CONSTRUCTION OBSERVATION REPORT
Client: Paragon Homes Denver Project No.: 18-7-555 Day: Monday
Attn: Ed Venerable Date: 11/5/18
6460 S. Quebec Street#400 Page: 1 of 1
Englewood, Colorado 80111
Project: Proposed New Eastern Half Duplex Addition, Lot 27, Block 7, Vail Village 1st Filing, 175
Forest Road, Vail, Colorado
Weather: Cloudy, light wind, light snow Temperature: 32°F at 12:00 pm
Construction Activities Observed: The contractor was performing snow removal.
Equipment in Use:
H-P/Kumar's Site Activities: As scheduled, we visited the site to perform an epoxy dowel
inspection. The contractor was not ready for an inspection.
Verbal Communication: Jim Meehan with Mountain Home Construction requested we return
the following day 11-6-18.
•
distribution:
Paragon Homes Denver-Ed Venerable(ed(aparagonhomesdenver.com)
Jay Nobrega(javevailconstructiongroup.com)
Mountain Home Construction—Jim Meehan(imeehan-mhcacomcast.net)
Justin Orgill David A. Young, P.E.
/ljf
Field Technician Reviewed By
H-P KU mAR5020 County Road 154
Glenwood Springs, CO 81601
Geotechnical Engineering I Engineering Geology Phone: (970)945-7988
Materials Testing I Environmental Fax: (970)945-8454
Email: hokglenwood(a�kumarusa.com
Office Locations: Parker, Glenwood Springs,and Silverthorne, Colorado
REINFORCEMENT STEEL INSPECTION REPORT
Client: Paragon Homes Denver Project No.: 18-7-555 Day: Tuesday
Attn: Ed Venerable Date: 11/6/18
6460 S. Quebec Street#400 Page: 1 of 1
Englewood, Colorado 80111
Project: Proposed New Eastern Half Duplex Addition, Lot 27, Block 7, Vail Village 1st Filing, 175
Forest Road, Vail, Colorado
Area of Inspection: Epoxied Dowels into existing Foundation wall.
Reference Documents Structural Drawings provided by the contractor.
Used:
Inspection Notes: Dowel holes were correct diameter and met minimum depth required and
were blown free of debris prior to application of HILTI HIT-RE 500 V3 as
per manufactures specifications.
Inspection Status: ❑ Preliminary ® Final
® Concrete reinforcement as noted above was judged to be in reasonable conformance with
the referenced construction documents.
❑ Exceptions Noted:
Verbal The contractor was informed of our inspection results.
Communication:
Distribution:
Paragon Homes Denver-Ed Venerable(ed anparagonhomesdenver.com)
Jay Nobrega(java vailconstructionproup.com)
Mountain Home Construction—Jim Meehan(imeehan-mhc(a comcast.net)
nif Justin Orgill David A. Young, P.E.
Field Technician Reviewed By