HomeMy WebLinkAbout2013-12-17 Agenda and Support Documentation Town Council Special SessionVAIL TOWN COUNCIL
SPECIAL MEETING AGENDA
VAIL TOWN COUNCIL CHAMBERS
75 S. Frontage Road W.
Vail, CO 81657
1:00 P.M., DECEMBER 17, 2013
NOTE: Times of items are approximate, subject to change, and cannot be relied
upon to determine at what time Council will consider an item.
Public comments on work session item may be solicited by the Town
Council
1.
ITEM/TOPIC: VAIL REINVESTMENT AUTHORITY MEETING - separate
meeting.
1) Vail Reinvestment Authority (VRA) Resolution No. 3, Series of 2013 - 2013
Supplemental;
2) Vail Reinvestment Authority approval of Vail I-70 Underpass Commitment
Letter (5 min. )
PRESENTER(S): Kathleen Halloran
2. ITEM/TOPIC: Adjournment
12/17/2013
VAIL TOWN COUNCIL AGENDA MEMO
MEETING DATE: December 17, 2013
ITEM/TOPIC: VAIL REINVESTMENT AUTHORITY MEETING - separate meeting.
1) Vail Reinvestment Authority (VRA) Resolution No. 3, Series of 2013 - 2013 Supplemental;
2) Vail Reinvestment Authority approval of Vail I-70 Underpass Commitment Letter
PRESENTER(S): Kathleen Halloran
ATTACHMENTS:
Resolution No. 3, Series of 2013
I70 Commitment Letter
12/17/2013
TO: Vail Reinvestment Authority
FROM: Finance Department
DATE: December 11, 2013
SUBJECT: 2013 Budget Amendment – Resolution 2
I. SUMMARY
Staff is requesting approval of Resolution No. 2, making supplemental appropriations and
adjustments to the 2013 budget.
II. DISCUSSION
This supplemental appropriation request will update to the VRA budget to correlate with
expenditures approved during the year in the Capital Projects Fund, and to adjust both revenue
and expenditures relating to the collection of TIF revenues.
Specifically, the budget adjustments include:
Reduction of revenue by $7,084 for the federal subsidy of the Build America Bonds
credit, reduced due to government budget cuts.
Increasing expenses by $3,600 for the town’s 2% fee collected on TIF property tax
(town’s portion only) to manage the VRA funds (directly related to previously adjusted
revenue for TIF property tax collections).
Increasing expenses by $29,100 for the pass-through of TIF property tax revenue to the
Vail Square Metro District
A reduction of $500,000 in transfers to the town’s Capital Projects Fund. This is merely
an update to the VRA budget to correlate with expenditures approved and adjusted
during the year in the Capital Projects Fund. The projects are being paid for out of the
Capital Projects Fund, with reimbursement from the Vail Reinvestment Authority (VRA)
because those projects (or a related portion) are capital improvements within the TIF
district.
Total budget adjustments result in a reduction in revenue of $7,084 and a reduction in
expenditures of $467,300.
1 - 1 - 1
12/17/2013
Vail Reinvestment Authority
Summary of Revenue, Expenditures, and Changes in Fund Balance
2013
Original1st 20132nd2013
BudgetSupplemental AmendedSupplementalProposed
Revenue
Property Tax - LionsHead TIF2,953,000$ 180,000$ 3,133,000$ 3,133,000$
Property Tax - Vail Square Metro Districts385,000 30,000 415,000 415,000
Federal Subsidy for Build America Bonds173,343 173,343 (7,084) 166,259
Earnings on Investments33,000 33,000 33,000
Total Revenue3,544,343 210,000 3,754,343 (7,084) 3,747,259
Operating Expenditures
Professional Fees25,000 25,000 25,000
Management Fee 59,060 59,060 3,600 62,660
Treasurer's Fee -LionsHead TIF88,590 5,400 93,990 93,990
Treasurer's Fee -Vail Square Metro Districts11,550 900 12,450 12,450
Vail Square Metro District Pass Through373,450 373,450 29,100 402,550
Total Operating557,650 6,300 563,950 32,700 596,650
Debt Service
Principal460,000 460,000 460,000
Interest605,203 605,203 605,203
Fiscal Agent fees2,200 2,200 2,200
Bond Issuance costs
Total Debt Service 1,067,403 - 1,067,403 - 1,067,403
Total Expenditures 1,625,053 6,300 1,631,353 32,700 1,664,053
Excess of Revenues Over Expenditures1,919,290 203,700 2,122,990 (39,784) 2,083,206
Other Financing Sources (Uses)
Debt Proceeds
Transfer Out - Capital Projects Fund
Lionshead Transit Center
Lionshead Welcome Center(94,536) (94,536) (94,536)
Surface Parking at Charter Bus Lot
Guest Services Enhancements/Wayfinding(500,000) (70,000) (570,000) 500,000 (70,000)
Library Remodel(298,497) (298,497) (298,497)
East LionsHead Portal (VRA)(463,561) (463,561) 112,000 (351,561)
West LionsHead Portal (VRA)(129,544) (129,544) (129,544)
Energy Audit Enhancements - -
Lionshead Parking Structure Entry (200,000) (200,000) (200,000)
Frontage Road improvements (LH Pkg to Muni)- -
Parking Entry System / Equipment (LH only)- -
Bike Lanes: Westwind to LH Pkg Structure - -
Lionshead Medians
CDOT-Required Parking - -
Sundial Plaza fountain & surround (840,568) (840,568) (112,000) (952,568)
Demolition of current LH Info Booth - -
East LH Circle pathway to Dobson - -
Dobson Plaza - -
Simba Run Underpass Feasibility study (200,000) (200,000) (200,000)
Simba Run Underpass - RAMP Project
Lionshead Parking Structure Capital Maintenance(310,000) (310,000) (310,000)
Total Other Financing Sources (Uses)(1,210,000) (1,896,706) (3,106,706) 500,000 (2,606,706)
Net Change in Fund Balance 709,290 (1,693,006) (983,716) 460,216 (523,500)
Beginning Fund Balance3,028,132 6,736,091 6,736,091
Ending Fund Balance 3,737,422$ 5,752,375$ 6,212,591$
‐ 2 ‐ 1 - 1 - 2
12/17/2013
Resolution No. 2, Series 2013
RESOLUTION NO. 2, SERIES OF 2013
VAIL REINVESTMENT AUTHORITY
A RESOLUTION ADOPTING AN AMENDED BUDGET AND MAKING
APPROPRIATIONS TO PAY THE COSTS, EXPENSES, AND LIABILITIES OF
THE VAIL REINVESTMENT AUTHORITY FOR ITS FISCAL YEAR JANUARY 1,
2013, THROUGH DECEMBER 31, 2013.
WHEREAS, contingencies have arisen during the fiscal year 2013 which could
not have been reasonably foreseen or anticipated by the Vail Reinvestment
Authority at the time it enacted Resolution No. 2, Series of 2012, adopting the
2013 Budget for the Vail Reinvestment Authority of Vail, Colorado; and
WHEREAS, in accordance with CRS section 29-1-106 a notice of budget hearing
has been published; and
WHEREAS, notice of this public hearing to consider the adoption of the proposed
Vail Reinvestment Authority budget was published in the VAIL DAILY on the 28th
day of March, 2013; and
NOW, THEREFORE, LET IT BE RESOLVED by the Vail Reinvestment Authority
of Vail, Colorado, as follows:
The Vail Reinvestment Authority adopts the amended budget with a reduction of
expenditures by $467,300 beginning on the first day of January 2013 and ending
on the 31st day of December 2013.
Attested: Signed:
_________________________ _______________________
Stan Zemler, Secretary Andrew P. Daly, Chairman
1 - 1 - 3
12/17/2013
Safety People Integrity Customer Service Excellence Respect
Page 1 of 3
Assurance that 1
Town of Vail 2
Remains Committed to Entering into a Partnership with CDOT Concerning 3
Vail I-70 Underpass 4
Tracking No.: 3-9
Project
Name:
I-70 Simba Run Underpass
Commission Requirement. The purpose of this document is to satisfy the requirement 5
established by the Transportation Commission that applicants for Public-Public Partnership1 projects 6
confirm their commitment to the project. Transportation Commission Resolution TC-3106 adopted on 7
October 17, 2013, provides in part: 8
BE IT… RESOLVED that the Transportation Commission requires for each Public-9
Public Partnership project on or before January 6, 2014, a project scope, schedule, and 10
budget developed by the Colorado Department of Transportation in the form and to the 11
level of detail specified by the Chief Engineer; and 12
BE IT FURTHER RESOLVED that the Transportation Commission also required for 13
each Public-Public Partnership project on or before January 6, 2014, evidence, in a form 14
specified by the Chief Financial Officer, confirming a commitment by the applicant to the 15
project scope, schedule, and budget developed by the Department, including an 16
agreement to hold a public vote to authorize the local match by no later than April 8 if 17
such vote is necessary; and 18
BE IT FURTHER RESOLVED that the Chief Engineer may extend the January 6, 19
2014, deadlines to April 7, 2014, upon application for extension form any applicant or 20
CDOT Region Transportation Director for projects in a flood damaged area. 21
Project Scope, Schedule, and Budget Prepared by CDOT. The Colorado Department of 22
Transportation has prepared the required scope, schedule, and budget for this Public-Public Partnership 23
project. This scope, schedule, and budget is incorporated as Exhibit A of this document. Exhibit A 24
specifies the financial and other commitments of Town of Vail and identifies when it is reasonably 25
anticipated that such commitments will be provided or performed. 26
Changes in Project Costs. CDOT and the Local Agency Partner will assess at the Final Office 27
Review (FOR) the project budget to be contracted. An estimate over the Exhibit A amount will trigger a 28
reevaluation of the project as well as the project match. CDOT and Town of Vail will engage in 29
negotiations to determine how and if the project moves to advertisement for construction, as well as the 30
project match. If a project is determined by CDOT to no longer be feasible or if an agreement cannot be 31
reached, CDOT will advise the Transportation Commission that the project is unable to be moved forward 32
1 CDOT interprets Public-Public Partnership projects references in TC-3106 to include Operations projects that
have Local Agency Partners.
1 - 2 - 1
12/17/2013
Safety People Integrity Customer Service Excellence Respect
Page 2 of 3
and should be removed from the list of approved Public-Public Partnership projects. On a CDOT 33
administered project, any cost variance discovered after the Final Office Review (FOR) will be the 34
responsibility of CDOT. On a project administered by the Local Agency Partner, the CDOT contribution 35
will not increase after the Final Office Review. Any addition of a “betterment” at the request of the Local 36
Agency Partner is the responsibility of the Local Agency Partner. 37
If there is a cost savings regardless of who is administering the project or when the cost savings 38
occurs, the savings will be prorated. 39
Intergovernmental Agreement. An Intergovernmental Agreement will be completed and fully 40
executed prior to any CDOT expenditure other than the five percent of the total project cost for Fiscal 41
Year 2014 authorized in the RAMP Resolution for pre-construction expenditures unless an exception is 42
granted by the CDOT Chief Financial Officer. It is the policy of CDOT that the Intergovernmental 43
Agreements must be executed by June 30, 2014. Any change in the standard wording of the 44
Intergovernmental Agreement may delay the project and thus put the project in jeopardy. 45
Criteria for Approval of RAMP Local Commitments. The CDOT Chief Financial Officer has 46
issued the following criteria: 47
(1) Local agencies acknowledge receipt of CDOT estimated project cost and drawdown schedule 48
and confirm their ability to provide funding on the schedule. 49
(2) Resolution by city councils or county commissioners or signed commitments by local officials 50
with authority to commit agency resources constitute adequate funding reaffirmation by the local. Where 51
ballot initiative or future budget adoptions are required, locals are fully disclosing and committing to all 52
necessary steps to ensure that it will be on the ballot and/or receive budget consideration. 53
(3) Dollar amount of local agency commitment must align with dollar amounts of CDOT cost 54
estimates. 55
(4) Local agencies cannot commit traditional federal transportation funds. 56
(5) Where multiple local agencies are involved, commitments are required from those local 57
agencies with the authority to commit all local agency funds before approval of funding commitment will 58
be considered. 59
(6) IGAs already in place should meet the above criteria. 60
Evidence of the Continued Commitment by Town of Vail to the Project. As an officer of 61
Town of Vail, I confirm that appropriate officials of Town of Vail have reviewed and considered Exhibit 62
A which contains the scope, schedule, and budget developed by CDOT for the project and the policy 63
regarding changes in project cost stated in the body of this document. 64
I confirm that to the best of my knowledge I know of no reason why Town of Vail and CDOT 65
will not execute an Intergovernmental Agreement as specified in Exhibit B and based on the scope, 66
schedule, and budget contained in Exhibit A and the policy regarding changes in project cost stated in the 67
body of this document by June 30, 2014. 68
69
__________________________________ 70
Andrew P. Daly 71
Vail Town Mayor 72
73
Date: __________________ 74
1 - 2 - 2
12/17/2013
Exhibit A – Scope, Schedule, and Budget Developed by CDOT
Safety People Integrity Customer Service Excellence Respect
Page 3 of 3
75
1 - 2 - 3
12/17/2013
DEPARTMENT OF TRANSPORTATION
Eagle Residency
PO Box 298, 714 Grand Avenue
Eagle, CO 81631-0298
(970) 328-6385
Exhibit A
I-70 Vail Underpass Project
RAMP Tracking Number 3-9
Project Scope, Schedule and Budget
STA 0702-327 (s/a 19094)
Scope:
This project is located along I-70 between the West Vail (MP 173) and Main Vail (MP 176) interchanges.
It will connect the North and South I-70 Frontage Roads by means of a new underpass in the vicinity of
the Simba Run condominiums. The new I-70 underpass will improve mobility and safety at the existing
interchanges. It will also provide a safe pedestrian/bicycle crossing of I-70, enhance the transit service
routing and connectivity, improve emergency response routing and provide water quality improvements
for storm water before it enters Gore Creek.
Schedule:
Survey – November 2013
Scoping – January 2014
Prelim Horiz. And Vert. Alignments – Jan 2014
FIR – May 2014
Structure Selection Report – May 2014
Form 128 Signed (Top) – September 2014
FOR – January 2015
ROWPR/Final ROW Plans– February 2015
Utility Clearance – February 2016
ROW Clearance – February 2016
Environmental Clearance – February 2016
Final PS&E – February 2016
Advertisement Date – March 2016
Construction Start – June 2016
Project Complete – December 2017
Budget and Drawdown:
FY14 -$ 0.6M (PE)
FY15 -$ 1.2M (PE and start ROW)
FY16 -$ 1.8M (ROW and finish PE)
FY16 -$ 9.8M (utility & construction)
FY17 -$ 7.4M (utility & construction)
$20.8M
TOV Funds:
Calendar Yr 13 - $0.2M
Calendar Yr 14 - $0.6M
Calendar Yr 15 - $0.7M
Calendar Yr 16 - $2.2M
Calendar Yr 17 - $2.3M
$6.0M
1 - 2 - 4
12/17/2013
I-70 Vail Underpass
Project Cost Estimate
Completed by: Jen Babcock Current Indirect Rate 11.00%
Sub Account No: 19094
Creation Date: 11/25/2013
Date Modified: 11/26/2013
Ad Date: Feb. 2016
Bridge$11,134
Survey$12,014
Right of Way $53,640
Consultant-ROW$43,520
Materials$5,567
Hydraulic$3,992
Traffic$0
Utilities$11,175
Environmental$17,061
Design$80,711
Consultants$1,640,749
Total Preconstruction including Indirects 1,879,564$
ROW Acquisition $1,700,000
Construction, including FA, CE & Indirects 17,182,419$
20,761,983$
Budget Action DateAmountComments
Remaining to Budget 20,761,983$
Project Total
COLORADO DEPARTMENT OF TRANSPORTATION
Scope: This project is located along the I‐70 corridor between the West Vail (MP 173) and Main Vail (MP 176) interchanges. It will connect the North and South
I‐70 Frontage Roads by means of a new underpass in the vicinity of the Simba Run condominiums.
1 - 2 - 5
12/17/2013
Alternative:
Prepared By:
Creation Date:
Date Modified:
ItemUnitUnit CostQuantityExtended Cost
Asphalt planing SY4.007,989.0031,956.00
Unclassified Exc (CIP)CY13.0045,000.00585,000.00
Guardrail Type 3 LF28.002,500.0070,000.00
ABC (various classes)ton30.006,922.00207,660.00
HBP ton125.003,461.00432,625.00
Retaining Walls-MSE/SN SF100.0013,895.001,389,500.00
Retaining Wall - CIP SF165.005,500.00907,500.00
Curb and Gutter (2-IIB)LF20.005,000.00100,000.00
Sidewalk (6")SY45.004,400.00198,000.00
WB Bridge SF200.003,801.00760,200.00
EB Bridge SF200.003,801.00760,200.00
Storm Sewer (30")LF125.002,000.00250,000.00
Inlet Each5,000.0025.00125,000.00
Manhole Each5,500.0012.0066,000.00
WQ Vault Each150,000.001.00150,000.00
8"/10" Sewer (PVC)LF150.002,500.00375,000.00
0.00
0.00
0.00
6,408,641.00
% UsedCost
N / A $6,408,641
30.0%$1,922,592
0.0%$0
3.0%$249,937.00
2.0%$166,624.67
5.0%$416,561.67
25.0%$2,082,808.33
5.0%$416,561.67
7.0%$583,186.33
$12,246,913
0.0%
0.0%
0.0%
0.0%
2.0%$244,938
8.0%$979,753
5.0%$612,346
Subtotal FA $1,837,037
$14,083,950
22.00%$3,098,469
Construction TOTAL - PRESENT COST $17,182,419
No. of years 0 $0
Total Construction Cost $17,182,419
Inflation @ 3%/year
Subtotal of Construction Cost
Construction Engineering (11%) + Indirects11% + Indirects
Force Account - Utilities(1 - 2%)
MCR(5-10%)
Force Account - Misc.(2-5%)
Force Account - HMA EscalationCalculated
Force Account - SmoothnessCalculated
Force Account - Quality IncentiveCalculated
Mobilization(4 - 7%)
Total of Construction Bid Items
Force Account - Fuel Cost adjCalculated
Signing and Striping(1 - 5%)
Construction Signing & Traffic Control(5 - 25%)
Erosion Control/Landscaping(10-25%)
Lighting(1 - 5%)
Contingencies/other bid items(15 - 30%)
ITS(6 - 10%)
Drainage / Utilities(3 - 10%)
Sub Account Number: Project Name:
Engineers (Semi) Detailed Estimate
Enter Major Roadway Bid Items Only Shaded Fields are for INPUT
Jen Babcock
11/26/13
Project Construction Bid ItemsProject Dependent
% Range
Comments:
1 - 2 - 6
12/17/2013
VAIL TOWN COUNCIL AGENDA MEMO
MEETING DATE: December 17, 2013
ITEM/TOPIC: Adjournment
12/17/2013