1. Presentation on EuroFaire
2. Town Attorney's Report on Streamwalk Private Covenants
3. Discussion of Vail Gateway Project Progress
4. Review of the Byrne/Taylor project, which is scheduled for final
review by the Design Review Board on August 2, 1989 (126 and 146
Forest Road)
5. Information Update
6. Other
7. Site Visits
A. 950 Fairway Drive
B. 705 West Lionshead Circle
C. 2880 Booth Creek Drive
VAIL TOWN COUNCIL
WORK SESSION
TUESDAY, AUGUST 1, 1989
2:00 p.m.
EXPANDED AGENDA
2:00 1. Presentation on EuroFaire
John Horan-Kates
Action Requested of Council: Receive presentation and make
comments as desired.
2:15 2. Town Attorney's Report on Streamwalk Private Covenants
Larry Eskwith
3:00 3. Discussion of Vail Gateway Project Progress
Buff Arnold
Action Requested of Council:_ Receive progress report and
made comments as desired.
Background Rationale: Gateway representatives asked to be
placed on the agenda to talk with Council about the clean up
process at the Amoco site. Representatives of Amoco and
Palmer Development are expected to be present.
3:20 4. Review of the Byrne/Taylor project, which is scheduled for
Mike Mollica final review by the Design Review Board on August 2, 1989
Action Requested of Council: None required.
Background Rationale: This project consists of two primary/
secondary residences, on Lots 5 and 6, Block 7, Vail Village
1st Filing (126 and 146 Forest Road). Both residences have
a proposed GRFA of 3;800 square feet. The DRB, on July 19,
1989, has conceptually reviewed the proposal.
3:35 5. Information Update
Ron Phillips
3:45 6. Other
4:00 7. Site Visits
A. 950 Fairway Drive
B. 705 West Lionshead Circle
C. 2880 Booth Creek Drive