26 1:24 PM 1:52 PM 8194.9 6.0 6 Conforms Conforms Conforms 18 27 1:31 PM 2:12 PM 8196.2 6.0 6 Conforms Conforms Conforms 15 28 2:56 PM 3:18 PM 8194.9 6.0 6 Conforms Conforms Conforms 20 29 3:11 PM 3:50 PM 8196.2 6.0 6 Conforms Conforms Conforms 25 30 4:12 PM 4:42 PM 8194.9 6.0 6 Conforms Conforms Conforms 20 Reinforcing Steel Required Vertical Actual Vertical Required Vertical Actual Vertical Required Splice Actual Splice Micropile No. Reinforcement Reinforcement Reinforcement Reinforcement Length(in) Length(in) Length(ft) Length(ft) 22 Threaded Bar/#18 Threaded Bar/#18 41 41.7 - - 23 Threaded Bar/#18 Threaded Bar/#18 41 42.3 - - 24 Threaded Bar/#18 Threaded Bar/#18 41 41.5 - - 25 Threaded Bar/#18 Threaded Bar/#18 41 41.8 - - 26 Threaded Bar/#10 Threaded Bar/#10 26 27 - - 27 Threaded Bar/#18 Threaded Bar/#18 41 41.6 - - 28 Threaded Bar/#10 Threaded Bar/#10 26 26.7 - - 29 Threaded Bar/#18 Threaded Bar/#18 41 41.8 - - 30 Threaded Bar/#10 Threaded Bar/#10 26 27.1 - - Grout Placement Micropile No. Grout Placement Grout Placement Water Depth Before Theoretical Grout Estimated Grout Method of Grout Start Time Finish Time Grout Placement(in) Volume(ft) Volume(ft) Placement 22 9:55 AM 10:06 AM 0 8.2 Tremmie 23 10:20 AM 10:31 AM 0 8.3 Tremmie 24 11:40 AM 11:50 AM 0 8.1 Tremmie 25 11:55 AM 12:11 PM 0 8.2 Tremmie 26 2:05 PM 2:20 PM 0 5.3 Tremmie 27 2:30 PM 2:45 PM 0 8.2 Tremmie 28 3:26 PM 3:38 PM 0 5.2 Tremmie 29 4:10 PM 4:23 PM 0 8.2 Tremmie 30 5:05 PM 5:21 PM 0 5.3 Tremmie Results apply only to the specific items and locations referenced and at the time of testing, observations or special inspections. This report should not be reproduced,except in full,without the written permission of GROUND Engineering Consultants, Inc. www.groundeng.com Englewood I Commerce City I Loveland I Granby I Gypsum Page 2 of 3 Client: Chad Salli Town of Vail GROUND 1309 El 81rn Drive ENGINEERING Red Sandstone Parking Garage Report Date: Aug 3,2018 Work Order No.: 18-6523.Micropiles.0026;ver: 1 Work Order Date: Aug 2,2018 Reviewed by: Shane Sorensen Micro•files Comments Micropile No. Description of Soil Location of Obstructions Comments 22 Silty,Clayey SAND w/Gravel - - 23 Silty,Clayey SAND w/Gravel - - 24 Silty,Clayey SAND w/Gravel - - 25 Silty,Clayey SAND w/Gravel - - 26 Silty,Clayey SAND w/Gravel - - 27 Silty,Clayey SAND w/Gravel - - 28 Silty,Clayey SAND w/Gravel - - 29 Silty,Clayey SAND w/Gravel - - 30 Silty,Clayey SAND w/Gravel - - Photos 5 r'�i R�— -- —711 r ttrwigrillftigeL7.1:-. :,,c3 te.: a� I 11 rte= --4 - il . .ter' 1 . ig •1. Il i / • • ' ' ' • t ��. 1ai'A' el r - :11114 i 'l7 II I s.- .. ./I I . I . : ',----..z.. :.. . • - 0 1 yf Micropile Micropile Results apply only to the specific items and locations referenced and at the time of testing, observations or special inspections. This report should not be reproduced,except in full,without the written permission of GROUND Engineering Consultants, Inc. www.groundeng.com Englewood I Commerce City I Loveland I Granby I Gypsum Page 3 of 3