HomeMy WebLinkAbout2018-08-21 Agenda and Supporting Documentation Town Council Afternoon AgendaVAIL TOWN COUNCIL REGULAR MEETING
Agenda
Grand View at Lionshead Parking Structure
8:30 AM, August 21, 2018
TOWN Of 4IAJt
Notes:
Times of items are approximate, subject to change, and cannot be relied upon to determine what time Council will
consider an item.
Public comment on any agenda item may be solicited by the Town Council.
1. Light Breakfast will be served at 8:00 am
2. Presentations / Discussion
2.1. 2019 Budget Preview 240 min.
Presenter(s): Greg Clifton, Town Manager and Kathleen Halloran, Finance
Director
Action Requested of Council: Provide feedback to staff in preparation for
the 2019 budget
Background: The budget preview meeting kicks off the annual budget
process, which after multiple Council meetings on various budget topics
culminates in two readings of a budget ordinance later in the year.
Staff Recommendation: Provide feedback to staff on preliminary revenue
assumptions and long term capital planning.
3. Break
3.1. Break 10:30 am - 10:45 am
4. DRB / PEC Update
4.1. DRB / PEC Update
Presenter(s): Chris Neubecker, Planning Manager
5. Information Update
5.1. July 2018 Al PP Meeting Minutes
5.2. CSE meeting minutes DRAFT from August 8, 2018
5.3. VLHA Meeting Results
6. Matters from Mayor, Council and Committee Reports
7. Executive Session
7.1. Executive Session, pursuant to: 1) C.R.S. §24-6-402 (4)(b) - to receive
legal advice on specific legal questions; Regarding Quasi Judicial decision
making; 2) C.R.S. §24-6-402(4)(a)(e) - to discuss the purchase,
5 min.
20 min.
August 21, 2018 - Page 1 of 82
acquisition, lease, transfer, or sale of property interests; and to determine
positions, develop a strategy and instruct negotiators, Regarding: 6 West.
Presenter(s): Matt Mire, Town Attorney
8. Recess
8.1. Recess at 1:00 pm
Meeting agendas and materials can be accessed prior to meeting day on the Town of Vail website
www.vailgov.com. All town council meetings will be streamed live by High Five Access Media and available for
public viewing as the meeting is happening. The meeting videos are also posted to High Five Access Media
website the week following meeting day, www.highfivemedia.org.
Please call 970-479-2136 for additional information. Sign language interpretation is available upon request with 48
hour notification dial 711.
August 21, 2018 - Page 2 of 82
TOWN OF 1 X41
VAIL TOWN COUNCIL AGENDA MEMO
ITEM/TOPIC: 2019 Budget Preview
PRESENTER(S): Greg Clifton, Town Manager and Kathleen Halloran, Finance Director
ACTION REQUESTED OF COUNCIL: Provide feedback to staff in preparation for the 2019
budget
BACKGROUND: The budget preview meeting kicks off the annual budget process, which after
multiple Council meetings on various budget topics culminates in two readings of a budget
ordinance later in the year.
STAFF RECOMMENDATION: Provide feedback to staff on preliminary revenue assumptions
and long term capital planning.
ATTACHMENTS:
Description
preview
memo etc
August 21, 2018 - Page 3 of 82
August 21, 2018 - Page 4 of 82
BUDGET PREVIEW 1 Agenda
• Introduction: Greg Clifton
• Guest speaker: Tim Gagen
• Budget Philosophies
• Reserves
• Capital plan
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 5 of 82
TOWN OF VA�
BUDGET PREVIEW 1 Budget Philosophies
• Budget will reflect the town's vision and support the Council Action
Plan
• Revenues are projected conservatively using analytical processes
• General Fund reserves of at least 25% of budgeted revenue; Staff
recommends increasing to 30%
• Town develops a five year financial projection for all major funds,
including a long-term capital improvement plan
• The town will operate within annual revenue streams
• Sales tax split between the General Fund and Capital Projects Fund is
recommended to stay at the current split of 62% to the General Fund
and 38% to the Capital Projects Fund
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 6 of 82
TOWN OF VA�
BUDGET PREVIEW 1 Budget Philosophies
• Town has generally adopted a 'save and pay' approach toward its
capital projects and programs; no debt outside of Renewal Authority
(TIF)
• Importance of reserve fund balances is to enable the town to
withstand unforeseen events and economic downturns
• The annual budget process is thorough and comprehensive, allowing
for informed appropriations in accordance with fiscal policies and
objectives
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 7 of 82
TOWN OF VA�
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 8 of 82
TOWN OF VA�
BUDGET PREVIEW 1 Revenue Sources
2019 Total Revenue Sources:
$66.2M
Property and Ownership
Tax
7%
Ski Lift Tax and Franchise
Fees
9%
Earnings on Investments
1%
Transfer from VRA
2%
Town of Vail 1 Finance 1 8/21/2018
Rent, Fines &
Miscellaneous
7%
Charges for Services
3%
Real Estate Transfer Tax
10%
Licenses and Permits
4%
Intergovernmental
Revenue
5%
Transportation Centers
8%
August 21, 2018 - Page 9 of 82
TOWN OF VAIL.
BUDGET PREVIEW 1 Revenue Projections
Revenue Item
% change from
Forecasted 2018
Sales Tax
+ 2.5% II $27.OM"IIIIM
RETT
+ 3.0%
$6.3M
Lift Tax + 1.6% $5.0M
Parking
+ 3.9%
$5.4M
Property Tax - 10.4% $4.8M
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 10 of 82
TOWN OFD
BUDGET PREVIEW 1 Revenue Projections
30.0
25.0
20.0
■ Actual 15.0
Budget
10.0
5.0
Sales Tax Collections (in millions)
2013 2014 2015 2016 2017 2018 Forecast 2019 Proposed
Budgeted Incr/(Decr) 4.5%
5.0% 2.5%
1.8% -0.9%
1.8% 2.5%
Actual Incr/(Decr)
9.7% 8.6%
5.3% 2.5%
-0.7% 2.9%
Budget vs. Actual
Town of Vail 1 Finance 1 8/21/2018
3.6%
2.8% 0.7%
0.2% 1.1%
August 21, 2018 - Page 11 of 82
TOWN OF VA
BUDGET PREVIEW 1 Revenue Projections
8
N
a
0
Actual
Budget
7
6
5
4 —
3
2 —
1 —
RETT Collections (in millions)
2013 2014 2015 2016 2017 2018 Forecast 2019 Proposed
Budget Incr/(Decr) -29.0% 24.9% -9.6% -6.7% -14.5% -3.4% 3.0%
Actual Incr/(Decr)
11 ='•
-3.4%
Budget vs. Act
11.3% 4.9% 6.8% 0.0%
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 12 of 82
TOWN OF VARA
BUDGET PREVIEW 1 Revenue Projections
80.00
70.00
60.00
50.00
■ Actual 40.00
Budget
30.00
20.00
10.00
Total Revenues (in millions)
2013 2014 2015 2016 2017 2018 Forecast 2019 Proposed
Budgeted Incr/(Decr) -4.6%
16.6% -2.7%
-2.3% 5.3%
2.1% -2.2%
Actual Incr/(Decr)
-2.5% 20.8%
4.9% -0.7%
- 0.8% 2.5%
Budget vs. Act
2.1%
4.2%
7.6% 1.6%
- 6.1% 0.4%
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 13 of 82
TOWN OF VAIL/
BUDGET PREVIEW 1 Revenue Projections
• Other Major Sources of Revenue:
• Construction Use Tax
• Property Tax — will be impacted again from Gallagher Act
• Lift Tax
• Construction Fees
• Parking Revenues
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 14 of 82
TOWN OF VA�
BUDGET PREVIEW 1 Operating Expenditures
Town of Vail 1 Finance 1 8/21/2018
TOWN OFtql.)
August 21, 2018 - Page 15 of 82
BUDGET PREVIEW 1 Operating Expenditures
Where the Money Goes
2018 Amended Budget $43.1M
Facilities & Fleet
Maintenance
10%
Transportation &_
Parking
15%
Parks & AIPP
4%
Public Works &
Streets
11%
Contributions,
Marketing, & Specials
Events Library/
7% 2%
Town of Vail 1 Finance 1 8/21/2018
Health & EHOP
1% Police
11%
Public Safety
Communications
6%
Fire
11%
\Town Officials
4%
Comm Dev &
Housing Dept
7%
Administrative
Services & Risk
Management
11%
August 21, 2018 - Page 16 of 82
TOWN OF VA�
BUDGET PREVIEW 1 Operating Expenditures
2019 Proposal will include:
• Staff and compensation recommendations set for
September 18th Council meeting
• Operating expenditures will be presented to Council
at the November 6th meeting with a first draft of the
Town Manager Budget
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 17 of 82
TOWN OF VA�
Town of Vail 1 Finance 1 8/21/2018
TOWN OF
August 21, 2018 - Page 18 of 82
BUDGET PREVIEW 1 5 Year Capital Plan
• Revenues within the Capital Fund are used for capital projects as
identified through the Capital Improvement Plan (CIP).
• A well written CIP ensures that the physical assets of the Town are
maintained or improved at a level adequate to (1) protect the
Town's capital investment; (2) minimize future maintenance and
replacement costs; and (3) meet the growing needs of the Vail
community.
• The priorities the departments, boards & commissions and Town
Council are collectively considered in the Plan.
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 19 of 82
TOWN OF VA�
BUDGET PREVIEW 1 5 Year Capital Plan
• The CIP process identifies projects based upon priorities of
occurrence over the next five years ... some projects are identified
but not prioritized within the five year window
• The CIP is a budgeting and planning tool ... only those projects and
programs identified in the upcoming fiscal year (2019) would be
proposed for appropriation
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 20 of 82
TOWN OF VA�
BUDGET PREVIEW 1 5 Year Capital Plan
A look at average annual capital spending over the next 5 years:
Annual Maintenance
Parks & Landscape
Operations
Capital Projects
Total
Town of Vail 1 Finance 1 8/21/2018
Capital
Projects
Fun
$ 4.5M
n/a
$1O.4M
$14.9M
1r$ 1.5M
$ 1.8M
$ 3.5M
$ 6.8 M
IP
n/a
$ 6.OM
n/a $ 1.8M
$2.5M
$16.4M
$2.5M $24.2M
August 21, 2018 - Page 21 of 82
TOWN OFVA�
BUDGET PREVIEW 1 5 Year Capital Plan
Capital projects have been prioritized:
Priority Timetable
Nature of Project
A fiscal budget year
Identified as top prioity by Council
B 1-3 years out
essential project
LC
3-5 years out
desirable project
D when budget allows; identified project to meet projected needs;
future project; not likely listed as "Unfunded"
to occur within 5 years
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 22 of 82
TOWN OF VAIL
BUDGET PREVIEW 1 5 Year Capital Plan
Notable projects over the past few years:
• InDeed Housing Program (2018) $7.2M ($3.4M funded from Fee in
Lieu / $3.8M funded from CPF)
• Sandstone Underpass (2017-2018) $8.2M VRA / $21.3M CDOT
• Red Sandstone Parking Garage (2018-2019) $9.1M TOV / $4.5M
Vail Resorts / $1.5M Eagle County School District
• East Vail Fire Station (2016) $3.6M
• Chamonix Housing —(2016-2017) $19.5M ($17.7M repaid)
• Vail Golf and Nordic Center (2016) $11.2M / $1.15M VRD
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 23 of 82
TOWN OF VA�
BUDGET PREVIEW 1 5 Year Capital Plan
Notable projects proposed for 2019:
• Public Works Expansion ($13.5M over 2 years) CPF
• InDeed Housing Program ($1.5M) per year; CPF
• Phase 2 of Data Center remodel and network upgrades ($2.4M) CPF
• Extensions to the Vail Valley Drive pathways ($800K) CPF
• Main Vail Roundabout concrete "apron" ($250K) CPF
• Parking equipment ($83K) CPF
• Ford Park softball field shelter ($585K) RETT
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 24 of 82
TOWN OF VA�
BUDGET PREVIEW 1 Unfunded Projects
The largest unfunded projects over the next five years
include:
• Civic Area Plan Improvements
• Municipal Complex
• Main Vail and West Vail Round -about Reconstruction
• Timber Ridge Redevelopment
• Lionshead parking structure east entry improvements
• Open Lands Plan implementation
• Historical / Cultural Heritage
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 25 of 82
TOWN OF VA�
Town of Vail 1 Finance 1 8/21/2018
TOWN OF
August 21, 2018 - Page 26 of 82
BUDGET PREVIEW 1 Reserves: 10 Year History & 5 Year Projection
90
c
0
2 80
70
60
50
40
30
20
10
$80.1
$49.5
$47.5
$45.8 $45.3
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 27 of 82
mAII Other
Conference Center
Fund
RETT Fund
Capital Projects
Fund
General Fund
Reserve Min
TOWN OF VAIL.
BUDGET PREVIEW 1 Capacity for Spending
• Not enough cash reserves to fund all of these
projects
• Strategic plan for financing
• Options include:
> Incur debt
> Save and Pay
> Scale back on projects
> New revenue sources
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 28 of 82
TOWN OF VA�
BUDGET PREVIEW 1 Final Thoughts
• Does Council agree with the standard budget philosophies and
practices?
• Does Council have comments on staff's preliminary revenue
assumptions?
• Are there changes Council would like us to consider as we bring the
5 -year capital projects budget forward?
• Is there anything else you would like staff to be aware of as we build
the budget?
Town of Vail 1 Finance 1 8/21/2018
August 21, 2018 - Page 29 of 82
TOWN OFV�
2019 Budget Preview Session
With Town Council
Agenda
I. Introduction — Greg Clifton
II. Guest Speaker — Tim Gagen
III. Budget Philosophies
IV. Revenue Assumptions- Kathleen Halloran
V. Reserves
VI. 5 -year Capital Plan, TIF Long Term Plan
VII. Additional discussion / Any potential impacts to the 2019 budget staff
should be aware of?
August 21, 2018 - Page 30 of 82
TOWN OF VAIL
Memorandum
TO: Vail Town Council
FROM: Town Manager / Department Heads
DATE: August 21, 2018
SUBJECT: 2019 Budget Preview
I. SUMMARY
The purpose of this meeting is to provide a high-level preview of the town's 2019 budget
process and gather feedback from Council on preliminary budget assumptions. This feedback
will be used for the creation of the 2019 draft proposed budget to be presented to Council on
November 6th. The final budget ordinance reading is scheduled for December 4th. Please see
Appendix A for the Budget Timetable outlining the meeting schedule for budget topics.
11. BACKGROUND
During the 2019 budget development, departments are working to propose a budget that
continues to strive for the goals and accomplish the initiatives stated in the Council Action Plan
which is geared toward continuing Vail's leadership position. The 2019 budget will also focus on
Town Council priorities as outlined in the Council Action Plan:
To be the
PREMIER
international
mountain resort
community
4.•.
eco
• ENHANCE THE LOCAL ECONOMY: Preserve our vibrant and diverse economy that
keeps Vail at the forefront of our resort competitors.
• GROW A BALANCED COMMUNITY: Engage our community on honoring our social,
recreational, cultural, educational, and environmental values that will guide sustainable
strategies throughout our neighborhoods as the foundation of our town's continued
success.
August 21, 2018 - Page 31 of 82
• ELEVATE THE EXPERIENCE: Deliver on the promise, "VAIL, Like nothing on earth,"
that also supports "preserving our earth," in everything we do.
• PRESERVE OUR NATURAL ENVIROMENT: Balance our economic, environmental,
and social needs to deliver a sustainable community.
In addition to the key initiatives in the Council Action Plan, there are standard budget
philosophies and practices developed over time and agreed to or revised by Council that are
used to develop the budget. Please see Appendix B for the Budget Philosophies.
III. BUILDING THE BUDGET
The base information to begin the budget process consists of revenue and fund balance
projections. Fund balances have been adjusted to reflect budget appropriations that
occurred mid -year. During 2018 Town Council adjusted budgeted expenditures that were
not anticipated in the 2018 annual budget process. Other than the re -appropriation of
capital projects carried over from the prior year, the following items impacted the current
budget year:
• $7.2 million was appropriated to address housing concerns by funding the
purchase of deed restrictions
• $310K cash plus in-kind was provided to the Colorado Classic
• An additional $86K was awarded to the Burton US Open Snowboarding
Championships
• An additional $270K was awarded to revitalize the Snow Daze event in
December
While unanticipated funding requests may come in during the year, the annual budget
process strives to forecast operating needs and capital improvements.
Revenue:
We have included a preliminary review of revenue assumptions (Appendix C) used as a basis
for the projection of annual revenues. Revenue projections set the stage for direction given to
the internal departments regarding annual operating expenditures. Staff is proposing a
conservative approach to revenue projections based on the continued trend of a levelling off
of revenue growth. A 10 -year lookback of major revenue to accompany the 2019 proposed
projections are included in Appendix D.
The town's 2019 budget is funded by a projected $66.2 million. Excluding the one time
revenues in 2018 which included the sales of Chamonix housing units ($17.7M) and the
Red Sandstone parking structure reimbursements from Vail Resorts ($4.5M) and Red
Sandstone Elementary School ($1.5M), the $66.2M projection is a 2.2% decrease from
the 2018 forecast and a decrease of 0.8% from the 2017 actual results. The below chart
identifies the various sources of town revenue:
Town of Vail Page 2
August 21, 2018 - Page 32 of 82
2019 Budgeted Net Revenue:
$66.2M
Property and
Ownership Tax
7%
Use Tax
3% Ski Lift Tax and
Franchise Fees
9%
Earnings on
Investments
1%
Transfer from VRA
2%
Rent, Fines &
Miscellaneous
7%
Real Estate
Transfer Tax
10%
Licenses and
Permits
4%
Intergovernmental
Revenue
5%
Transportation
Charges for Centers
Services 8%
3%
After the 2009 recession, Vail was able to quickly bounce back from a decline in revenues.
Between 2010 and 2015, sales tax was growing at an average of 8.4% per year while total
revenues were pacing at an average of 3.4% per year. Sales tax and overall revenue collections
have since leveled off and have been trending flat year over year. Since 2015 sales tax growth
averaged increases of less than a percentage per year with 2017 down 0.7% from 2016. Lack of
snow and delayed business openings such as the Hotel Talisa (Vail Cascade) and the
DoubleTree (Holiday Inn) impacted sales tax growth in 2017 and contributed to the slow- down.
Vail's sales tax growth has also not kept pace with other mountain communities. Although Vail
rebounded quickly after the Great Recession, other communities have continued to grow at a
faster pace. The below chart is a year over year sales tax growth comparison between
Breckenridge, Aspen, Steamboat, and Vail.
Town of Vail
Page 3
August 21, 2018 - Page 33 of 82
Sales Tax
YTD Growth (June)
2017-2018
2016-2017
5 yr
Breckenridge
10.38%
3.70%
8.80%
10.47%
Steamboat
7.05%
3.60%
6.90%
7.55%
Vail
5.20%
-0.70%
2.50%
5.70%
Aspen
5.00%
2.20%
6.70%
7.61%
Town of Vail
Page 3
August 21, 2018 - Page 33 of 82
All of this information has been considered in staff's proposed sales tax projection of a 2.5%
increase over the 2018 forecast (a 5.5% increase from 2017 collections). Sales tax
collections in 2018 are currently pacing 5.2% up from 2017 with the summer performance
helping to offset a lackluster winter. If we conservatively forecast sales tax collections for the
remaining portion of the year (July- Dec) to be flat with prior year, 2018 will end the year up
2.9% from 2017. The 2019 sales tax projection is proposed at a 2.5% increase from the 2018
forecast, assuming a similar trend of growth.
RETT Tax is proposed at $6.3 million, an increase of 3% from 2018, based on a five year
average. RETT typically fluctuates year to year, and no major redevelopment projects
are included at this time.
Parking revenues are proposed at $5.4 million, a 3.9% increase over 2018. Revenues from
daily sales at the structures were projected using an average winter plus summer overnight
collections. Pass sales include a nominal amount pass sales for the Red Sandstone parking
structure.
Property tax collections are estimated at $4.75 million, a 10.4% decrease from 2018. The
projected tax revenue includes impacts from a reduction in residential taxes due to the
Gallagher Amendment. The Gallagher Amendment reduces the residential multiplier from 7.2%
to 6.2% and will impact the town's General Fund by $550,000 in 2019. We'II know more later
this month when the assessor provides an estimate of valuations. If valuations have increased,
we may have some offset to the Gallaher impact.
Construction Use Tax is proposed at $2.2 million for 2019, a 12.4% increase over 2018,
mainly due to anticipated projects such as Launch, Park Meadows and Lion View. Those
project estimates were also included in the proposed 2019 construction permits and fees
revenue of $2.1 million, a 9% increase over 2018.
Operating Budget:
Town operating expenditures are budgeted as part of the General Fund and make up the
majority of all yearly expenses. While we don't have 2019 expenditures finalized as yet, the
2018 amended budget includes total operating expenses of $47.9 million. A breakout of
operating expenses by department is provided in the chart below. Within the General Fund,
28% of spending is for public safety which includes Fire, Police, and Police Communications.
Fifteen percent of the total is spent on transportation and parking, which includes the free bus
system, operating the parking structures at Vail Village, Lionshead and Ford Park. Public
Works accounts for 11 % of spending. This consists of daily repairs and maintenance of the
town's infrastructure and support of special events but does NOT include any new capital or
items that extend the life of the existing capital. Facility and fleet maintenance is 10% and
includes daily repairs and maintenance of town owned buildings and equipment. This also does
not include any new capital items.
Town of Vail Page 4
August 21, 2018 - Page 34 of 82
Where the Money Goes
Municipal Services by Area
Employee Housing
EHOP Program
1%
Public Safety
iiiCommunications
Facilities & Fleet
Maintenance
10%
Parks & AIPP I
4%
Public Works &
Streets
11%
Police
11%
6%
Town Officials
4%
Contributions, Administrative
Marketing, & Special Community Services & Risk
Events Library Development Management
7% 2% 7% 11%
When making considerations for the 2019 expenditure budget, it is also useful to look at
expenses by category. General Fund expenses can be divided into four major categories;
salaries, benefits, contributions and special events; and all other. "All other" operating expenses
consist of operating and maintenance fees, professional fees, contracts, office supplies etc.
Where the Money Goes
Municipal Services by Category
All Other
Operating ph
Expenses
29%
Salaries
48%
Contributions,
Marketing, Benefits
Special Events 18%
5%
Town of Vail Page 5
August 21, 2018 - Page 35 of 82
As a service organization, salaries and benefits typically represent nearly two-thirds of the total
operating budget. During 2018, Town Council authorized a comprehensive review of the Town's
compensation plan. Based on results from that review, staff will return to Council on September
18 for a discussion on the town's compensation philosophies and strategies for 2019.
Proposed operating expenditures for 2019 will be presented to Council during the first draft of
the Town Manager budget, scheduled for November 6.
Reserves & Capital Plan
Town reserves are projected to be $49.5 million at the end of 2018 down from $71.9M in
2017. After the recession the town focused on its core responsibilities, refrained from new major
capital projects and built up the reserve levels to a high of $82.4M in 2016. The town has since
used some of these reserves to fund events, housing, and other major capital projects including
the construction of the four level parking structure at Red Sandstone elementary school. Other
capital projects over the past five years that have been completed by the town utilizing cash
include:
• InDeed Housing Program (2018) $7.2M ($3.4M funded from Fee in Lieu collections)
• Sandstone Underpass (2017-2018) $8.2M VRA; $21.3M CDOT Grants
• Red Sandstone Parking Garage (2018-2019) $9.1M TOV / $4.5M Vail Resorts / $1.5M
Eagle County School District
• East Vail Fire Station (2016) $3.6M
• Chamonix Housing —(2016-2017) $19.5M ($17.7M repaid from sales)
• Vail Golf and Nordic Center (2016) $11.2M
Staff has provided a preliminary five year capital plan. The capital plan has been updated
to reflect new projects and revisions since the prior year. Outside of annual capital
maintenance required for core services, capital projects are prioritized into three
categories: Priority A for Council top priorities funded in the upcoming year; Priority B
for essential projects 1 to 3 years out; Priority C for desirable projects 3-5 years out and
Priority D are identified projects, but currently "unfunded" and not included in the 5 year
capital plan.
As in the previous capital worksheets, cost increases are highlighted in orange, new
requests are highlighted in green, timing changes to projects in purple and items
previously included as placeholders are highlighted in blue. New requests or changes
to 2019 not previously listed in the 5 -year capital plan include:
• InDeed Housing Program ($1.5M) per year (CPF)
• Phase 2 of Data Center remodel and network upgrades ($2.4M) CPF
• Extensions to the Vail Valley Drive pathways ($800K) CPF
• Main Vail Roundabout concrete "apron" ($250K) CPF
• Parking equipment ($83K) CPF
• Ford Park softball field shelter ($585K) RETT
• Renovation of Ford Park art cottage ($472K) RETT
Town of Vail Page 6
August 21, 2018 - Page 36 of 82
Renovations to Slifer Square Plaza are budgeted in 2018 with the original scope of project.
Based on Council feedback, this project will be brought back for consideration of added scope
and cost. Any added cost estimates are not included at this time.
The five-year capital plan also includes $13.5M (over a two year span 2019-2020) for an
expansion and remodel of the public works shop complex as outlined in the public works master
plan. This plan is a project which sets the stage for a phased expansion overtime. Critical to the
plan is to ensure that the expansions to the shop meet the needs of the department and the
changing operations, such as electrified buses. The last masterplan for the shop was completed
in 1994. The ensuing programs being considered are a shop building expansion, system
upgrades, ADA upgrades, additional employee housing, covered cold storage and the
expansion of the shop yard foot print to the north, project staging and space, snow dump
expansion, photovoltaic array as major GHG emission offset, a left turn lane on the frontage
road, hazard mitigations and visual screening.
A majority of town -owned facilities and amenities have been renovated in the past five years
with the exception of the municipal building and the public works shops/admin buildings. The
municipal building renovation was previously included in the budget, but was moved to the
"unfunded" list in 2018 with an approximate cost of $20.0M - 25.0M to be included as part of the
Civic Area Master Plan.
While total reserves at the end of 2018 are projected to be $49.4 million, not all of that is
available for new capital projects. Some of the funds such as Heavy Equipment, Health
Insurance and Dispatch Services cannot be spent for anything other than their specific
designation. In addition, the Vail Reinvestment Authority funds are restricted to capital
improvements within the district, and the RETT Fund is restricted for parks, recreation,
environmental sustainability, forest health and open space acquisition. The Capital Projects
Fund is typically the only source of funding used for capital projects that fall outside of
these restrictions.
While the Vail Reinvestment Authority is another source of funds for projects in the district, there
will not be significant funds available until 2023 due to the Sandstone Underpass project and the
new parking structure at Red Sandstone Elementary. The VRA does have debt capacity
however, for future projects such as improvements resulting from a Civic Area Master Plan.
On the topic of reserves, staff is proposing to increase the General Fund reserves
requirement to 30% of General Fund revenue from the current 25%. Although the town
maintains a healthy reserve balance, increasing the reserve requirement will help ensure the
town can maintain its high level of operations during an economic downturn or an impactful
incident.
Town of Vail Page 7
August 21, 2018 - Page 37 of 82
ACTION REQUESTED
The feedback given during this work session will help establish a foundation from which to build
the 2019 budget, and is not considered an "approval" of any particular item within the budget.
Upcoming budget presentations as outlined in the timetable (Attachment A) will provide more
opportunities for adjustments. However, in order to give direction to departments in beginning
to build their budgets, staff is requesting feedback on the following:
1. Does Council agree with the standard budget philosophies and practices?
2. Does Council have comments on staff's preliminary revenue assumptions?
3. Does Council agree to increase the General Fund fund balance reserve
minimum from 25% of revenues to 30%?
4. Are there any capital projects you would like staff to include in the budget
proposal?
5. Is there anything else you would like staff to be aware of as we build the
budget?
Town of Vail Page 8
August 21, 2018 - Page 38 of 82
Attachment A
Aug Sep Oct Nov Dec 2019
Budget Retreat- Special Meeting 0 Draft Town Manager Budger Presented to Council
August 21, 2018 November 6,
Staff Prepares Proposed Department Budgets • First Reading of 2019 Budget Ordinance
August 22, 2018 - September 14, 2018 November 20, 2018
Town Manager Reviews Department Proposed Budgets • Second Reading of 2019 Budget Ordinance
September 17, 2018 - September 28, 2018 December 4, 2018
August 21, 2018 - Page 39 of 82
APPENDIX B
Budget Philosophies
There following standard budget philosophies and practices have been developed over
time and are agreed to or revised by Council and then used to develop the budget.
■ Budget will reflect the town's vision and supports the Town Council's areas of strategic
focus
■ Revenues are projected conservatively using analytical processes
■ When appropriate, new programs are funded by new or increased revenues or
reallocation of existing revenue
■ General Fund reserves of at least 25% of budgeted revenue; Staff recommends
increasing to 30%
■ Town develops a five-year financial projection for all major funds, including a long-term
capital improvement plan
■ The town will operate within annual revenue streams (expectation of "break-even"), with
the exception of Extraordinary Event funding from reserves
■ The sales tax "split" between the General Fund and Capital Projects Fund is set by
ordinance, subject to annual review. Currently, staff recommends maintaining the
current "split" of 62% to the General Fund and 38% to the Capital Projects Fund. At year
end, any sales tax collections over the budgeted amount go entirely to the Capital
Projects Fund.
■ Fund balances shall be adequate to cover short-term fluctuations in revenues,
emergencies, and planned future expenditures.
1. Does Council agree with the current standard budget philosophies and
practices?
2. Does Council have any revisions to the standard budget philosophies and
practices?
August 21, 2018 - Page 40 of 82
APPENDIX C
2019 Preliminary Revenue Assumptions
Sales Tax
2019 is proposed at $27.0M, a 2.5% increase from 2018 forecast and up nearly
5.5% from 2017 actual.
2018 sales tax collections are currently up 5.2% through June. Summer results
are encouraging, with June up 18.6% from the prior June. Destimetrics has
reported Vail's summer occupancy up 5% compared to the "industry" up 3% and
ADR (Avg. Daily Rate) increase of 2% flat with competitors. In total, RevPar for
Vail (combined occupancy and rate) is up 7% compared to industry, up 5%.
The sales tax "split" proposed is unchanged at 62% General Fund and 38% Capital
Projects Fund.
RETT
2019 proposed at $6.3M, a 3% increase from 2018 forecast, and flat with 2017.
Five year average annual growth is 3.2%. Year-to-date collections are tracking
13% up from prior year due to sales at the Lion. Otherwise, YTD is trending up
9% with 2017.
Construction
Use Tax
2019 proposed at $2.2M, a 12.4% increase from 2018 forecast and up 27.5%
from 2017 actuals. The 2019 projection is based on a 2 year average, but also
includes estimates for Lion View, Park Meadows and Launch projects.
Property Tax
2019 proposed at $4.8M, a decrease of 10.4% from 2018. The General Fund will
lose approx. $550K in 2019 from further reductions based on Gallagher Act. In
2018, the multiplier on residential properties was reduced from 7.96% to 7.2%.
In 2019, that multiplier will be reduced to 6.2%. There may be increases to
valuations that will help to offset the Gallagher impact; we'll know more later in
August when the assessor sends out the preliminary valuations.
Lift Tax
2019 proposed at $5.0M, a 1.6% increase from 2018 forecast and a 6.7% increase
from 2017 actuals. This is assuming an average winter season rather than the
2017 Not including 2017, the historical five-year average growth was 8% per
year.
Construction
Fees
2019 Construction Fees are proposed at $2.1M, an 8.9% increase from 2018
forecast, and a 26.6% increase from 2017 actuals. Year to date collections of
$1.4M are up 46% from the prior year. 2019 is based on a 5 year average plus
estimated fees from Launch, Park Meadows, and Lion View projects.
Parking
2019 proposed at $5.4M, based on 2016 actuals plus summer overnight parking
and a nominal amount for pass sales at Red Sandstone structure. This is a 3.9%
increase over 2018.
August 21, 2018 - Page 41 of 82.
Major Revenue Analysis
2018 Proposed Budget
APPENDIX D
August 21, 2018 - Page 42 of 82
% from 2017
% from Forecast
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2018
2019
Actual
Actual
Actual
Actual
Actual
Actual
Actual
Actual
Actual
Amended
Forecast
Proposed
Comments
General Sales Tax
16,913,338
17,676,115
19,581,414
20,046,455
21,999,999
23,881,130
25,141,932
25,763,244
25,591,483
26,046,000
26,339,793
27,000,000
2019 proposed at a 2.5% increase from 2018 forecast, or 5.5% increase from 2017 actuals; YTD
collections as of June are up 5.2% from 2017; 2018 forecast would end the year up 2.9% from 2017
-13.8%
4.5%
10.8%
2.4%
9.7%
8.6%
5.3%
2.5%
-0.7%
1.8%
2.9%
2.5%
RETT Tax
2,513,481
6,950,701
4,403,706
5,452,937
4,725,589
6,849,449
6,965,617
6,843,356
6,313,611
6,100,000
6,100,000
6,283,000
2019 anticipates 3% growth from 2018 (5 year average annual growth is 3.2%)
-72.4%
176.5%
-36.6%
23.8%
-13.3%
44.9%
1.7%
-1.8%
-7.7%
-3.4%
-3.4%
3.0%
Parking Revenue
4,975,795
5,037,042
4,023,940
3,453,836
4,170,065
4,528,137
4,948,993
5,230,062
4,902,756
5,147,900
5,222,900
5,426,000
2019 based on 2016 actuals (2017 was lower than normal); 2019 also includes summer parking
5.7%
1.2%
-20.1%
-14.2%
20.7%
17.9%
9.3%
5.7%
-6.3%
5.0%
6.5%
3.9%
based on 2018 actuals and a nominal amount of pass sales at Red Sandstone structure
Property & Ownership Tax
4,506,491
4,951,386
5,031,770
4,157,279
4,227,966
4,358,411
4,389,241
4,911,842
4,940,193
5,300,000
5,300,000
4,750,000
2019 decrease based on Gallagher reduction of residential multiplier from 7.2% to 6.2%
4.6%
9.9%
1.6%
-17.4%
1.7%
0.1 %
0.7%
11.9%
0.6%
7.3%
7.3%
-10.4%
We will know more late in August from Assessor's first estimate of valuations
Lift Tax Revenue
3,048,011
3,357,717
3,529,125
3,433,686
4,007,908
4,351,624
4,763,956
5,032,970
4,708,765
4,944,200
4,944,200
5,025,000
2019 proposed at a 1.6% increase from 2018 and a 6.7% increase from 2017 actuals
-7.0%
10.2%
5.1 %
-2.7%
16.7%
15.1%
9.5%
5.6%
-6.4%
5.0%
5.0%
1.6%
Assuming an average winter season rather than the lackluster performance of 2017.
Construction Fees
1,341,731
1,272,606
985,377
1,333,681
1,404,928
2,608,807
1,949,884
1,552,569
1,628,471
1,619,321
1,891,960
2,061,207
2019 is a 9.4% increase from 2018 budget, based on 5 year average plus Launch, Park Meadows
-64.7%
-5.2%
-22.6%
35.3%
5.3%
4.4%
-25.3%
-20.4%
4.9%
-0.6%
16.2%
8.9%
and Lion View projects; 2018 collections of $1.4M is trending up 46% YTD from PY
Construction Use Tax
713,582
1,103,119
721,002
1,221,734
1,360,585
1,803,853
2,220,168
1,688,841
1,740,754
1,975,900
1,975,900
2,220,000
2019 based on two year average plus estimated collections from Lion View, Park Meadows
17.3%
54.6%
-34.6%
69.4%
11.4%
0.2%
23.1%
-23.9%
3.1%
13.5%
13.5%
12.4%
and Launch projects; 2020 based on 5 year average
Other Taxes
1,545,535
1,711,350
1,806,708
1,672,112
1,735,016
1,829,591
1,886,347
1,812,997
1,803,508
1,878,472
1,905,000
1,904,400
County sales tax (based on TOV sales tax), Road & Bridge, Hwy users revenue, etc.
-6.0%
10.7%
5.6%
-7.4%
3.8%
5.6%
3.1%
-3.9%
-0.5%
4.2%
5.6%
0.0%
Federal / County Grants
203,765
3,785,144
1,596,040
916,067
82,630
474,399
152,193
184,827
169,883
1,633,406
1,633,406
695,000
2018 includes $700K CDOT Water Quality "TAP" grant; $675K bus grants and $135K state grant
N/A
1757.6%
-57.8%
-42.6%
-91.0%
-45.6%
-67.9%
21.4%
-8.1%
861.5%
861.5%
-57.5%
for water quality improvements at PW Shops
2019 federal grant for buses and ERWSD share of Dowd Junction path reconstruction
Earnings on Investments
460,234
330,216
539,541
492,015
426,975
674,027
271,896
191,992
563,885
217,698
217,698
241,616
Based on available fund balance and investment returns assumed at 0.7%
-75.0%
-28.3%
63.4%
-8.8%
-13.2%
57.9%
-59.7%
-29.4%
193.7%
-61.4%
-61.4%
11.0%
Rental Income
912,090
862,151
895,872
832,134
918,691
1,044,463
1,028,950
1,019,509
1,027,199
1,064,138
1,064,138
1,092,352
Includes Donovan Pavillion at $330K; employee housing rentals and parking structure leases
-4.0%
-5.5%
3.9%
-7.1%
10.4%
24.2%
-1.5%
-0.9%
0.8%
3.6%
3.6%
2.7%
E911 and Interagency Dispatch
1,904,572
1,908,591
1,958,581
1,915,218
1,982,170
1,931,359
1,896,010
1,918,590
2,008,451
2,042,068
2,042,068
2,082,909
Funding by E911 Authority Board and participating agencies
14.9%
0.2%
2.6%
-2.2%
3.5%
-2.6%
-1.8%
1.2%
4.7%
1.7%
1.7%
2.0%
2019 Red Sandstone parking garage
Vail Reinvestment Authority Transfers
-
1,070,365
7,125,196
5,354,864
1,842,286
3,049,280
2,757,637
3,546,063
4,179,718
4,202,023
4,202,023
1,550,000
N/A
565.7%
-24.8%
-65.6%
65.5%
-9.6%
28.6%
17.9%
0.5%
0.5%
-63.1%
Sale of Chamonix Housing Units
-
17,693,900
17,693,900
Project Reimbursment Red Sandstone
-
5,800,000
5,800,000
$4.3M from Vail Resorts; $1.5 from Eagle County School District cost share of RSES parking structure
All Other Revenue
4,885,916
7,957,308
6,463,634
4,725,743
4,725,539
7,522,484
9,577,305
7,783,483
7,358,044
6,188,318
5,803,679
5,865,200
In general, this item includes franchise fees, fines and forfeitures, employee portion of healthcare
-24.8%
62.9%
-18.8%
-26.9%
0.0%
59.2%
27.3%
-18.7%
-5.5%
-15.9%
-21.1%
1.1%
premiums, license revenue, administration fees collected from VLMD and RETT and other charges
for service such as out of district fire response and Police contracted services. It may also include
use of Traffic Impact fees or Holy Cross Community Enhancement Funds
Total Revenue
% compared to Prior Year
43,924,542
57,973,811
58,661,907
55,007,762 53,610,347
64,907,014
67,950,130
67,480,345
66,936,720
91,853,343
92,136,664
66,196,684
-24.3%
32.0%
1.2%
-6.2% -2.5%
21.1%
4.7%
-0.7%
-0.8%
37.2%
37.6%
-28.2%
-2.2%
Without one-time Chamonix sales & RSES reimbursement & Fed'I grants
August 21, 2018 - Page 42 of 82
TOWN OF VAIL 2019 PROPOSED BUDGET
SUMMARY OF REVENUE, EXPENDITURES, AND CHANGES IN FUND BALANCE
CAPITAL PROJECTS FUND
Increased cost from prior 5-year plan
Project timing changed from prior 5-year plan
Revisions / newly added project ■
* Placeholder items
2018
2018
Amended
Forecast
2019
2020
2021
2022
2023
Revenue
3%
3%
3%
3%
3%
Total Sales Tax Revenue:
$ 26,046,000
$ 26,046,000
$ 26,850,000
$ 27,656,000
$ 28,486,000
$ 29,341,000
$ 30,221,000
2019 at 2.5% increase from 2018 amended budget (5.5% increase from 2017 actuals);
Sales Tax Split between General Fund & Capital Fund
62/38
62/38
62/38
62/38
62/38
62/38
62/38
Sales Tax - Capital Projects Fund
$ 9,897,000
$ 9,897,000
$ 10,205,000
$ 10,509,000
$ 10,825,000
$ 11,150,000
$ 11,484,000
Use Tax
1,975,900
$ 1,975,900
2,220,000
1,750,000
1,803,000
1,857,000
1,913,000
2019 based on two year average plus estimated for Lion View, Park Meadows, and Launch Projects; 2020 based on 5
year average then 3% increase
Other County Revenue
260,302
$ 260,302
-
-
_
_
$260.3K reimbursement for radios from Eagle County Sheriffs Office, Eagle County Health Services District, and Avon
Police Department
Other State Revenue
83,691
$ 893,750
-
525,287
-
-
-
Forecast includes $675K FASTER grant to cover 80% of two buses and $135K state grant transferred to CPF from RETT
for PW runoff 2018: $83.7K DOLA grant for license plate readers (2 vehicles) and upgraded police intel sharing software;
2020: $525,287 CDOT bus grant
Lease Revenue
159,135
$ 159,135
164,067
164,067
164,067
164,067
164,067
Per Vail Commons commercial (incr. every 5 years); adjusted to remove residential lease revenue ($38K)
Sales of Chamonix Housing Development Units
17,693,900
$ 17,693,900
--
-
-
-
Sale of Chamonix Housing Units
Project Reimbursement
6,989,416
$ 6,989,416
200,000
00,000
200,000
2018: Red Sandstone parking structure reimbursement with $4.3M from Vail Resorts and $1.5M from Eagle County
School District; $50K Use of Holy Cross Community Enhancement Funds to offset project to bury electric lines from
Liftside to Glen Lyon Office Building- see corresponding expense below; $1.1M use of Holy Cross Enhancements funds to
be used towards Big Horn Rd and Intermountain during 2018; 2021: $1.5M from traffic impact fee for Vail Health/
Frontage Road Project; 2019-2023 $200K reimbursement from Holy Cross for 2019/2020 Big Horn Rd and Intermountain
project
Timber Ridge Loan repayment
489,419
$ 489,419
463,171
463,129
463,086
463,043
462,999
$28.5K interest on $1.9M loan to TR; Principal and interest on $8M loan to Timber Ridge Fund
Earnings on Investments and Other
38,723
38,723
92,899
74,292
33,167
22,039
77,436
0.7% rate assumed on available fund balance
Total Revenue
37,587,486
38,397,545
13,345,137
13,685,775
14,988,320
13,856,149
14,301,502
Expenditures
Capital Maintenance
Bus Shelters
118,825
118,825
30,000
230,000
697,000
30,000
30,000
30,000
Annual maintenance; Re-appropriate for repairs to Spruce Way bus shelter and lights; 2020 Lionshead transit center
Westbound Bus shelter
Parking Structures
695,000
695,000
700,000
795,000
785,000
950,000
2018-2022 Various repairs including deck topping replacement, expansion joint repairs, ventilation, HVAC, plumbing and
other structural repairs; 2023 includes $200K for expansion joint replacement
Welcome Center Interior
250,000
250,000
-
-
100,000
-
-
2018: Furniture replacement for Lionshead Welcome Center- current furniture has reached it's 5 year life. This includes
paint and built in desks; 2021: Furniture replacement in Vail Village Welcome Center
Children's Garden of Learning-Boiler replacement
12,800
12,800
-
-
-
-
-
Council contribution for a new boiler at the Children's Garden of Learning. The town owns the building
Traffic Impact Fee and Transportation Master Plan Updates
233,482
233,482
--
-
-
-
2018: 20-year Transportation Master Plan to coincide with West Vail Master Plan and Civic Center Master Plan
Neighborhood Bridge Repair
689,134
689,134
350,000
-
350,000
-
-
Major Bridge Repair Projects based on bi-annual bridge inspection; 2018: Kinnickinnick (West) Bridge Repair, West
Forest Bridge Repair; 2019: Lupine Bridge Repair; 2021: Placeholder based on bridge inspection reports
Facilities Capital Maintenance
476,000
476,000
393,000
372,500
523,500
489,500
615,000
2018 - 2022 various repairs to town buildings including the upkeep of exterior (roofing, siding surfaces, windows, doors),
interior finishes (paint, carpet, etc.), and mechanical equipment (boilers, air handlers, etc.). 2018: Comm Dev kitchen
update ($25K), transit offices skylight replacement ($50K); Buzzard Park repairs ($67.5K), PW and bus barn
maintenance including window replacement($92K), PW admin carpet replacements ($50K)' library door replacement
($25K); 2019: PW admin heated walkway repair ($50K), PW admin kitchen update ($15K), PW shops and bus barn
maintenance including wood siding maintenance and exhaust system replacement ($130K), TM residence roof,
skylight, and solar panel ($70K); 2020:PW garage door replacements ($50K), transit station skylight replacement
($50K); 2021: PW shops fire panel replacement ($40K), garage door replacements ($50K), PW boiler replacement
($20K), 2nd phase of transit center skylight replacement ($50K), Buzzard Park repairs ($41 K); 2022: Fire Station interior
paint ($35K), Library Skylight maintenance ($150K), PW roof repairs ($50K), Phase 3 of transit center skylight
replacement ($50K); 2023: Fire Station II exhaust extraction system $(75K), library air handling replacement ($125), Bus
barn gradient tube replacement ($50K)
Municipal Complex Maintenance
138,
798,000
255,000
335,000
2019: PD window replacement ($80K), PD circulation pump repairs and replacement ($15K), PD elevator drive
controls ($44K); 2020: Replace Admin building air handlers ($250K), Comm Dev roof replacement ($125K), Comm Dev
interior flooring replacement ($25K), PD balcony repairs ($50K), PD boiler replacement ($45K), replace PD air handling
205,000 units ($75K), replace PD rooftop units ($125K); 2021:Admin Upper level system installation ($175K), PD Stucco patching
and painting ($40K), PD wood siding replacement ($30K); 2022: Replace HR heat system ($100K); 2020: PD locker room
and restroom repairs ($50K), Comm Dev window replacement ($100K), Comm Dev interior wall and ceiling maintenance
($30K); 2023: Comm Dev boiler replacement ($100K), Comm Dev air handler replacement ($75K)
August 21, 2018 - Page 43 of 82
TOWN OF VAIL 2019 PROPOSED BUDGET
SUMMARY OF REVENUE, EXPENDITURES, AND CHANGES IN FUND BALANCE
CAPITAL PROJECTS FUND
Increased cost from prior 5 -year plan
Project timing changed from prior 5 -year plan
Revisions / newly added project
* Placeholder items
2018
2018
Amended
Forecast
2019
2020
2021
2022
2023
Donovan Park Pavilion
15,000
15,000
5,000
755,100
5,100
5,100
5,100
Annual $5K Maintenance to repair HVAC; 2020 includes HVAC Replacement at Donovan Pavilion
Street Light Improvements
147,057
147,057
75,000
75,000
75,000
75,000
75,000
Annual maintenance to street lights; LED light enhancements
Capital Street Maintenance
1,220,000
1,220,000
1,225,000
1,345,000
1,225,000
1,405,000
1,350,000
On-going maintenance to roads and bridges including asphalt overlays, patching and repairs; culverts; 2022/2023 includes
Asphalt and Mill overlay ($575K)
East Mill Creek Culvert Replacement
-
-
-
-
-
-
Replacement of East Mill Creek culvert at Gold Peak and Vail Valley Drive
Snowmelt Boilers
-
-
-
500,000
500,000
500,000
500,000
Replacement of 8 boilers (2 per year)
Town -wide camera system
140,000
140,000
70,000
22,000
22,000
22,000
22,000
2018-2019 replace Bosch system(30 cameras); $22K Annual maintenance
Audio -Visual capital maintenance
18,000
18,000
18,000
18,000
18,000
18,000
18,000
Audio visual, phone and IT equipment for an EOC at the West Vail Fire Station
Document Imaging
30,000
30,000
30,000
30,000
30,000
30,000
30,000
Annual maintenance, software licensing, and replacement schedule for scanners and servers.
Software Licensing
217,000
217,000
144,410
146,193
147,417
63,665
63,665
2018-2020: Upgrade Microsoft products on all equipment; renewal of licenses; $3K per year increase from original 5 year
plan due to additional software products; 2018: Includes Virtual Desktop terminal services replacement; $75K placeholder
for Asset Management System in 2018, and $50K per year for 3 years (thru 2021)
Police Equipment
121,791
121,791
-
-
-
-
-
2018: Replace existing headsets, vests, and helmets for 6 SOU members ($20.5K), Upgrade mass casualty supplies in
patrol cars ($5.6K); DOLA grant for License plate readers for two vehicles ($65.3K) upgraded police Intel sharing platform
($18.4K); Replacement of 40 body worn cameras ($12K)
Thermal Imaging Cameras
-
-
12,000
12,000
-
12,000
12,000
For the purchase of 3 cameras (2019,2020,2022) which will allow firefighters to see through areas of smoke, darkness, or
heat barriers
Hardware Purchases
150,000
150,000
50,000
350,000
50,000
50,000
50,000
2018: Replacement of 50 workstations; $300K in 2020 for scheduled replacement of larger servers
Website and e-commerce
12,000
12,000
12,000
12,000
12,000
12,000
12,000
Internet security & application interfaces; website maintenance; includes $550/month for web hosting svcs
Fiber Optics / Cabling Systems in Buildings
62,000
62,000
90,000 15,000
15,000
15,000
15,000
2018-2020: Repair, maintain & upgrade cabling/network Infrastructure $15K; 2018: Install fiber optics from data center to
CenturyLink; 2019: NWCOG Project THOR Broadband project Meet Me Center $75K
Network upgrades
30,000
30,000
380,000 200,000
30,000
30,000
30,000
Computer network systems - replacement cycle every 3-5 years; 2019: Retrofit networking gear for public access
system installed in 2014 $350K; 2020 replacement of switches and routers
Phone System
77,220
77,220
-
-
2018: IPO Phone system replacement ($25.5K), normal replacement of Ipads, (phones $20K;phone system; replacement
of phones, headsets
Public Wi-Fi Systems
-
-
-
250,000
-
-
-
Upgrade/replace public Wi-Fi system initially installed by Crown Castle
Business Systems Replacement
338,700
338,700
-
-
30,000
2018: $1.3K for final bills for financial statement module, $160K for sales tax software, $90K STR software; $19K for Com
Dev project Docs software; $38K new bus scheduling software (approx. operating costs is $20/yr.); $30K every other year
for parking system upgrades
Public Safety System
97,768
97,768
119,000
50,000
50,000
50,000
50,000
Annual capital maintenance of "County -wide "Computer Aided Dispatch/Records Mgmt. System"; includes patrol car and
fire truck laptops and software used to push information to TOV and other agencies; TOV portion of annual Intergraph
software maintenance; ; 2018: Fire and police mobile data computer replacement ($24K); 2019: Long Range acoustical
device ($50K), fire prevention safety prop ($10K), personal protective equipment dryer ($9K)
Bus Camera System
-
-
15,000
15,000
-
-
-
Installation of software and cameras in buses; 2019/20 annual capital maintenance of camera replacement, etc.
Extrication Equipment
100,000
100,000
-
-
-
-
-
To purchase updated extrication equipment that will work with newer and more advanced vehicles
RHMAEC vehicle and equipment
60,000
60,000
-
-
_
_
-
TOV's portion of a RHMAEC(Regional Hazardous Association of Eagle County) vehicle and equipment- Eagle county is
putting $120K towards this vehicle.
Event Equipment
-
-
=PIM -
-
-
-
Event trailer and moveable barricades
Fire engine equipment
50,000
50,000
-
To purchase the necessary fire engine equipment to fully equip 4th fire engine; this will allow this vehicle to be used when
other engines our being repaired or in an emergency
Total Maintenance
5,361,777
5,361,777
3,962,160
5,892,793
4,263,017
4,477,265
4,062,765
2
August 21, 2018 - Page 44 of 82
TOWN OF VAIL 2019 PROPOSED BUDGET
SUMMARY OF REVENUE, EXPENDITURES, AND CHANGES IN FUND BALANCE
CAPITAL PROJECTS FUND
Increased cost from prior 5 -year plan
Project timing changed from prior 5 -year plan
Revisions / newly added project '
* Placeholder items
2018
2018
Amended
Forecast
2019
2020
2021
2022
2023
Priority A
8,000,000
Data Center (Computer Rooms)
909,036
15,000
15,000
15,000 2018: 1st half of data center equipment (HCI) 2019: 2nd half of hyper -converged infrastructure (HCI) equipment
$750K, Data Center remodel at Station 3 $1.2M, Cooling/UPS system upgrade for data center in Muni building $128K
Public Works Shops Expansion
150,000
150,000
5,5s . s i i
-
-
2018:$150K Design for PW building remodel; 2019: Expansion and remodel of the Public Works shop complex as
outlined in an updated public works master plan (previously completed in 1994). The plan will ensure shop
expansions will meet the needs of the department and changing operations, such as electrified buses into the
future. The plan will consider a shop building expansion, system upgrades, ADA upgrades, additional employee
- housing (in various locations including the current administration building), covered cold storage and the
expansion of the shop yard foot print to the north, project staging and space, snow dump expansion,
Photovoltaic Array as a major GHG emission offset, Frontage Road left turn lane, and hazard mitigations and
visual screening
Vehicle Expansion
265,000
265,000
115,100
80,000
-
-
2018: Snow Blower ($200K), Landscape architect truck ($30K), Drug Task Force vehicle ($35K); 2019: Police chief
- vehicle ($39K), building inspector vehicle ($37.1K), construction project manager vehicle ($39K); 2020: 2
commander vehicles ($80K)
Parking Entry System / Equipment
93,037
93,037
93,000
-
1,400,000
-
-
-
I12018:
850,000
ii
Ongoing parking equipment maintenance; $75K for conversion of Ford Park gates to automatic ticketing system to
enhance Ford Park parking management; 2019: Spare parking system equipment including ticket creator, ticket
processor, ticket feeder, circuit boards, power supply modules, print heads ($93K); 2023: New parking equipment
Neighborhood Bridge Reconstruction
1,554,106
1,554,106
450,000
-
-
-
2018/ 2019: Bridge Road Bridge replacements; 2020: Nugget Lane Bridge Reconstruction
East Meadow Drive Snowmelt
800,000
-
54,740
800,000
-
54,740
750,000
VOW
-
-
-
-
2018: Design Snowmelt major repairs from Solaris to Austria House/Covered Bride area to be done at same time as the
Slifer Plaza construction. This includes paver removal, snowmelt, asphalt replacements with concrete pavers; 2019:
Installation of snowmelt system
illign Vail Roundabout
Neighborhood Road Reconstruction
-
-
-
-
3,500,000
-
-
-
2019: Main Vail Roundabout truck apron
-
-
2018: Continuation of shared drainage project that began in 2015 with ERWSD on Rockledge Rd/Frontage Rd; 2019:
East Vail major drainage improvements; 2021: East Vail road Major Drainage Improvements construction ($3.5M),
street total reconstruction eliminated (was $9M+)
Data Center equipment replacement and generator
300,000
300,000
-
-
2018: Replace data center server infrastructure; upgrade and replace emergency generator to increase capacity
Lionshead Express Bus Stop Improvements (VRA)
400,000
400,000
-
-
-
-
-
2018: Improvements to Lionshead Express Bus stop to allow for West bound stop and turnaround
Vail Spa Heated Walk (VRA)
250,000
250,000
-
-
2018: Connect the Lion with Vail Spa via heated sidewalks; $43K reimbursement from the Lion with remaining $206K to
be reimbursed by VRA
Heated walkway between underpass and 1st chair (VRA)
281,432
281,432
-
-
-
-
-
2018: Heated walkway between new underpass and 1st chair building
Energy Enhancements
87 899
87 899
-
-
_
2018: Continuation of energy audit enhancements; includes LED lighting project with shared cost of $170K from Holy
Cross
Pedestrian Safety Enhancements
1,500,000
1,500,000
-
-
-
-
-
2018: Lighting for Main Vail roundabouts and West Vail Roundabouts (approved by council on 7/5/16)
West Vail Roundabout
350,000
350,000
-
-
-
-
-
2018: West Vail roundabout concrete replacement/repair near Marriott Streamside (currently there is exposed re -bar)
Library Self -Check System Updates
38,000
38,000
-
-
-
-
-
2018: Library replacement kiosk and security gate replacement
Chamonix- TOV
230,322
230,322
-
-
-
-
-
-
-
Chamonix contingency- TOV
Slifer Plaza/ Fountain/Storm Sewer
4,377,119
4,377,119
-
-
-
-
2018: Repairs to Silfer Plaza fountain and storm sewers; 2019: Includes placeholder for possible increase in scope
West Vail Interchange Sidewalk Repair
325,000
325,000
-
-
2018: To repair sidewalk damage underneath the 1-70 bridge
Lionshead Parking Structure Landscape Renovations (VRA)
100,000
100,000
-
-
-
-
-
2018: Improvements to parking structure landscaping around the eastern areas of the Vail Transportation Center where
trees have been lost and planting eroded by years of snow storage
Colorado Ski Museum renovation
500,000
500,000
-
-
-
-
-
2018: Town contribution toward expansion and remodel of Colorado Ski Museum
Radio Equipment replacement/expansion
860,340
860,340
-
-
-
-
_
2018: Additional Radios for backup radios and crew expansion; related yearly County fees ($10K) included in HEF;
Previously $693K budgeted in 2014 for replacement of approximately 59 radios for PW, PD and Fire. Adjusted to only
include radios purchased over 12 years ago (in 2008 the town replaced a number of radios; these will not be replaced until
2018)
Hybrid Bus Battery Replacement
431,772
431,772
-
-
-
-
-
2018: Scheduled replacement placeholder; Estimated life of 6 years; While batteries are passed their lifecycle
replacement has not been needed as of yet
Public Works Building Remodel
300,000
300,000
-
-
-
-
-
2018: $300K for PW HVAC (2)
Municipal Redevelopment
300,643
300,643
-
-
-
-
-
2018: planning of possible future municipal building redevelopment
Red Sandstone Parking Structure (VRA)
14,696,953
14,696,953
-
-
-
-
-
2018: Construction of 4 level parking structure at Red Sandstone Elementary school, with contributions from Vail Resorts
($4.3M) and Eagle County School District ($1.5M); Remainder to be reimbursed by VRA
Chamonix Housing Development
4,083,151
4,083,151
-
-
-
-
-
2018: Final construction of the Chamonix town home development project
3
August 21, 2018 - Page 45 of 82
TOWN OF VAIL 2019 PROPOSED BUDGET
SUMMARY OF REVENUE, EXPENDITURES, AND CHANGES IN FUND BALANCE
CAPITAL PROJECTS FUND
Increased cost from prior 5 -year plan
Project timing changed from prior 5 -year plan
Revisions / newly added project
* Placeholder items
2018
2018
Amended
Forecast
2019
2020
2021
2022
2023
1-70 Underpass (VRA)
492,990
492,990
-
-
-
-
-
2018: The town's portion to complete and pay final bills for the 1-70 underpass
East LH Circle pathway to Dobson (VRA)
93,560
93,560
-
-
-
-
_
2018: Planning and Design for project to Improve connection from the E Lionhead bus stop to Dobson originally scheduled
in 2016; Project has been moved to unfunded pending the civic center master plan revision
Dobson Plaza (VRA)
100,000
100,000
-
-
-
-
-
2018: Redevelop the center plaza of Dobson for better flow of bus traffic, people traffic (concerts); planning/design
originally scheduled in 2016; Project has been moved to unfunded pending the civic center master plan revision
Underground Utility improvements
2,188,066
2,188,066
-
-
-
-
-
2018: $50K for undergrounding electric between Glen Lyon office building and Liftside- see reimbursement above; $71K
for CDOT project; $2.1M for Big Horn Rd and Intermountain Eastern portion projects to be completed in 2018 using
Community Enhancement Funds ($1.1M reimbursement from the Holy Cross enhancement funds)
Public Works Equipment Wash Down/WO Improvements
246,967
246,967
-
-
-
-
-
2018: Exterior wash area for large trucks not safe in the winter; also includes improvement to how the waste water is
disposed
Total Priority A:
36,360,133
36,360,133
12,091,100
6,995,000
3,515,000
15,000
865,000
Priority B
Frail Village Streetscape/Snowmelt Replacement
Fire Truck Replacement
-
-
-
-
-
2,500,000 Replacement of 18 yr. old streetscape and snowmelt infrastructure in Vail Village
-
-
-
-
1,700,000
-
400,000 2021: Replacement of Ladder truck purchased in 2000; 2023: Type 3 Truck
Replace Buses
3,229,587
3,229,587
- 6,525,000
198,000
- -
-
-
-
2018: 7 buses ordered in 2017 scheduled for replacement and delivery in 2018 ($440.5K per bus); 2020 7 buses for
replacement at $875K each, plus 5 charging stations at $50K each, and $30K for additional power chargers. Grant funding
is being pursued.
Fire Station Alert System
9,000,000
2019: Fire Station Alerting System to improve response times. This system will work with the Dispatch system
and the timing is being coordinated with Eagle River Fire
Vail Health / TOV Frontage Road improvements
202,229
202,229
-
-
2018: Design phase of Vail Health/Frontage Rd improvements which includes a 3rd party review, utility potholing and
public information based on VH plans for expansion; Improvements would span from LH Parking structure to Municipal
building; Design funded by Traffic Impact Fee funds; Original Plan: 2021: VH plans for expansion; Improvements would
span from LH Parking structure to Municipal building; funded by VRA (Total $3.6M to be repaid by VRA in 2021, Traffic
impact fee ($1.5M), Remaining CPF & Developments ($3.9M) Timing of this project is pending the Civic Center Master
Plan
Total Priority B:
3,431,816
3,431,816
-
6,723,000
12,450,000
-
2,900,000
Priority C
Transit Stop Improvements
650,000
650,000
-
-
-
-
2,000,000
2018:Transit improvements at Vail Village Transit Center; Add pedestrian improvements, bus turning improvements to
West Vail Arosa bus stop in West Vail; 2023: Transit Stop Improvements to coincide with Timber Ridge Phase!!
Redevelopment
Vail Road Sidwalk Construction
-
-
-
-
-
550,000
2022: Sidewalk construction on Vail Rd. between Beaver Damn and Forest Rd.
Buffeher Creek Turn Lan.
-
-
-
-
-
1,450,000
-
2,500,000
150,000
2022: Turn Lane at Buffehr Creek to coincide with Marriott Residence Inn; This turn lane different from the one to be put in
by Marriott; project was originally scheduled for 2019 and delayed to 2021 to coincide with the Marriott construction
.... ... - ... - - ... ... ... - -- - -
Guest Services Enhancements/Wayfinding
-
-
-
-
-
-
2023: Replacement of 18 yr. old streetscape and snowmelt infrastructure in Lionshead
647,684
647,684
-
2023: Continuation of Guest Service / Wayfinding enhancements outside of VRA district; 2023: $150K for design phase of
town wide way finding replacement
Total Priority C:
1,297,684
1,297,684
-
-
-
2,000,000
4,650,000
Total Expenditures
46,451,410
46,451,410
16,053,260
19,610,793
20,228,017
6,492,265
12,477,765
Other Financing Sources (Uses)
Transfer from Vail Reinvestment Authority
4,202,023
4,202,023
1,550,000
(1,500,000)
(2,658,123)
1,550,000
(1,500,000)
(5,875,017)
5,150,000
(1,500,000)
(1,589,696)
2,050,000
I (1,500,000)
7,913,884
50,000
(1,500,000)
373,738
2018: $2.5M Red Sandstone, $400K Lionshead Express Bus Stop, $206K Vail Spa heated sidewalk, $100K $500K 1-70
underpass completion $100K LH parking structure improvements, $281K heated walk between ped overpass and First
Chair ; 2019: $1.5M Red Sandstone, 2020: $1.5M Red Sandstone, 2021: $3.6M Frontage Road Vail Health,$1.5M Red
Sandstone; 2022: $2M Red Sandstone
Transfer to Housing Fund
(2,261,550)
(2,261,550)h
Transfer to Housing Fund; 1.5M per year
Revenue Over (Under) Expenditures
(6,923,451)
(6,113,392)
Beginning Fund Balance
19,384,700
19,384,700 13,271,308
10,613,185
4,738,168
3,148,471
11,062,356
Ending Fund Balance
12,461,249
13,271,308 10,613,185
4,738,168
3,148,471
11,062,356
11,436,093
4
August 21, 2018 - Page 46 of 82
TOWN OF VAIL 2019 PROPOSED BUDGET
SUMMARY OF REVENUE, EXPENDITURES AND CHANGES IN FUND BALANCE
HOUSING FUND
Revenue
Housing Fee in Lieu (balance)
Housing Fee in Lieu (2017 collections)
Transfer from Capital Projects Fund (balance)
Capital Projects Funding - New
Total Revenue
Expenditures
InDEED Program
Solar Vail Housing Development
Buy Down Housing
Total Expenditures
Operating Income
Beginning Fund Balance
Ending Fund Balance
2017 2018 2019
Actual Amended Proposed
$ 3,112,482 $ - $ -
316,557 -
667,500 - 1,500,000
1,124,548 2,261,550 -
5,221,087 2,261,550 1,500,000
328,588
2,500,000 1,500,000
4,225,000
429,049
328,588 7,154,049 1,500,000
4,892,499 (4,892,499)
4,892,499
$ 4,892,499 $
$
August 21, 2018 - Page 47 of 82
5
August 21, 2018 - Page 48 of 82
TOWN OF VAIL 2019 PROPOSED BUDGET
SUMMARY OF REVENUE, EXPENDITURES, AND CHANGES IN FUND BALANCE
REAL ESTATE TRANSFER TAX
Increased cost from prior 5 -year plan
Project timing changed from prior 5 -year plan
visions / newly added project
2018
2018
Placeholder items
Amended
Forecast
2019
2020
2021
2022
2023
Revenue
3%
2%
2%
2%
2%
Real Estate Transfer Tax
$ 6,100,000
$ 6,100,000
$ 6,283,000
$ 6,471,500
$ 6,666,000
$ 6,866,000
$ 7,072,000
2019 anticipates 3% growth from 2018 budget (5 year average is 3.2%)
Golf Course Lease
165,000
165,000
166,650
168,317
170,000
171,700
173,417
Annual lease payment from Vail Recreation District; annual increase will be based on CPI until after
first 3 years under new lease; then revenue share potential will be reviewed; Rent income funds the
"Recreation Enhancement Account" below
Intergovernmental Revenue
235,847
800,847
1,170,000
20,000
20,000
20,000
20,000
2018 Forecast includes $700 CDOT TAP grant awarded in 2017 and will be received in 2018 upon
completion on the project in 2018, forecast also includes removal of $135K transferred to CPF for
water mitigation runoff grant; 2018: $135K State funding for water mitigation for PW runoff- See
corresponding expenditure below; $20K from Eagle County for Intermountain Fuels project; 2019-
2020: $20K Lottery fund proceeds; 2019 includes $150K reimbursement from ERWSC and $1M from
Eagle County for restabilization of Down Junction budget currently included in 2018 budget but will
take place in 2019
Project Reimbursements
6,000
6,000
-
-
-
-
-
2018: $6K Contribution from the Nature Conservancy for Intermountain Fuels Project
Donations
32,457
32,457
-
-
-
-
_
$28.4K donation from Vicki and Kent Logan Family Trust for installation of Lawrence Weiner art; $1K
donation from Varlaufer HOA for Roger Staub park maintenance access improvements included in the
capital maintenance budget; $1K donation from East West Partners for Sole Power prizes; $2.1K use
of Sole Power Donations
Recreation Amenity Fees
10,000
10,000
10,000
10,000
10,000
10,000
10,000
Earnings on Investments and Other
49,059
49,059
10,785
9,140
8,404
19,494
5,899
0.7% rate assumed; 2018: Reimbursement from bag fee collections for Clean -Up Day and America
Recycles Day.
Total Revenue
6,598,363
7,163,363
7,640,435
6,678,956
6,874,404
7,087,193
7,281,316
Expenditures
Operations
Forest Health Management
277,248
277,248
282,800
288,400
294,150
300,000
306,000
Operating budget for Wildland Fire crew
Annual Park and Landscape Maintenance
1,696,395
1,696,395
1,691,224
1,743,159
1,764,278
1,806,875
1,851,166
Ongoing path, park and open space maintenance, project mgmt.
Management Fee to General Fund (5%)
305,000
305,000
314,150
323,575
333,300
343,300
353,600
5% of RETT Collections - fee remitted to the General Fund for administration
Tree Maintenance
65,000
65,000
65,000
65,000
66,300
67,600
69,000
On going pest control, tree removal and replacements in stream tract, open space, and park areas
Alpine Garden Support
Nature Center Operation
Eagle River Watershed Support
69,700
45,450
69,700
45,450
70,397
46,814
71,101
80,000
48,218
71,812
80,000
49,182
72,530
80,000
50,166
73,255
80,000
51,169
Annual operating support of the Betty Ford Alpine Gardens; annual increase to follow town's general
operating annual increase
Nature Center operating costs including $65K Walking Mountains contract and $15K for maintenance
and utilities
Annual support of the Eagle River Watershed Council programs with 1% increase for 2017
Public Art - Operating
111,201
111,201
113,425
115,694
118,007
120,368
122,775
Art in Public Places programming
Environmental Sustainability
539,563
539,563
499,254
509,239
519,424
529,813
540,409
$3.1K for Sole Power awards and prizes- see corresponding donations above; $6K for two new E -
bikes for Town of Vail employee program; Environmental EMS system $34K ($12K re -appropriate
from 2017, $22K new funding), $2K Local Climate Resolution approved 12/5, $5K Annual Rocky
Mountain Climate Membership
Total Operations
3,109,557
3,109,557
3,163,064
3,244,386
3,296,454
3,370,651
3,447,374
Maintain Town Assets
Forest Health VHF Radios
31,863
31,863
-
-
-
-
_
2018: 13 VHF radios for Wildland crew ($2,450/each) for incidents outside of Eagle County; Will
enable communication with other agencies using this technology such as Summit County
Intermountain Fuels Reduction
74,328
74,328
-
-
-
-
_
Intermountain Fuels Project $63.3K Phase II; Nature Conservancy contribution $6K- See
corresponding reimbursement above; Phase III ($5K)
Street Furniture Replacement
25,000
25,000
90,000
90,000
85,000
85,000
85,000
Annual replacement or capital repairs, benches, recycling and bike racks; 2019 includes pedestrian
bridge inspection report ($25K), 2020 includes pedestrian bridge recommendations contract ($15K)
Rec. Path Capital Maint
110,986
110,986
85,000
87,550
90,177
92,882
95,668
Capital maintenance of the town's recreation path system
5
August 21, 2018 - Page 48 of 82
6
August 21, 2018 - Page 49 of 82
TOWN OF VAIL 2019 PROPOSED BUDGET
SUMMARY OF REVENUE, EXPENDITURES, AND CHANGES IN FUND BALANCE
REAL ESTATE TRANSFER TAX
Increased cost from prior 5 -year plan
Project timing changed from prior 5 -year plan
visions / newly added project
2018
2018
Placeholder items
Amended
Forecast
2019
2020
2021
2022
2023
Park / Playground Capital Maintenance
235,076
235,076
125,000
128,750
132,613
136,591
140,689
Annual maintenance items include projects such as playground surface refurbishing, replacing bear -
proof trash cans, painting/staining of play structures, picnic shelter additions/repairs, and fence
maintenance; 2018 includes $54K increase for improvements to access into Stab Park
Alpine Garden - Capital Contribution
38,433
38,433
-
-
-
-
-
Contribution request to repair ADA pathways ($6K) and upgrade irrigation system ($19K)
Total Maintenance
515,686
515,686
300,000
306,300
307,789
314,473
321,357
Priority A
Vail Valley Drive Path Extension: Ford Park to Ptarmigan
Vail Valley Drive Path Extension: Ptarmigan West to GC Mtn
Building il
Wildland Fire Shelter
-
-
400,000 -
-
-
-
2019: Extension of Vail Valley Drive path to ease congestion and enhance pedestrian safety
-
-
400,000
17,500
585,000
67,000
-
-
-
-
2019: Extension of Vail Valley Drive path to ease congestion and enhance pedestrian safety
-
-
2019: 'To purchase a wildland shelter safety device
Ford Park: Softball Weather Shelter
-
-
-
-
-
-
2019: Shelter at the Ford Park softball fields to provide weather and lighting protection for
spectators and players
Ford Park Landscape Enhancement: Parking Lot/Sport
-
-
-
-
-
-
2019: DRB req'd parking lot plantings and landscape enhancements at Central Portal
Central Portal
Turf Grasp Reduction Pilot Project
-
- 30,000
-
-
-
-
2019: Turf grass reduction project at Buffehr Creek. This project will be a pilot example of ways
to reduce turf grass in areas across town resulting in water and maintenance savings
Gore Valley Trail Bridge Replacement
Covered Bridge Pocket Park Rehabilitation
Nature Center New
Open Space Land Acquisition
-
- 300,000
-
-
_
-
2019: Reconstruction of south bridge abutment due to significant scour and replacement of
bridge structure
-
-
400,000
50,000
-
-
-
-
2019: Streambank stabilization, riparian enhancements, walking surface replacement Could be
one the riparian area projects
182,740
182,740
-
-
4,000,000
50,000
-
-
2018: Temporary Nature Center structure ($95.5K); Research on historical preservation and design
($17.8K); Exterior windows, doors, wood siding and slope roof ($69.8K); 2019: $400K Design for new
Nature Center Remodel/Structure; 2022: Construction of new Nature Center
150,000
150,000
-
-
-
-
-
2018: Acquisition of East Moran streamtract parcel; 2019/2023 $50K for open space surveys,
studies, titling, and appraisals
Stephens Park Safety Improvements
150,000
150,000
300,000
-
2019: Access improvements to include extended sidewalk, new stairs and other site
improvements; playground was built in 1990's
Gore Valley Trail Realignment
-
-
50,000
600,000
-
-
-
2019: Design Gore Valley Trail Realignment at Lionshead gondola; 2020: Gore Valley Trail
Realignment
Water Quality Infrastructure
2,512,181
2,377,181
1,000,000
100,000
85,000
1,000,000
400,000
60,000
1,000,000
300,000
1
60,000
-
-
2018 Forecast remove $135K for water mitigation at PW from grant for roof runoff supplemented in
2017; 2019-2021 funds to continue water quality improvement to Gore Creek; Stormwater site
specific water and water quality construction projects as part of "Restore the Gore"
Streambank Mitigation
900,458
900,458
-
-
2018: $30K Fishing is Fun grant for Gore Creek riparian habitat improvements; $38,847 Great
Outdoors grant for riparian plants near covered bridge and Vail Valley Drive; 2019: Riparian Site
specific construction projects for Water Quality Strategic Action Plan
Public Art -General program / art
646,585
646,585
60,000
60,000
To purchase sculptures, artwork, art programs and events; remainder is re -appropriated each year to
accumulate enough funds.
Public Art - Winterfest
352
352
30,000
30,000
30,000
30,000
30,000
Winterfest $30K per year
East Vail Water Quality TAPS
1,125,111
1,125,111
-
-
-
-
-
2018: East Vail Water Quality Improvements; $700K CDOT TAP grant funding budgeted in $700K -
revenue will be rolled in Supp 3 2018
East Vail Interchange Improvements
1,423,960
1,423,960
-
-
-
-
-
2018: Continuation of landscaping design and construction of the interchange
Dowd Junction repairs and improvements
2,138,515
2,138,515
-
-
-
-
-
2018: Re -stabilization of Dowd Junction path; Repairs to culverts, drainage, and preventative
improvements; project in cooperation with Eagle River Water and Sand (ERWSC); $150K
reimbursement from ERWSC and $1M reimbursement from Eagle County
6
August 21, 2018 - Page 49 of 82
7
August 21, 2018 - Page 50 of 82
TOWN OF VAIL 2019 PROPOSED BUDGET
SUMMARY OF REVENUE, EXPENDITURES, AND CHANGES IN FUND BALANCE
REAL ESTATE TRANSFER TAX
Increased cost from prior 5 -year plan
Project timing changed from prior 5 -year plan
-visions / newly added project
2018
2018
Placeholder items
Amended
Forecast
2019
2020
2021
2022
2023
■
Ford Park Improvements & Fields
262,620
146,220
-
-
-
-
-
2018: Softball field shelter currently undergoing re-evaluation ($116.4) ; Ford Park Soccer Field ADA
Route ($55K), East Ford Park special event power ($91.2K)
Streamtract Education/Mitigation
103,061
103,061
-
-
-
-
-
2018: Includes water quality and streamtract education, outreach, signage and marketing; water
quality personnel
Vail Transit Center Landscape
125,000
125,000
-
-
-
-
2018: 'Landscaping at Vail transit center to coincide with construction of additional bus lane at Vail
TRC
Golf Clubhouse & Nordic Center
118,729
118,729
-
-
-
-
-
2018: Completion of Clubhouse and Nordic Center;
Chalet Road Sport Courts
38,463
38,463
-
-
-
-
-
2018: Acoustic barriers to minimize noise at Chalet Road Sport Courts
Soft Surface Trails
168,109
168,109
-
-
-
-
-
2018: Trail enhancements to coincide with Open Lands plan discussions
Gore Valley Trail Reconstruction Conoco to Donovan
450,000
450,000
-
-
-
-
-
2018: Gore Valley Trail Reconstruction between Conoco and Donovan Pavilion
North Recreation Path Sun Vail to Pedestrian Bridge
235,000
235,000
-
-
-
_
-
2018: $235K for North Recreation Bike Path reconstruction on North Frontage road between Sun Vail
and the pedestrian Bridge to coincide with the Red Sandstone parking garage project
Bighorn Park Improvements
13,208
13,208
-
-
-
-
-
2018: Drainage repairs and improvements near pavilion $13.2K
Ford Park Portal Improvements
23,868
23,868
-
-
-
-
-
2018: Continue improvements to Ford Park entry points
■Seibert
Memorial Statue
150,000
150,000
-
-
-
-
-
2018: Placeholder for Pete Seibert Memorial statue- contingent upon remaining funds to be raised
during 2018 budget year
Open Lands Plan
404,623
404,623
-
-
-
-
-
2018: Continuation of Comprehensive Open Lands Plan Update
Booth Creek Park
40,000
40,000
-
-
-
-
-
2018: $40K to modify foot traffic pattern in park
Total Priority A
11,362,583
11,111,183
3,901,500
2,090,000
1,390,000
4,140,000
90,000
Priority B
■Ford
Park Landscape Enhancement: Bikes Racks at Sport
Courts
-
-
- 18,000 -
-
-
2020: Additional 12 space bike racks near restroom/concessions building
■Ford
Park Landscape Enhancement: Priority 3 Landscape
eare
-
-
- 68,000 -
-
-
2020: Landscape playground/basketball berm, softball frontageRd & east berms, below tennis
Ford Park: Synthetic Turf Replacements-
-
-
410,000 -
2020: Scheduled replacement of synthetic turf based on 7 year life expectancy
Athletic Field ADA Walkway-
-
-
326,000 -
-
-
2020: Construction of ADA compliant walkway between parking lot and Vail Valley Drive
R-. -n. .n- park Picnic Shelter-
-
-
-
50,000 -
-
2021: Modest 12'x12' shelter near volleyball court
Total Priority B-
-
-
822,000
50,000
-
-
Priority C
Buffehr Creek Park Safety Improvements-
-
-
-
-
240,000
-
2022: Replacement 20 -yr old "catalog" playground equipment with custom build
Buffehr Creek Park park picnic shelter-
-
-
-
-
60,000
2022: 15x 25' shelter at existing picnic area
■
Ford Park: Parking lot entry reconfiguration-
-
-
-
-
400,000
-
2022: Parking lot reconfiguration to improve turning and queuing characteristics of the parking lot entry
Library Landscape and reading area-
-
-
-
-
100,000 -
2022: Exterior landscaping and site work enhancements for an outdoor reading area
Ellefson Park Safety Improvements-
-
-
-
-
-
300,000
2023: Replacement 10 -yr old "catalog" playground equipment with custom build
Total Priority C-
-
-
-
-
800,000
300,000
VRD-Managed Facility Projects
Recreation Enhancement Account
305,094
305,094
166,650
168,317
170,000
171,700
173,417
Annual rent paid by Vail Recreation District; to be re -invested in asset maintenance;
Golf Clubhouse
-
-
65,000
-
-
40,000
-
2019: Wood trim replacement ($40K), AC and catering kitchen improvements ($30K); 2022:
Wood Trim replacement ($40K)
El
Athletic Field Restroom/Storage Building -
-
-
-
-
-
1,000,000
2023:Replacement of existing restroom/concession with new 2000 sq. ft restroom/storage building
7
August 21, 2018 - Page 50 of 82
8
August 21, 2018 - Page 51 of 82
TOWN OF VAIL 2019 PROPOSED BUDGET
SUMMARY OF REVENUE, EXPENDITURES, AND CHANGES IN FUND BALANCE
REAL ESTATE TRANSFER TAX
Increased cost from prior 5-year plan
Project timing changed from prior 5-year plan
visions / newly added project
2018
2018
Placeholder items
Amended
Forecast
2019
2020
2021
2022
2023
Golf Course Other
1,007,141
1,007,141
176,396
25,792
61,288
13,679
76,295
2019: parking lot asphalt repairs ($10K), repair asphalt at maintenance building ($3k), replace
roof on maintenance building ($161.2K), replace wood trim at maintenance building ($2.7K);
2020: Repair wood trim on maintenance building ($25.8K), 2021:Maintenance building HVAC
replacement ($17.7K), furnace replacement ($11.8K), gas fire replacement ($8.9K) ); 2022: parking lot
asphalt repairs ($11K), parking lots repairs at maintenance building ($3.3K; 2023: Repaint wood trim
($45K), clubhouse walkway repairs ($12.4k), replace drain pans and curb gutters ($18.8K)
Dobson Ice Arena
471,311
471,311
102,943
122,239
2,952
-
53,862
2018: complete pavers and concrete slab replacement ($54K)remodel rink bathrooms and changing
rooms ($131.1K), rock wall repair ($10.5K), clean wood structure ($38.2K), replace pumps ($45.9K),
redesign and rebuild electrical room ($120.2K); replace windows and heat pumps ($68K); 2019:
Repair exterior doors ($96K), window replacement ($7K); 2020: Repair exterior lighting ($22.9K),
Repaint and repair exterior wood trim and beams ($9.3K), replace copper piping ($75K); 2021:
Exhaust stack repairs ($3K); 2023:Grading and drainage improvements ($9.4K), rock wall replacement
($15K), repairs to brick pavers ($17.9K), replace HVAC ($12.5K)
Ford Park /Tennis Center Improvements
157,931
157,931
-
5,015
-
19,762
21,137
2018: Complete replace gutters ($9.3K), remodel bathrooms ($31K), replace lockers ($13.1K), furnace
($13.7K), hot water tank ($7.6K), and base board heaters ($18.6K); Stain wood siding of concessions
($5.6K) and restrooms ($5.6K), $50K for restroom remodel; 2020: Repair exterior doors ($5K); 2022:
Replace wood siding and trim ($4.5K), exterior siding of restrooms and concessions replacement
($15.2K); 2023: Clubhouse grading and drainage maintenance ($15.6K), Repairs to exterior doors
($5.5K)
Athletic Fields
35,523
35,523
-
-
11,659
123,510
-
2018: paint wood structure and exterior trim ($8K), rooftop replacement for restrooms and athletic field
($21.3K), Seal coat and crack fill in parking lot ($6K); 2021: Coat exterior gypsum board ($3.7K),
Repaved parking lot ($8K), 2022: Grading and drainage repairs ($136.9K), paint wood trim ($4.5K),
paint wood structure ($6.8K)
Gymnastics Center
52,089
52,089
-
-
-
35,470
-
Installation of cooling system in 2018 ($52K); 2022: Restroom remodel ($35.5K)
Total VRD-Managed Facility Projects
2,029,089
2,029,089
510,989
321,362
245,898
404,120
1,324,710
Total Expenditures
17,016,915
16,765,515
7,875,553
6,784,048
5,290,141
9,029,244
5,483,442
Revenue Over (Under) Expenditures
(10,418,552)
(9,602,152)
(235,117)
(105,092)
1,584,262
(1,942,051)
1,797,874
Beginning Fund Balance
11,142,915
11,142,915
1,540,763
1,305,646
1,200,554
2,784,816
842,766
Ending Fund Balance
$ 724,363
$ 1,540,763
$ 1,305,646
$ 1,200,554
$ 2,784,816
$ 842,766
$ 2,640,640
8
August 21, 2018 - Page 51 of 82
VAIL REINVESTMENT AUTHORITY
Summary of Revenue, Expenditures, and Changes in Fund Balance
Amended
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Revenue 0.0% 5.0% 0.0% 5.0% 0.0% 5.0% 0.0% 5.0% 0.0% 5.0% 0.0% 5.0%
Property Tax - LionsHead TIF 4,200,000 4,200,000 4,410,350 4,410,000 4,631,000 4,631,000 4,863,000 4,863,000 5,106,000 5,106,000 5,361,000 5,361,000 5,629,000
Property Tax - Vail Square Metro Districts 540,000 586,000 615,000 615,000 646,000 646,000 678,000 678,000 712,000 712,000 748,000 748,000 785,000
Federal Subsidy for BAB bonds 167,444 167,444 165,082 153,460 140,609 127,280 113,420 98,976 83,204 66,074 48,186 29,483 9,964
Project Reimbursement
Earnings on Investments 1,745 2,615 2,492 2,500 2,500 2,500 2,500 2,500 2,500 2,500 2,500 2,500 2,500
Total Revenue 4,909,189 4,956,059 5,192,924 5,180,960 5,420,109 5,406,780 5,656,920 5,642,476 5,903,704 5,886,574 6,159,686 6,140,983 6,426,464
Operating Expenditures
Professional Fees
Management Fee
Treasurer's Fee -LionsHead TIF
Treasurer's Fee -Vail Square Metro Districts
Vail Square Metro District Pass Through
Total Operating
Capital Outlay
Frontage Road improvements (LH Pkg to Muni)
LH Parking Structure Landscape Improvements
Red Sandstone Parking Garage ($9.2M)
East LH Circle Vantage Point Walkway
East LH Circle pathway to Dobson
Dobson Plaza
Lionshead Express Bus Stop Improvements (VRA)
Vail Spa Heated Walk (VRA)
Heated Walk Between Ped overpass and First Chair
1-70 Underpass - RAMP Project
Lionshead Parking Structure Capital Maintenance
Total Transfer to Capital Projects Fund
Total Expenditures before Financing
10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000
84,000 84,000 88,207 88,200 92,620 92,620 97,260 97,260 102,120 102,120 107,220 107,220 112,580
126,000 126,000 132,311 132,300 138,930 138,930 145,890 145,890 153,180 153,180 160,830 160,830 168,870
16,200 17,580 18,450 18,450 19,380 19,380 20,340 20,340 21,360 21,360 22,440 22,440 23,550
523,800 568,420 596,550 596,550 626,620 626,620 657,660 657,660 690,640 690,640 725,560 725,560 761,450
760,000 806,000 845,518 845,500 887,550 887,550 931,150 931,150 977,300 977,300 1,026,050 1,026,050 1,076,450
3,600,000
100,000
2,478,041 1,500,000 1,500,000 1,500,000 2,000,000
93,560
100,000
400,000
206,000
281,432
492,990
50,000 50,000 50,000 50,000 50,000
50,000 50,000
50,000 50,000
50,000 50,000
50,000 50,000
4,202,023
4,962,023
1,550,000
2,356,000
1,550,000
2,395,518
5,150,000
5,995,500
2,050,000
2,937,550
50,000 50,000 50,000 50,000 50,000 50,000 50,000 50,000
937,550 981,150 981,150 1,027,300 1,027,300 1,076,050 1,076,050 1,126,450
Financing
2010A Princ (535,000)
2010B Princ (555,000) (575,000) (595,000) (615,000) (640,000) (665,000) (695,000) (720,000) (750,000) (785,000) (820,000) (855,000)
Interest (526,753) (501,432) (471,662) (438,458) (401,741) (363,658) (324,058) (282,788) (237,726) (188,783) (137,675) (84,236) (28,467)
Fiscal Agent Fees (2,800) (2,800) (2,800) (2,800) (2,800) (2,800) (2,800) (2,800) (2,800) (2,800) (2,800) (2,800) (2,800)
Subtotal Financing (1,064,553) (1,059,232) (1,049,462) (1,036,258) (1,019,541) (1,006,458) (991,858) (980,588) (960,526) (941,583) (925,475) (907,036) (886,267)
Revenue Over (Under) Expenditures After Financing (1,117,387) 1,540,827 1,747,944 (1,850,798) 1,463,018 3,462,772 3,683,912 3,680,738 3,915,878 3,917,691 4,158,161 4,157,897 4,413,747
Beginning Fund Balance 3,064,772 1,741,707 3,282,534 5,030,478 3,179,681 4,642,699 8,105,471 11,789,383 15,470,121 19,386,000 23,303,690 27,461,852 31,619,748
Ending Fund Balance $ 1,947,385 $ 3,282,534 $ 5,030,478 $ 3,179,681 $ 4,642,699 $ 8,105,471 $ 11,789,383 $ 15,470,121 $ 19,386,000 $ 23,303,690 $ 27,461,852 $ 31,619,748 $ 36,033,495
August 21, 2018 - Page 52 of 82
VAIL TOWN COUNCIL AGENDA MEMO
ITEM/TOPIC: Break 10:30 am - 10:45 am
TOWN Of UAIL
August 21, 2018 - Page 53 of 82
VAIL TOWN COUNCIL AGENDA MEMO
ITEM/TOPIC: DRB / PEC Update
PRESENTER(S): Chris Neubecker, Planning Manager
ATTACHMENTS:
Description
August 1, 2018 DRB Meeting Results
August 13, 2018 PEC Meeting Agenda
TOWN OF 1 X41
August 21, 2018 - Page 54 of 82.
TOWN OF UAJt
DESIGN REVIEW BOARD
August 1, 2018, 3:00 PM
Town Council Chambers
75 S. Frontage Road - Vail, Colorado, 81657
1. Call to Order
1.1. Attendance
Present: Doug Cahill, David Campbell, Peter Cope, Bill Pierce
Absent: John Rediker
2. Project Orientation
2.1. 2:00 PM
3. Site Visits
3.1. 3971 Bighorn Road - Pitkin Creek Park Condominiums
3.2. 2810 Aspen Court - J adios Residence
3.3. 1278 Vail Valley Drive - Vail Golf Course Maintenance Building
3.4. 183 Gore Creek Drive - Sitzmark at Vail
4. Main Agenda
4.1. DRB18-0223 - Moore Residence
Final review of new construction
Address/Legal Description: 2841 Basingdale Boulevard/Lot 3, Block 8, Vail
Intermountain Development Subdivision
Applicant: Michael & Yoshimi Moore, represented by I ntermetrix Investments
Planner: Justin Lightfield
Doug Cahill moved to approve. David Campbell seconded the motion and it
passed (4-0).
Absent(1) Rediker
4.2. DRB18-0245 - Vail Golf Course
Final review of new construction (maintenance building)
Address/Legal Description: 1278 Vail Valley Drive/Parcel E, Unplatted
Applicant: Vail Golf Course, represented by Pierce Architects
Planner: Justin Lightfield
August 21, 2018 - Page 55 of 82
David Campbell moved to approve. Peter Cope seconded the motion and it
passed (3-0).
Abstair(1) Pierce
Absent(1) Rediker
4.3. DRB18-0260 - Sandstone Creek Club
Final review of an exterior alteration (paint/balconies/shingles/stone)
Address/Legal Description: 1020 Vail View Drive/Lots B4 & B5, Block B,
Lion's Ridge Subdivision Filing 1
Applicant: Sandstone Creek Club, represented by Steve Gerhardt
Renovations, Inc.
Planner: Chris Neubecker
1. Applicant shall install horizontal lap siding above and below all windows.
2. Applicant shall install board and batten siding at all balcony dividers.
3. Green board and batten balcony divides shall be wrapped with green
trim board.
Doug Cahill moved to approve with conditions. Peter Cope seconded the
motion and it passed (4-0).
Absent(1) Rediker
4.4. DRB18-0298 - Sitzmark at Vail Inc.
Final review of an exterior alteration (deck)
Address/Legal Description: 183 Gore Creek Drive/Lot A, Block 5B, Vail
Village Filing 1
Applicant: Sitzmark at Vail Inc., represented by Victor Mark Donaldson
Architects
Planner: Chris Neubecker
Doug Cahill moved to approve. Peter Cope seconded the motion and it
passed (4-0).
Absent(1) Rediker
4.5. DRB18-0352 - Betty Ford Alpine Gardens
Final review of an exterior alteration (playhouse)
Address/Legal Description: 522 South Frontage Road East / Unplatted
Applicant: Betty Ford Alpine Gardens, represented by Nanette Kuich
Planner: Chris Neubecker
1. Applicant shall paint all trim white.
2. Applicant shall paint bottom wood dark brown to match logs on
schoolhouse.
3. Applicant shall paint door to match door color on schoolhouse
4. Applicant shall paint all window divides white.
5. Green siding shall match green on schoolhouse.
6. Bottom wood shall be replaced with log look material.
Doug Cahill moved to approve with conditions. David Campbell seconded the
motion and it passed (4-0).
August 21, 2018 - Page 56 of 82
Absent(1) Rediker
4.6. DRB18-0321 - Jadlos Residence
Conceptual review of new construction (single family)
Address/Legal Description: 2810 Aspen Court/Lot 13, Vail Village Filing 11
Applicant: James Jadlos, represented by KH Webb Architects
Planner: Chris Neubecker
4.7. DRB18-0292 - Ski Club Vail
Final review of a change to approved plans (windows)
Address/Legal Description: 598 Vail Valley Drive/Tract B, Vail Village Filing 7
Applicant: Ski Club Vail, represented by K.H Webb Architects
Planner: Jonathan Spence
David Campbell moved to approve. Peter Cope seconded the motion and it
passed (4-0).
Absent(1) Rediker
4.8. DRB 18-0307 - Breakaway West
Final review of a change to approved plans (trash enclosure)
Address/Legal Description: 963 Lions Ridge Loop Building 500/Lot B3,
Block B, Lion's Ridge Subdivision Filing 1
Applicant: Breakaway West, represented by Pierce Architects
Planner: Jonathan Spence
David Campbell moved to approve. Peter Cope seconded the motion and it
passed (3-0).
Abstair(1) Pierce
Absent(1) Rediker
4.9. DRB18-0324 - Pitkin Creek Park Condominium Association
Final review of an exterior alteration (stairs)
Address/Legal Description: 3931 Bighorn Road/Pitkin Creek Park Phase 1
Applicant: Pitkin Creek Park Condominium Association, represented by
Saundra L Spaeh Architect PC
Planner: Jonathan Spence
1. The roofing material and color shall match the approved roofing of the
associated building, as demonstrated on the building permit
application.
David Campbell moved to approve with conditions. Peter Cope seconded the
motion and it passed (4-0).
Absent(1) Rediker
4.10. DRB18-0349 - Pitkin Creek Park Condominium Association
Final review of an exterior alteration (reroof)
Address/Legal Description: 3971 Bighorn Road/Pitkin Creek Park Phase III
Applicant: Pitkin Creek Park Condominium Association, represented by
August 21, 2018 - Page 57 of 82
Snowcap Roofing
Planner: Jonathan Spence
Doug Cahill moved to table to August 15, 2018. David Campbell seconded the
motion and it passed (4-0).
Absent(1) Rediker
4.11. DRB18-0327 - Golden Peak Enterprises LLC
Final review of a change to approved plans (design changes)
Address/Legal Description: 815 Potato Patch Drive/Lot 2, Block 1, Vail
Potato Patch Filing 1
Applicant: Golden Peak Enterprises LLC, represented by Pierce Architects
Planner: Jonathan Spence
David Campbell moved to approve. Doug Cahill seconded the motion and it
passed (2-0).
Abstair(2) Cope, Pierce
Absent(1) Rediker
5. Staff Approvals
5.1. B18-0269 - West Vail Associates LTD
Final review of an exterior alteration (reroof)
Address/Legal Description: 2455 Garmisch Drive/Lot 7-9, Block H, Vail Das
Schone Filing 2
Applicant: West Vail Associates LTD, represented by Master Sealers Inc.
Planner: Glen Morgan
5.2. B18-0270 - Phillips Residence
Final review of an exterior alteration (reroof)
Address/Legal Description: 2696 Davos Trail/Lot 6, Block C, Vail Ridge
Subdivision
Applicant: Michael & Carol Phillips, represented by Master Sealers Inc.
Planner: Glen Morgan
5.3. B18-0271 - Pitkin Creek Park Condominiums
Final review of an exterior alteration (re -roof)
Address/Legal Description: 3971 Bighorn Road/Pitkin Creek Park Phase III
Applicant: Pitkin Creek Park Condominiums, represented by Snowcap
Roofing
Planner: Glen Morgan
5.4. B18-0279 - Fratarcangeli Residence
Final review of an exterior alteration (windows)
Address/Legal Description: 884 Spruce Court/Lot 10, Vail Village Filing 9
Applicant: Gina Fratarcangeli, represented by Home Depot USA Inc.
Planner: Glen Morgan
5.5. DRB18-0265 - Ghate Residence
August 21, 2018 - Page 58 of 82
Final review of an exterior alteration (deck)
Address/Legal Description: 1890 Lions Ridge Loop Unit 5/Lot 27, Bock 2,
Lion's Ridge Subdivision Filing 3
Applicant: Raju & Jennifer Ghate, represented by ECE Design Build
Planner: Jonathan Spence
5.6. DRB18-0272 - West Vail Associates LTD
Final review of an exterior alteration (siding)
Address/Legal Description: 2455 Garmisch Drive/Lot 7-9, Block H, Vail Das
Schone Filing 2
Applicant: West Vail Associates LTD, represented by Above All Construction,
Inc.
Planner: Jonathan Spence
5.7. DRB18-0279 - Vucich Residence
Final review of an exterior alteration (reroof)
Address/Legal Description: 4957 Juniper Lane Unit E/Lot 3, Block 4,
Bighorn Subdivision 5th Addition
Applicant: Karen A. Vucich Revocable Trust, represented by Umbrella
Roofing
Planner: Chris Neubecker
5.8. DRB18-0283 - Rembert Residence
Final review of an exterior alteration (landscaping)
Address/Legal Description: 1547 Spring Hill Lane/Lot 2, Vail Valley Filing 2
Applicant: Marlene & Frank Rembert, represented by Ceres Landcare
Planner: Justin Lightfield
5.9. DRB18-0285 - Bolton Residence
Final review of an exterior alteration (paint/deck/drainage/walkway)
Address/Legal Description: 2832 Kinnikinnick Road Unit 5A/Lot 5, Innsbruck
Meadows Subdivision
Applicant: Robert & Mary Bolton, represented by Labine Builders, Inc.
Planner: Justin Lightfield
5.10. DRB18-0286 - Ronck Residence
Final review of an exterior alteration (landscaping)
Address/Legal Description:
4301 Glen Falls Lane/Lot 1, Forest Glen Subdivision
Applicant: Bryan & Catherine Ronck, represented by Old Growth Tree
Service
Planner: Jonathan Spence
5.11. DRB18-0289 - Sunlight Condominium Association
Final review of an exterior alteration (windows)
Address/Legal Description: 2289 Chamonix Lane/Lot 6, Block A, Vail Das
Schone Filing 1
Applicant: Sunlight Condominium Association, represented by Crockford
August 21, 2018 - Page 59 of 82
Builders
Planner: Justin Lightfield
5.12. DRB18-0291 - Langmaid Residence
Final review of an exterior alteration (windows/siding)
Address/Legal Description: 2940 Manns Ranch Road Unit 2/Lot 9, Block 1,
Vail Village Filing 13
Applicant: Charles & Patricia Langmaid, represented by Casabonne
Enterprises, Inc.
Planner: Chris Neubecker
5.13. DRB18-0297 - Shoup Residence
Final review of an exterior alteration (garage doors/railings)
Address/Legal Description: 1100 Hornsilver Circle/Lot 7, Block 1, Vail Village
Filing 8
Applicant: Thomas Shoup
Planner: Jonathan Spence
5.14. DRB18-0301 - St. Moritz Holdings LLC
Final review of an exterior alteration (landscaping)
Address/Legal Description: 1285 Westhaven Circle North/Lot 47, Glen Lyon
Subdivision
Applicant: St. Moritz Holdings LLC, represented by Old Growth Tree Service
Planner: Justin Lightfield
5.15. DRB18-0302 - Sandstone Park Condominiums Association
Final review of an exterior alteration (decks/stairs)
Address/Legal Description: 945 Red Sandstone Road/Lot B7, Block B,
Lion's Ridge Subdivision Filing 1
Applicant: Sandstone Park Condominiums Association, represented by A4S
LLC
Planner: Jonathan Spence
5.16. DRB18-0303 - Vail Golf Course Townhomes Association
Final review of an exterior alteration (re -roof)
Address/Legal Description: 1610 Sunburst Drive/Lot 1, Sunburst Filing 3
Applicant: Vail Golf Course Townhomes Association, represented by
Umbrella Roofing Inc.
Planner: Justin Lightfield
5.17. DRB18-0308 - Vail Heights Condominiums
Final review of an exterior alteration (reroof)
Address/Legal Description: 2059 Chamonix Lane/Lot 16, Vail Heights Filing
1
Applicant: Vail Heights Condominiums, represented by Umbrella Roofing
Planner: Jonathan Spence
5.18. DRB18-0309 - Vail Conoco Station
Final review of an exterior alteration (canopy/columns)
August 21, 2018 - Page 60 of 82
Address/Legal Description: 2154 South Frontage Road West/Unplatted
Applicant: Vail Service Stations LLC, represented by KTK General
Contracting Limited
Planner: Chris Neubecker
5.19. DRB18-0311 - Cahill Residence
Final review of an exterior alteration (paint)
Address/Legal Description: 2855 Snowberry Drive/Lot 6, Block 9, Vail
Intermountain Development Subdivision
Applicant: Douglas Cahill
Planner: Jonathan Spence
5.20. DRB18-0312 - Welaj Residence
Final review of a change to approved plans (windows/guardrail)
Address/Legal Description: 5177 Black Gore Drive Unit B1/Lot B1 -B4,
Cedar Point Townhouses Subdivision Filing 2
Applicant: John Welaj, represented by Suman Architects
Planner: Justin Lightfield
5.21. DRB18-0313 - Grace Residence
Final review of an exterior alteration (snowmelt/exhaust)
Address/Legal Description: 4410 Columbine Drive/Lot 1, White River
Estates
Applicant: Eugene W. Grace Trust - Mari Jo Grace Trust, represented by
Barefoot Construction
Planner: Chris Neubecker
5.22. DRB18-0314 - Plzak Residence
Final review of an exterior alteration (reroof)
Address/Legal Description: 740 Sandy Lane/Lot 4, Vail Potato Patch Filing 2
Applicant: Maximilian & Elizabeth Plzak, represented by Red Eagle
Construction
Planner: Jonathan Spence
5.23. DRB18-0317 - Sunlight Condominiums
Final review of an exterior alteration (repaint)
Address/Legal Description: 2289 Chamonix Lane/Lot 6, Block A, Vail Das
Schone Filing 1
Applicant: Sunlight Condominium Association
Planner: Jonathan Spence
5.24. DRB18-0318 - Storr Residence
Final review of a change to approved plans (solar)
Address/Legal Description: 1965 Sunburst Drive/Lot 11, Vail Valley Filing 3
Applicant: Hans G. Storr Revocable Trust, represented by Sipes Architects,
Inc.
Planner: Justin Lightfield
August 21, 2018 - Page 61 of 82
5.25. DRB18-0319 - Harman Residence
Final review of an exterior alteration (Landscaping)
Address/Legal Description: 4290 Columbine Drive/Parcel D, Bighorn
Subdivision
Applicant: Jeremy Harman
Planner: Jonathan Spence
5.26. DRB18-0320 - FB50 LLC
Final review of an exterior alteration (windows)
Address/Legal Description: 151 Vail Lane Unit 11/Tract B, Front Door Three
Dimensional Subdivision
Applicant: FB50 LLC, represented by SRE Building Associates
Planner: Jonathan Spence
5.27. DRB18-0326 - Schacht Residence
Final review of a change to approved plans (GRFA change)
Address/Legal Description: 1800 Sierra Trail/Lot 25, Vail Village West Filing
1
Applicant: Robert & Selina Schacht Family Trust, represented by Current
Architects
Planner: Justin Lightfield
5.28. DRB18-0329 - Gazioglu Residence
Final review of an exterior alteration (landscaping)
Address/Legal Description: 3120 Booth Falls Court/Lot 7, Block 2, Vail
Village Filing 12
Applicant: Halide Gazioglu, represented by Ceres Landcare
Planner: Justin Lightfield
5.29. DRB18-0331 - Sigfusson Residence
Final review of an exterior alteration (landscaping)
Address/Legal Description: 1370 Sandstone Drive Unit 14/Lot G3, Lion's
Ridge Subdivision Filing 2
Applicant: Andrew Sigfusson, represented by Ceres Landcare
Planner: Jonathan Spence
5.30. DRB18-0339 - Lionshead Mall
Final review of an exterior alteration
Address/Legal Description: Lionshead Mall
Applicant: Town of Vail, represented by John King
Planner: Justin Lightfield
5.31. DRB 18-0340 - Town of Vail
Final review of an exterior alteration (windows)
Address/Legal Description: 1329 Elkhorn Drive/Unplatted TOV Public Works
Buzzard Park Employee Housing
Applicant: Town of Vail, represented by John King
Planner: Justin Lightfield
August 21, 2018 - Page 62 of 8'
5.32. DRB18-0342 - Galvin Residence
Final review of a change to approved plans (?)
Address/Legal Description: 303 Gore Creek Drive Unit 9/Lot 9, Block 5, Vail
Village Filing 1
Applicant: Christopher B. Galvin Revocable Trust, represented by Shepherd
Resources, Inc.
Planner: Jonathan Spence
5.33. DRB18-0343 - Sun Up Trust
Final review of a change to approved plans (?)
Address/Legal Description: 303 Gore Creek Drive Unit 10/Lot 10, Block 5,
Vail Village Filing 1
Applicant: Sun Up Trust, represented by Shepherd Resources, Inc.
Planner: Jonathan Spence
5.34. DRB18-0347 - Vail Golfcourse Townhomes
Final review of an exterior alteration (landscaping)
Address/Legal Description: 1730 Golf Lane/Area A, Sunburst at Vail
Applicant: Vail Golfcourse Townhomes, represented by Ceres Landcare
Planner: Jonathan Spence
5.35. DRB18-0348 - Savoy Villas Condominiums
Final review of an exterior alteration (landscaping)
Address/Legal Description: 1200 Lions Ridge Loop/Simba Run Subdivision
Applicant: Savoy Villas Condominiums, represented by Ceres Landcare
Planner: Jonathan Spence
5.36. DRB18-0354 RS2 LLC
Final review of a changes to approved plans (windows)
Address/Legal Description: 4273 Columbine Drive/Lot 16, Block 9, Bighorn
Subdivision 3rd Addition
Applicant: RS2 LLC, represented by La Dolce Architecture Inc.
Planner: Justin Lightfield
The applications and information about the proposals are available for public inspection during
regular office hours at the Town of Vail Community Development Department, 75 South
Frontage Road. The public is invited to attend the project orientation and the site visits that
precede the public hearing in the Town of Vail Town Council Chambers. Times and order of
items are approximate, subject to change, and cannot be relied upon to determine at what time
the Design Review Board will consider an item. Please call 970-479-2138 for additional
information. Sign language interpretation available upon request with 24-hour notification, dial
711.
August 21, 2018 - Page 63 of 82
PLANNING AND ENVIRONMENTAL COMMISSION
TOWN OF UAJi August 13, 2018, 1:00 PM
Town Council Chambers
75 S. Frontage Road - Vail, Colorado, 81657
1. Call to Order
Attendance
Present: Brian Gillette, Ludwig Kurz, Rollie Kjesbo, Pam Hopkins, John
Ryan Lockman and Brian Stockmar
Absent: Karen Perez
2. Site Visits
2.1. 680 Lionshead Place - Antlers Condominiums
Main Agenda
3. A request for the review of a Major Exterior Alteration, pursuant to Section 12-7H-7, 45 Min.
Exterior Alterations or Modifications, Vail Town Code, to allow for the conversion of
offices and a meeting room into one (1) dwelling unit, expansion of the existing lobby
and check-in area with an elevator serving all levels, and the construction of second
level offices above the existing lobby, located at 680 Lionshead Place/Vail Lionshead
Filing 3 (Antlers Condominiums), and setting forth details in regard thereto. (PEC18-
0029)
ApplicantAntlers Condominiums, represented by GPSL Architects
Planner: Chris Neubecker
1. Approval of this project is contingent upon the applicant obtaining
Town of Vail design review approval for this proposal.
2. The Transportation Impact Fee shall be paid to the Town of Vail by
the applicant prior to issuance of any building permit.
Spence — code allows PEC special approval for parking requirements
Henry Pratt — intent is to "decompress" the office spaces and free up
spaces in the parking garage. Parking was previously approved for 94 units
and are now technically over on parking based on the previous approval
Gillette — what is the net increase on office space?
Pratt — 2,500 sq. ft.
Spence — property is functioning with the existing parking
Pratt — parking is not an issue, there have not been any complaints from
owners
Stockmar — have you seen an increase in demand for parking?
Rob Levine, former GM of Antlers - have in recent years started charging
for parking which has increased use of shuttle services
Lockman — believes it meets criteria and thinks the changes will improve
the property
Hopkins — agree and sees the need is there to continue upgrades
August 21, 2018 - Page 64 of 82
Kurz — meets criteria and enhances guest experience. Parking has been well
managed in the past.
Gillette — agrees
Kjesbo — agrees
Stockmar — agrees and believes the addition of another elevator is a major
improvement and is not concerned with the parking. Was concerned about
egress during the site visit but believes it will be addressed during
construction.
Ludwig Kurz moved to approve with conditions.Brian Gillette seconded
the motionand it passed (6-0).
4. A request for review of a final plat, pursuant to Title 13 Chapter 4, Minor Subdivisions, 10 min.
Vail Town Code, to allow for a subdivision to reconfigure the property line between two
(2) parcels located at 814 Potato Patch Drive/Lot 3, Block 1, Vail Potato Patch Filing 1,
and 815 Potato Patch Drive/Lot 2, Block 1, Vail Potato Patch Filing 1, and setting forth
details in regard thereto. (PEC18-0030)
ApplicantGolden Peak Enterprises LLC, represented by Pierce Architects
Planner: Jonathan Spence
Spence — In many other communities this type of application is handled
administratively. These lots were presented previously for a lot line
adjustment and are being amended again.
Gillette — asked what the previous vote was
Spence — all in favor with the exception of Commissioner Perez.
Kjesbo — final tweaks on a unique property.
All commissioners agree with Staff's recommendation.
Ludwig Kurz moved to approve.Brian Gillette seconded the motionand it
passed (6-0).
5. Approval of Minutes
July 23, 2018 PEC Results
Brian Gillette moved to approve.Ludwig Kurz seconded the motionand it
passed (6-0).
6. Adjournment
Brian Gillette moved to Motion.Ludwig Kurz seconded the motion
The applications and information about the proposals are available for public inspection during regular office hours at the
Town of Vail Community Development Department, 75 South Frontage Road. The public is invited to attend the project
orientation and the site visits that precede the public hearing in the Town of Vail Community Development Department.
Times and order of items are approximate, subject to change, and cannot be relied upon to determine at what time the
Planning and Environmental Commission will consider an item. Please call (970) 479-2138 for additional information. Please
call 711 for sign language interpretation 48 hour prior to meeting time.
Community Development Department
August 21, 2018 - Page 65 of 82
VAIL TOWN COUNCIL AGENDA MEMO
ITEM/TOPIC: July 2018 AI PP Meeting Minutes
ATTACHMENTS:
Description
July 2018 AIPP Meeting Minutes
TOWN OF 1 X41
August 21, 2018 - Page 66 of 82
TOWN OF VAIL
1309 Elkhorn Drive
Vail, Colorado 81657
artinvail.com
Public Notice - Art in Public Places Board Meeting
Monday, July 2, 2018 - 8:30 a.m.
Town Council Chambers
Art in Public Places
970.479.2344
970.479.2166 fax
AIPP Board members present: Susan Bristol, Patricia Donovan, Julie Hansen, Kathy Langenwalter, Bill
Pierce, Margaret Rogers,
AIPP Board members absent: Kara Woods
Others present: Molly Eppard, AIPP Coordinator
1. Approval of minutes from May 30th meeting.
2. No citizen input.
3. RSES Garage update
Molly explains we are in the midst of negotiating the contract and payment timeline with selected artist John
Fleming. We are also examining the exhibits A (location) & B (design) for the contract. The location for the art
was determined to be flanking the pathway just east of the pedestrian bridge. Molly asks Kathy to address
some of these changes Fleming has proposed in his design. Molly notes his heights are now varying from 16
to 20 feet, but the total of 18 is the same. Julie comments that trees vary in height, so it makes sense to her.
Molly notes that the "aspening" is now on the interior of the blades versus both sides. The board would like to
know why the artist is now focusing on the inside of the "aspening." Molly explains that we will want to see an
example of the steel with "aspening." Margaret comments the blades are staggered, so we would see the
"aspening" from both sides regardless. Bill comments it would be beneficial to understand his reasoning.
Susan would like to discuss in Fleming's original presentation squares were alternating, but that no longer
seems to be the design. She thinks it should have some visual break-up. Molly comments we are also
discussing possibilities for the foundation and footing. At this point, there are no benches which would make it
better for snow removal. We are hoping for a fall installation. The foundations should be poured by August at
this stage in the construction. Julie asks if he has selected a fabricator. Molly mentions he is familiar with
Demiurge, but not sure what Fleming has decided. Susan asks the board their thoughts on children versus the
artist creating the "aspening." Molly comments it was presented to have interaction with the children, so the
board should consider this when they selected his proposal. Julie and Kathy are ambivalent because of the
timeline. Margaret comments that the students should be involved in the classroom level and the artist should
execute the work in the studio. Susan agrees. Trish comments that he can have involvement with the children
participating in another aspect if time is an issue. She explains that there are other ways he can stimulate
artistic interest with the students. Molly remarks involving the school children was a big part of his presentation,
so he should maintain that aspect of his proposal for the art. Trish thinks the work should be meaningful for the
school children so they have a connection to it.
4. Lawrence Weiner installation review
Demiurge and ShipArt did a great job with the installation of the work. Kent Logan is very pleased with the
installation. The plants in the landscaping will grow to about 3 to 4 feet to cover the imperfections of the lower
level of the wall. The landscaping was thoughtfully designed with height and color by Gregg Barrie. Molly
shows the board the design for the plaque which includes the Logan's commentary on the work. It is a
stainless steel plaque with black etched text located in close proximity of the sidewalk so people can read it.
August 21, 2018 - Page 67 of 82
Molly reached out to LaTour about potential dates for a thank you reception for the Logan's. We would have a
dedication and remarks at the site and then walk to the patio of LaTour. Molly comments colleagues at the
Americans for the Arts conference in Denver were very impressed that Vail secured this donation for the public
art collection. Molly will look at dates for the reception.
5. Patrick Dougherty installation review
We have a full page "Thank You" ad with images running in the Daily. We have received a lot of social media
attention and have been able to track with hash -tags. We have received a lot of press from her various
contacts. Molly goes down daily to check on the installation and is working on additional informational signage.
We applied the fire retardant to the entire installation. There are signs which indicate the art is under
surveillance. Patrick was very happy, complimented the organization and said it was a well oiled machine.
Molly also compliments the public works department for their involvement. She has received a lot of positive
compliments on the project. When she goes to check on the installation, she is constantly being asked
questions and everyone has been incredibly mesmerized with the installation. Many are familiar with the artist
and impressed Vail was able to have Dougherty in Vail. Trish mentions Patrick told her that it was an
impressive operation and everything has been very straightforward and a pleasure working with Town of Vail.
Molly comments that his artist fee was $30,000. She is still waiting for several bills to get the total expenditure
on the project. Julie comments that this is money well spent on such an impressive project which is getting so
much public attention. Molly comments that we had people from the Front Range come up for just the book
signing. The books are being sold at the BFAG shop. She knows they have already sold 20 and has delivered
more to them. Kathy comments the board should let the others know how many non -local volunteers came to
participate on the project and how it has drawn many people to town.
6. Coordinator updates:
Art Cottage:
Margaret would like to discuss the status of the Art Cottage in Ford Park on behalf of the BFAG. Molly
comments that it was on her agenda in coordinator notes as well. She explains that the building has VRD
equipment stored in it. AIPP has monies from the Manor Vail project allocated to the cottage to create a
working artist residency studio. Molly asks the board where their thoughts are on exploring the space and what
the vision might be. Kathy confirms that the $50,000 was designated for this space. Molly confirms it was the
agreed upon public art contribution and allocation during their development process. Margaret comments the
BFAG would like to rent this space for their gift shop. They would like to turn the schoolhouse into a program
space. Margaret comments since it would only be used as a gift shop they would only need drywall. Molly
remarks it is pretty rough shape and it requires quite a bit more work than drywall for it to be occupied. The
topic of water comes up and Molly notes the new sewer line should make it more feasible. The space needs to
be cleared out, so it can be properly assessed. Kathy comments that the board should go down to look at the
building. Molly remarks we can all agree the space should be utilized in a more functional way rather than for
storage. Trish remarks about the conference in Breckenridge a few years ago and their use of older buildings
for artist spaces is a real draw for their town. She does not think we should let the building be rented by
another entity at this time. It seems too soon to make any commitment for leasing out the space. She thinks it
can be used in multiple ways to promote the visual arts. Molly remarks she often gets asked about artist
residencies and studios - questioning why Vail does not have a program. Kathy remarks now we have the
funds from Manor Vail, we can properly explore the space. Plans were done a number of years ago and she
thinks the timing is appropriate for the discussion of repurposing the space. Bill asks what the AIPP vision
would be. Molly comments it has been discussed to be a working studio, activating interaction with an artist
creating in the park, classes, talks, etc. Molly observed after having Patrick Dougherty in the park, there is
definite interest for visual arts in the park. We would need to clearly outline our mission and vision. Kathy
remarks after having volunteered in Ford Park for Stickwork she can confirm it is exceptionally busy in the
summer. People are curious, looking for activation in the park, and programming. She explains we have the
right to the one building and not the schoolhouse. We need to assess this particular building. Julie comments
we are not landlords, so renting the building is not of interest. Bill comments we need to look at water/sewer,
electricity, utilities, foundation. We need to look at the expectation of the space and investment. Molly
comments it would be worthwhile to see the activity, usage of space, and how a small building can be
Town of Vail Page 2
August 21, 2018 - Page 68 of 82
converted into an arts space similar to the many buildings in Breckenridge. Molly comments we are not
creating a district, we are looking at a singular space and reiterates it would be worthwhile for board members
to see the spaces in Breckenridge being activated in order to have the vision of what is possible. We have one
building which can be utilized for this activity, so we should explore it. She reiterates Kathy's comments that it
is incredibly busy in the summer months. Susan moves that we look at the plans, utilities, and if they can clear
the building, take a site visit. Kathy thinks the bigger part of this issue is that this has been put on hold, so if
there is interest now as a board, we need to reexamine the original concepts. Trish agrees with Kathy's
comments that we need to look at the vision of the board for the usage of the space. The board approves the
motion to review the plans at the next meeting and have a site visit if it is cleaned out.
Relocation of sculptures:
Molly reviews the two works already approved for relocation by the board — the Tobolowsky and Bird of
Paradise. These works will be relocated after the Fourth of July. The Tobolowsky will be in front of the Vail
Village transit center and the Bird of Paradise will be in close proximity to where it was in front of the Lionshead
parking structure. The Resurrecting the Matriarch sculpture was restored by the new body shop painter in
public works. It was removed from the bus turnaround west of Dobson due to tree removal. New trees were
replanted in the turnaround. It is a great improvement with the new paint surface. Molly shows the board some
options along the southern area by the Lionshead parking structure. Molly comments anything in Lionshead
which is removed typically has to be relocated within the district. It will be just east of the present sculpture in
place at this location. The board agrees to the relocation.
Collection:
The bronze TOV works were cleaned June 11 except for the 10th Mountain Soldier. The 10th Mountain Division
Soldier should be completely refurbished this fall. Molly has an estimate for this conservation from the
DeDecker's in Loveland.
Summer Art Walks:
July 11 — August 29 @ 11 am
Golf/Nordic Clubhouse:
The Ford Tournament posters and photos were reproduced from Diana and John Donovan's ephemera. A
second photo was courtesy of the Vail Valley Foundation. The VRD wanted the works upstairs in the grill area
versus the pro -shop. Julie comments on the dim lighting in the space. The AC control in the middle of the grill
wall is unfortunate for the placement, but it seems to be well received.
Meeting adjourned.
Town of Vail Page 3
August 21, 2018 - Page 69 of 82
VAIL TOWN COUNCIL AGENDA MEMO
ITEM/TOPIC:
CSE meeting minutes DRAFT from August 8, 2018
ATTACHMENTS:
Description
CSE Meeting Minutes DRAFT - 8/8/18
TOWN Of 9
August 21, 2018 - Page 70 of 82
TOWN OF VAIL
Commission on
Special Events
DR,T
COMMISSION ON SPECIAL EVENTS MEETING
Vail Town Council Chambers
Wednesday, August 8, 2018 @ 8:00a.m.
AGENDA:
Meeting materials can be accessed at the following link:
https://bit. ly/2Ag k3G 1
CSE Members Present:
Alison Wadey
Barry Davis
Rayla Kundolf
Marco Valenti
Samantha Biszantz
Kim Newburry Rediker
CSE Members Absent: Mark Gordon
TOV Staff Present: Laura Waniuk, Event Liaison Specialist
Ernest Saeger, Special Events Coordinator
Others Present: Laurie Asmussen, Eagle Valley Events
Shawn Carney, Vail Mountain
Ariel Rosemberg, Vail Summer Bluegrass Series
Andrea Sbicca, Highline
Peggy Wolf, Highline
Jeff Andrews, Vail Jazz
Leon Fell, King of the Mountain Volleyball
Sandra Perrig, Vail Valley Partnership
Sarah Franke, Vail Valley Foundation
Mac Garnsey, Vail Valley Foundation
Mark Foster, Vail Lacrosse Tournament
Pete Orosio, Vail Mountain
CSE Chair, Barry Davis, called the meeting to order at 8:32am.
Administrative Items
Approval of the Minutes of the CSE Meeting on July 11, 2018
CSE Minutes
August 8, 2018 Page 1 of 6
August 21, 2018 - Page 71 of 82
Motion to approve the minutes of the CSE Regular Meeting on July 11,
2018 as presented.
M/S/P: Kundolf/Wadey/Unanimous. The motion passed 6-0 (Gordon Absent)
Meeting reminders:
• Joint Meetings with VLMDAC — August 23
• August 6: 2019 RFP released
• September 5: Regular Meeting
• September 24: 2019 RFP Due
• October 3: Regular Meeting (All Recaps)
• October 10: Funding Meeting — Producer Interviews (The Antlers)
• October 17: Funding Meeting — Allocations (The Antlers)
Event Recaps:
Vail Arts Festival
*motion to release final funding disbursement required
Please see presentation for further details.
• Asmussen noted they formed a partnership with Alpine Arts
• Asmussen said they utilized vendors' social media accounts to help
market the event
• Kundolf said Asmussen executed the event very well and the event was a
much more sophisticated event than in the past
• Valenti asked how many vendors they had last year
• Asmussen said they used to be at 78 and were at 62 in 2018
• Asmussen noted this created a much better atmosphere
Motion to approve the final funding distribution for Vail Arts Festival.
M/S/P: Kundolf/Valenti/Unanimous The motion passed 6-0 (Gordon absent)
Vail Lacrosse Tournament
*motion to release final funding disbursement required
Please see presentation for further details.
• Foster noted that there are multiple videos available and encouraged the
CSE to watch them
• Foster said Honeywagon did not remove trash one day and left the venue
a mess for attendees which may have negatively affected the NPS
• Davis asked how many total participants
• Foster said they had 94 teams and each team is about 20 players
• Foster added that most of the players come with families
• Rediker said this is an event that puts heads in beds
• Biszantz asked if 67% new attendees were teams or families
• Foster said it is generally new teams and families
• Foster said 2019 will be their 25th year and hopes to create plans to
celebrate it
CSE Minutes
August 8, 2018 Page 2 of 6
August 21, 2018 - Page 72 of 82
• Wadey noted she encourages collaboration with local lacrosse teams
y Motion to approve the final funding distribution for Vail Lacrosse
Tournament.
M/S/P: Kundolf/Biszantz/Unanimous The motion passed 6-0 (Gordon absent)
Vail America Days
*motion to release final funding disbursement required
Please see presentation for further details.
• Wolf said that lodging occupancies on the Tuesday and Wednesday was
very high
• Wolf noted their push for sustainability this year including water refill
stations and an effort to reduce gas vehicles
• Wolf noted they were able to add an announce booth at the Bridge and
Gore intersection because of GMC's sponsorship
• Wolf said they are going to look into a permanent alternative to fireworks
such as a laser or drone show
• Wolf noted the Vail Health plan worked very well
• Valenti asked if the cost of a drone show is similar to fireworks
• Wolf said the costs are similar
• Wolf added that a drone or laser show would require a center focal point
for attendees to enjoy it
• Rediker asked why W Lionshead Circle was closed toward the end of the
parade
• Wolf said they are looking at extending the parade in 2019 past The
Antlers but is not sure why it was closed this year
• Saeger said he was unaware and will ask Vail Police
Motion to approve the final funding distribution for Vail America Days
M/S/P: Kundolf/Rediker/Unanimous The motion passed 6-0 (Gordon absent)
King of the Mountain Volleyball Tournament
*motion to release final funding disbursement required
Please see presentation for further details.
• Fell noted that the tournament was successful despite the weather
concerns
• Fell said they learned they need to change their communication structure
as it relates to weather delays and schedule
• Kundolf asked how Fell knows the number of overnight visitors
• Fell said he uses data from the survey and that his host hotels were full
• Kundolf asked if Fell has replaced his former employee
• Fell said yes he did get a new personal assistant
CSE Minutes
August 8, 2018 Page 3 of 6
August 21, 2018 - Page 73 of 82.
Motion to approve the final funding distribution for King of the Mountain
Volleyball Tournament
M/S/P: Rediker/Biszantz/Unanimous The motion passed 6-0 (Gordon absent)
Vail Summer Bluegrass Series
*motion to release final funding disbursement required
Please see presentation for further details.
• Rosemberg noted that there are now numerous weekday music events
throughout the Valley including in Avon, Beaver Creek, Eagle, and more
• Wadey said the activation was fantastic and businesses very much
enjoyed the 4th of July event
• Valenti said Lionshead stores saw an increase in traffic
➢ Motion to approve the final funding distribution for Vail Summer
Bluegrass Series
M/S/P: Rediker/Biszantz/Unanimous The motion passed 6-0 (Gordon absent)
GoPro Mountain Games
*motion to release final funding disbursement required
Please see presentation for further details.
• Garnsey noted that the swap of Dock Dogs and Adventure Village was
very well received
• Garnsey noted that climbing is going to be an Olympic sport in 2020 so
they are looking at ways to enhance their IFSC World Cup event
• Franke noted their estimated economic impact was $6.2 million
• Franke said they want to look at how they can encourage guests to stay
longer, not necessarily bring more people into town
• Franke said 25-30% of athletes have never been to Vail and the event is
the only reason they come
• Kundolf noted that she would like the VVF to add "Staff" to their t -shirts so
they are easily identifiable
• Valenti suggested utilizing electric golf carts instead of gas
• Garnsey said he loves the idea and will continue to explore the
possibilities
Motion to approve the final funding distribution for GoPro Mountain
Games
M/S/P: Wadey/Valenti/Unanimous The motion passed 6-0 (Gordon absent)
Discuss 2018 Snow Days Council Funding:
• Kundolf noted that Councilwoman Mason asked for a band that has never
been here and asked that the Council know the band before committing to
funding
CSE Minutes
August 8, 2018 Page 4 of 6
August 21, 2018 - Page 74 of 82.
• Kundolf said that Dieghan's response was that it is not possible due to
contractual limitations
• Wadey noted that Vail Resorts is contributing $200,000 cash plus
marketing efforts
• Biszantz noted that the Council funding is faith based funding
• Biszantz said the schedule is very vague and they still don't have
complete activation details
• Biszantz noted that Council never asked for public comment and is
worried that the late ask for funding similar to Spring Back to Vail is going
to happen again in future years
• Wadey said we need to remember that the acts need to be able to bring
people to Vail
• Biszantz said it is the CSE's job to find a producer to deliver a quality
product
• Davis said that if the CSE was presented the Snow Days schedule during
the RFP process, the CSE would be much more critical due to the lack of
details
• Waniuk noted that the CSE will have the responsibility of reviewing the
event through the recap
• Waniuk said Councilman Moffet stated that there was not enough data
• Waniuk noted that there is data that was provided but was not included in
the packet
• Waniuk suggested that the CSE keeps an eye on their marketing efforts,
specifically to the Front Range
• Waniuk said that the CSE needs to understand if the Council funding is
going to be included in future budgets because it will affect how CSE
funds the event
• Waniuk noted the previously completed signature event funding process
that was not followed for this funding request
• Wadey said she believes this funding will make or break the event
• Waniuk suggested asking Highline to come into CSE to give an update on
the event planning
• Waniuk said it is important to ensure Vail Holidays and Snow Days work
together
• Saeger noted that Council approved funding for Ford Park parking lot
power improvements
New Business and Community Input:
• Davis noted that Restaurant Week is not using their funding
• Davis suggested utilizing the $7,500 toward Vail Holidays programming
and marketing
• Wadey said it should be an agenda item to be discussed
• Davis asked if it should be an RFP or should the CSE allocate it at their
will
CSE Minutes
August 8, 2018 Page 5 of 6
August 21, 2018 - Page 75 of 82
• Wadey said she would like to know what the event would do with the
additional funding
• Rediker agreed and said we don't necessarily need to put an RFP out but
rather reach out to events to learn more about what they'd use it for
• Kundolf suggested including the ice skating event that Council funded
• Waniuk noted that the funding has to be spent in 2018 and that events
that already happened could be included
• Saeger said he will get it out this week and ask for responses by Friday,
August 17th
• Kundolf clarified that it is only open to CRC
• Waniuk confirmed
• Davis noted that the Town of Avon has approached the CSE in regards to
the GoPro Mountain Games hosting a standup paddleboard event in 2019
• Kundolf said it is a growing sport and just wants to ensure that Town of
Avon provides funding
• Wadey said that we need to be careful because other municipalities may
try to do the same and wants to ensure that the event is not diluted within
Vail
• Waniuk noted that the CSE did not approve standup pebble boarding in
Avon in the past
• Wadey said she would rather have VVF approach the CSE to have the
conversation
• Rediker agrees that it should come from the VVF
• Davis said the recommendation is that the VVF approaches the CSE with
the idea
• Wadey said overnight parking needs to be communicated to events
• Rediker said events need to do a better job communicating overnight
parking costs to their attendees
• Kundolf said this is the best board she worked on and that Waniuk has
done a fantastic job and her legacy will live on
• Wadey noted that the Businesses, Bogeys and Bragging Rights golf
tournament is September 6th
•
7. Motion to adjourn at 9:32am.
M/S/P: Rediker/Kundolf/Unanimous. Motion passed 6-0 (Gordon absent)
CSE Minutes
August 8, 2018 Page 6 of 6
August 21, 2018 - Page 76 of 82
VAIL TOWN COUNCIL AGENDA MEMO
ITEM/TOPIC: VLHA Meeting Results
ATTACHMENTS:
Description
VLHA July 24, 2018 Meeting Results
TOWN Of UAIL
August 21, 2018 - Page 77 of 82
TOWN OFD
Vail Local Housing Authority
Meeting Results
Tuesday, July 24, 2018
Regular Meeting
Public Meeting
3:00 PM — 5:O0PM
Housing Department
Large Conference Room
75 South Frontage Road West, Vail, Colorado 81657
MEMBERS PRESENT
Steve Lindstrom (via phone)
Mary McDougall
Francisco Meza
James Wilkins
Staff
George Ruther
Lynne Campbell
MEMBERS ABSENT
Molly Morales
Public Present: Sandy LaBaugh, Vice President with ANB Bank
Wilkins called the meeting to order at 3:10PM, Steve Lindstrom via phone and Molly
Morales absent.
The July 18, 2018 meeting results were reviewed and approved as presented.
MOTION: Lindstrom SECOND: McDougall VOTE: 4-0
Sandy LaBaugh provided an update of ANB stating there are 30 branches 2 of which
are in Eagle County. ANB is a full service bank with an interest in financing deed
restricted properties. They do have ability to provide up to 97% loan to value depending
on restriction language. Currently, they do development finance up to 30 million. All
financing is portfolio. ANB is active in the Aspen deed restriction programs. Underwriting
is done out of the Cherry Creek office. ANB does not do 30 year fixed rather 5-7 year
arms.
The Board reviewed the Open Lands Plan and Short Term Rentals (STR) position
statements. Discussion resulted in the Board suggesting to not be overly restrictive on
the Open Lands in order to keep options open for future consideration. Staff said to
refer to the recently adopted housing policies as a guide for developing and maintaining
August 21, 2018 - Page 78 of 82
housing options. Ruther stated finance is performing an audit of STR which resulted in
the Board questioning what the plans to bring more homes into compliance are.
Lindstrom believes the Board needs to create a housing database to assist with the
STR and housing options.
Next steps, both the Open Lands Plan and Short Term Rental will be presented at the
August 7th Town Council meeting. Ruther will prepare Board memos on both items,
route to them for review and present at the Council meeting.
Next the Board discussed Long Term Funding and next steps to move the Tax Ballot
question forward.
The Board needs to identify and further investigate:
• Goals
• Sources of Funds —
o Selling density
o Sales tax
o RETT fund redirected
o New Tax
o Revenue Generating Assets
o Fees
o Increase Fees, reallocate existing fees
o Issue bonds
• Uses —
o Clear ballot language, how and what will funds be used
o Provide use for what and what not used for
• Process —
o Who - pays, (council, staff, outside group?) who is authorized, what are the legal
steps
o Legal - Can spend TOV funds of do we need to raise funds
o Strategies: Consultant
• Resources - goal looking for support and not to blindside groups
o Groups: Vail Homeowner Association (buy in), Eagle County
o Individuals: David Cunningham, Chris Romer -Vail Valley Partnership, Bobby
Lipnick, for example
o Update The Economic Value of the Town of Vail's Investment in Employee
Housing report
o Environmental impacts, what are they and how to address
o Clean up Town codes, other items which would be helpful and in support of
the tax
Next Steps:
• Update The Economic Value of the Town of Vail's Investment in Employee
Housing and include environmental impacts.
o Ruther will contact BBC regarding an update and cost to add the environmental
piece. He will also reach out to Willa Williford - Williford LLC and Kim Langmaid
August 21, 2018 - Page 79 of 82
for an environmental consultant reference. Ruther will present proposals to the
Board at the next meeting.
• Request for Proposal (RFP) for the Board to review
o VLHA suggested two separate reports for economic and environmental reporting.
Another option presented by Ruther is one consulting group who could manage
the process and produce one comprehensive report.
• Lindstrom asked the Board to think about lists of who could be helpful to push tax
through.
Wilkins motioned to enter executive session per C.R.S. §24-6-402(4)(a)(e) - to discuss the
purchase, acquisition, lease, transfer, or sale of property interests and to determine positions,
develop a strategy and instruct negotiators, regarding: submitted Vail InDEED applications and
program details.
MOTION: Wilkins SECOND: Lindstrom VOTE: 4-0
Wilkins motioned to re-enter the regular meeting.
MOTION: Wilkins SECOND: Meza
VOTE: 4-0
Present were McDougall, Meza, Wilkins, Lindstrom (via phone), Ruther and Campbell.
McDougall motioned to recommend to staff continue forward with Vail InDEED negotiations.
MOTION: McDougall SECOND: Meza VOTE: 4-0
Meeting adjourned at 4:45 PM.
MOTION: Wilkins SECOND: McDougall VOTE: 4-0
Next Meeting — August 14, 2018
Future Agenda Items:
• Long Term Funding Source
• 2019 Budget
• Housing Data
• Update Economic Value of Housing
Discussion
Page 3
• VLHA Business Plan
• East Vail Parcel Update
• Open Lands Plan Discussion
• West Vail Master Plan Discussion
August 21, 2018 - Page 80 of 82
TOWN Of 9
VAIL TOWN COUNCIL AGENDA MEMO
ITEM/TOPIC: Executive Session, pursuant to: 1) C.R.S. §24-6-402 (4)(b) - to receive legal
advice on specific legal questions; Regarding Quasi Judicial decision making; 2) C.R.S. §24-6-
402(4)(a)(e) - to discuss the purchase, acquisition, lease, transfer, or sale of property interests; and
to determine positions, develop a strategy and instruct negotiators, Regarding: 6 West.
PRESENTER(S): Matt Mire, Town Attorney
August 21, 2018 - Page 81 of 82
VAIL TOWN COUNCIL AGENDA MEMO
ITEM/TOPIC: Recess at 1:00 pm
TOWN Of UAIL
August 21, 2018 - Page 82 of 82