CONSTRUCTION OBSERVATION REPORT
Client: Paragon Homes Project No.: 16-7-596.01 Day: Tuesday
Attn: Ed Venerable Date: 8/28/18
6460 S. Quebec St. #400 Page: 1 of 1
Centennial, Colorado 80111
Project: Proposed Residence, Lots 14A and 14B, Bighorn Fifth Addition, 4872 Meadow Lane, Vail,
Colorado
Construction Activities Observed: Excavating for lower level bench of Primary Residence.
Equipment in Use:
H-P/Kumar's Site Activities: Excavation for lower bench was cut in two levels from about 3' to 6'
below adjacent ground surface. Materials exposed in the bottom of
excavation consisted of natural silty clayey sand and gravel soils
which were moist. Two areas had received from 11' to 3' depth of
Class 2 aggregate base course placed in a compacted condition.
Dewatering drain was lowered into sump manhole since grade was
too high to gravity discharge. We recommended permanent
discharge into storm drain manhole.
Verbal Communication:
distribution:
Paragon Homes-Ed Venerable(ed@paragonhomesdenver.com)
Mountain Home Concrete—Jim Meehan (jmeehan-mhc@comcast.net)
Vail Construction Group—Jay Nobrega(jay@vailconstructiongroup.com)
Joe Benedict David A. Young, P.E.
/Ijf
Field Technician Reviewed By
H P KU mAR5020 County Road 154
Glenwood Springs, CO 81601
Geotechnical Engineering I Engineering Geology Phone: (970)945-7988
Materials Testing I Environmental Fax: (970)945-8454
Email: hpkqlenwood@kumarusa.com
Office Locations: Parker, Glenwood Springs, and Silverthorne, Colorado
CONSTRUCTION OBSERVATION REPORT
Client: Paragon Homes Project No.: 16-7-596.01 Day: Wednesday
Attn: Ed Venerable Date: 8/29/18
6460 S. Quebec St. #400 Page: 1 of 1
Centennial, Colorado 80111
Project: Proposed Residence, Lots 14A and 14B, Bighorn Fifth Addition, 4872 Meadow Lane, Vail,
Colorado
Weather: Clear, calm, dry Temperature: 50°F at 8:15 am
Construction Activities Observed: Excavation for lower level bench of Primary Residence.
Equipment in Use:
H-P/Kumar's Site Activities: Excavation was completed. From 11'to 3' of Class 2, (minus 3")
base course material was placed and compacted in subexcavated
areas. Southern area dewatered to sump. Sump should be made
permanently discharge into storm drain manhole.
The lower bench subgrade area is suitable for spread footings
designed for an allowable bearing pressure of 2,000 psf at this
time. Upper bench area was previously observed as acceptable as
discussed in our letter dated August 23, 2018.
Verbal Communication:
distribution:
Paragon Homes-Ed Venerable(ed@paragonhomesdenver.com)
Mountain Home Concrete—Jim Meehan(imeehan-mhc@comcast.net)
Vail Construction Group—Jay Nobrega(jay@vailconstructiongroup.com)
Joe Benedict David A. Young, P.E.
/Ijf
Field Technician Reviewed By