HomeMy WebLinkAboutB18-0406 approved plans.pdf• --R 5I~ 01 8 ~ Sl ~ l5' tr' ~ ~ ~' ~ H <-0 z ~-~ Jf1 --< w --< rn c: z_ ~ .. f <;;--Cj'\ ---~ . ~ c:. C) ~ ,.._ -~ CJ --; ~v --0 ~ ~<-8 ~ ~~ _6_ ~-----/~\ :::::---RArtlJ G-1<1t1~A ""'""' . .s;, "'x C _y/J ("". A) ~ l(&a. 'lJ ~ IJ j;: I Z "tO IJ~ /)c.1 c Te() OvT J104 ~II!:} /Jvc1 CtJHNoT PEw~ilfrl1i° /(t'T£u c~ILt1t1& t,/1Tl/0~7 /I /!17EtJ CHt1J6 ENCL7Jvt1.l:i. "rD D ' :· I 1' I I I B 0 ::tl G) z > r 11 r 0 0 ::tl IJ r > z / \ ~' Town of Vail OFFICE COPY ~-t I ' ' rown oi Vail REVI . WED FOR CODE COM.LIANCE Date ~ ... .ZI ·If' RECEIVED ~t.t' ·, 4 2018 Town of Vail By: .. 1 ?.~ CodJi IS=---·----I i l ~ ~ ::}-~ ' \)o ----(11
Environmental Development and Training ACM LLC.
September 12, 2018
Mike Dowling
C.A.E Abatement LLC
Box 5110 Eagle, Co 81631
P. 0. Box 452 Wheat Ridge, CO
80034
Phone 303-638-3 778
Site: Unit #165 of 525 Vail Valley Drive, located in Vail , Colorado.
Task: Asbestos Visual and Air Clearance testing of unit 165 abatement of asbestos containing
textured wall and ceiling material. The abatement Contractor removed the identified asbestos
containing drywall texture ceiling and wall materials within a single full containment system.
Clearance testing was conducted post removal of identified asbestos containing materials, and
prior to planned repair and renovation of unit loss area.
Task 1 -Field Work:
1.0 Asbestos Clearance
Project Scope of Work Conducted during Air Monitoring:
A. Contractor conducted abatement according to Colorado Regulation 8, EPA, and OSHA
containment work practices for OSHA clearances.
B. Completion of final inspections, for applicable ACM removal, and removal of all
materials, within the regulated areas.
Environmental Development & Training, ACM LLC (EDT) conducted a post abatement
visual investigation at the above-referenced site. The investigation was conducted to discern the
successful removal of ACM material using applicable State of Colorado Regulation 8, OSHA,
and EPA regulations.
2.0 SAMPLE COLLECTION METHODS
EDT ACM LLC used NIOSH method 7400, 40 CFR 763 AHERA and OSHA 29CFR 9010
methodology during activities to support abatement activities.
FINAL AIR SAMPLES:
Clearance air sampling was conducted according to Colorado Regulation 8. All of the
clearance samples collected within the work area were less than 0.0 l F/CC, (fibers per
Cubic Centimeter. No concentrations were observed in excess of the Maximum
Allowable Asbestos Level (MAAL).
3.0 CONCLUSIONS
Based on observations during the site visit, and the laboratory analytical results, EDT LLC ACM
concludes the following:
All Environmental and Final work Area or Clearance Air samples collected outside
and inside the regulated work area clearance criteria indicated; fiber concentrations
less than or equal to 0.01 flee (fibers per cubic centimeter of air sampled). No fiber
concentrations were observed in excess of the Maximum Allowable Asbestos Level
(MAAL) per CDPHE.
Based on sampling and analysis results attached, no further action is recommended or required
for this phase of the project for the impacted areas. As additional abatement items are addressed
environmental and clearance air monitoring should be performed according to Colorado and
EPA Regulations.
4.0 LIMITATIONS
Limitations
Environmental Development and Training ACM LLC prepared this report, for the exclusive and
present use of CAE Abatement and DRS . This report addresses certain physical characteristics
of the site with regards to the release or presence of asbestos in limited, client determined, areas
only. These services were performed in a manner consistent with practices common in the
environmental health profession. The information and conclusions provided herein are valid only
with respect to the specific locations and analytes investigated at the time this report was
prepared. The findings, conclusions, and recommendations presented here are based on
information available at the time the site was evaluated.
In the event of any reuse or publication of any portion of this report, Environmental
Development and Training ACM LLC shall not be liable for damages arising out or such reuse
of publication. Any reuse a third party makes of this report, or any reliance on or decisions
made are the responsibility of such third party. Environmental Development and Training ACM
LLC accepts no responsibility for damages, if any, suffered by any third party as the result of
decisions made or actions taken based on this report.
~'"4 7. ')(/~
Kris Thomas Wilson
President
Environmental Development and Training ACM LLC
Environmental Development and Training ACM LLC
Phone 303-638-3778
Bob Regan
210-1349
5177 South Ventura Way
Centennial, CO 80015
R2 Samgle #
Xl-BL-01
Xl-BL-02
Xl-CLR-03
Xl-CLR-04
Xl-CLR-05
Xl-CLR-06
Xl-CLR-07
AIHA Laboratory Certification
Colorado Laboratory Certification
R2 Analytical Job Number
Client
Client Project Number
Date/ Time Logged In
Analysis Due
Analysis Requested
f/mm2
flee
R2 LAB ID Volume(L) #Fields #Fibers Fiber Density
Fiber Concentration
BL-I 0 100 0
BL-2 0 100 0
595Cl-3 553 100 6.0 0.006
595Cl-4 553 100 4.5 0.006
595Cl-5 553 100 6.5 0.006
595Cl-6 553 100 4.5 0.006
595Cl-7 553 100 4.0 0.006
•BDL-Below Limit of Detection
#156492
#14903
R59509122018-1
595X-l
595DX-1
09/12/2018@2020hrs
2 Hour Rush
NIOSH 7400 A-Rules
flee & f/mm2
Detection Limit
0.005 BDL
0.004 BDL
0.005 BDL
0.004 BDL
0.004 BDL