Specifications:
R-56 BIBS to exterior ceilings 2x14 TJI
With MemBrain Smart Vapor Barrier
R-50 (8”) Polyurethane Spray foam to Deck exterior ceiling 2x10 at main entrance
R-30 Unfaced Fiberglass batts to garage ceiling 2x12 TJI (living space above)
R-13 (2”) Polyurethane spray foam to 2x2 furr wall in garage
R-13 (2”) Polyurethane spray foam to 2x2 furr wall in living space
R-19 (3”) Polyurethane Spray foam to 2x4 furr wall in living space
R-27 Hybrid insulation to 2x6 exterior walls (Combination R-13 (2”) Polyurethane spray foam and R-15 BIBS)
R-24 BIBS to Garage 2x6 exterior walls
With Poly 6 MIL
R-24 BIBS to garage 2x6 common wall
With Poly 6 MIL
R-30 Unfaced fiberglass batts to 2x12 midfloor for sound
R-32 (5”) Polyurethane Spray foam to rim joist
R-11 Unfaced batts to interior walls for sound
R-19 Unfaced batts to interior walls for sound
Foam all windows and doors
Fire rated foam to all penetrations
Air sealing package (air sealing to all stud packs-windows & door headers-top & bottom plates, and gaps at any framing member)
Total $20,280.00
TOTAL INCLUDES SALES TAX AND LABOR
Work shall commence on ____________________, and will be completed approximately in 9 business day(s) subject to changes in the plan approved by the owner
and events and conditions beyond our control.
All material is guaranteed to be as specified above. All work shall be completed in a workmanlike manner, in accordance with standard industry practices and
manufacturers’ instructions. Any deviation or alteration from the above specifications that involves extra costs will be completed only upon executing a written
change order, and will require extra charges and time to complete, above and beyond this estimate. Owner shall carry fire and other required insurances. All labor is
guaranteed against defects for a period of one year from the date of completion.
When polyurethane spray foam is being installed on a project, several precautions are required. No one and no trades should be in the building or home when
polyurethane spray foam is being sprayed for a period of 24 hours. Area of work needs to be between 50-60 degrees in temperature 24 hours prior to and during
application. Area of work should be well vented during and after application. No open flames, torches or other hot surfaces near the polyurethane foam during and
after installation.
Acceptance of Proposal: The above price, specifications, and conditions are satisfactory and are hereby accepted. You are authorized to do the work as specified.
Payment shall be made as described above.
Signature(s) of Acceptance Date
___________________________ _________ ______ ________________________________
345 Spring Creek Circle, Gypsum, CO 81637 970-445-8518