HomeMy WebLinkAbout2018.09.25 VGC Improvments Schedule.pdf r1/. RA NELSON VGC Starter & Maintenance - Construction Schedule Rev. date: 9/25/2018 9:33:17 AM
BUILDING MOUNTAIN COMMUNITIES
2018 2019
Line Name Working
Start Finish Aug ,September, October 1 November I December 1 January February March April May 1 Jun
120, 13 , 117, 11 , 115 129 112 126, 110, 124 17 , 21, 4 118, 4 118, 1 15 29, 113 27,
Milestones 183d 9/21/2018 A 6/11/2019 ilmii i 1
2 NTP 1d 9/21/2018 A 9/21/2018 A 21
3 Dry In 12/21/2018 12/21/2018 I 3
4 Complete Drywall 3/25/2019 3/25/2019 I I 4.
5 Substantial Completion 5/29/2019 5/29/2019 I I I 5
6 Final Completion 6/11/2019 6/11/2019 6•
1 I I
Preconstruction 24d 8/17/2018 A 9/20/2018 Ari ll '
8 Documents&Pricing 14d 8/17/2018 A 9/20/201:1
I I
9 GMP Pricing&Contract 24d 8/17/2018 A 9/20/2018 A 9 I
L L
Maintenance 174d 9/21/2018 A 5/29/2019 10 r , 1
11 11
12 Mobilize&Setup BMP 1d 9/21/2018 A 9/21/2018 A 12 1 I I I
13 Maintenance Building Demolition 1d 9/21/2018 A 9/21/2018 A 13 1 I I I
14 Building Excavation 2d 9/21/2018 A 9/24/2018 A 141
15 Utility Connections 3d 10/1/2018 10/4/2018 15U
16 Perimeter Drains 2d 10/5/2018 10/8/2018 1 1161
17 Backfill Foundation 3d 10/17/2018 10/19/2018 I 17•
18 Interior Slab Prep 2d 10/22/2018 10/23/2018 I 18, i
19 ;9 I I
20 Form and Pour Footings 4d 10/1/2018 10/5/2018 20 IN
21 Form and Pour Foundation Walls 5d 10/8/2018 10/12/2018 121•
22 Foundation Waterproofing 2d 10/15/2018 10/16/2018 22'
I I
23 Underslab Electrical 4d 10/24/2018 10/29/2018 23.
I I
24 Frame Exterior Walls 7d 10/30/2018 11/8/2018 24_
25 Frame Roof 8d 11/9/2018 11/26/2018 I 25
26 Dry-in Roof 2d 11/27/2018 11/28/2018 261
27 Set Doors&Exterior Trim 5d 11/29/2018 12/6/2018 27• I I
28 Pour Interior Slab on Grade 2d 12/7/2018 12/10/2018 281 I I
29 Set Overhead Doors 2d 12/11/2018 12/12/2018 I 291 I I
30 Electrical Rough&Trim 10d 11/29/2018 12/14/2018 I 30- I I
31 I 31 1= 11
32 Roofing 4d 11/29/2018 12/4/2018 I 32•
33 Stucco 10d 12/13/2018 12/27/2018 I 33_
34 Gutters&Downspouts 1d 12/28/2018 12/28/2018 I 341
Job#: 00001 1 Data Date:9/26/2018 Owner View Filter:None Page 1 of 4
r1/. RA NELSON VGC Starter & Maintenance - Construction Schedule Rev. date: 9/25/2018 9:33:19 A
BUILDING MOUNTAIN COMMUNITIES
2018 2019
Line Name WDaysg Start Finish Aug ,September, October 1 November i December 1 January February March April May 1 Jun
120, 13 , 117, 11 , 115 129 112 126, 110, 124 17 , 121, 14 118, 4 118, 1 115 29, 113 27,
35 Exterior Punch&Turn Over 10d 12/31/2018 1/16/2019 35 I
36 36 imi
37 37 1.1
I I I
38 Landscaping 10d •19 5/21/2019 38
I I I
39 Site Punch&Turn Over 39 11
I I I
Starter Building 183d 9/21/2018 A 6/11/2019 40 , , 1
41 PIE m
42 421 I I I
43 Existing Starter • 43, I I I
44 Footing Excavation and Slab•ver Ex 5d 9/24/2018 A 9/28/2018 44 I I
45 45- I I
46 Storm• - 146- I I
47 Backfill FoundationI 47 1 I I
48 I 48. I I
49 49i 1
50 Form and Pour Footings50• I I
51 Form and Pour Foundation • , •18 10/17/2018 51-
52 Foundation VVaterproofing 3d 521 I I
53 Underslab MEP 7d 118 11/13/2018 53_
I I I
54 Frame Exterior Bearing Walls 10d 54
I I I
55Frame 0• 55
• I I I
56 • Roof 2d • 561
57 WRB&Set INindows • 57d
,
58 5§M
59 I I 59.
60 Frame Interior Partition Walls 10d I I 60_
61 Rough-in - 0• 2/1/2019 3/5/2019 61- I
62 I I 621
63 I 63r , , 1
64 Roofing 15d 12/24/2018 1/17/2019 I 64
65 Stone Veneer&Trim 20d 1/18/2019 2/18/2019 65
66 Siding&Exterior Trim 15d 2/19/2019 3/14/2019 66
67 Stucco 15d 3/15/2019 4/5/2019 67
68 Gutters&Downspouts 5d 4/8/2019 4/15/2019Li 68 I.
Job#: 00001 1 Data Date:9/26/2018 Owner View Filter:None Page 2 of 4
I^ RA NELSON VGC Starter & Maintenance - Construction Schedule Rev. date: 9/25/2018 9:33:20 A
/� BUILDING MOUNTAIN COMMUNITIES
2018 2019
Line Name WDaysg Start Finish Aug ,September, October 1 November 1 December I January February March April May 1 Jun
120, 13 , 117, 11 , 115 129 112 126, 110, 124 17 , 21, 4 118, 4 118, 1 115 29, 113 27,
69 Storage Fence&Gate 5d 3/15/2019 3/21/2019 I I I 69.
70 Exterior Punch&Turn Over 5d 4/16/2019 4/22/2019 I
71 71
72 Drywall 10d , , 72_ '
I I I
73Prime&First Goat 73..
74 : Doors' ,. ,19 4/11/2019
I I
74i=
75 , , I I I 75.
76 ,19 4/23/2019I I I 76.
77 Wall Tile&Kitchen FRP 10d ,19 5/7/2019I I I 77_
78 , 5/10/2019 I I I 78•
79 I I I 79
80 I I I 80•
81 Interior Punch&Tum Over 5/30/2019 , I I I 81.
82 82I I I 1
83 Demo Asphalt&Hardscape 4d 9/26/2018 10/1/2018
84 Site Grading 2d 10/2/2018 10/4/2018 1,'•
M
85 Site Concrete . 3d 4/29/2019" , • I I I 85
86 Pour Site Concrete5d 5/3/2019 5/9/2019
I I I 86.
87 1 Asphalt • 3d 5/10/2019 , 87•
I I I
88 Asphalt Paving 2d 5/15/2019 5/16/2019 881
I I I
89 Landscaping 10d 5/17/2019 , • 89
90 Site Punch&Turn Over 6d 6/3/2019 , • I I I 90-
L L I
Bridges 18 9/24/2` 6/11/2019 91 1
L L
92 I d '''4/2018 A ' I, i
93 10d 9/24/2018 A 10/5/2018 93
94 Excavate&Prep Abuttments Bridge 14 6d 10/8/2018 10/15/2018 194M
95
4-
95 Form&Pour Abuttrnents Bridge 14 15d 10/16/2018 11/5/2018 I 95
96 Install Drainage Systems Bridge 14 3d 11/6/2018 11/8/2018 I 96• I I
97 Demo Existing Bridge Bridge 14 5d 11/9/2018 11/15/2018 I 97. I I
98 Backfill Abuttments6d 11/16/2018 11/27/2018 I 98_Finish Grades and I I
River Side 99
99 8d 9/26/2018 10/5/2018
Brid.e 14
100 Set Bridge Steel Bridge 14 4d 10/8/2018 10/11/2018 1 oo•
101 4Pour Bridge Deck and Approaches Bridge 6d 10/12/2018 10/19/2018 101-
102 Build&Set Railings Bridge 14 15d 10/22/2018 11/9/2018 102
Job#: 00001 1 Data Date:9/26/2018 Owner View Filter:None Page 3 of 4
rl/� RA NELSON VGC Starter & Maintenance - Construction Schedule Rev. date: 9/25/2018 9:33:21 AM
BUILDING MOUNTAIN COMMUNITIES
2018 2019
Line Name WDaysg Start Finish Aug ,September, October I November I December I January February March April May 1 Jun
_ 120, 13 , 117, 11 , 115 129 112 126, 110, 124 17 , 21, 4 118, 4 118, 1 15 29, 113 27,
103 Reconnect Cart Paths Bridge 14 5d 11/12/2018 11/16/2018 103•
104 Landscaping Bridge 14 10d 5/1/2019 5/14/2019 I I I 104_
105 Punch&Turn Over Bridge 14 10d 5/15/2019 5/29/2019 105
I I I
106 :_ 106, - v
107 Mobilize,Install BMP's Bridge 15 10d 9/24/2018 A 10/17/2018 107 I
108 Demo Existing Bridge Bridge 15 5d 10/18/2018 10/24/2018 108. I !
109 Excavate&Prep Abuttments Bridge 15 6d 10/25/2018 11/1/2018 109• I I
110 Form&Pour Abuttments Bridge 15 15d 11/2/2018 11/26/2018 110
111 Install Drainage Systems Bridge 15 3d 11/27/2018 11/29/2018 111 U I I
112 Backfill Abuttments Bridge 15 6d 11/30/2018 12/7/2018 1 112• I I
113 Finish Grades and Rip-Rap River Side 8d 9/26/2018 10/5/2018 113- I I
Bridge 15
114 Set Bridge Steel Bridge 15 4d 10/8/2018 10/11/2018 114. I I
115 Pour Bridge Deck and Approaches Bridge 6d 10/12/2018 10/19/2018 1 115• I I
116 Build&Set Railings Bridge 15 15d 10/22/2018 11/9/2018 I 116-
117 Reconnect Cart Paths Bridge 15 5d 11/12/2018 11/16/2018 I 117•
118 Landscaping Bridge 15 10d 5/15/2019 5/28/2019 I I I 118M
119 Punch&Turn Over Bridge 15 10d 5/29/2019 6/11/2019 I I I 119
I I I
•
I I I
I I I
I I I
I I I
I I I
I I I
I I I
I I I
I I I
I I I
I I I
I I I
I I I
I I I
I I I
Job#: 00001 1 Data Date:9/26/2018 Owner View Filter:None Page 4 of 4