HomeMy WebLinkAboutB07-0005 PlansDecember 4, 2008
Martin Haeberle
Head Building Official, Town of Vail
75 S. Frontage Road
Vail, Colorado 81657
Re: Lodge at Lionshead Certificate of Occupancy
I9
Thanks for your efforts to help us obtain a Certificate of Occupancy for the Lodge at Lionshead!
To recap our discussions, on October 16, 2008 a meeting was held at the Lodge at Lionshead to review the as-built
conditions of the sloping sidewalk access route from East Lionshead Circle to the lobby entrance. The meeting was
requested to discuss the comment from the Town of Vail Senior Building Inspector, Greg Denckla, that the building was
unable to receive a Certificate of Occupancy due the sloping sidewalk access route not meeting all the requirements of
ANSI 117.1 -1998. The contention from both the Owner and Design Team is this sloping sidewalk access route was
reviewed with the Town of Vail (Planning & Engineering Departments) prior to the design being submitted for permit.
At the time of the meetings with the Town of Vail Planning & Engineering Departments it was understood that this
sloping sidewalk access was not being designed to meet all the requirements of a ramp, as defined by ANSI 117.1-
1998.
The reason it was being allowed a concession from all the requirements were due to a review and understanding of
the existing conditions. Prior to this renovation and improvement project the only pedestrian access to the lobby from
East Lionshead Circle was via the driveway, pedestrians and vehicles were not separated and the unheated driveway
varied between a 12 -18% slope. The new design has separated the vehicles and pedestrians by providing a sidewalk,
both the driveway and the sidewalk are heated and both the driveway and the sidewalk have been reduced to a 5-
7.6% slope. The floor elevation of the lobby is existing as is the elevation of East Lionshead Circle, and the Town of
Vail Planning & Engineering dictated the location where the driveway was to intersect with East Lionshead Circle due
to sightlines and existing easements and property lines.
The permit drawings were submitted to the Town of Vail on December 19, 2006, revised and re- submitted on February
28, 2007, revised and re- submitted on March 26, 2007; the design for the driveway and sloping sidewalk access route
was shown in the same configuration during all of these submissions and there was never a comment from the Town
of Vail indicating any concern or questioning of the design. The design team assumed since this design was reviewed
With Town of Vail Planning & Engineering prior to submitting drawings for permit and during all three permit
submissions(revisions there were no comments or questions relating to the design of the sloping sidewalk access route
that it was acceptable. During the inspections for the Temporary Certificate of Occupancy the only comment relating
cp to the sloping sidewalk access route was that the single handrail, on the East side of the sidewalk (as shown on the
permit drawings) had not yet been installed and was required to be installed prior to issuance of TCO. The contractor
installed the single handrail on the East side of the sidewalk and the TCO for Phase II was issued on December 11,
2007.
b..
• � During a Final Inspection, requested to allow issuance of the Certificate of Occupancy, on August 29, 2008 Greg
Denckla added a handwritten comment to the inspection report stating that the sloping sidewalk access route from
East Lionshead Circle to the lobby entrance is required to meet ANSI 117.1 -1998, including handrails on both sides of
the sidewalk, landings at appropriate intervals and the sloping surface is not to exceed 5 %. After both the Owner and
Architect were informed of this new comment and requirement a meeting was requested with the Town of Vail to
review/discuss this comment. A meeting was held on October 16, 2008 with Martin Haeberle
710 WEST LIONSHEAD CIRCLE, SUITE A VAIL COLORADO 81647
970.477. ?.440 970.477.296 S( F) www.kb web b.rom
AIflliEER Of THE AMERfC44 €NSIITUTI Of ERCHITf(IS
Martin Haeberle
Page two,
(Chief Building Official), Chris Gunion (Plans Examiner), Greg Denckla (Senior Building Inspector), Jeff Bailey (Lodge at
Lionshead Owner's Rep.), Jon Keiser (TAB Associates, Inc.), Kyle Webb (K.H. Webb Architects PC), Heather Barrie (K.H.
Webb Architects PC), Colleen Kaneda (Evans Chaffee Construction Group), Greg Chaffee (Evans Chaffee Construction
Group), Ryan Burke (Evans Chaffee Construction Group) to review the as -built conditions and discuss the options
available to the Owner and Design Team.
A consensus was reached among everyone involved that the existing sloping sidewalk could remain but additional items
were required to be installed. The existing sloping sidewalk is to be surveyed and where the slope is 5% or greater
handrails are required to be installed on both sides of the sidewalk, on the edge adjacent to the driveway edge
protection (per ANSI 117.1 -1998) is required, a sign is to be installed identifying the ramp as not an accessible route,
and a letter is to be produced stating the reasons why the sloping sidewalk is not compliant as an accessible route (as
defined by ANSI 117.1- 1998).
If you agree with the above proposal as we discussed, Jeff Bailey will proceed with the remedial work based upon the
drawings attached, and we will call for Final inspection after completion.
i thank you for your attention to this matter and we look forward to your confirmation of this matter..
Sincerely,
710 WEST LIONS8EA0 CIRCLE, SUITE A VAIL COLORADO 91647
970.477.2990 970.477.2965(f) www.khwehb.com
hiEIV BER Of THE 1A4EPi( T INSTITU11 Of ARCHI If( IS
Maigaguma
r z .
1 1/2" DIA. PAINTED
STEEL HANDRAIL
2" DIA, CORE DRILL
INTO EXISTING CONCRETE
EXISTING CONCRETE -�
CURB
EXISTING PAVERS
AT DRIVELANE TYP.
EXISTING HEATED
CONCRETE SIDEWALK
1g, EXISTING SIDEWALK
j� EXPANSION /CONTROL
11 " 3" /' JOINTS TYP.
EXISTING HEATED
CONCRETE SIDEWALK TYP.
m
EXISTING SIDEWALK
EXPANSION/CONTROL
JOINTS TYP.
1 U2" DIA. PAINTED
STEEL HANDRAIL
1■
1 In" DIA. FAINTED
STEEL HANDRAIL
FULLY GROUTED INTO
2" 01A. CORE DRILL TYP.
2" DIA. CORE DRILL
INTO EXISTING CONCRETE
TOP OF EXISTING
CONCRETE CURB
ww "M a MQJ� •� ..
MWAI
WMA tr-AdVA �#Rj
OUTLINE OF
EXISTING
HANDRAIL TYP.
a
1 1/2" DIA. PAINTED
STEEL HANDRAIL.
XTENSION
OUTLINE OF
NEW HANDRAIL TYP.
w
Ohl
mr
NOTE.
WORK WITH
DETAIL. 5 /Al.l
r r r r
s -.
r •
M i r
• r • � �;, r i i
r � r "' • • M "' * i
OUTLINE OF EX ISTING
HANDRAIL TYP. � OUTLINE OF NEW
HANDRAIL TYP.
CUT - OFF EXISTING HANDRAIL
END AND WELD NEW 1 112" OIA.
STEEL HANDRAIL - INSTALL
NEW 1 1/2" OIA. VERTICAL POST
DIRECTLY BENEATH SPLICE, WELD
NEW VERTICAL POST TO SPLICED
HORIZONTAL HANDRAILS: REMOVE
ANY AND ALL BURRS, GRIND SMOOTH
WELDS AND PAINT NEW HANDRAIL TO
MATCH EXISTING HANDRAIL
r +•
WAR rAlM
� :.
M
_ _RAM
3£5140.45
EXISTING
P
: r ON
1 3 ED TYP. IN
HEATE
r ' A
08140.15
39.55
,,
y!
I
010 39.55
�o
EXISTING HEATED
388(8, 39.25 CONCRETE SIDEWALK TYP.
SEE DETAIL 3 /A1.1 FOR
TYPICAL HANDRAIL DETAIL
SEE DETAIL 2 /AI.1
FOR HANDRAIL EXTENSION
DETAIL TYF.
SEE DETAIL 2 /All
FOR HANDRAIL EXTENSION
DETAIL TYP.
ri
EME2
lkl .= A .
=XMWA
mr ri
EXISTING BUILDING (PHASE 11)
:•� H AN D RA IL
i R EMAIN
SL OP E
1
0
t
=f
Y
s
1
s