HomeMy WebLinkAbout2015-0309 PECTOWN OF VAIt f PLANNING AND ENVIRONMENTAL COMMISSION
March 9, 2015 at 1:00pm
TOWN COUNCIL CHAMBERS / PUBLIC WELCOME
75 S. Frontage Road - Vail, Colorado, 81657
MEMBERS PRESENT MEMBERS ABSENT
Site Visit: None
25 minutes
A request for a final review of a major exterior alteration or modification, pursuant to Section 12-
71-1-7, Major Exterior Alterations or Modifications, Vail Town Code, to allow for a change to the
approved mix of residential unit types, and a request for final review of an amended conditional
use permit, pursuant to Section 12-71-1-3, Permitted and Conditional Uses: First Floor or Street
Level, Section 12-71-1-4, Permitted and Conditional Uses; Second Floor and Above, Vail Town
Code, to allow for a reduction in the number of timeshare units, located at 705 West Lionshead
Circle/Lot 1, Strata Vail, and setting forth details in regard thereto. (PEC150006, PEC150007)
Applicant: Lionshead Inn LLC, represented by Mauriello Planning Group
Planner: Warren Campbell
ACTION:
MOTION: SECOND: VOTE:
CONDITION(S):
90 minutes
2. A request for final review of an amendment to a conditional use permit, pursuant to Section 12-
9C-3, Conditional Uses, Vail Town Code, for an existing healthcare facility, amending the
development plan to allow for an additional floor plate on the west wing, located at 181 West
Meadow Drive and 108 South Frontage Road West (Vail Valley Medical Center)/Lots E, F, and
10 Vail Village Filing 2, Lot 2E, Block 1, Vail Lionshead Filing 1 and Lot D-2, A Resubdivision of
Lot D, Vail Village Filing 2 (PEC150002, PEC150003)
Applicant: Vail Valley Medical Center, represented by Braun Associates
Planner: Warren Campbell
ACTION:
MOTION: SECOND: VOTE:
CONDITION(S):
3. A request for a recommendation to the Vail Town Council for an amendment to the Lionshead
Redevelopment Master Plan, pursuant to Section 2.8, Adoption and Amendment of the Master
Plan, Lionshead Redevelopment Master Plan, to amend the Detailed Plan Recommendations for
the Evergreen Lodge at Vail, located at 250 South Frontage Road West/Lot 2W, Block 1, Vail
Lionshead Filing 2, and setting forth details in regard thereto. (PEC140044)
Applicant: Evergreen Lodge at Vail, represented by Mauriello Planning Group
Planner: Warren Campbell
ACTION: Table to April 13, 2015
MOTION: SECOND: VOTE:
4. Approval of February 23, 2015 minutes
MOTION: SECOND: VOTE:
5. Information Update
Page 1
6. Adjournment
MOTION: SECOND: VOTE:
The applications and information about the proposals are available for public inspection during
regular office hours at the Town of Vail Community Development Department, 75 South Frontage
Road. The public is invited to attend the project orientation and the site visits that precede the public
hearing in the Town of Vail Community Development Department. Times and order of items are
approximate, subject to change, and cannot be relied upon to determine at what time the Planning
and Environmental Commission will consider an item. Please call (970) 479-2138 for additional
information. Sign language interpretation is available upon request with 24-hour notification. Please
call (970) 479-2356, Telephone for the Hearing Impaired, for information.
Community Development Department
Published March 6, 2015 in the Vail Daily.
Page 2
TOWN OF VAIL i
PLANNING AND ENVIRONMENTAL COMMISSION
March 9, 2015 at 1:00pm
TOWN COUNCIL CHAMBERS / PUBLIC WELCOME
75 S. Frontage Road - Vail, Colorado, 81657
MEMBERS PRESENT
Pam Hopkins
Dick Cleveland
Webb Martin
John Rediker
Michael Kurz
Henry Pratt
Luke Cartin
Site Visit: None
MEMBERS ABSENT
25 minutes
A request for a final review of a major exterior alteration or modification, pursuant to Section 12-
7H-7, Major Exterior Alterations or Modifications, Vail Town Code, to allow for a change to the
approved mix of residential unit types, and a request for final review of an amended conditional
use permit, pursuant to Section 12-7H-3, Permitted and Conditional Uses: First Floor or Street
Level, Section 12-7H-4, Permitted and Conditional Uses; Second Floor and Above, Vail Town
Code, to allow for a reduction in the number of timeshare units, located at 705 West Lionshead
Circle/Lot 1, Strata Vail, and setting forth details in regard thereto. (PEC150006, PEC150007)
Applicant: Lionshead Inn LLC, represented by Mauriello Planning Group
Planner: Warren Campbell
Development Plan
ACTION: Approved with Conditions
MOTION: Kurz SECOND: Cartin VOTE: 6-1-0 (Rediker opposed)
CONDITION(S):
1. That the Developer prepares The Lion Art in Public Places Plan, for input and
comment by the Town of Vail Art in Public Places Board, Chapter 12-25, Public Art,
Vail Town Code, prior to the request for a temporary certificate of occupancy. Subject
to the above input and comment by the Art in Public Places Board, the Applicant will
determine the type and location of the art to be provided. Said Plan shall include the
funding for a minimum of $70,000.00 in public art improvements to be developed in
conjunction with The Lion project.
2. That the Developer shall be assessed a transportation impact fee in the amount of
$6,500 per increased vehicle trip in the peak hour generated (25.06 trips), or $162,890,
created by The Lion project. The total fee of $162,890 shall be paid in full by the
Developer prior to the issuance of a temporary certificate of occupancy or certificate
of occupancy for The Lion project. At the sole discretion of the Town of Vail Public
Works Director, said fee may be waived in full, or part, based upon the completion of
certain off-site improvements.
Conditional Use Permit
ACTION: Approved
MOTION: Kurz SECOND: Cartin VOTE: 6-1-0 (Rediker opposed)
Page 1
Warren Campbell introduced the application and provided clarification on what was being
requested. Campbell provided the differences between different unit types and the previous
requests of a similar nature. Campbell also spoke to the site specific recommendation of the
Lionshead Redevelopment Master Plan. Campbell addressed the criteria and spoke to the fact
that a timeshare by it vary nature is more "live" than an attached accommodation unit. Campbell
concluded with a synopsis of the recommended motions and conditions.
Dominic Maurellio, applicant's representative, made himself available for questions.
Commissioner Pratt asked about the interval proposed for the timeshares.
Rocky Cortina, representing the developer, discussed the unit mix and market demand and the
proposed uses of the various units.
Commissioner Rediker inquired as to what would happen if the developer purchased all of the
timeshares.
Cortina explained the ideas and intent of making all the units live beds for this project. He spoke
to the lodge like amenities including a front desk, lounge, commercial/restaurant space, etc.
Campbell suggested that a condition requiring compliance with the regulations regarding
timeshares could be appropriate if the Commission felt so inclined.
Commissioner Hopkins expressed her approval of the proposal.
Commissioner Cartin had nothing to add.
Commissioner Cleveland stated his concerns had been addressed int eh presentation by staff
and that he felt the proposal complied with the criteria.
Commissioner Kurz had expressed his belief that the request complied with the criteria.
Commissioner Rediker expressed his belief that the proposal is not in keeping with the
Lionshead Redevelopment Master Plan recommendations as attached accommodation units
were not as "live" as timeshare units.
Commissioner Webb expressed his belief that the request complied with the criteria.
Commissioner Pratt spoke to timeshare intervals and how shorter intervals tend to be hotter.
Stated his believe that the proposal was in compliance, but cautioned on returning for further
revisions to the unit mix.
90 minutes
2. A request for final review of an amendment to a conditional use permit, pursuant to Section 12-
9C-3, Conditional Uses, Vail Town Code, for an existing healthcare facility, amending the
development plan to allow for an additional floor plate on the west wing, located at 181 West
Meadow Drive and 108 South Frontage Road West (Vail Valley Medical Center)/Lots E, F, and
10 Vail Village Filing 2, Lot 2E, Block 1, Vail Lionshead Filing 1 and Lot D-2, A Resubdivision of
Lot D, Vail Village Filing 2 (PEC150002, PEC150003)
Applicant: Vail Valley Medical Center, represented by Braun Associates
Planner: Warren Campbell
ACTION: Tabled to March 23, 2015
MOTION: Kurz SECOND: Martin VOTE: 6-0-1 (Cleveland recused)
Page 2
Warren Campbell introduced the project and the goals for the meeting. Topics to be discussed
included employee generation, parking, and mass and scale. The project review schedule and
criteria for approval was provided. Campbell walked the commission through the staff report.
Tom Braun representing the applicant provided a PowerPoint presentation. Braun walked
through the items to be discussed. He added that the senior housing coordinator had yet to
review and comment on the materials submitted.
Employee Housing
Braun provided information concerning the employee housing requirement. Trends in hospital
uses were discussed. Braun walked the commission through each floor plate, the uses proposed
and the impacts on employee generation. The required findings to be exempted from locating
50% of the required employee housing on site was presented. Braun spoke to the reasons for
requesting the waiver from the onsite requirement.
Commissioner Martin asked about the method for calculating all employees including house
keeping/maintenance, engineering, etc.
Commissioner Rediker had no comment
Commissioner Kurz spoke to his support of the waiver from the onsite requirement
Commissioner Cartin requested clarification from the applicant regarding
compression/decompression and how these employees are accounted for.
Campbell provided additional information on this item.
Commissioner Cartin proposed an audit a number of years after full operation to verify employee
generation created by the expansion.
Braun discussed how the codified generation rates in Chapter 12-23, Commercial Linkage, did
not contain a generation rate for a healthcare facility. Therefore, an effort was underway to
develop competent evidence to arrive at an appropriate generation rate.
Commissioner Hopkins support the audit concept.
Commissioner Pratt shared in Cartin's concerns related to employee generation and method of
calculation. Does not support leaving it up to the hospital to relay their employment levels.
Supports a square foot generation rate as opposed to actual count.
Parking
Braun spoke to the demand, resources, solutions and management of parking. Braun discussed
the proposed parking formulas. Braun walked through each floor of the facility and the effects of
the proposed changes on the parking requirement. Parking would be calculated based upon one
parking space per exam room, patient room, and maximum number of employees present onsite
during the largest shift. Braun then discussed the parameters that were considered in designing
the parking lot, and the proposed design influences circulation. Braun then spoke about the
implication on traffic circulation on Meadow Drive and Frontage Road.
Commissioner Hopkins asked about shift changes and how they would impact parking demand
Page 3
Braun said he would address that question later in the presentation
Commissioner Cartin asked about the methodology used to determine adequate parking
requirements.
Braun elaborated on how his methodology and Staff's methodology arrived at similar figures
The methodology was discussed within the WMC MP.
Commissioner Kurz asked about library staff parking and whether it would continue to occur on
Lot 10.
Campbell stated there are several dedicated spaces for library staff. The future of Lot 10 has yet
to be determined by the Vail Town Council.
Commissioner Kurz suggested the library staff parking be relocated to the Lionshead parking
structure. He expressed concern about the uncertainties (Lot 10, TOV entrance/access to Lot
10, and the land exchange).
Campbell stated that efforts are in motion to create more certainty.
Commissioner Kurz agreed that that a needs based approach to calculate necessary parking
was appropriate.
Commissioner Rediker expressed concern about the increased care and decreased parking
accommodations that would occur after the West Wing construction during the East Wing
construction. Also, he was concerned about the hospital visitor experience; coal tar sealants;
and the need for a sand oil separator, and a vegetative creek buffer.
Commissioner Martin asked for details on the snow management plan.
Braun stated that the team is still working on a snow management plan.
Commissioner Martin ask how the drainage was handled in the current parking structure.
Braun was unsure how it's currently handled, but stated in the future it would be directed to a
water quality vault on-site.
Commissioner Hopkins expressed concern about the small interior landscape islands and the
need to facility plow operations.
Campbell spoke to the parking lot interior landscaping requirements. He mentioned that he had
been in discussions with the applicant with regard to the 10% interior landscaping requirement
and that the areas proposed for inclusion should be of a quality to meet the intent of the
regulation.
Commissioner Pratt thought the landscaping requirements ought to be waived for this phase of
the project. Pratt also expressed concern for snow storage. He provided a comment regarding
a recent experience he had as a user of the hospital and parking in the existing parking garage.
He stated that it appeared as though the spaces in the garage were very tight.
Russ Sedmak, VVMC architect, delivered a presentation on the design and architecture of the
West Wing project. Russ presented the differences between the current proposal and that of two
weeks prior.
Page 4
Commissioner Martin appreciated the changes but felt more work was needed. Martin then
asked about the setback on Meadow Drive. Sedmak explained the changes. Martin was still
concerned that it is not enough of a buffer. Martin also asked for the applicant to look into other
solutions for fall protection than the railing on the roof.
Commissioners Rediker and Kurz both expressed support for the changes to the fagade of the
southern expansion.
Commissioner Cartin asked about the landscaping that was being proposed to address the need
for a soft buffer.
Sedmak elaborated upon the plan to include some dwarf evergreens, aspens, ornamental trees,
and a varity of smaller plant species. There would be the ability to irrigate under the canti-
levered portion of the third and fourth floor.
Commissioner Cartin then asked about the location of the mechanical equipment. He highlighted
that the west fagade would benefit from greater articulation.
Sedmak explained that it will be located on the roof with specific screening measures
surrounding each piece.
Commissioner Cartin then expressed concern about light pollution. He asked the applicant to
use full cut-off fixtures and minimize the amount of lighting.
Commissioner Hopkins was pleased with a number of revisions shown. She was concerned
about two columns located between the corner columns. She suggested that they move inward
to be under the canti-lever verses on the face of the building.
Commissioner Pratt share Cartin's concern with the west fagade and its lack of articulation.
Campbell asked for comments on the north side as focus has been on the south side. He
wanted to ensure that any feedback was received regarding that elevation as well.
Commissioner Pratt was concerned about the sign but felt that the north fagade was less
impactful on the adjacent properties.
Commissioner Martin agreed.
Campbell stated that the Sign Code did not permit the amount of signage shown on the plans
and that it would be reviewed as a separate Design Review application.
Mery Lapin, owner of 234 West Meadow Drive, expressed support for the hospital but had
concerns with regard to the phasing and assurances that the project would be completed. He
stated that the prudent thing to do is for the Commission to attach incentives for the hospital to
complete the master plan. He spoke to the financial stability of the hospital through a document
he provide citing its assets. The conclusion was that this was not a small rural hospital and there
were resources in place to ensure the project would move forward. He suggested the town could
condemn the Evergreen site and sell it to the hospital as the land area will be needed in 10 — 15
years. Also, Lapin asked the Commission to consider what the circumstances would be if the
hospital was owned by one of the larger hospital groups in Denver or elsewhere. Lapin was also
concerned about the future of Lot 10. He cited the Tannenbaum example of a property owner
attempt to purchase land from the Forrest Service. He was concerned about the precedence
Page 5
create if town owned land were to be sold. Lapin then discussed the emergency helicopter flight
path and that a penalty should be levied anytime a flight deviates from the prescribed approach
and departure paths. He said there are safety concerns that should not be overlooked. Parking
was also a concern. Lapin asked why visitor parking wasn't given greater consideration. He
voiced support for the architectural changes, but asked that the hospital be required to install a
heated sidewalk along West Meadow Drive.
Dan Reynolds, attorney representing the Corrigans, property owners at 252 West Meadow Drive,
asked that the setbacks be set at distance large enough to house large trees, similar to the
surrounding neighborhood. The Corrigans ask that the electrical transformer equipment be
relocated to be less impactful to Meadow Drive.
Jim Lamont, Vail Homeowners Association, asked for progress on establishing a flight path and
noise monitoring system for the emergency helicopter. He was concerned about the proposed
flight path being located above occupied structures. Lamont then discussed employee housing
and parking and how natural "compression" will negatively impact demand for each. Lamont was
concerned how parking demand and circulation would impact the transit system with particular
regard to the off-site parking requirement and how it coincides with town -wide parking demand
on the weekends. A pedestrian bridge is needed should parking be developed on the municipal
site. Heated sidewalks should also be considered as a condition of an approval. The town
should consider a partnership to address the need to heat the street. Lamont then spoke to the
proposed architecture. He voiced general support, but was critical of the west fagade and its
expansive application of brick. Lamont found it worrisome the prospect of the east wing's
redevelopment and the need to temporarily divert traffic onto West Meadow Drive. Lamont
thanked the Commission members that are stepping down at the end of the month for their
service.
Commissioner Martin reiterated his previous comments; supported Mr. Lapin's comment to
include incentives to see the master plan completed; and also mentioned the need for the
sidewalk to be heated.
Commissioner Rediker agreed tha the sidewalk adjacent to the hospital should be heated.
Commissioner Kurz agreed but stated his uneasiness all sequences of the master plan as
conditions change. He suggested that the town step up and participate in an effort to heat the
sidewalk.
Commissioner Cartin reiterated a need to address the west fagade, heat the sidewalk, determine
a snow storage and management plan, and a need to address recompression in to the future.
Commissioner Hopkins felt that the process was dealing with architecture in incremental pieces
and suggested a more holistic approach with the architecture.
Commissioner Pratt agreed with Hopkins regarding the architecture. He too agreed that efforts
should be undertaken to ensure the sidewalk could be heated at some point in the future. He
suggested the potential for waste heat from the mechanical room being used for heating the
sidewalk.
3. A request for a recommendation to the Vail Town Council for an amendment to the Lionshead
Redevelopment Master Plan, pursuant to Section 2.8, Adoption and Amendment of the Master
Plan, Lionshead Redevelopment Master Plan, to amend the Detailed Plan Recommendations for
the Evergreen Lodge at Vail, located at 250 South Frontage Road West/Lot 2W, Block 1, Vail
Lionshead Filing 2, and setting forth details in regard thereto. (PEC140044)
Page 6
Applicant: Evergreen Lodge at Vail, represented by Mauriello Planning Group
Planner: Warren Campbell
ACTION: Table to April 13, 2015
MOTION: Cleveland SECOND: Kurz VOTE: 7-0-0
4. Approval of February 23, 2015 minutes
MOTION: Kurz SECOND: Cleveland VOTE: 7-0-0
5. Information Update
none
6. Adjournment
MOTION: Kurz SECOND: Martin VOTE: 7-0-0
The applications and information about the proposals are available for public inspection during
regular office hours at the Town of Vail Community Development Department, 75 South Frontage
Road. The public is invited to attend the project orientation and the site visits that precede the public
hearing in the Town of Vail Community Development Department. Times and order of items are
approximate, subject to change, and cannot be relied upon to determine at what time the Planning
and Environmental Commission will consider an item. Please call (970) 479-2138 for additional
information. Sign language interpretation is available upon request with 24-hour notification. Please
call (970) 479-2356, Telephone for the Hearing Impaired, for information.
Community Development Department
Published March 6, 2015 in the Vail Daily.
Page 7
rowN of vain
Memorandum
TO: Planning and Environmental Commission
FROM: Community Development Department
DATE: March 9, 2015
SUBJECT:A request for a final review of a major exterior alteration or modification, pursuant
to Section 12-7H-7, Major Exterior Alterations or Modifications, Vail Town Code,
to allow for a change to the approved mix of residential unit types, and a request
for final review of an amended conditional use permit, pursuant to Section 12-7H-
3, Permitted and Conditional Uses: First Floor or Street Level, Section 12-7H-4,
Permitted and Conditional Uses; Second Floor and Above, Vail Town Code, to
allow for a reduction in the number of timeshare units, located at 705 West
Lionshead Circle/Lot 1, Strata Vail, and setting forth details in regard thereto.
(PEC150006, PEC150007)
Applicant: Lionshead Inn LLC, represented by Mauriello Planning Group
Planner: Warren Campbell
SUMMARY
The applicant, Lionshead Inn LLC, represented by the Mauriello Planning Group, is
requesting a final review of an amended major exterior alteration, pursuant to Section
12-7H-7, Major Exterior Alterations or Modifications, Vail Town Code, to allow for a
change to the approved mix of residential unit types, and a request for a final review of
an amended conditional use permit, pursuant to Section 12-7H-4, Permitted and
Conditional Uses; Second Floor and Above, Vail Town Code, to allow for a reduction in
the number of timeshare units, located at 705 West Lionshead Circle. The 2014
approved development plan includes a mixture of dwelling units, time share units, lodge
dwelling units, lock -offs, an employee housing unit (EHU), commercial/retail space,
miscellaneous project amenities, and a private parking club. The proposed
amendments include an increase in the number of attached accommodation units and a
decrease in the number of timeshare units.
Upon review of the applicable elements of the Town's planning documents and adopted
criteria for review, the Community Development Department is recommending the
Planning and Environmental Commission approve, with conditions, the applicant's
request for an amended major exterior alteration and approve the conditional use
permit for the reduction in the number of timeshare units. A complete summary of
Staff's review is provided in Section VIII of this memorandum.
II. DESCRIPTION OF THE REQUEST
The approved redevelopment of the sites known as the Lionshead Inn and the
Lionshead Inn Annex includes three levels of below grade parking and seven floors of
residential, commercial, and common amenities above grade. The applicant is
proposing to amend their approved development plan to change the mix of residential
unit types within the project. In order to accomplish these amendments, the applicant
has submitted two applications. These applications include the following:
• A major exterior alteration application to allow for a change in the residential unit
type mix in the structure; and
• A conditional use permit application to allow for a reduction in the number of
timeshare units located on the second floor and above.
The key components of the current proposal include:
• An increase in the number of attached accommodation units from 17 to 20;
• A decrease in the number of timeshare units from 12 to 9; and
• An increase in the number of surplus parking spaces within the project from 13 to
15.
The proposed changes to the unit mix do not affect the bulk, mass, height, setbacks,
site coverage, or landscaping currently approved for the site.
A copy of the document entitled The Lion. Application for a Major Exterior Alteration &
Conditional Use Permit in the Lionshead Mixed Use -1 Zone District to Allow for a Minor
Program Change dated February 9, 2015 (Attachment A), and a reduced set of plans
dated are attached for reference (Attachment B).
III. BACKGROUND
The subject property was annexed into the Town of Vail by Ordinance No. 8,
Series of 1969, which became effective on August 23, 1969.
The Lionshead Inn and Lionshead Annex (Fabulous Vail Glo), and Enzian were
initially developed as a single project in the late 1960's and early 1970's. They
were later subdivided onto separate parcels resulting in the existing Enzian
structure being located on a parcel which is enclosed by the lot the Lionshead
Inn is located upon.
In April of 2006, the Town Council passed a moratorium on all new development
within Lionshead until a policy for retaining a live bed base could be determined.
In July of 2006, the Town Council passed Resolution No. 4, Series of 2006,
which amended portions of the Lionshead Redevelopment Master Plan to include
the provision for the inclusion of "Live Beds" in all projects that included hotel
rooms and other lodge style units in Lionshead.
Town of Vail Page 2
In February of 2007, the Town Council passed Ordinances No. 7 and No. 8,
Series of 2007, which enacted regulations for the provision of employee housing
units through several possible mitigation methods for all projects in the
Lionshead Mixed -Use 1 district.
On August 13, 2007, the Planning and Environmental Commission held a work
session to discuss the Fogata project. At that hearing the Commission generally
expressed support for the bulk, mass, and height of the proposed structure.
Several members of the Commission identified a goal of locating a portion of the
required employee housing mitigation within the project. There was discussion
regarding several specific architectural elements and their lack of compliance
with the Lionshead Redevelopment Master Plan.
On October 22, 2007, the Planning and Environmental Commission approved a
major exterior alteration conditional use permit for multi -family residential units on
the first floor, and a conditional use permit for a private parking club, to facilitate
the redevelopment of the Lionshead Inn and Lionshead Inn Annex.
The key components of the October 22, 2007 approved development plan
included:
0 51 dwelling units, 14 time share units, 12 lock -off units, and 12 lodge
dwelling units.
o The inclusion of one Type IV employee housing unit measuring
approximately 875 square feet.
0 127,606 square feet of Gross Residential Floor Area (GRFA).
o A front desk, lobby, lounge area, pool and hot tubs, business center, on
site laundry services, and meeting/conference space.
o Two commercial/retail spaces measuring approximately 7,117 square feet.
0 183 parking spaces in three below grade floors. This would be 69 in
excess of the required 114 parking spaces.
o A fully enclosed, two bay loading and delivery facility and an enclosed
trash receptacle.
On April 14, 2008, the Planning and Environmental Commission approved an
amendment to the approved Strata employee housing mitigation plan. The
approved amendment included the applicant deed restricting one 870 square foot
manager's unit on-site, seven dwelling units off-site totaling 11,686 square feet,
and paying a fee -in -lieu for the remaining 75.1 square feet required to be
mitigated in the amount of $17,772.40.
• On June 3, 2008, the Town Council denied a request to proceed forward through
the development review process with a vehicle pull -off on West Lionshead Circle
to serve as a guest loading and unloading zone.
On June, 9, 2008, the Planning and Environmental Commission unanimously
approved amendments to the major exterior alteration and conditional use permit
approvals for Strata.
Town of Vail Page 3
The key components of the June 9, 2008 approved development plan included:
o A reduction in the number of lock -of units from 12 to 8 and the increase in
the number of timeshare units from 14 to 16; bringing the total unit make-
up of the structure to 51 dwelling units, 16 timeshare units, 8 lock -off units,
and 12 lodge dwelling units.
o The increase in the on site Type IV employee housing unit from 875
square feet to 909 square feet.
o The reduction in the GRFA on the site from 127,606 square feet to
125,657 square feet of Gross Residential Floor Area (GRFA).
0 169 parking spaces in three below grade floors. This would be 53 in
excess of the required 116 parking spaces.
o A reduction in the number of the parking spaces to be included within the
private parking club from 69 to 53 spaces.
o The bulk, mass, and height of the structure were not affected
On June 9, 2008, the Planning and Environmental Commission approved an
Exemption Plat for Strata. The Final Plat was not recorded however, and the
approval of which subsequently expired as a result on June 9, 2009.
• On January 27, 2014, the Planning and Environmental Commission approved an
Exemption Plat for Strata which was subsequently recorded establishing Lot 1,
Strata Vail.
• On September 8, 2014, the Planning and Environmental Commission
unanimously approved amendments to the major exterior alteration and
conditional use permit approvals for Strata.
The key components of the September 8, 2014 approved development plan
included:
o An increase in the number of dwelling units from 51 to 53;
o An increase in the number of attached accommodation units from 8 to 17;
o A decrease in the number of lodge dwelling units from 12 to 3;
o A decrease in the number of timeshare units from 16 to 12; and
o A decrease in the commercial floor area from 7,117 sf to 5,803 sf.
o The bulk, mass, height, setbacks, site coverage, and landscape areas
were not affected.
IV. APPLICABLE DOCUMENTS
Staff has provided portions of the Vail Town Code and Lionshead Redevelopment
Master Plan which are relevant to the topics for the review included in the proposal.
Zoning Regulations
Lionshead Mixed Use — 1 Zone District (in part)
Town of Vail Page 4
12-7H-1: PURPOSE.-
The
URPOSE.
The Lionshead Mixed Use -1 zone district is intended to provide sites for a mixture of
multiple -family dwellings, lodges, hotels, fractional fee clubs, time shares, lodge
dwelling units, restaurants, offices, skier services, and commercial establishments in a
clustered, unified development. Lionshead Mixed Use 1 zone district, in accordance
with the Lionshead Redevelopment Master Plan, is intended to ensure adequate light,
air, open space and other amenities appropriate to the permitted types of buildings and
uses and to maintain the desirable qualities of the District by establishing appropriate
site development standards. This District is meant to encourage and provide incentives
for redevelopment in accordance with the Lionshead Redevelopment Master Plan.
This Zone District was specifically developed to provide incentives for properties to
redevelop. The ultimate goal of these incentives is to create an economically vibrant
lodging, housing, and commercial core area. The incentives in this Zone District include
increases in allowable gross residential floor area, building height, and density over the
previously established zoning in the Lionshead Redevelopment Master Plan study area.
The primary goal of the incentives is to create economic conditions favorable to
inducing private redevelopment consistent with the Lionshead Redevelopment Master
Plan. Additionally, the incentives are created to help finance public off-site
improvements adjacent to redevelopment projects. With any
development/redevelopment proposal taking advantage of the incentives created
herein, the following amenities will be evaluated. streetscape improvements,
pedestrian/bicycle access, public plaza redevelopment, public art, roadway
improvements, and similar improvements.
12-7H-5. PERMITTED AND CONDITIONAL USES, SECOND FLOOR AND ABOVE.-
B.
BOVE.
B. Conditional Uses. The following uses shall be permitted on the second floors and
higher above grade, subject to issuance of a conditional use permit in accordance with
the provisions of chapter 16 of this title.-
Banks
itle.
Banks and financial institutions.
Child daycare centers.
Conference facilities and meeting rooms.
Eating and drinking establishments.
Electronics sales and repair shops.
Fractional fee clubs.
Liquor stores.
Personal services and repair shops.
Professional offices, business offices, and studios.
Recreational facilities.
Retail establishments.
Skier ticketing, ski school, and skier services.
Theaters.
Timeshare units.
Town of Vail Page 5
Additional uses determined to be similar to conditional uses described in this
subsection, in accordance with the provisions of section 12-3-4 of this title.
12-7H-8. COMPLIANCE BURDEN.-
It
URDEN.It shall be the burden of the applicant to prove by a preponderance of the evidence
before the Planning and Environmental Commission and the Design Review Board that
the proposed exterior alteration or new development is in compliance with the purposes
of the Lionshead Mixed Use 1 zone district, that the proposal is consistent with
applicable elements of the Lionshead Redevelopment Master Plan and that the
proposal does not otherwise have a significant negative effect on the character of the
neighborhood, and that the proposal substantially complies with other applicable
elements of the Vail comprehensive plan.
12-7H-18. MITIGATION OF DEVELOPMENT IMPACTS:
Property owners/developers shall also be responsible for mitigating direct impacts of
their development on public infrastructure and in all cases mitigation shall bear a
reasonable relation to the development impacts. Impacts may be determined based on
reports prepared by qualified consultants. The extent of mitigation and public amenity
improvements shall be balanced with the goals of redevelopment and will be
determined by the planning and environmental commission in review of development
projects and conditional use permits. Mitigation of impacts may include, but is not
limited to, the following. roadway improvements, pedestrian walkway improvements,
streetscape improvements, stream tract/bank improvements, public art improvements,
and similar improvements. The intent of this section is to only require mitigation for large
scale redevelopment/development projects which produce substantial off site impacts.
Chapter 12-16: Conditional Uses Permits (in part)
Section 12-16-1. Purpose, Limitations
In order to provide the flexibility necessary to achieve the objectives of this title,
specified uses are permitted in certain districts subject to the granting of a conditional
use permit. Because of their unusual or special characteristics, conditional uses require
review so that they may be located properly with respect to the purposes of this title and
with respect to their effects on surrounding properties. The review process prescribed
in this chapter is intended to assure compatibility and harmonious development
between conditional uses and surrounding properties in the Town at large. Uses listed
as conditional uses in the various districts may be permitted subject to such conditions
and limitations as the Town may prescribe to insure that the location and operation of
the conditional uses will be in accordance with the development objectives of the Town
and will not be detrimental to other uses or properties. Where conditions cannot be
devised, to achieve these objectives, applications for conditional use permits shall be
denied.
Lionshead Redevelopment Master Plan (in part)
Chapter 2, Introduction
Town of Vail Page 6
2.1 Purpose of the Master Plan (in part)
"This master plan was initiated by the Town of Vail to encourage redevelopment
and new development initiatives in the Lionshead study area. Both public and
private interests have recognized that Lionshead today lacks the economic
vitality of Vail and fails to offer a world class resort experience. Lionshead's
economic potential has been inhibited by a number of recurrent themes.
• Lack of growth in accommodation units ("hot beds'),
• Poor retail quality;
• Deterioration of existing buildings,
• Uninteresting and disconnected pedestrian environment;
• Mediocre architectural character; and the
• Absence of incentives for redevelopment.
This master is a comprehensive guide for property owners proposing to
undertake development or redevelopment of their properties and the municipal
officials responsible for planning public improvements. The plan outlines the
Town's objectives and goals for the enhancement of Lionshead and proposes
recommendation, incentives, and requirements for redevelopment and new
development. "
2.2 Definition of a Master Plan
In the development of the Lionshead Master Plan, the following definition has
been used as the basis for this work.
A master plan is a guide, a flexible framework for future action. It articulates a
community's fundamental land use policies, principles, and goals in a broad and
general way. It plans for the future physical development or redevelopment of an
area of the community, including its functional and circulation systems and its
public facilities.
The land use policies in a master plan are generally implemented through zoning
ordinances. Existing zoning and land use codes may be modified and new
provisions enacted in order to conform to the master plan and carry out the plan's
objectives.
A master plan does not convey approval for particular development proposals or
concepts, nor can it be implemented in a short time frame. After adoption of the
Lionshead Master Plan, every development proposal will have to go through the
applicable development review and approval process, with its attendant public
notices and public hearings. A proposal's adherence to the policies contained in
the adopted master plan will be one of the factors analyzed by staff, the Planning
and Environmental Commission (PEC), the Design Review Board (DRB), and the
Town Council (as applicable) in determining whether to approve or disapprove
the specific proposal.
Town of Vail Page 7
2.3 Policy Objectives
The Town Council adopted six policy objectives on November 4, 1996 to outline
the important issues to be addressed in the master plan and to provide a policy
framework for the master planning process.
2.3.3 Stronger Economic Base Through Increased Live Beds
In order to enhance the vitality and viability of Vail, renewal and
redevelopment in Lionshead must promote improved occupancy rates and
the creation of additional bed base ("live beds" or "warm beds') through
new lodging products. Live beds and warm beds are best described as
residential or lodging rooms or units that are designed for occupancy by
visitors, guests, individuals, or families on a short term rental basis. In
order to improve occupancy rates and create additional bed base in
Lionshead, applications for new development and redevelopment projects
which include a residential component shall provide live beds in the form
of accommodation units, fractional fee club units, lodge dwelling units,
timeshare units, attached accommodation units (i.e, lock -off units), or
dwelling units which are included in a voluntary rental management
program and available for short term rental. Further, it is the expressed
goal of this Plan that in addition to creating additional bed base through
new lodging products, there shall be no net loss of existing live beds within
the Lionshead Redevelopment Master Plan study area.
Chapter 4, Master Plan Recommendations — Overall Study Area
This section of the master plan addresses issues that affect Lionshead as a
whole. These issues, and recommendations to address them, should be
considered in all planning and policy decisions as Lionshead develops.
4.13 Live Beds
The maintenance, preservation, and enhancement of the live bed base are
critical to the future success of Lionshead and as such, special emphasis should
be placed on increasing the number of live beds in Lionshead as the area
undergoes redevelopment. The Lionshead area currently contains a large
percentage of the Town's overall lodging bed base. The bed base in Lionshead's
consists of a variety of residential and lodging products including hotels,
condominiums, timeshares and hybrids of all three. The vast majority of live
beds in Lionshead are not accommodation units in hotels, but instead, in dwelling
units in residential condominiums such as the Vail 21, Treetops, Antlers Lodge,
Lion Square Lodge, Lifthouse Lodge, Landmark Tower and Townhomes,
Lionshead Arcade, and Montaneros, all of which have some form of
rental/property management program that encourages short term rental of
dwelling units when the owners are not in residence. It has been the experience
in Lionshead that condominium projects which include a voluntary rental
management program have occupancy rates which exceed the occupancy rate
Town of Vail Page 8
of hotel products, and therefore tend to provide more live beds and produce more
lodging tax revenues to the Town.
Applications for new development or redevelopment which maintain,
preserve, and enhance the live bed base in Lionshead have a significantly
greater chance of approval in the development review process than those which
do not.
4.13.2 Location of Live Beds
Live beds should be located in Lionshead pursuant to the Lionshead
Mixed Use 1 and 2 zone districts. All properties within Lionshead, when
developing or redeveloping and providing new residential or lodging
products, should provide live beds as defined herein.
4.13.3 Hotel -types of Services and Amenities
To aid in the furtherance of Policy Objective 2.3.3 of the Plan, the creation
of additional live beds should include hotel -types of services and
amenities. Such services and amenities may include, but not be limited
to, the operation of a front desk, registration/reservation capabilities,
recreational amenities, guest drop-off, on-site management, etc. These
types of services and amenities in multiple family residential dwellings will
increase the likelihood that the dwelling units will be made available for
short term occupancy and help to promote improved occupancy rates.
Vail Land Use Plan
The Vail Land Use Plan was adopted by the Vail Town Council on November 18, 1986.
The plan is intended to serve as a basis from which future decisions may be made
regarding land use within the valley. The primary focus of the Vail Land Use Plan is to
address the long-term needs and desires of the Town as it matures.
The goals articulated in the plan reflect the desires of the citizenry. The goal statements
that were developed reflect a general consensus of the comments shared at public
meetings. The goals contained in the Vail Land Use Plan are to be used as the Town's
adopted policy guidelines in the review process for new development proposals.
According to the Official Town of Vail Land Use Plan map, the applicant's proposed
redevelopment site is located with the "Lionshead Redevelopment Master Plan" land
use category. Pursuant to the Plan, the "Lionshead Redevelopment Master Plan" land
use category description,
"Included in this category are those properties which are identified as being
included in the Lionshead Redevelopment Master Plan boundaries. Properties
located within this land use category shall be encouraged to redevelop, per the
Master Plan recommendations, as it has been found that it is necessary in order
for Vail to remain a competitive four -season resort. Uses and activities for these
areas are intended to encourage a safe, convenient and an aesthetically -
Town of Vail Page 9
pleasing guest experience. The range of uses and activities appropriate in the
Lionshead Redevelopment Master Plan (LRMP) land use category may include
skier and resort services, ski lifts, ski trails, base facilities, public restrooms, ticket
sales, clubs, public plazas, open spaces, parking and loading/delivery
facilities/structures, public utilities, residential, lodges, accommodation units,
deed restricted employee housing, retail businesses, professional and business
offices, personal services, and restaurant uses."
V. ZONING ANALYSIS
Address/Legal Description:705 West Lionshead Circle/Lot 1 Strata Vail
Zoning: Lionshead Mixed Use 1
Land Use Designation: Lionshead Redevelopment Master Plan
Development Standard Allowed Approved Proposed
Lot Area: 10,000 sq. ft. 68,336.9 sq. ft. No change.
Setbacks All Sides: 10 ft. North - 30 ft. No change
East- 10 ft. No change
West- 10 ft. No change
South- 10 ft. No change
Building Height: 71 ft. avg. 69.5 ft. avg. No change
82.5 ft. max 82.5 ft. max No change
Density: 54 DUs (35/ac.) 53 DUs No Change
Lodge Dwelling Unit 3 LDUs No Change
(1/4 a dwelling unit) 53.75 DUs (34.2/ac.)
Unlimited Attached
Accommodation Units 17 AAUs
(AAUs)
Unlimited Timeshare 12 TSUs
Units (TSUs)
GRFA: 170,840 sq. ft.
Site Coverage: 47,835 sq. ft.
(70%)
Landscape Area: 13,667 sq. ft.
(20%)
125,657 sq. ft
42,397 sq. ft
(62%)
17,401 sq. ft
(25.5%)
20 AAUs
9 TSUs
No change
No change
No change
Town of Vail Page 10
Parking: 74.2 (1.4/DU) 169 spaces* No change
6.3 (0.7/Time Share)
4.2 (1.4/Lodge Dwelling Unit)
8.2 (1/250 s.f. of restaurant seating area)
6.2 (2.3/1,000 s.f. of retail net floor area)
1_4 (1.4/EHU)
101 required
53 (Parking Club CUP)
154 total required
Loading 3 berths 3 berths No change
* Of the parking spaces proposed, 116 spaces will serve The Lion which is in excess of the
101 required. 53 are approved to be placed in a private parking club.
VI. SURROUNDING LAND USES AND ZONING
VII. CRITERIA
Maior Exterior Alteration
Section 12-7H-8, Compliance Burden, Vail Town Code, outlines the review criteria for
major exterior alteration applications proposed within the Lionshead Mixed Use 1 (LMU-
1) zone district. According to Section 12-7H-8, Vail Town Code, a major exterior
alteration shall be reviewed for compliance with the following criteria:
1. That the proposed major exterior alteration is in compliance with the
purposes of the Lionshead Mixed Use 1 zone district;
The purposes of the Lionshead Mixed Use 1 (LMU-1) zone district are stated in
Section 12-7H-1, Purpose, Vail Town Code. The LMU-1district is intended to
provide sites within the area of Lionshead for a mixture of multiple -family
dwellings, hotels, fractional fee clubs, restaurants, skier services and
commercial/retail establishments. The development standards prescribed for the
district were established to provide incentives for development in accordance
with the goals and objectives of the Lionshead Redevelopment Master Plan. The
purpose statement for the LMU-1 district has been included in Section IV of this
memorandum.
Town of Vail Page 11
Land Use
Zoning
North:
CDOT right-of-way
No zoning
South:
Mixed use
Lionshead Mixed Use 1 District
East:
Mixed use
Lionshead Mixed Use 1 District
West:
Mixed use
Lionshead Mixed Use 1 District
VII. CRITERIA
Maior Exterior Alteration
Section 12-7H-8, Compliance Burden, Vail Town Code, outlines the review criteria for
major exterior alteration applications proposed within the Lionshead Mixed Use 1 (LMU-
1) zone district. According to Section 12-7H-8, Vail Town Code, a major exterior
alteration shall be reviewed for compliance with the following criteria:
1. That the proposed major exterior alteration is in compliance with the
purposes of the Lionshead Mixed Use 1 zone district;
The purposes of the Lionshead Mixed Use 1 (LMU-1) zone district are stated in
Section 12-7H-1, Purpose, Vail Town Code. The LMU-1district is intended to
provide sites within the area of Lionshead for a mixture of multiple -family
dwellings, hotels, fractional fee clubs, restaurants, skier services and
commercial/retail establishments. The development standards prescribed for the
district were established to provide incentives for development in accordance
with the goals and objectives of the Lionshead Redevelopment Master Plan. The
purpose statement for the LMU-1 district has been included in Section IV of this
memorandum.
Town of Vail Page 11
The proposal to amend the unit type mix through the conversion of three
timeshare units to attached accommodation units is in keeping with the purpose
statement of the district. The three attached accommodation units will become a
lock -off fourth bedroom to the three existing dwelling units. The proposal to
change the unit mix is in keeping with the stated purpose of provide for a mixture
of various unit types in a unified development.
Staff has performed a review of the proposed amendments to the approved
major exterior alteration for compliance with the development requirements of the
LMU-1. In Section V of this memorandum staff performed a zoning analysis of
the project with regard to the development parameters of the LMU-1. Within this
analysis staff reaffirmed that the project is in compliance with the development
parameters for setbacks, height, density, GRFA, site coverage, and landscape
area.
Staff finds the proposed amendments comply with this criterion.
2. That the proposal is consistent with applicable elements of the Lionshead
Redevelopment Master Plan;
The Lionshead Redevelopment Master Plan (LRMP) contains detailed plan
recommendations for the site being redeveloped as The Lion within Chapter 5,
Detailed Plan Recommendations. It provides the following direction.
5.15.4 Preservation of Existing Live Beds
The Lionshead Inn and Lionshead Annex presently contain 85
accommodation units. Given the importance and need for live beds
to the vitality and success of the community, any future
redevelopment of the sites shall ensure the preservation of short
term accommodation on the site. The preservation of live beds
should focus on maintaining the number of existing live beds and
the amount of gross residential square footage devoted to that use
on the site. With this in mind, the quality of the existing live bed
base could be upgraded and the rooms could be reconfigured to
create increased lodging opportunities. In no instance,
however, shall the amount of gross residential floor area devoted to
live beds be reduced. The construction of "attached
accommodation units", "lodge dwelling units", "timeshare units",
"fractional fee club units", and dwelling units in a voluntary rental
program, as defined in the Zoning Regulations, could significantly
increase the availability of short term rental opportunities within the
building.
Town of Vail Page 12
Additionally, the LRMP includes a definition for what is considered a live bed for
the purposes maintain vitality and success of the community. Live beds are
defined as follows:
4.13.1 Live Bed Definition
Pursuant to Policy Objective 2.3.3, live beds (and warm beds) are
defined as residential or lodging rooms or units that are designed
for occupancy by visitors, guests, individuals, or families, on a short
term rental basis. A live bed may include the following residential
products. accommodation units, fractional fee club units, lodge
dwelling units, timeshare units, attached accommodation units (i.e.,
lock -off units), and dwelling units which are included in a voluntary
rental management program and available for short term rental.
The Lionshead Inn and Lionshead Inn Annex contained 85 accommodation units
measuring 28,863 square feet. The amended proposal for The Lion, includes a
combination of 53 dwelling units, 9 time share units, 20 lock -off units, and 3 lodge
dwelling units. These unit types combined equal 85 units measuring 125,657
square feet of GRFA. The unit types proposed are included within the definition
of live beds as detailed in Section 4.13.1, Live Bed Definition, LRMP. In order for
any unit type contained within the definition to be considered "live" it needs to be
included within a voluntary rental management program and available for short-
term rental.
To encourage owners within The Lion project to participate in the rental program,
there are provisions for a front desk with registration/reservation capabilities,
lobby, lounge area, pool and hot tubs, business center, on site laundry services,
and meeting/conference space. Furthermore, there are provisions for
commercial/retail spaces measuring approximately 5,803 square feet within the
project. As stated in Section 14.13.3, Hotel -types of Services and Amenities, the
incorporation of these components in the development will hope to increase the
likelihood that the units included within The Lion will participate in the voluntary
rental management program.
Section 4.13.4, Review of New Development and Redevelopment Projects, was
adopted to guide the Commission in reviewing projects for compliance with the
"live bed" requirements of the Master Plan. Section 4.13.4 is as follows:
4.13.4 Review of New Development and Redevelopment Projects
The Planning and Environmental Commission shall consider the
policies and direction given by this Plan with respect to live beds
when reviewing new development and redevelopment projects in
Lionshead. Applications for new development or redevelopment
maintain the live bed base in Lionshead. Applications for new
development and redevelopment which enhance the live bed base
have a significantly greater chance of approval in the development
review process than those which do not. A proposal's adherence to
Town of Vail Page 13
the policies contained in the adopted master plan will be one of the
factors analyzed by staff, the Planning and Environmental
Commission (PEC), the Design Review Board (DRB), and the
Town Council (as applicable) in determining whether to approve or
disapprove the specific proposal.
The proposed amendments to the unit mix are in keeping with the definition of
live beds and result in a total of 85 units within the development. The three
timeshare units are proposed to become attached accommodation units to three
existing dwelling units. With the inclusion of the identified hotel -type of services
and amenities, the expectation is that unit owners may choose to participate in
the voluntary rental management program for the development. The result is that
the three three-bedroom dwelling units will become three four-bedroom dwelling
units. The new four bedroom dwelling units could be included in the rental
management program as a four bedroom, three bedroom, or one bedroom units.
Timeshare units are a desirable unit type for inclusion within projects in the town
as they have a tendency of being warmer beds due to the fractional ownership.
The inclusion of timeshares within the project is not required pursuant the LMU-1
district zoning on the property. The inclusion of timeshares within the
development increases the likelihood the units are occupied more frequently
which addresses the goals and objectives of the Lionshead Redevelopment
Master Plan to have live beds to generate numbers of guests participating in the
vitality of Vail's commercial cores.
On a spectrum of how "live" a unit is staff would find that a timeshare unit, by its
fractional ownership nature, is more "live" than an attached accommodation unit.
An attached accommodation unit (lock -off) is designed to encourage
incorporation within a voluntary rental management program; however, it is
physically attached to a dwelling unit which is typically owned by a single
ownership entity and not required to be available on a short-term basis. A
timeshare is not required to be included within the voluntary rental management
program, however, a timeshare unit is likely to be occupied more frequently than
an attached accommodation unit not included within the program. The proposed
conversion of three timeshare units to three attached accommodation units may
result in a less "live" unit mix within the development.
Live Bed Spectrum
Least Live Most Live
Dwelling Unit Attached AU Timeshare Unit Accommodation Unit (AU)
Staff has reviewed The Lion proposal and found it to be in compliance with the
requirements of LRMP with regard to the detailed pan recommendations for the
maintenance of live beds and GRFA devoted to units defined as live beds. Staff
finds the proposed amendments to The Lion development comply with this
criterion.
Town of Vail Page 14
3. That the proposal does not otherwise have a significant negative effect on
the character of the neighborhood; and,
Staff has reviewed the proposed amended major exterior alteration and found
that the proposed changes do not affect the bulk, mass, height, and setbacks of
the structure as approved, therefore staff believes that for the same reasons
presented at the initial approval, the project is in compliance with this criterion.
4. That the proposal substantially complies with other applicable elements of
the Vail Comprehensive Plan.
Staff has reviewed the proposed amended major exterior alteration application
and found that the proposed changes continue to comply with the following
elements of the Vail Comprehensive Plan:
Town of Vail Transportation Master Plan,
Lionshead Redevelopment Master Plan,
Art in Public Places Strategic Plan.
With regard to the Town of Vail Transportation Master Plan the applicant
provided the Public Works Department with traffic studies and roadway
improvement designs. The Town Engineer has reviewed the proposed
amendments to the unit type mix and found there to be no change in the peak
hour net new trips of 25.06. This increase in peak hour net new trips results in a
fee of $162,890 to mitigate traffic impacts created by the development. These
funds may go towards traffic improvements in the vicinity of the project.
Staff finds that for the same reasons presented at the initial approval that the
project is in compliance with this criterion.
Conditional Use Permit
According to Section 12-16-6, Vail Town Code, the Planning and Environmental
Commission shall consider the following factors with respect to the proposed timeshare
unit use:
1. Relationship and impact of the use on development objectives of the
town.
Timeshare units are a desirable unit type for inclusion within projects in
the town as they have a tendency of being warmer beds due to the
fractional ownership. The inclusion of timeshares within the project is not
required pursuant the Lionshead Mixed Use 1 district zoning on the
property. The inclusion of timeshare within the development increases the
likelihood the units are occupied more frequently which addresses the
goals and objectives of the Lionshead Redevelopment Master Plan to
Town of Vail Page 15
have live beds to generate numbers of guests participating in the vitality of
Vail's commercial cores. While a reduction in the number of timeshare
units is proposed from 12 to 9 there is no requirement for the inclusion of
timeshares.
Staff finds the proposed amendments to The Lion development comply
with this criterion.
2. Effect of the use on light and air, distribution of population,
transportation facilities, utilities, schools, parks and recreation
facilities, and other public facilities and public facilities needs.
The proposal to reduce the number of timeshare units from 12 to 9 will
have no effect on the elements listed in the criterion above as the proposed
change will occur within the currently approved bulk, mass, and height for
The Lion development. Staff finds the proposal complies with this criterion.
3. Effect upon traffic, with particular reference to congestion,
automotive and pedestrian safety and convenience, traffic flow and
control, access, maneuverability, and removal of snow from the
streets and parking areas.
The proposed reduction in timeshare units from 12 to 9 will continue to
have impacts on traffic generation and flow in the vicinity. Those impacts
are addressed and mitigated in the approved roadway improvements
associated with the approved development plan for The Lion. Staff
believes the proposal is in compliance with this criterion.
4. Effect upon the character of the area in which the proposed use is to
be located, including the scale and bulk of the proposed use in
relation to surrounding uses.
The proposal to reduce the number of timeshare units from 12 to 9 will
have no effect on the character of the area as the proposed change will
occur within the currently approved bulk, mass, and height for The Lion
development. Staff believes the proposal complies with this criterion
VIII. STAFF RECOMMENDATION
The Community Development Department recommends that the Planning and
Environmental Commission approves, with conditions, the request for final review of
a major exterior alteration or modification, pursuant to Section 12-7H-7, Major Exterior
Alterations or Modifications, Vail Town Code, to allow for a change to the approved mix
of residential unit types, and approves the request for final review of an amended
conditional use permit, pursuant to Section 12-7H-4, Permitted and Conditional Uses;
Second Floor and Above, Vail Town Code, to allow for a reduction in the number of
Town of Vail Page 16
timeshare units, located at 705 West Lionshead Circle/Lot 1, Strata Vail, and setting
forth details in regard thereto. Staff's recommendation is based upon the review of the
major exterior alteration and conditional use permit review criteria outlined in Section VII
of this memorandum and the evidence and testimony presented at the public hearing.
Should the Planning and Environmental Commission choose to approve the amended
major exterior alteration, Staff recommends that the Commission makes the following
the motion:
"The Planning and Environmental Commission approves, with conditions, a
major exterior alteration or modification, pursuant to Section 12-7H-7, Major
Exterior Alterations or Modifications, Vail Town Code, to allow for a change to the
approved mix of residential unit types, located at 705 West Lionshead Circle/Lot
1, Strata Vail, and setting forth details in regard thereto."
Should the Planning and Environmental Commission choose to approve the amended
major exterior alteration, Staff recommends that the Commission makes the following
finding as part of the motion:
"Pursuant to Section 12-7H-8, Compliance Burden, Vail Town Code, the
applicant has proven by a preponderance of the evidence before the Planning
and Environmental Commission that the proposed major exterior alteration is in
compliance with the zoning regulations, the purposes of the Lionshead Mixed
Use -1 zone district, that the proposal is consistent with applicable elements of
the Lionshead Redevelopment Master Plan and that the proposal does not
otherwise have a significant negative effect on the character of the
neighborhood, that the proposal substantially complies with other applicable
elements of the Vail Comprehensive Plan."
Should the Planning and Environmental Commission choose to approve the amended
major exterior alteration, Staff recommends that the following conditions be placed upon
the amended approval:
Prior to Requesting a Temporary Certificate of Occupancy
1. That the Developer prepares a The Lion Art in Public Places Plan, for input and
comment by the Town of Vail Art in Public Places Board, Chapter 12-25, Public Art,
Vail Town Code, prior to the request for a temporary certificate of occupancy.
Subject to the above input and comment by the Art in Public Places Board, the
Applicant will determine the type and location of the art to be provided. Said Plan
shall include the funding for a minimum of $70,000.00 in public art improvements to
be developed in conjunction with The Lion project.
2. That the Developer shall be assessed a transportation impact fee in the amount of
$6,500 per increased vehicle trip in the peak hour generated (25.06 trips), or
$162,890, created by The Lion project. The total fee of $162,890 shall be paid in full
by the Developer prior to the issuance of a temporary certificate of occupancy or
Town of Vail Page 17
certificate of occupancy for The Lion project. At the sole discretion of the Town of
Vail Public Works Director, said fee may be waived in full, or part, based upon the
completion of certain off-site improvements.
Should the Planning and Environmental Commission choose to approve the amended
conditional use permit, Staff recommends that the Commission makes the following the
motion:
"The Planning and Environmental Commission approves an amended conditional
use permit, pursuant to Section 12-7H-4, Permitted and Conditional Uses,-
Second
ses,Second Floor and Above, Vail Town Code, to allow for a reduction in the number
of timeshare units, located at 705 West Lionshead Circle/Lot 1, Strata Vail, and
setting forth details in regard thereto. "
Should the Planning and Environmental Commission choose to approve the amended
conditional use permit, Staff recommends that the Commission makes the following
finding as part of the motion:
"Pursuant to Section 12-16-6, Criteria, Findings, Vail Town Code, the planning
and environmental commission finds.-
1.
inds.
1. That the proposed location of the use is in accordance with the
purposes of this title and the purposes of the zone district in which the
site is located.
2. That the proposed location of the use and the conditions under which it
would be operated or maintained will not be detrimental to the public
health, safety, or welfare, or materially injurious to properties or
improvements in the vicinity.
3. That the proposed use will comply with each of the applicable
provisions of this title."
IX. ATTACHMENTS
A. Applicant's written request entitled The Lion: Application for a Major Exterior
Alteration & Conditional Use Permit in the Lionshead Mixed Use -1 Zone District
to Allow for a Minor Program Change dated February 9, 2015
B. Copy of proposed plans dated February 3, 2015
Town of Vail Page 18
The Lion
Application for a Major Exterior Alteration &
Conditional Use Permit in the
Lionshead Mixed Use -1 Zone District to allow for
a Minor Program Change
Submitted: February 9, 2015
1. Introduction
The Lion, located at 705 W.
Lionshead Circle, was originally
approved in November of 2007
and later amended June 2008 and
in September of 2014. This project
is the first of four redevelopment
projects that were granted approval
extensions due to the economic
recession. The Lion includes luxury
residences and timeshare units
designed to be clean, contemporary
and provocative spaces with
expansive natural day lighting and
vaulted ceilings. Contemporary materials such as copper, stucco, and natural cedar will
impart European styling, however, stay in line with the forty years of Vail traditions. A
mixture of spacious units will capture the market niche that is absent in Vail making The Lion
one of the most coveted new addresses at this world class year-round resort.
The Lion was approved in 2014 for:
• 53 dwelling units with 17 attached accommodation units (lock -offs) for a total of 70 live
beds
• 3 lodge dwelling units for a total of 3 live beds
• 12 timeshare units for a total of 12 live beds
• 1 onsite employee housing unit of 909 sq. ft. Overall GRFA of 125,657 sq. ft. 5,803
sq. ft. of commercial space
• 169 parking spaces, 53 of which are approved for leasing as a private parking
structure, 13 of which are surplus.
The applicant is proposing a slight change to the overall residential programming. It is this
minor change that generates the need for review and approval by the PEC. No other
changes are proposed to the building and the building exterior is exactly as originally
approved in 2008. There is no addition of GRFA or commercial floor area. In fact, the
proposed changes have an overall reduced impact on parking and traffic.
The revised programming includes:
• 53 dwelling units with 20 attached accommodation units (lock -offs) for a total of 73 live
beds (an increase of 3 attached accommodation units)
• 3 lodge dwelling units for a total of 3 live beds (no change)
• 9 timeshare units for a total of 9 live beds (a reduction of 3 timeshare units)
• 1 onsite employee housing unit of 909 sq. ft. (no change)
The Lion
February 9, 2075 2
• Overall GRFA of 125,657 sq. ft. (no change)
• 5,803 sq. ft. of commercial space (no change)
• 169 parking spaces, 53 of which are approved for leasing as a private parking
structure, 15 of which are surplus due to the changes proposed
The proposed changes still result in a total of 85 live beds as recommended by the Lionshead
Redevelopment Master Plan for this property as was approved last September. The loss of
keys due to the reduction in timeshare units was offset by the addition of lock -off units geared
toward short-term accommodation. It should be noted that dwelling units, attached
accommodation units, and lodge dwelling units are all uses by right in the LMU-1 zone
district. Timeshare units require a conditional use permit and what is proposed is a reduction
in the number of timeshare units from 2014. The proposed changes result in a slight decrease
in the required number of parking spaces.
The applicant has provided plans showing the all of the unit types. It should be noted that the
dwelling unit and timeshare unit designations can be interchanged as long as the unit counts
remain the same for each unit type.
The Lion
February 9, 2075 3
2. Background
The Lionshead Inn properties were originally developed as The Enzian Lodge (later to
become the L'Ostello and eventually the Lionshead Inn) the Enzian Condominiums, and the
Vail Glo Lodge (Lionshead Inn Annex), which was originally a Best Western. They were
gym„ developed on a portion of Lot
R 1, Block 2, Vail/Lionshead
Third Filing, and were
A- k,_a`* subsequently subdivided.
Prior to demolition, the uses on-site were as follows:
Existing Dwelling GRFA
Units
Lionshead Inn 10
Lionshead Inn Annex 1 1
Vail/Lionshead, Filing 3 was
recorded in 1971. This plat
created Lot 1, Block 2, Vail
Lionshead Third Filing, upon
which Vail Spa and the
Lionshead Inn properties sit.
The subject property was
replatted with an exemption
plat in March of 2014.
Accommodation
Units
18,451 sq. ft. 52
10,412 sq. ft. 33
TOTAL 11 128,863 sq. ft. 185
Restaurant
2,560 sq. ft.
0
2,560 sq. ft.
In April of 2006, the Town of Vail passed a moratorium on all new development within the
Lionshead area. The ordinance prohibited the filing of any development application that
would cause a reduction in the existing number of hotel rooms, employee housing units or
parking spaces within the Lionshead zone district. In July of 2006, Resolution No. 4 was
approved, amending the Lionshead Redevelopment Master Plan with regards to the
preservation of "live beds," including specific language for the subject property
recommending a minimum of 85 live beds.
Following the approval of the amendments to the Lionshead Redevelopment Master Plan, the
Town enacted an emergency ordinance, requiring that any applications for development in
the Town of Vail would be subject to future regulations with regards to employee housing.
The Lion
February 9, 2075 4
Ordinances No. 7 and No. 8 were passed in February of 2007, providing regulations for
commercial linkage and inclusionary zoning.
On October 22, 2007, the Strata redevelopment was approved, followed by a minor change
to the approval on June 6, 2008. In 2012, the Town of Vail passed Resolution No. 13 which
extended the vested approval date on four projects including the The Lion/Strata
redevelopment until June 1, 2015. The applicant obtained a building permit and began
construction in May 2014. In August of 2014, the applicant submitted some minor
programmatic changes which the Planning and Environmental Commission approved in
September of 2014.
The Lion
February 9, 2075 5
3. Zoning and Parking Analysis
Proposed changes from the 2014 approval are indicated in red.
Zoning Analysis:
Lot Size: 1.5688 acres
Zoning: Lionshead Mixed Use -1
Setbacks
Height -max
Height -average
Density*
GRFA
Site Coverage
Allowed/
Required
10 ft.
82.5 ft.
71 ft.
TOTAL: 54
170,815 sq. ft.
47,828 sq. ft.
Approved
(2008)
10 ft./30 ft. on
n. property line
82.5 ft.
70.88 ft.
TOTAL: 54
51 du
8 lock -off
12 Idu
16 is
Approved
(2014)
10 ft./30 ft. on
n. property line
82.5 ft.
70.88 ft.
TOTAL: 53.75
53 du
17 lock -off
3 Idu
12 is
Proposed (2015)
10 ft./30 ft. on
n. property line
82.5 ft.
70.88 ft.
TOTAL: 53.75
53 du
20 lock -off
3 Idu
9 is
125,657 sq. ft. 125,657 sq. ft. 125,657 sq. ft.
42,397 sq. ft. 42,397 sq. ft. 42,397 sq. ft.
Loading 2 berth 2 berth 2 berth 2 berth
*lock -offs and timeshare do not count towards density. Ldu count as 1/4 du.
The Lion
February 9, 2015 6
21,329 sq. ft.
21,329 sq. ft.
21,329 sq. ft.
Landscape Area
with hardscape
with hardscape
with hardscape
14,668 sq. ft.
14,668 sq. ft.
14,668 sq. ft.
13,665 sq. ft.
softscape only
softscape only
softscape only
Loading 2 berth 2 berth 2 berth 2 berth
*lock -offs and timeshare do not count towards density. Ldu count as 1/4 du.
The Lion
February 9, 2015 6
Parking Analysis:
Use
Dwelling Units
Time Share Units
Lock -off
Lodge Dwelling Unit
Restaurant
Retail
EHU
The Lion
Required
Unit
Calculation
1.4 per unit
.7 per unit
Parking
53
74.2
9
6.3
20
only if more than 1 lock -off
1.4 per unit
1 space per 250 sq. ft. of seating floor area
2.3 spaces per 1,000 sq. ft. of net floor area
1.4 per unit
0
3
2,052 sq. ft.
4.2
8.2
2,688 sq.ft.
6.2
1
1.4
Total Required Parking: 100.5
Private Parking Structure: 53
Surplus Parking: 15.5
Total Parking Provided: 169
February 9, 2015 7
4. Employee Housing
The applicant is not proposing to make any changes to the employee housing
mitigation that was previously approved for the project. There is no new floor area
being proposed that would generate a new employee housing requirement.
The Town's original inclusionary zoning and commercial linkage program was in
place when this project was approved in 2007. Subsequent to the approval of this
project the Town amended the employee housing standards to require 50% of the
employee housing to be placed onsite. In 2012 the Town Council approved Resolution
No. 13 which granted extensions to the vested approval for this project. This
extension to the vested approval period had the effect of vesting the project for
changes to code that may have occurred during the vesting period (i.e.,
"grandfathering" the onsite employee housing).
The total employee housing square footage required for the project is 12,405 sq. ft.
which comes entirely from the inclusionary requirement (the project has a credit of
5.91 employees on the commercial linkage requirement due to the pre-existing
hotels). The project was previously approved with one onsite employee housing unit
of 909 sq. ft. (7.5%) and seven off-site units (11,756 sq. ft.) for a total of 12,665 sq.
ft. of employee housing. The previous project approval provides an excess of 260 sq.
ft. of employee housing for the inclusionary requirement.
On May 29, 2012, the Town acknowledged in a letter (below) that the "Town of Vail
has received, and approved, 11,761 square feet of deed restricted employee housing
units that are dedicated to the Strata Development Approval (DEV07-0003/
PRJ11-0701)." With that acknowledgement and with the 11,761 sq. ft. of deed
restricted offsite employee housing actually provided, the total employee housing
(inclusionary) provided for this project, including the onsite unit of 909 sq. ft., is
12,670 sq. ft. That is 265 sq. ft. in excess of the Town requirements for inclusionary
zoning.
The 265 sq. ft. excess inclusionary and the 5.91 excess employee commercial linkage
shall remain a credit to this property should there be additions or changes to the
building in the future that generate an employee housing requirement.
The Lion
February 9, 2075 8
rowN of Vain"'�
75 South Frontage Road West
Vail, Colorado 81657
vaiigov.com
May 29, 2012
Mr. Wendell Porterfield
Otto, Porterfield & Ayres, LLC
Post Office Box 3149
Vail, Colorado 81658
Dear Mr. Porterfield,
Community Development Department
970.479.2138
970.479.2452 fax
The purpose of my letter is to respond to your letter to the Town of Vail dated May 24,
2012 regarding Lionshead Inn, LLC/Strata Vail, and the required deed restricted
employee housing units.
The Town of Vail has received, and approved, 11,761 square feet of deed restricted
ernployee housing units that are dedicated to the Strata Development Approval
(DEV07-0003 / PRJ11-0701).
Please consider my letter written confirmation of compliance with the Town of Vail's
Inclusionary Zoning Requirements (Title 12, Chapter 24, Inclusionary Zoning, Vail Town
Code) for Strata's approved development plan.
If you have any questions or need additional information, please let me know. You can
reach me via email at gruther a.vailgov.com or by telephone at (970) 376-2675.
Kind Regards,
George Ruther, AICP
Director, Community Development Department
Town of Vail /r
The Lion
February 9, 2015 �%
5. Criteria for Review
The Lionshead Mixed Use -1 Zone District does not supply criteria for review for a
Major Exterior Alteration. However, it does provide for a "compliance burden."
12-71-1-8: COMPLIANCE BURDEN:
It shall be the burden of the applicant to prove by a preponderance of the
evidence before the planning and environmental commission and the design
review board that the proposed exterior alteration or new development is in
compliance with the purposes of the Lionshead mixed use 1 district, that the
proposal is consistent with applicable elements of the Lionshead
redevelopment master plan and that the proposal does not otherwise have a
significant negative effect on the character of the neighborhood, and that the
proposal substantially complies with other applicable elements of the Vail
comprehensive plan.
A. Purpose of the LMU-1 Zone District
The Lionshead Mixed Use 1 zone district was created in 1999, as the implementation
phase of the Lionshead Redevelopment Master Plan. The zone district rezoned all
Lionshead properties from Commercial Core 2 to LMU-1. It intended to create
incentives for properties to redevelop. The purpose of the LMU-1 zone district is as
follows:
The Lionshead mixed use 1 district is intended to provide sites for a mixture of
multiple -family dwellings, lodges, hotels, fractional fee clubs, timeshares, lodge
dwelling units, restaurants, offices, skier services, and commercial establishments in a
clustered, unified development. Lionshead mixed use 1 district, in accordance with the
Lionshead redevelopment master plan, is intended to ensure adequate light, air,
open space and other amenities appropriate to the permitted types of buildings and
uses and to maintain the desirable qualities of the zone district by establishing
appropriate site development standards. This zone district is meant to encourage and
provide incentives for redevelopment in accordance with the Lionshead
redevelopment master plan.
This zone district was specifically developed to provide incentives for properties to
redevelop. The ultimate goal of these incentives is to create an economically vibrant
lodging, housing, and commercial core area. The incentives in this zone district
include increases in allowable gross residential floor area, building height, and
density over the previously established zoning in the Lionshead redevelopment
master plan study area. The primary goal of the incentives is to create economic
conditions favorable to inducing private redevelopment consistent with the Lionshead
redevelopment master plan. Additionally, the incentives are created to help finance
The Lion
February 9, 2015 10
public off site improvements adiacent to redevelopment protects. With any
development/redevelopment proposal taking advantage of the incentives created
herein, the following amenities will be evaluated: streetscape improvements,
pedestrian/bicycle access, public plaza redevelopment, public art, roadway
improvements, and similar improvements.
Our Analysis:
When the Lionshead Master Planning process was undertaken, there was clear
recognition that Lionshead lacked the vitality of Vail Village. The structures were
dated, the pedestrian mall did not function, and older lodging properties were
suffering from low occupancy rates as a result of substandard conditions. As the
purpose statement indicates, the Town recognized these issues and created a zone
district to incentivize the redevelopment of Lionshead. Many properties in Lionshead
have since redeveloped: the Antlers; the Arrabelle; the Marriott; the Ritz-Carlton
Residences; the Landmark - all successful examples of redevelopment as a result of
the Lionshead Master Planning process.
The Lionshead Inn and Lionshead Inn Annex were constructed in the 1970s. At the
time, both hotels were considered luxurious. However, since then, times have
changed dramatically, and the standards that Vail visitors expect their hotels to meet,
have also changed dramatically. The previous facilities were not up to visitor
expectations, which resulted in low returning customer rates. Both facilities suffered
from low occupancy rates.
The Lion
February 9, 2015
The incentives offered by the Lionshead Mixed Use -1 zone district allow the
Lionshead Inn properties the opportunity to redevelop into a project more fitting the
needs of Lionshead and visitors to Vail. The previous buildings on the site have been
demolished, allowing for a completely new structure meeting all aspects of the zoning
regulations. The Lion meets the purposes of the Lionshead Mixed Use -1 zone district
along with all of the development standards prescribed by that zone district.
B. Lionshead Redevelopment Master Plan Compliance
Our Analysis
The Lionshead Redevelopment Master Plan was adopted by the Town of Vail on
December 15, 1998. It is a guide for property owners proposing to undertake
development or redevelopment of their properties and the municipal officials
responsible for planning public improvements. The Lionshead Redevelopment Master
Plan (LRMP) sets out recommendations for the entire Lionshead area, provides
detailed plan recommendations for specific areas, and outlines site design and
architectural design guidelines, and then provides specific development standards that
are implemented through the Lionshead Mixed Use -1 zone district. Below is the
language from the LRMP that is applicable to the vehicular and pedestrian circulation
surrounding the Lionshead Inn properties:
Modifications to West Lionshead Circle and Lionshead Place
West Lionshead Circle and Lionshead Place currently handle the heaviest load of
lodging access and delivery traffic in Lionshead and will likely continue to do so. The
recommended improvements to these roads are both aesthetic and functional,
working to provide for safe and efficient vehicular traffic while also insuring a safe
pedestrian environment visually consistent with the overall goals of the master plan.
East Intersection of W. Lionshead Circle and S. Frontage Road
This intersection will experience the greatest increase in traffic volume due to the
projected increase in lodging units and the proposed north day lot transit center.
Mitigation measures may be required, as outlined in the traffic study.
Intersection of Lionshead Place and West Lionshead Circle
Due to the projected volume of lodging traffic that will be accessing Lionshead
Place (Monteneros, Antlers, Lionsquare Lodge, and the Vail Associates core site),
it is recommended that this intersection be realigned so the primary through -traffic
axis is north -south (see figure 4-10). West Lionshead Circle would form a T -
intersection at the northeast corner of the Marriott. In addition to facilitating
traffic flow, this realignment will create a much safer, logical pedestrian crossing
from West Lionshead Circle into the Lionshead pedestrian core.
Pedestrian Sidewalks and Crossings
The Lion
February 9, 2075 12
A series of primary and secondary
pedestrian walks should be : 1
created connecting the West r
Lionshead area with the Lionshead
core, the frontage road, and the
ski yard. These walks and
crosswalks are identified on Map 1�_
0 and Map T.
Visual Improvements
--
MAP
�y MASTER PLAN FRAMEWORK
PEDESTRIAN WALKS
A_VD PATHS
- . m . PUMUN MrN n1AN WALK
ry rJ~ 4FLCN�ARY RR FRMANWAM
PFDOTMPAN PATH
As the road systems and adjacent
lodging properties in west Lionshead are upgraded it is critical that a consistent
visual character be developed through the design of new pedestrian walkways,
landscaping, retaining walls, lighting, and site furnishings. For further information
on these systems, see chapter six, Site Design Guidelines.
Chapter 5: Detailed Plan Recommendations
Chapter 5 of the LRMP provides detailed plan recommendations for every area of
Lionshead. This section provides the language from the LRMP regarding the detailed
plan recommendation for the Lionshead Inn properties, and includes the July 2006
amendment found in Resolution No. 4, requiring "no net loss of live beds" on the
Lionshead Inn properties.
5.75 Lionshead Inn, Lionshead Annex, Enzian Cluster
Redevelopment and/or enhancement of the buildings in this cluster at West Lionshead
Circle and South Frontage Road (see figure 5-19) is encouraged.
The Lionshead Redevelopment Master Plan clearly encourages the redevelopment of
this site, due to the aging structures and dated hotel rooms.
The Pedestrian Street
The existing structures are recessed from the street, elevated above it, and separated
from it by surface parking lots. To improve the pedestrian character of the
neighborhood, a better relationship with the street is desirable. The principal
objective for redevelopment in this area is to engage the surrounding pedestrian
environment, either by adding building elements toward the street or by lowering the
finish grade at the entries so that they are closer to the level of the street.
The entry has been oriented to minimize vehicular penetration into the more
pedestrianized core, adjacent to the Marriott to enhance the pedestrian experience.
The first floor, along West Lionshead Circle, steps down to a one-story element and
includes commercial uses to improve the pedestrian character of the frontage. The
surface parking lots have been removed (except where required to maintain the
The Lion
February 9, 2015 13
As the road systems and adjacent
lodging properties in west Lionshead are upgraded it is critical that a consistent
visual character be developed through the design of new pedestrian walkways,
landscaping, retaining walls, lighting, and site furnishings. For further information
on these systems, see chapter six, Site Design Guidelines.
Chapter 5: Detailed Plan Recommendations
Chapter 5 of the LRMP provides detailed plan recommendations for every area of
Lionshead. This section provides the language from the LRMP regarding the detailed
plan recommendation for the Lionshead Inn properties, and includes the July 2006
amendment found in Resolution No. 4, requiring "no net loss of live beds" on the
Lionshead Inn properties.
5.75 Lionshead Inn, Lionshead Annex, Enzian Cluster
Redevelopment and/or enhancement of the buildings in this cluster at West Lionshead
Circle and South Frontage Road (see figure 5-19) is encouraged.
The Lionshead Redevelopment Master Plan clearly encourages the redevelopment of
this site, due to the aging structures and dated hotel rooms.
The Pedestrian Street
The existing structures are recessed from the street, elevated above it, and separated
from it by surface parking lots. To improve the pedestrian character of the
neighborhood, a better relationship with the street is desirable. The principal
objective for redevelopment in this area is to engage the surrounding pedestrian
environment, either by adding building elements toward the street or by lowering the
finish grade at the entries so that they are closer to the level of the street.
The entry has been oriented to minimize vehicular penetration into the more
pedestrianized core, adjacent to the Marriott to enhance the pedestrian experience.
The first floor, along West Lionshead Circle, steps down to a one-story element and
includes commercial uses to improve the pedestrian character of the frontage. The
surface parking lots have been removed (except where required to maintain the
The Lion
February 9, 2015 13
access easement for the Enzian) and all parking is located underground. The
commercial uses are at street level, creating a pedestrianized area along West
Lionshead Circle.
Access and Street Frontage
The existing accesses into these properties should be adiusted to align with the
opposing curb cuts on the east side of West Lionshead Circle. The street edge should
be strengthened for pedestrian use with landscaping, enhanced signage, and
retaining walls as described in the site design guidelines, chapter six. The Lionshead
Inn secured a permit in the past which is now expired to add another vehicular access
point from the South Frontage Road, and the property owner is encouraged to
pursue the opportunity to screen the surface parking lot on the north and regrade
the lot to reduce the significant cross -slope.
Parking is located underground and the garage entrance is accessed from the existing
access easement that is being maintained for the Enzian. Load and delivery, along
with Fire Department access and staging will occur off the Frontage Road.
Building Height
Because it sits considerably above the frontage road, the Lionshead Inn is
encouraged to explore a ground level or lower floor infill solution if development
scenarios are pursued. Additional building height, if proposed, must conform to the
design guidelines.
As proposed, the proposal meets the height requirements of 71 ft. average and 82.5
ft. maximum.
Preservation of Existing Live Beds
The Lionshead Inn and Lionshead Annex presently contain 85 accommodation units.
Given the importance and need for live beds to the vitality and success of the
community, any future redevelopment of the sites shall ensure the preservation of
short term accommodation on the site. The preservation of live beds should focus on
maintaining the number of existing live beds and the amount of gross residential
square footage devoted to that use on the site. With this in mind, the quality of the
existing live bed base could be upgraded and the rooms could be reconfigured to
create increased lodging opportunities. In no instance, however, shall the amount of
gross residential floor area devoted to live beds be reduced. The construction of
"attached accommodation units", "lodge dwelling units", "timeshare units",
"fractional fee club units", and dwelling units in a voluntary rental program, as
defined in the Zoning Regulations, could significantly increase the availability of short
term rental opportunities within the building.
As proposed, The Lion includes 85 live beds consistent with this Master Plan policy.
The Lion
February 9, 2015 14
C. Character of the Neighborhood
Our Analysis:
The neighborhood of the Lionshead Inn properties is architecturally and aesthetically
diverse. The property most adjacent to the Lionshead Inn is the Enzian
Condominiums, which will be most impacted by the redevelopment proposal. As a
result, the design team made every effort to minimize impacts to the Enzian
Condominiums, including respecting the existing access easement. No development is
proposed adjacent to the Enzian, on the Lionshead Inn property to the south. The
Enzian Condominiums have not been redeveloped at this point in time and therefore
the architecture and character of the Enzian Condominiums is more of the old
Lionshead aesthetic, and while the design of The Lion respects the existing structure, it
isdesigned based on the
Design Guidelines of the
Lionshead Redevelopment
Master Plan. It is assumed,
like most properties in
Lionshead that have not yet
been redeveloped, that at
some point in the future,
redevelopment will occur.
Adjacent to the Lionshead
Inn to the west is the Vail
Spa. Unlike the Enzian
Condominiums, the Vail
Spa's architectural
character is more modern,
with a flat roof, interesting angles, and large panes of glass. Built in 1980, this site
also has development potential based on the Lionshead Mixed Use - 1 zone district.
However, without knowing the future plans for this building, the design of The Lion
includes some more modern elements to allow for some consistency of character in
the neighborhood.
The Marriott, to the south of the Lionshead Inn properties, went through a major
redevelopment in the late 1990s. In this case, the existing structure was maintained,
but the building was renovated to be more in compliance with the Design Guidelines
of the Lionshead Redevelopment Master Plan. Many of the old forms remained, but
the materials and colors were updated and upgraded. The Lion is proposed with
similar materials and will be of a character that compliments the Marriott.
The Lion
February 9, 2075 15
Other properties in the vicinity include the North Day Lot, Concert Hall Plaza, and
Montaneros. The design of The Lion will be complimentary to these properties,
maintaining the character of Lionshead, while creating a project that is remarkable on
its own.
D. Other Applicable Elements of the Vail Comprehensive Plan
Our Analysis:
The Lionshead Redevelopment Master Plan has been covered in depth in previous
sections of this submittal and is incorporated here by reference. The Vail Land Use
Plan, which was originally adopted in 1986, also includes goals that are applicable
to this project.
7.3 The quality of development should be maintained and upgraded
whenever possible.
7.72 Vail should accommodate most of the additional growth in
existing developed areas (infill areas).
3.7 The hotel bed base should be preserved and used more
efficiently.
4.2 Increased density in the Core areas is acceptable so long as the
existing character of each area is preserved through
implementation of the Urban Design Guide Plan and the Vail
Village Master Plan.
Now over 30 years old, the Town of Vail Land Use Plan is outdated in general, but
many of the concepts of the plan are applicable to development today. The Lion
helps to further these goals as outlined in the Vail Land Use Plan.
The Lion
February 9, 2075 16
6. Conditional Use Permit Criteria for Review
The proposed reduction in the number of timeshare units necessitates the need for a
Conditional Use Permit. The dwellings, lodge dwelling units, employee housing unit, and the
attached accommodation units (lock -offs) are all uses allowed by right which do not require a
special approval from the PEC. The change from 12 timeshare units to 9 timeshare units
requires an amendment to the Conditional Use Permit.
A. Relationship and impact of the use on development objectives of the town.
Our Analysis: The development objectives for this property are summarized in the
Lionshead Redevelopment Master Plan. The Master Plan clearly states that the
objective for this property is to have 85 "live beds" available on the property. This
application, as did the previous applications and approvals, demonstrates compliance
with the development objectives of the Town and the specific policy of maintaining 85
live beds on the property.
B. The effect of the use on light and air, distribution of population, transportation
facilities, utilities, schools, parks and recreation facilities, and other public facilities
neecls.
Our Analysis: The proposal to reduce the number of timeshare units does not change
the building and development site in any way. It does reduce the parking requirement
slightly which suggests a minor reduction in need for public facilities. The proposed
change will have only positive effects on this criterion.
C. Effect upon traffic with particular reference to congestion, automotive and pedestrian
safety and convenience, traffic flow and control, access, maneuverability, and
removal of snow from the street and parking areas.
Our Analysis: The minor reduction in the number of time share units has a reduced
parking impact to the project which suggests a general reduction in traffic to the site.
The proposed change will have only positive effects on this criterion.
D. Effect upon the character of the area in which the proposed use is to be located,
including the scale and bulk of the proposed use in relation to surrounding uses.
Our Analysis: This minor change in programming does not result in any outward
change to the building whatsoever. Therefore the proposed amendment does not
have a negative impact on the character of the area or bulk and mass of the building.
The proposed change will have no effects on this criterion.
The Lion
February 9, 2075 17
7. Adjacents
TOWN OF VAIL
C/O FINANCE DEPT
75 S FRONTAGE RD
VAIL, CO 81657
VAIL CORP
THE FIXED ASSETS DEPARTMENT
390 INTERLOCKEN CRES STE 1000
BROOMFIELD, CO 80021-8056
LANDMARK CONDO ASSOCIATION
DESTINATION RESORT MANAGEMENT INC
610 W LIONSHEAD CR
VAIL, CO 81657
MONTANEROS CONDOMINIUM ASSOCIATION,
INC.
LAURIE JEAN ES
641 W LIONSHEAD CIR,
VAIL, CO 81657
DIAMONDROCK VAIL OWNER LLC
DIAMONDROCK HOSPITALITY CO
3 BETHESDA METRO CTR STE 1500
BETHESDA, MD 20814-635
VAIL SPA CONDOMINIUM ASSOC
710 W LIONSHEAD CIR
VAIL, CO 81657
VAIL SPA CONDOMINIUM ASSOCIATION
EAST WEST RESORTS
PO BOX 5480,
AVON, CO 81620
ENZIAN AT VAIL CONDOMINIUM ASSOCIATION
GEOFFREY WRIGHT
610 W LIONSHEAD CIR,
VAIL, CO 81657
SUN VAIL CONDO ASSOCIATION
635 N FRONTAGE ROAD #3
VAIL, CO 81657
CDOT
4201 E. ARKANSAS AVENUE
DENVER, CO 80222
LION SQUARE NORTH CONDOMINIUM
ASSOCIATION, INC.
BILL ANDERSON
660 WEST LIONSHEAD PLACE
The Lion
VAIL, CO 81657
CONCERT HALL PLAZA
ASSOCIATION
LES ROOS
500 GOLDEN EAGLE DRIVE
BROOMFIELD, CO 80020
CONDOMINIUM
THE MARK -LODGE CONDOMINIUM
ASSOCIATION, INC.
KELLIE NEWMAN
715 WEST LIONSHEAD CIRCLE
VAIL, CO 81657
VAIL MARRIOTT MOUNTAIN RESORT
715 WEST LIONSHEAD CIRCLE
VAIL, CO 81657
MAURIELLO PLANNING GROUP
PO BOX 4777
EAGLE, CO 81631
HUGHES LAND HOLDING TRUST
28 ANACAPA ST STE D
SANTA BARBARA, CA 93101-1881
CHARLES H. STONE FAMILY LP
OWNER ADDRESS 641 LIONSHEAD PL
VAIL, CO 81657-5214
VAIL GEAR CORP
BOB WALSH
OWNER ADDRESS 641 W LIONSHEAD CIR
VAIL, CO 81657-5227
February 9, 2015 18
50VAN FloN1 PGS �,o PO
14�
nmin®n®in®n®i
p nm®nn
. ®m®®=®m®nil n n
U
w
K
u
H
m'
m
ENTRY
„ � O
J
O_
BUSINESS
_
CENTER
II
III III
_ I,
2
O
r
KIN K ®
„,
w 1
IIS a�
N
r
J
I PARKING
QLU
�
w 0®
L
Y F
K 2
Q w
6
H
O_
QLU
�
W
W
W
O
J O
Z
0
O
Q
W
H
LU
<1J
Y
w
F
U
U
■
J
w
o
o
p
0
z
14�
w
LU
' z O a y
LU F °
o x w -- w 9 c
O O / J O x
J H J H w w U w 0 U
O F O
J
14�
W
J
LU
J
T
14�
LU u LL a> m
J O y L
o o i / J O = G
J H J H w W U W 0 U
0 J o
TOWN OFVAIL'
Memorandum
TO: Planning and Environmental Commission
FROM: Community Development Department
DATE: March 9, 2015
SUBJECT: A request for final review of an amendment to a conditional use permit, pursuant
to Section 12-9C-3, Conditional Uses, Vail Town Code, for an existing healthcare
facility, amending the development plan to allow for an additional floor plate on
the west wing, located at 181 West Meadow Drive and 108 South Frontage Road
West (Vail Valley Medical Center)/Lots E, F, and 10 Vail Village Filing 2, Lot 2E,
Block 1, Vail Lionshead Filing 1 and Lot D-2, A Resubdivision of Lot D, Vail
Village Filing 2 (PEC150002, PEC150003)
Applicant: Vail Valley Medical Center, represented by Braun and Associates
Planner: Warren Campbell
I. SUMMARY
The applicant, Vail Valley Medical Center (VVMC), represented by Braun and
Associates, is requesting a work session with the Planning and Environmental
Commission to review an amendment to a conditional use permit, pursuant to Section
12-9C-3, Conditional Uses, Vail Town Code, for an existing healthcare facility,
amending the development plan to allow for an additional floor plate on the west wing,
located at 181 West Meadow Drive and 108 South Frontage Road. The applicant is
requesting a public hearing with the Planning & Environmental Commission (PEC) to
discuss the following:
Massing/Architecture/West Meadow Drive
o Response to Commission comments from previous hearing
■ Changes to architectural design
■ Changes to streetscape and landscaping
ADA ramp heating
Employee Generation Mitigation
o Introduction to the VVMC West Wing Employee Housing Plan
o Proposed mitigation method
o Discussion of findings to permit off-site mitigation
• Parking
o Parking need created by the West Wing redevelopment
o Overview of parking lot design
o Overview of interim parking plan
o Impacts of West Wing redevelopment on West Meadow Drive traffic
As this public hearing will limit the scope of discussing the topics listed above, which are
elements of the proposed VVMC West Wing CUP, staff has not prepared a
recommendation for any action by the Planning and Environmental Commission.
Town staff will provide a recommendation to the PEC on the proposed VVMC CUP at
the March 23, 2015 public hearing.
II. DESCRIPTION OF REQUEST
As was discussed during the VVMC MP review the hospital needs to remain operational
during all sequences of the hospital redevelopment. The proposed West Wing
expansion will allow for uses to begin to reconfigure, expand, consolidate, and relocate
in anticipation of the East Wing redevelopment.
The West Wing is the first in a sequence of improvements that will be proposed and
constructed in order to implement the recommendations of the Vail Valley Medical
Center Site Specific Redevelopment Master Plan (VVMC MP). As proposed the West
Wing redevelopment will comprise approximately 45,000 sf feet of floor area. Over 50%
of the proposed new floor area is located within a new fourth floor atop the existing
structure. The expansion will include a new ground level entry to the structure on the
northwest corner and expansions to the south side of the building from the basement
level up to the new fourth floor.
The applicant has provided a written narrative discussing the topics to be covered at the
public hearing. This narrative includes images to help in understanding the
modification being made to the south expansion to address the comments heard at the
previous hearing. The applicant will present additional imagery at the public hearing.
This document has been attached for reference (Attachment A). Additionally, the
applicant has provided a document entitled VVMC West Wing: Employee Housing Plan
dated March 2, 2015 (Attachment B) and a parking lot design (Attachment C).
III. CRITERIA
Before acting on an amendment to conditional use permit application, the PEC shall
consider the following factors with respect to the proposed use:
1. Relationship and impact of the use on the development objectives of the
Town.
Town of Vail Page 2
2. The effect of the use on light and air, distribution of population,
transportation facilities, utilities, schools, parks and recreation facilities, and
other public facilities needs.
3. Effect upon traffic with particular reference to congestion, automotive and
pedestrian safety and convenience, traffic flow and control, access,
maneuverability, and removal of snow from the street and parking areas.
4. Effect upon the character of the area in which the proposed use is to be
located, including the scale and bulk of the proposed use in relation to
surrounding uses.
5. Such other factors and criteria as the commission deems applicable to the
proposed use.
6. The environmental impact report concerning the proposed use, if an
environmental impact report is required by chapter 12 of this title.
IV. DISCUSSION ITEMS
The West Wing of the VVMC is located upon a parcel zoned General Use (GU) District.
Within the GU District the PEC, in conjunction with the review of the CUP, shall
prescribe the following development categories.
1. Lot area and site dimensions.
2. Setbacks.
3. Building height.
4. Density control.
5. Site coverage.
6. Landscaping and site development.
7. Parking and loading.
Massing/Architecture/West Meadow Drive
The applicant is proposing to respond to comments heard at the February 23rd public
hearing. The PEC expressed the following at the February 23rd hearing:
Concern with the minimum setback proposed along the south expansion and its
negative impact upon West Meadow Drive and the character of the
neighborhood.
o Discussed the proposed minimum setback and its negative impact on the
ability to incorporate landscaping to adequately buffer the proposed bulk
and mass.
o Discussed the negative impact upon the sidewalk that is created by five (5)
stories three (3) to (8) feet off the property line.
Town of Vail Page 3
o Discussed the ability of the proposal to expand to the north verses the
south.
o Discussed a possible solution may be to pull the basement and first floors
back to address the impacts of the proposed structure upon the sidewalk.
o Discussed that the setbacks should have a relationship to the height of the
structure and that the proposed setbacks were not appropriate.
o Discussed the need to articulate the south expansion and include
landscaping to address negative impacts.
o Discussed the possibility of heating the pedestrian sidewalk along the
VVMC frontage.
o Discussed the Lionshead Redevelopment Master Plan and how it
addressed larger structures in terms of fagade articulation which may be
applicable to this application.
Concern with the proposed mansard roof form and its impact on the overall
architectural appearance.
o Discussed the additional eight (8) feet in height created by the roof form.
o Discussed the dormers included in the roof form anticipated for the East
Wing and how that design might be more architecturally compatible.
o Discussed that the proposed roof lacked visual interest.
• Concern with the accessible ramp at the southwest corner.
o Discussed the potential to heat the walkway.
o Discussed the need to create larger landscaping beds so that trees could
be incorporated in the design of the area.
Concern with quantity of glazing proposed on the south expansion.
o Discussed that the proposed glazing did not have the effect of making the
new fourth floor appear "lighter".
o Discussed the negative impact that sunlight reflectance might have on
neighboring properties as a result of the glazing.
Chapter 4 of the VVMC MP speaks to the Architecture, Building Massing, and Building
relationship to West Meadow Drive. Chapter 4 has been included within Attachment D.
The following goals included within the VVMC MP addressing these areas are as
follows..
Goal for Building Massing — The massing (and scale) of hospital
expansions to be responsive and sensitive to the surrounding
neighborhood.
Goal for Building Relationship to West Meadow Drive — To establish
an appropriate physical and visual relationship between the hospital and
the pedestrian corridor along West Meadow Drive by use of effective
building design, architecture and landscape improvements.
Town of Vail Page 4
Goal for Architecture — To integrate the design of new buildings and
expansion areas with existing portions of the hospital so as to create a
varied but unified architectural expression.
The VVMC MP speaks to each of these goal statements on pages 12 through 17 of
Chapter 4.
Setbacks
Properties surrounding the VVMC Campus are zoned Two Family District, Lionshead
Mixed Use 1 District, General Use District and High Density Multiple Family District.
Setbacks within these zone districts are as follows:
District
Front Rear Sides Location
Two -Family 20 feet
High Density Multiple Family 20 feet
Lionshead Mixed Use 1 10 feet
General Use
15 feet
20 feet
10 feet
Determined by PEC
15 feet South
20 feet East
10 feet North
West
Staff is previously stated concern that a setback of 3 to 8 feet along the southerly
addition would not adequately provide for a landscaped area to buffer the proposed
south expansion. Staff believes a setback with adequate area to allow for the
maturation of trees is necessary to address the proposed scale and bulk relationship to
surrounding uses. Within the GU district the required setbacks will be determined in
conjunction with the review of the CUP criteria which include compliance with the
adopted VVMC MP goals and text.
The applicant is developing images to depict how the south expansion can be modified
to address the concerns expressed by the PEC. This imagery will be presented at the
public hearing on the 9t". Staff is unable to provide its comments and feedback on the
modifications at this point as materials were not available prior to the completion of the
memorandum.
The proposed modifications need to be evaluated against the CUP criteria and the
VVMC MP goal statements. Without prior time to review the proposed modifications
any feedback will be limited in terms of determining compliance with the regulatory
requirements.
Relationship to West Meadow Drive
There is a pedestrian walkway measuring between 12 and 15 feet in width located
between the VVMC Campus property line and West Meadow Drive. The unheated
walkway has been installed pursuant to the Streetscape Master Plan Addendum (SMP)
having a serpentine alignment. The SMP identified an opportunity for public art along
the walkway and in particular an art wall in the area where the southerly expansion is
proposed. The SMP anticipated a future public portal to the VMMC in this location
(Figures 7 and 8 of Attachment D).
Town of Vail Page 5
Architecture
The proposed southerly expansions and new fourth floor utilize several architectural
elements to address the bulk, mass, and height of the redevelopment. These include a
mansard parapet roof form, extensive glazing, and application of materials. The
proposed material palette can be found in the existing materials upon the structure.
Those include red brick, stone, metal panels, concrete banding, and standing seam roof
material.
While the review and approval of the application of materials is generally a function of
the Design Review Board, there are elements of the discussion that fall within the
criteria the PEC will utilize in reviewing the CUP. The selection and application of
architectural fagade materials can have an effect on the perceived bulk, mass, height,
and setback of a structure. Additionally, the incorporation of certain building elements,
such as lower roof forms can have a positive effect on the perceived bulk, mass, height,
and setback of a structure.
Staff anticipates that at the public hearing the applicant will address modifications to the
proposed south expansion architecture to address the roof form and glazing concerns.
Discussion was focused on the south expansion of the proposed West Wing application
at the previous hearing. Staff wants to ensure there isn't any feedback to be provided
on the northwest corner expansions.
Does the Commission have any comment on the expansions proposed for
the northwest corner of the building which includes a new entry and cover,
and upper floor expansions?
Employee Generation Mitigation
Chapter 12-23, Commercial Linkage, Vail Town Code, establishes the methodology for
determining the generation of employees and requirements for mitigation for
commercial land uses. When a type of commercial use is not listed within Table 23-1,
Employee Generation Rates By Type of Commercial Use, Vail Town Code, a process is
established for the determination of an applicable generation rate. Table 23-1 does not
identify an employee generation for a healthcare facility. Pursuant to Chapter 12-23 the
following would apply.
12-23-2: Employee Generation and Mitigation Rates:
A. The employee generation rates found in table 23-1, "Employee Generation
Rates By Type Of Commercial Use'; of this section, shall be applied to each type
of use in a commercial development. For any use not listed, the administrator
shall determine the applicable employee generation rate by consulting the town's
current nexus study.
Section 12-23-6, Methods of Mitigation, Vail Town Code, includes a regulation requiring
50% of the required employee generation mitigation to occur on site. An exception to
this requirement can be granted by the PEC if one of four findings can be made. The
Town of Vail Page 6
applicant has included in there written analysis, a response to the findings that must be
made to grant an exemption to this requirement.
12-23-6: Methods of Mitigation:
A. For all new construction (i.e., development that does not affect any existing
buildings or structures) and demo/rebuild projects that result in a mitigation
requirement of 1.25 employees or greater, no less than one-half (1/2) the
mitigation of employee housing required by this chapter shall be accomplished
with on site units.
1. Exceptions. At the sole discretion of the applicable governing body, ar
exception may be granted from this subsection based upon one of the
following findings.-
a.
indings.
a. Implementation of the on site unit mitigation method would be contrary to
the intent and purpose of the applicable zone district.
b. Implementation of the on site unit mitigation method would be contrary to
the goals of the applicable elements of the Vail comprehensive plan and
the town's development objectives.
c. Exceptional or extraordinary circumstances or conditions apply to the site
that prevents the implementation of the on site unit mitigation method.
d. The method of mitigation proposed better achieves the intent and purpose
of this chapter and general and specific purposes of this title than the on
site mitigation unit method.
The VVMC MP speaks to the employee mitigation requirement in Chapter 9, specifically
page 32. The Master Plan establishes the following goal with regard to employee
housing.
Goal for Employee Housing — To provide employee housing consistent
with the provisions of Chapter 23 of the Vail Town Code.
The VVMC MP addresses the requirement to provide 50% of the required employee
housing mitigation on site. It discusses two primary reasons to be considered in making
a finding to exempt this redevelopment from this requirement.
o Incompatibility of residential uses and the institutional healthcare facility.
o Limited land area resource which should be utilized for current and future
healthcare facility needs.
The applicant has submitted a document entitled VVMC West Wing Expansion:
Employee Housing Plan dated March 2, 2015 (Attachment B). The applicant will
provide an introduction to the analysis which has been performed in order to ascertain
Town of Vail Page 7
employee generation anticipated by the redevelopment of the West Wing. This
document is to serve as competent evidence to be reviewed by the Town's Housing
Coordinator in determination the applicable employee generation rate for a healthcare
facility. Staff is in the process of performing this review and will be prepared to respond
the report on March 23rd
Parking
Chapter 7 of the VVMC MP is devoted to the topic of parking. The VVMC has been
deficient with regard to parking since the redevelopment of the Central Wing. The
provision of adequate parking was identified as a fundamental goal at the start of the
VVMC master planning process. The VVMC MP establishes the following goal with
regard to parking.
Goal for Parking — To increase the supply of on-site parking to an
amount that when coupled with managed parking solutions meets the
needs of patients, visitors, and employees of VVMC.
The Master Plan acknowledges that at the completion of the redevelopment
anticipated that all required parking will be located upon the VVMC site. The
plan contemplates that some portion of the required parking will be addressed
through managed solutions such as the provision of shuttles and bus passes for
employees.
The applicant has submitted a proposed site plan for the west parking lot (Attachment
C). Staff has provided comment on the proposed design. Those comments included
the following:
• A concern about the circulation pattern and possible confusion by user groups
attempting to navigate the lot.
o Suggested possibility of the introduction of some one-way travel aisles
which might result in potentially more parking or the ability to include
greater landscaping area as a buffer or internally.
• A concern about the proximity of the parking lot pavement to the Middle Creek
riparian area.
o Plans includes curb, gutter, and sand and oil filtration, however, the
VVMC MP depicts a landscaping buffer on the west end of the parking lot
adjacent to Middle Creek.
• A concern with regard to not meeting the standards for snow storage, parking lot
perimeter screening and parking lot interior landscaping as contained within
Section 14-5-2, Other Requirements, Vail Town Code. These regulations
included in the applicable documents section of this memorandum.
• A concern regarding pedestrian access from the parking lot to the new porte
cochere entry.
o As proposed a pedestrian parking in the southern portion of the lot would
need to walk north around the landscape island being used to catch
grade.
Town of Vail Page 8
• A need to determine the future of Lot 10 and its use for VVMC parking solely,
shared parking for VVMC and town, or town parking solely.
o A need for vehicular easements for access to Lot 10 parking for town
purposes if a shared facility.
• A need to address several engineering design specifics such as turning
movements, storm sewer alignment, vault location, etc.
Staff and the applicant have been discussing the parking and traffic generation
anticipated by the changes included within the West Wing redevelopment. Specific
plans for addressing the generation of parking and traffic were not submitted prior to the
completion of this memorandum. Staff anticipates the applicant will be addressing
parking demand, interim parking solutions during construction and traffic impacts to
West Meadow Drive at the public hearing.
V. BACKGROUND
On January 26, 2015, the PEC, by a unanimous vote of 5-0-1 (Cleveland recused,
Cartin absent):
Forwarded a recommendation of approval, with modifications, with regard to the
adoption of Resolution No. 3, Series of 2015, making the VVMC MP an element
of the Vail Land Use Plan; and
Forwarded a recommendation of approval, with regard to the adoption of
Resolution No. 4, Series of 2015, amending the Vail Land Use Plan to establish
the VVMC MP land use category and designate it on the Plan Map.
On February 23, 2015, the PEC held a work session on the West Wing CUP to discuss
the bulk, mass, setbacks, and architecture being proposed. The PEC provided
feedback on the several concerns with regard to the proposed setbacks, impacts to
West Meadow Drive, landscaping, and architecture.
VI. APPLICABLE PLANNING DOCUMENTS
Town of Vail Zoning Code
General Use District (in part)
12-9C-1: Purpose:
The general use district is intended to provide sites for public and quasi -public uses
which, because of their special characteristics, cannot be appropriately regulated by the
development standards prescribed for other zoning districts, and for which development
standards especially prescribed for each particular development proposal or project are
necessary to achieve the purposes prescribed in section 12-1-2 of this title and to
Town of Vail Page 9
provide for the public welfare. The general use district is intended to ensure that public
buildings and grounds and certain types of quasi -public uses permitted in the district are
appropriately located and designed to meet the needs of residents and visitors to Vail,
to harmonize with surrounding uses, and, in the case of buildings and other structures,
to ensure adequate light, air, open spaces, and other amenities appropriate to the
permitted types of uses.
12-9C-3: Conditional Uses:
A. Generally: The following conditional uses shall be permitted in the GU district, subject
to issuance of a conditional use permit in accordance with the provisions of chapter 16
of this title.-
Child
itle.
Child daycare centers.
Equestrian trails.
Golf courses.
Healthcare facilities.
Helipad for emergency and/or community use.
Major arcades.
Plant and tree nurseries, and associated structures, excluding the sale of trees or other
nursery products, grown, produced or made on the premises.
Public and private parks and active outdoor recreation areas, facilities and uses.
Public and private schools.
Public and quasi -public indoor community facilities.
Public buildings and grounds.
Public parking structure.
Public theaters, meeting rooms and convention facilities.
Public tourist/guest service related facilities.
Public transportation terminals.
Public unstructured parking.
Public utility and public service uses.
Religious institutions.
Seasonal structures or uses to accommodate educational, recreational or cultural
activities.
Ski lifts, tows and runs.
Water and sewage treatment plants.
12-9C-5: Development Standards:
A. Prescribed By Planning And Environmental Commission. In the general use district,
development standards in each of the following categories shall be as prescribed by
the planning and environmental commission.-
1.
ommission.
1. Lot area and site dimensions.
2. Setbacks.
3. Building height.
4. Density control.
Town of Vail Page 10
5. Site coverage.
6. Landscaping and site development.
7. Parking and loading.
B. Reviewed By Planning And Environmental Commission. Development standards
shall be proposed by the applicant as a part of a conditional use permit application.
Site specific development standards shall then be determined by the planning and
environmental commission during the review of the conditional use request in
accordance with the provisions of chapter 16 of this title.
Commercial Linkage (in part)
12-23-1: Purpose and Applicability:
A. The purpose of this chapter is to ensure that new commercial development and
redevelopment in the town provide for a reasonable amount of employee housing to
mitigate the impact on employee housing caused by such commercial development
and redevelopment.
12-23-2: Employee Generation and Mitigation Rates:
A. The employee generation rates found in table 23-1, "Employee Generation Rates By
Type Of Commercial Use'; of this section, shall be applied to each type of use in a
commercial development. For any use not listed, the administrator shall determine
the applicable employee generation rate by consulting the town's current nexus
study.
TABLE 23-1
EMPLOYEE GENERATION RATES
BY TYPE OF COMMERCIAL USE
Type Of Use F1 Employee Generation Rate
Accommodation unit/ limited service lodger 0 7 employee per net new units
unit 1 1
Business office and professional office new
employees per 1 000 feet of
(excluding real estate office) I new net floor area
Conference facility
Eating and drinking establishment
Health club
Real estate office
rr 0.8 employee per 1,000 feet of
new net floor area
f 6.75 employees per 1,000 feet of
new net floor area
0.96 employee per 1, 000 feet of�
knew net floor area
[rF5_ i employees per 1,000 feet of
new net floor area
Town of Vail Page 11
Retail store/personal service/repair shop 2.4 employees per 1,000 feet of
new net floor area
Spa 2.1 employees per 1,000 feet of
new net floor area
B. If an applicant submits competent evidence that the employee generation rates
contained in table 23-1 of this section or the nexus study do not accurately reflect
the number of employees generated by the proposed commercial development or
redevelopment and the administrator finds that such evidence warrants a deviation
from those employee generation rates, the administrator shall allow for such a
deviation as the administrator deems appropriate.
C. Each commercial development or redevelopment shall mitigate its impact on
employee housing by providing EHUs for twenty percent (20%) of the employees
generated, pursuant to table 23-1 of this section, or the nexus study, in accordance
with the requirements of this chapter.
12-23-8. Administration.-
A.
dministration.
A. Employee Housing Plan. Each application for development review, except those
exempt pursuant to section 12-23-5 of this chapter, shall include an employee
housing plan which includes the following.-
Calculation
ollowing.
Calculation Method. The calculation of employee generation, including credits if
applicable, and the mitigation method by which the applicant proposes to meet the
requirements of this chapter;
2. Plans. A dimensioned site plan and architectural floor plan that demonstrates
compliance with section 12-23-3, "Size And Building Requirements", of this
chapter;
3. Lot Size. The average lot size of the proposed EHUs and the average lot size of
other dwelling units in the commercial development or redevelopment, if any;
4. Schedules. A time line for the provision of any off site EHUs,-
5.
HUs,
5. Off Site Units. A proposal for the provision of any off site EHUs shall include a
brief statement explaining the basis of the proposal;
6. Off Site Conveyance Request. A request for an off site conveyance shall include a
brief statement explaining the basis for the request;
7. Fees In Lieu. A proposal to pay fees in lieu shall include a brief statement
explaining the basis of the proposal; and
Town of Vail Page 12
8. Written Narrative. A written narrative explaining how the employee housing plan
meets the purposes of this chapter and complies with the town's comprehensive
plan.
B. Review.-
1.
eview.
1. The administrator shall approve, approve with modifications or deny an employee
housing plan involving a total mitigation requirement of less than 1.25 employees.
2. The planning and environmental commission shall approve, approve with
modifications or deny an employee housing plan unless the plan involves a total
mitigation requirement of less than 1.25 employees, the development is located
within a special development district; or the plan includes a request to convey
property.
3. The town council shall approve, approve with modifications or deny an employee
housing plan for a development located within a special development district or a
plan requesting to convey property.
4. Before granting approval of an employee housing plan, the applicable governing
body shall make findings that the employee housing plan conforms to the general
and specific purposes of this title, and that the plan is compatible with the
applicable elements of the Vail comprehensive plan and the development
objectives of the town.
Title 14 - Development Standards
14-5-2: Other Requirements:
G. Snow Storage. All required parking and access areas shall be designed to
accommodate on site snow storage (i.e., within boundaries of lot and not within the
right of way). A minimum functional area equaling thirty percent (30%) of the paved
area shall be provided contiguous to the paved area and designed to accommodate
snow storage. Turf areas and other areas without trees may be utilized for this
purpose. If driveways are heated, then the minimum snow storage area may be
reduced to ten percent (10%) of the required parking and access areas.
H. Landscaping. Not less than ten percent (10%) of the interior surface area of
unenclosed off street parking areas containing fifteen (15) or more parking spaces
shall be devoted to landscaping. In addition, landscape borders not less than ten
feet (10) in depth shall be provided at all edges of parking lots containing thirty (30)
or more parking spaces. A landscape berm, wall, or fence of not less than four feet
(4) in height, of the same architectural style as the building, in combination with
landscaping may be substituted for the landscape border. In developments with
cross access or shared parking facilities, the landscape border between the
developments shall not be required.
Town of Vail Page 13
VII. NEXT STEPS
March 23, 2015 — Request Final Action on CUP
• Follow-up from march 9t" public hearing
• Final deliberation and action
VIII. STAFF RECOMMENDATION
The Planning and Environmental Commission is asked to table this public hearing to
March 23, 2015. Are there any additional materials the Commission anticipates
needing at this time in order evaluate the conditional use permit on March 23ra.
IX. ATTACHMENTS
A. Applicant's written narrative dated February 23, 2015
B. VVMC West Wing Expansion: Employee Housing Plan dated March 2, 2015
C. Plan for West Parking Lot dated February 9, 2015
D. Town of Vail Streetscape Master Plan Addendum for West Meadow Drive
E. VVMC MP currently under review by the Town Council for adoption
F. Public comment
Town of Vail Page 14
VVMC West Wing CUP
3/3/15 PEC Hearing
The purpose of this narrative is to provide information in order to facilitate the PEC's review of
the West Wing CUP application at their hearing on March 9t". As presented at the last meeting,
below is the anticipated PEC review schedule for this application:
2/23/2015
Introduction/Overview of the West Wing Expansion
Criteria to be used in evaluation of the CUP
Overview of major elements of PEC review
Presentation of building design (architecture, height/massing, relationship to Meadow Drive)
3/9/2015
Follow-up from last meeting
West Wing Traffic Impact Analysis
Presentation of Parking demand, interim parking plan
Presentation of Parking Lot design
Presentation of Employee Housing Plan
3/23/2015
Follow-up from last meeting
Final deliberation
The balance of this report provides an overview level summary of the topics below. Additional
information on these topics will be presented at the PEC hearing on 3/9/2015:
Massing/Architecture/West Meadow Drive
• Response to PEC comments from 2/23 meeting
• Refinements to building design
• Refinements to streetscape/landscape
• Sidewalk and ramp/heating
Employee Mitigation
• Employee generation from West Wing
• Proposed mitigation
• Discussion of "findings", re: exception to 50% on-site requirement
Parking and Traffic
• Parking demand from West Wing
VVMC West Wing Expansion
CUP Review/PEC Hearing #2 Page 1
• Overview of parking lot design
• Overview of interim parking plan
• West Wing/Implications on West Meadow Drive Traffic
Massing/Architecture/West Meadow Drive
A variety of refinements to the design of the West Wing, specifically the southern expansion
along Meadow Drive have been initiated in response to PEC comments. These changes include:
1. Elimination of the mansard roof
2. Reduction in glazing on the fourth floor
3. Reduction in the building expansion at the basement (partial) and first level
4. Introduction of "notches" at the east and west corners of the southern expansion
5. Introduction of columns and other features to provide relief and interest to the
southern expansion
As depicted by the drawings below, the elimination of the mansard roof provides a substantial
reduction in the mass of the West Wing.
RM
oall
i
SOUTH ELEVATION AT NEST MEADO�N DRIVE
Conceptual sketch of south elevation at West Meadow Drive — original, with mansard roof at West Wing.
9
e
mu.vWL
9r
-Fecn� �£rS{�sawc-�
Conceptual sketch of south elevation at West Meadow Drive — proposed, with elimination of mansard roof at West
Wing.
VVMC West Wing Expansion
CUP Review/PEC Hearing #2 Page 2
A number of changes have been made to the southern expansion along West Meadow Drive.
While not fully evident in the elevation below, the basement and first level are recessed and
notches at the east and west corner of the southern expansion have been added. The notches
reduce the mass of the building, provide depth, shadow patterns and interest to the elevation.
fze4-
Conceptual sketch of revisions to the West Wing and southern expansion.
Refinements to site and landscape improvements have also been made. Changes to the
southern expansion will afford additional planting area for landscape material to soften the
appearance of the building. In addition, the sidewalk/ramp that connects the West Wing entry
with the Town's sidewalk has been redesigned. This change will provide a more gracious entry
to VVMC and also allow additional room for landscaping. The sketch on the following page
provides a general indication of how the ramp design has changed. An updated illustrative
site/landscape plan will be presented at Monday's meeting.
VVMC will also provide feedback on the PEC's comments regarding heating of the Town's
sidewalk and ramp to the West Wing entry.
VVMC West Wing Expansion
CUP Review/PEC Hearing #2 Page 3
t, Wmc, 5f tet c id —�
Employee Housing
A draft Employee Housing Plan has been prepared and submitted to staff for their review. The
Plan addresses:
• Two underlying factors relative to the expansion of VVMC that will influence employee
generation,
• Baseline inventory of existing uses and employees for all VVMC departments and all
other organizations that operate at the campus,
• Evaluation of specific expansion (and/or contraction or relocation) plans for each
department and organization within the West Wing and how these plans impact
employee generation, and
• Summary of required employee mitigation and how mitigation will be provided for the
West Wing expansion.
This Plan has been provided in the PEC packet. An overview of this report will be provided at
Monday's PEC hearing.
Parking and Traffic
Four distinct, yet related topics will be presented to the PEC on Monday. These include:
Parking demand from West Wing
The parking demand from the redevelopment of the West Wing has been calculated. The
demand reflects the net increase in parking based on proposed expansions, increases in
VVMC West Wing Expansion
CUP Review/PEC Hearing #2 Page 4
intensity of use and in some cases the relocation of existing West Wing uses. Demand was
calculated based on the "employee based" formula outlined in the VVMC Site Specific
Redevelopment Master Plan.
The parking demand from the West Wing will be presented at Monday's PEC hearing.
Parking lot design
A revised parking lot design has been completed. The primary assumptions, or parameters
used in this re -design included the following:
• Maintain the Town's use of 16 spaces within Lot 10
• Re -grading of the driveway and eastern portion of the parking lot (due to changes to the
entry to the West Wing and ADA requirements
• Accommodating deliver from large trucks
• Addressing water quality considerations
• Maximizing the number of parking spaces
The sketch below depicts the design of the parking lot. Final design details are still in progress.
While this plan is proposed as the "final" parking lot design to be completed as a part of the
West Wing, two factors may necessitate further refinement to this design. These factors and a
timeframe for if and when refinements may be necessary will be presented at Monday's
meeting.
Conceptual design of west parking lot.
VVMC West Wing
Conceptual Parking Plan
VVMC West Wing Expansion
CUP Review/PEC Hearing #2 Page 5
Interim Parking Plan
The west parking lot is considered a final design. However, in essence it is an interim plan as
changes to the west lot will be made upon completion of the East Wing. The final design of the
west lot could also change if the Evergreen Lodge land exchange is completed. An overview of
how parking will be managed during West Wing construction and following the completion of
the East Wing will be presented at Monday's PEC meeting.
West Wing Construction and Implications on West Meadow Drive Traffic
In allowing the West Wing to proceed as the first sequence of construction in the overall
redevelopment and expansion of VVMC, the Town Council established a standard or
expectation that upon opening of the West Wing there not be an increase to traffic on West
Meadow Drive. In order to accomplish this and to provide an improved patient/guest
experience during the construction of the West Wing, VVMC is proposing to modify parking
management of the west lot and the east parking structure. This change involves using the
west lot for employee parking and using the east structure for patient and guest parking, a
reversal of current operations. The modification will be discussed in greater detail at Monday's
PEC meeting.
VVMC West Wing Expansion
CUP Review/PEC Hearing #2 Page 6
VVMC WEST WING EXPANSION
Employee Housing Plan
March 2, 2015
Introduction
Expansion plans proposed by the Vail Valley Medical Center Master Plan will create new
employee generation. Chapter 23, Commercial Linkage of the Town Code requires
redevelopment projects to provide mitigation for net new employees in accordance with
Employee Generation rates found in Chapter 23. These employee generation rates do not,
however, address hospitals, medical centers, clinics or other uses similar to VVMC. In such
cases the ordinance stipulates that the "the administrator shall determine the applicable
employee generation rate by consulting the town's current nexus study'. In accordance with
section 12-23-2 B., the purpose of this report is to "provide competent evidence and
information regarding the anticipated employee generation of the redevelopment". Specifically,
this report includes the following:
• Summary of two underlying factors relative to the expansion of VVMC that will influence
employee generation,
• Baseline inventory of existing uses and employees for all VVMC departments and all
other organizations that operate at the campus,
• Evaluation of specific expansion (and/or contraction or relocation) plans for each
department and organization within the West Wing and how these plans impact
employee generation, and
• Summary of required employee mitigation and how mitigation will be provided for the
West Wing expansion.
A subsequent report will be provided with the CUP application for the East Wing portion of the
VVMC redevelopment that will address employee generation from the East Wing and all other
elements of the project.
Background
While considered one of the world's most advanced mountain -community hospitals, VVMC's
infrastructure is due for modernization. Facilities are at an age, condition and size where they
must be modernized to meet the challenges of modern medicine and to ensure that facilities
provide VVMC staff with the resources necessary to provide the utmost in quality health care.
The VVMC Master Plan involves the addition of just over 90,000 square feet of floor area. This
VVMC West Wing CUP
Employee Housing Report Page 1
addition will bring the total square footage of the campus to approximately 300,000 square
feet.
The VVMC Master Plan is not, however, a case of pursuing expansion simply to be larger. To
the contrary, this expansion is primarily necessary to bring the size and quality of existing
facilities up to current medical standards. During an internal planning process prior to
presenting the Master Plan to the Town, medical center staff and consultants evaluated all
existing facilities relative to current operations and how these facilities compared to industry
standards. Based on this evaluation it was found that the following hospital departments were
deficient in size (square footage):
• Emergency Department - 140%
• Imaging - 78%
• Patient Care Unit (hospital beds) - 53%
• VVMC Surgery - 32%
• VVSC Surgery - 30%
• Cardiopulmonary - 75%
• Howard Head PT/OT - 40%
• Steadman/SPRI - 83%
• Vail Summit Ortho - 167%
• Materials Management - 87%
• Sterile Processing Department - 39%
These deficiencies are significant and these statistics tell a compelling story with respect to the
current size of VVMC departments and other organizations that operate at the Vail campus.
Specifically that today, these and other departments warrant significant increases in square
footage. These increases are necessary to satisfy current needs and to bring facilities up to
contemporary standards. When implemented, VVMC expansion will improve a multitude of
aspects related to patient care, and with only a few exceptions will not drive increased business
or activity, nor will they generate a significant amount of new employee generation.
At a national level medical advances have resulted in shorter hospital stays and more out-
patient procedures that require no hospital stays what so ever. VVMC has observed these
same trends. In addition, facilities like the Surgery Center in Edwards and urgent care facilities
throughout the Valley have shifted patient activity away from the Vail Campus. The result of
this is that overall patient activity at VVMC over the past seven years has decreased. Since
1998 VVMC has seen declines in admissions, births, total patient days, emergency room visits
VVMC West Wing CUP
Employee Housing Report Page 2
and surgeries. These trends further support the premise that expansion to the campus is
necessary to improve the quality of patient care and not to foster more "business".
The underlying purpose of expanding VVMC is "de -compression", enlarging and improving
facilities to provide VVMC staff with the resources necessary to offer quality medical care.
While there are some exceptions, most VVMC departments are not expected to see increases in
activity from this redevelopment. By way of example, more than doubling the size of the
Emergency Department will not increase the number of emergencies treated at VVMC, but it
will improve the quality of care, patient privacy and other considerations. Doubling the size of
the Sterile Processing Department will not result in an increase to the number of surgeries
performed at VVMC, but it will improve the efficiencies of staff operations.
These two factors are foundational in evaluating information below regarding employee
generation from the West Wing expansion.
Existing Conditions
A baseline inventory of existing employees has been prepared in order to understand the
overall employee situation at VVMC. This inventory includes employees from all VVMC
departments that work at the Vail campus. A number of independent organizations also
operate at VVMC. Examples of these include The Steadman Clinic, Colorado Mountain Medical,
Mountain Surgical Associates and Vail Summit Orthopedics. Employees from these
organizations are also included in this inventory. In most cases the square footage of space
utilized by each department or organization is also provided. In some cases, however, due to
the nature of how departments are organized and how square footage is utilized, it is not
feasible to provide square footage allocations specific to all existing uses.
Employee numbers are presented two ways —the total number of employees that work for any
given department or organization and the typical number of employees on duty during the day
shift for each department or organization. This distinction is relevant for departments that
have 24/7 employee coverage. Examples of departments with "shift work" include the
Emergency Department and Patient Care/Intensive Care units.
VVMC employees 436 people who work at the Vail Campus. Other organizations employ a total
of 234 people, resulting in a total of 670 employees. On a typical weekday VVMC employees on
campus total 395 and other organizations employees total 173, resulting in 568 total employees
on a typical work day. The difference between total employees and typical day shift employees
is due to the number of departments that operate shifts 24/7.
VVMC West Wing CUP
Employee Housing Report Page 3
A spread sheet of the employee inventory is provided at the end of this report.
Employee Generation
The following is a summary of how each department and organization in the existing West
Wing will be affected by the West Wing expansion. This summary addresses changes to
location, square footage and operations of each use and how this will influence employee
generation. A number of uses will change with the West Wing expansion — existing uses will be
relocated elsewhere on campus, new uses will be introduced, some uses will get smaller and
other uses will get larger. As described below, each use is unique with respect to if or how it
will experience increased employee generation. Existing and proposed West Wing floor plans
depicting the changes described above and a spread sheet summarizes uses, employees and
square footage in the West Wing are found at the end of this report.
Basement Level
Existing uses in the basement level include food service/cafeteria, a small office for Facilities
Management and mechanical/back of the house spaces. The main changes at the Basement
Level include:
• The food service/cafeteria will remain virtually unchanged and no employee increases
are planned.
• Mechanical and other back of house functions will remain.
• The Facilities Management office will be removed (relocated to East Wing 2019)
• 3,230sf of meeting room space for VVMC staff will be created. With construction of this
new meeting room approximately 2,000sf of meeting room space in the East Wing will
be removed, resulting in a net gain of just 1,200sf of meeting room space.
Impact on new Employee Generation:
Changes to the basement level will result in no new generation of employees.
Level 1
A variety of uses on Level 1 include the retail pharmacy, gift shop, MRI office, Howard Head
Sports Medicine (HHSM) and Colorado Mountain Medical (CMM). The main changes on Level 1
and how they affect uses, square footage and/or employees include:
• The retail pharmacy and gift shop will be expanded slightly, but will have no increase to
employees (note, these uses are relocated to the East Wing in 2019).
• HHSM will be expanded by 3,342sf. While a significant amount of square footage, this
expansion will result in only a nominal increase to patient treatment areas (from 28 to
30). The bulk of new square footage is to improve patient care by increasing the size of
VVMC West Wing CUP
Employee Housing Report Page 4
patient treatment areas and by increasing areas for patient exercise (and apparatus).
An increase of two employees is planned for HHSM.
• CMM will be relocated to the US Bank Building, meaning CMM employees and patient
traffic from 16 exam rooms will be removed from the West Wing.
• SPRI will utilize the former CMM space and have 5,772sf on Level 1. SPRI will also have
space on new Level 4. Employee generation from the expansion of SPRI's space is
discussed below on page 4.
Impact on new Employee Generation:
Changes to Level 1 will result in the generation of 2 new employees from the expansion
of HHSM.
The new SPRI space will generate new employees, this generation is discussed below.
Level 2
The primary use on the second floor is patient care, or hospital beds. Both the Primary Care
Unit (PCU) and Intensive Care Unit (ICU) are located on this level and expansion of the West
Wing will add a total of 2,487 square feet to Level 2. Of this additional square footage, 1,630
square feet is dedicated to a new Cath Lab. The balance of new square footage will provide
space to enhance other aspects of patient care. The main changes on Level 2 and how they
affect uses, square footage and/or employees include:
• New square footage will be utilized in the conversion of a number of double -bed rooms
to single -bed rooms, this change will having no impact on employees.
• Four hospital beds will be eliminated (reducing the hospitals total bed count from 58 to
54), resulting in a nominal reduction in employees needed to service hospital beds.
• The ICU will be relocated and enlarged, however the number of ICU beds will remain
unchanged (4), having no impact on employees.
• The new Cath Lab will generate the need for 3 new employees.
Impact on new Employee Generation:
Changes to Level 2 will result in the generation of 3 new employees from the
development of the new Cath Lab.
Level 3
Existing uses on Level 3 include the Surgical Suites and The Steadman Clinic. The Steadman
Clinic's 6,502 square feet of space will be relocated to the new 4t" Level and with the
completion of the West Wing expansion Level 3 will be devoted entirely to the Surgical Suites.
Total square footage on Level 3 increases from 16,344sf to 21,780sf, an increase of 5,436sf.
VVMC West Wing CUP
Employee Housing Report Page 5
The main changes on Level 3 and how they affect uses, square footage and/or employees
include:
• There will be no increase to the four existing operating rooms. This is significant
because the number of operating rooms is the main driver in patient activity and
employees.
• The majority of new square footage on Level 3 (3,925sf) will be used to relocate the
Sterile Processing Department (SPD) to the West Wing from two areas of the East Wing.
The new SPD will be located adjacent to the Surgical Suites (a much improved location)
and will increase is size by roughly 40%. There will be no increase to SPD employees
(note that the space needs study described above concluded that the existing SPD is
deficient in size by 39%).
• 8,013sf will be added to the Surgical Suites. The bulk of this square footage will be used
to significantly increase the size and privacy of pre-op and post-op areas. Significant
enhancements will also be made to support space within the Suites. Examples of these
spaces include waiting areas, staff showers and lockers, staff lounge, offices,
consultation rooms and storage. With no increases to the number of operating rooms,
these enhancements will have no impact on employee generation.
Expansion of Level 3 is an excellent example of de -compression.
Impact on new Employee Generation:
Changes to Level 3 will result in no new generation of employees.
Level 4
Level 4 is a new level and will provide 17,165sf of space for The Steadman Clinic and 7,278sf for
SPRI. With 5,772sf on Level 1, SPRI will have a total of 13,050sf of space. At the completion of
the West Wing, The Steadman Clinic will vacate 8,401sf (on the 3rd and 2nd levels) and SPRI will
vacate 8,828sf (on the basement and 1s' levels). As a result, the net increase of new square
footage for these organizations is 8,764sf for The Steadman Clinic and 4,222sf for SPRI.
The Steadman Clinic currently operates out of five offices located throughout the Vail campus.
The new 4t" level will consolidate two of these offices (an MRI on the main level of the hospital,
an administrative office and a small clinic in the US Bank Building will remain). New space on
Level 4 will provide additional space for the Clinic, however much of the new square footage
will involve de -compression of existing uses or providing new space for uses not currently
provided for by existing facilities. The main changes to The Steadman Clinic on Level 4 and how
they affect uses, square footage and/or employees include:
VVMC West Wing CUP
Employee Housing Report Page 6
• Increased square footage will provide new space for many functions that are not
currently provided (or adequately provided) by existing space. Examples of these uses
include offices for all physicians and other staff members, space for athletic trainers,
PRP room, MDV rooms and a dedicated IT room.
• The Clinic currently operates with 30 exam rooms. 36 exam rooms are proposed on
Level 4. These rooms alone account for 5,210sf and reflect a significant increase when
compared to the size of existing exam rooms.
• The Steadman Clinic expects that the new West Wing will give them the flexibility to add
2 physicians to their practice. On average each physician will have 4 support employees,
resulting in up to 10 additional employees. The existing number of support employees
(billing, scheduling, etc.) can accommodate these additional physicians.
SPRI currently operates in under -sized facilities lacking in many basic elements necessary for
the organization's operation. While new space is designed to accommodate new programs, the
bulk of new square footage for SPRI will address existing space deficiencies. The main changes
to SPRI on Levels 1 and 4 and how they affect uses, square footage and/or employees include:
• Increased square footage will provide new space for many functions that are not
currently provided by existing space. Examples of these uses include meeting rooms for
educational programs and other uses, staff lockers, rest rooms, bio -hazards, IT, and
offices for staff and researchers. These predominantly "back of the house" uses will not
contribute to new employee generation.
• Increased square footage will decompress a number of existing uses, including but not
limited to bio skills, clinic research, bio -motion and surgical labs, bio -mechanical
research and machine shop. Increased space for these uses address the existing space
deficiencies outlined above.
• Improved and enlarged work stations will be created for staff, along with enhanced and
more controlled circulation patterns and reception/lobby areas.
• SPRI plans to expand research efforts to include regenerative medicine. Increased
square footage will allow this to happen. Employee growth from this expansion would
include one lead researcher and five support staff, or six new employees.
Impact on new Employee Generation:
Changes to the SPRI space on Level 4 (and Level 1) will result in the generation of 6 new
employees.
Changes to The Steadman Clinic on Level 4 will result in the generation of 10 new
employees.
VVMC West Wing CUP
Employee Housing Report Page 7
Employee Mitigation
Employee Generation from West Wing
Based on the analysis above, 21 new employees will be generated from the West Wing
expansion. These employees are a result of the following:
6 employees at SPRI - addition of new regenerative medicine research program
10 employees at The Steadman Clinic — two new physicians and support staff
3 employees at Cath Lab — staff to support new facility
2 employees at HHSM — addition of therapists
Method of Mitigation
Employee housing mitigation is to be provided by payment cash -in -lieu based on current cash in
lieu rates.
50% On-site Requirement
Section 12-23-6 of Chapter 23 stipulates that in cases where employee generation exceeds 1.25
employees, 50% of required mitigation must be provided on-site, provided however that at the
sole discretion of the applicable governing body, "an exception may be granted based upon one
of the following findings". Based on the response to findings below, a request for an exception
to the on-site requirement is proposed.
a. Implementation of the on-site unit mitigation method would be contrary to the
intent and purpose of the applicable zone district.
Response
N/A
b. Implementation of the on-site unit mitigation method would be contrary to the
goals of the applicable elements of the Vail comprehensive plan and the town's
development objectives.
Response
A waiver to the on-site requirement is consistent with the VVMC Master Plan. This plan
states that 'for two reasons all required employee housing will be provided off-site."
These reasons include:
• VVMC is an intensive, institutional land use. Introducing a residential land use on
the site would not be compatible with the primary purpose of the site, which is to
accommodate a hospital and relate medical uses.
• VVMC has very limited land area. The primary purpose of this site is to
accommodate the medical center's existing needs as well as to retain
opportunities for future expansion to the medical center. Introducing residential
VVMC West Wing CUP
Employee Housing Report Page 8
land use would conflict with the intended use of the site, limit future expansion
opportunities and not be consistent with the town's comprehensive plan.
c. Exceptional or extraordinary circumstances or conditions apply to the site that
prevents the implementation of the on-site unit mitigation method.
Response
VVMC is a unique land use and an "extraordinary circumstance". With VVMC's limited
land area, introducing housing to the site would compete with the need to accommodate
medical uses (now and in the future) and in doing so conflict with the Town's goal for
this site to be used for medical purposes. In essence, any portion of the site that was to
be used for housing would result in less site area available for future medical uses. This
situation is exacerbated by existing covenant restrictions that limit VVMC's future
expansion potential.
d. The method of mitigation proposed better achieves the intent and purpose of this
chapter and general and specific purposes of this title than the on-site mitigation unit
method.
Response
Addressing employee impacts with off-site mitigation provides a more workable solution
for addressing not only the goals of the housing regulations, but also the town's master
plan goals for VVMC.
VVMC West Wing CUP
Employee Housing Report Page 9
VVMCTotal Employees-Existing Baseline Condition
3/1/2015
Typical Peak
Total Location of Emp
Appx Existing SF
DEPARTMENT/ORGANIZATION
Day Shift Emp
Employees Work Place
of Work Place
VVMC
Patient Care/Intensive Care
39
WW/1-2
16349
Cardiatric Area
7
CW/L1
2001
Specialty Clinic/Avanti
12
US Bank Bldg
1615
Womans and Children Center
11
CW/1-2
11135
Surgery Suites/Pre-op
46
WW/1-3
9842
Sterile Processing
12
EWJ
2731
Mtn Surgical Assoc./Trauma
14
EW/1-2, US Bank
2532
Emergency Department
12
CW/L1
5503
Hospitalists - Ped and Adult
6
EW/1-1, WW/1-2
130
Lab
9
EWJL1, CWJLZ
2918
Rad, CTS, MRI
14
WWAL1
5515
Gift Shop
3
WW/L1
528
Retail Pharmacy
6
WW/L1
912
Hospital Pharmacy
8
EW/L1
1267
Howard Head Sports Medicine
33
WW/L1, US Bank Bldg
7301
Vail Valley Surgery Center
38
CWJL2
11160
Social Services
2
Health Info Systems
2
Patient Relations
5
WW/L1
390
SHC, MSOff, UtilRev, QRMgmt, PtRel
17
US Bank Bldg
1047
Cafeteria/Nuitrition
18
WW/Bmt
4163
Facilities Management
8
WWJBmt, ?
727
Valet/Parking Lot/Concierge
7
WW/L1
Security
3
CW/L1
100
House Keeping
9
EW/BMT
1502
IT, Comp., PatFinS
25
EW/Bmt, WWBmt, USB
3359
Admissions
13
CW/L1
589
Ad mistration
10
EW/1-2
3208
Material Management
3
EW/1-1
909
HR/Property Mgmt
3
EW/L1 and L2, USB
1131
395
436
98564
Other Organizations
VV EM Phy
3
3
Apollo
10
17 CW/1-2, WWL3
791
CMM
17
20 WW/L1
4216
The Steadman Clinic
98
114 WW/L1/3, CW/1-2, USB
12903
Vail Summit Orthopeadic
10
40 US Bank Bldg
2844
SPRI
32
35 CW/1-1, EW/Bmt, EW/L1
8828
Ambulance District
31
5 Separate Bldg
3828
1731
2341
33410
VVMC West Wing CUP
Employee Housing Report Page 10
VVMC West Wing CUP
Employee Housing Report Page 11
C
V
S
ro
^ r
-
-
-
IL
a
_
—
-
tj
c
4
CL
77,
02
a
L7 r
26
E
VVMC West Wing CUP
Employee Housing Report Page 11
9
N O co
5
rod �
rgi
o�
rr
S�ff
� I
W
y
z
w�
-
J
a �o
N O co
9
I`,- >,H�
t0 b!
1 -
lI �I �-
n
7 17
14 1 ✓`
rn rn m r, 0
Nolmr,00 N
!ri rl t\
Qn
E
O
N
�
d
�
4!
V 4 �
W
U
LL
v
T
Z v
�
N
_,fig J�
:71�C7V2r� E�L�'UZ�
E�
�LL
mGK
5
•
Ipso
LU
�..�
Lu
EE
L,
a
fia
ME
FTq P
¢
�4Q LL
(DQ N
(D Lu
rn rn m r, 0
Nolmr,00 N
!ri rl t\
N o0 �D .-• d' h
a c
Qn
E
O
N
�
d
�
4!
V 4 �
W
U
v
T
Z v
N o0 �D .-• d' h
a c
v '
N
�
d
�
N
v
T
Z v
�
N
:71�C7V2r� E�L�'UZ�
E�
9
N
T, m
E 7
00
O
eq
LU
ir
Q0 Ln
1.
m
El.
N
ITIT
T, m
E 7
00
O
ITIT
1�
r—j
T
CA
r
W
nn
o
can c
n
m
m
N
N
�
T
O
bri
r7'
W
0
N
7>U-)
F
SOC
F
a
Z
I
J
�
1
�
LU
5 LU LL
>
v
LLJ
Ov
��
�—
UN LU,,j
d
y
�o
W
nn
o
can c
n
m
m
N
N
�
T
O
bri
71
W
0
N
7>U-)
F
SOC
F
y �
H
x
c o
m
o
MW
_ �
w
m
M
�
�
N
�
O
x
U
W
=
G
LL,
U
N > U o v °—° w Z
$ W z Ho w- �sa zwZJI�l
i > ° 3> o _ °
I o a °N
"
3
rcg n 1
y x _
own .�, �I I � ��-- o—_�_� — �✓--�,���-_
I � I
I II til p a
— I
i
E
I I I
I
e,c I I I✓ I I i
I
T
I I
s
J o N
p
7` ❑
, jI ❑ � it l
Hc
i W
li ' I � � f✓ -- "r ——_•—__...__�_ ''� ' ;r a � � �s� .. �-pow w==
a m =
e "
t
eVIC,
a �
I
v �
O
H0 �"a v Z
H
R
i�
L-Ij
O M' s N O :x+ cz O
¢'0�
raj
cz U
Ln
Q. aJCZ
cd cq
OCAIn vCd
C Q cz
cu Q O
u
3° v uU v v
w o
Q a o
-o m a, o v P.
o a v 14.
• a, m u. N
o
0 v "u o u
cz m m aJ
O Cdu
c� cA 3 +m CU +m+ v O
CA cu
04,
1 cd � 1 .+, '(A v0 c�C Q)btu
W � � cu a) -0 o n o
m m O
!�1 m 14. O4�
m O u O
m aJ O cC u
c4 m m 4.1 O �. O O + O
s.4 brioCU
a� �1 S1, u >
cz O w �. v O p cz O
4Jtp
cz
Az
O aJ app + cz ci3 iC :z p O
u Ccz
�. cn H � �n cu
I�CU
m O O aJ •� C3 v O
I�
1-4
�I
v
O �
U
v
E...� v
CIS p., o
o �
U
cn
r
IN ;
lu
/(
t42
ap
o � T
vs-�o8�
�t
ui Z.:
UJod��m
Lu
9b
a
v
o�
cz
9
41
1 x a,
w O m fl
r+ 1-414,
Q. v
LA O
., c�j) •t CL V " 4+ N O�JO
D t bA cCScn
CIS
4-
C v v
.- 4� v cz V ++
}O w v cz
CD CZ +O+ w I -o t>A
a� m 1 a�
O
-
1
o
�
8
4J
3
opo
CL
3zs•�H
tt a
a
I
X41
x
,-+
O 1
CA
co
3� v�`��s
cu
Q
o� tt
14
00
m
P.
-
1
}kr
�
CL
co
cu
Q
t
x
�
00
m
P.
I
0
H
a�
75
0
u
u
c�
3
0
O
w
X
'•CY �
N
75
.4i
0
O
O
ca
3
O
0
C
O ate-'
O
a
co
-
r o
Q
u
�S s
DO
o a,
�L
.b.
o,
4
u4
4
u. f
�.rJHh'?J^Yr
r o
a
u
�S s
o a,
4.1
u (�
u. f
�.rJHh'?J^Yr
- - II, " a m " Lil
r o
a
u
o a,
4.1
u (�
O"
O 41
W
O
z v
p ro
O
W p
° �
o
W m
u
�
w v
U
cz
�
H
v z
- - II, " a m " Lil
gj
N
0
v
O �
H ° ° W
a�
o°'
H
� a
O
o b o 0
0
4.
U cJ
16.
+J
`, CZ O
Z
M M(D
H m>
c�
v
u
�
U
O
O
:64
N
0
v
O �
cid+ O O �
p bA O aJ
.-,o
Ou ° `a .
° a) w0
U v v u v vh
u as
"O > 4
i1,v
., cn
CZ W p a4
-
O pr p (u
C) p sa C3
N > Ov Q"
44 a.+ v v b0
cis vOi O v+
cz .� U u U v O -° v 0
ici C).N r w
O O
Cl
cz
°' a o
O
W v rl t4 X°
CU
p cC cd
L"
QcC N O� U b0 p
v 30 F" W �, w ;..
+' v u -j Q" o
cd cu
° v Q cz v
s� O U O p
O tl. x �, H w O a, .,
F I ® ® m LA I I f I p I f I W I I I ` a
7
v
o
v
3
v
°
�
a
.�
o
o
C.7
0
�
U
v
v
v T�1
w
I
�
p.,
Q)
�
�:
ucz
u
�
v
v
�
cz
on Q
as
00)
cu
v
3 �m
c
(U
v
vw
0
•+
m
�
(U
•�
0
3
v
cut
acv
a`�
�
�
a,�°'"�
v
v
v
�
v T�1
cz
p.,
(2)
ucz
�
v
v
�
cz
on Q
as
CU
� � v
v
3 �m
c
(U
14�
0
Warren Campbell
From: Vail Homeowners Association <vha@vail.net>
Sent: Monday, March 02, 2015 4:04 PM
To: Warren Campbell
Subject: VVMC West Wing Expansion Underway - VHA Recommends Changes to Master Plan to
Preserve Neighborhood's Character
VAIL HOMEOWNERS ASSOCIATION
View of the Proposed WMC West Wing Expansion on West Meadow Drive
Proposed VVMC West Wing Expansion Underway
03/02/15
To: Warren Campbell
-----------------------------------------------------------------------------------------------------------------------------------------
This message is intended to be CONFIDENTIAL and may contain PRIVILEGED COMMUNICATIONS.
The information contained in this message is confidential and intended only for the use of the individual or entity named above, and may be privileged.
Any unauthorized review, use, disclosure, or distribution is prohibited. If you are not the intended recipient, please reply to the sender immediately,
stating that you have received the message in error, then please delete this e-mail. Thank you.
The Proposed VVMC West Wing Expansion is Underway: The anticipated West Wing expansion of the Vail Valley Medical Center
(VVMC) has begun moving through the approval process with the presentation to the Vail Planning and Environmental Commission
(PEC) of a zoning proposal to allow this phase of the redevelopment to proceed. This is step one of the expansion of the overall VVMC
campus, even though the Master Plan for the area is still under review by the Town Council. The VVMC plans to begin construction of
this phase of the expansion in the summer of 2015 with completion scheduled for 2017. This specific part of the expansion, shown above,
would build southward toward Meadow Drive.
E XISIT NG W ESi` W4+ING EXISTING r-ENTRAL
!' Ir WI NG ip
dbk w
EVISTINf�_ BUIL rMKL, LINE
..
4
OLITIIDOORDIril
COLIRT'W/SYCREEN W_'..1
..!
Inti.=°,' .. NTERJSFATIN
WALL & LANI)SCAPING
POTENTIAL SCULPTURE
.. _._w.
EXISTING BUILDING LIFE
--—————— — — — — ——
_ -:I. _
NEW SOUTH EXPANSION
EXISITN G SIDEWALK &
LANDSCAPING
Expansion conflict shown with preserving landscape and mature trees that harmonize VVMC buildings with the adjoining street and neighborhood.
As can be seen from the following renderings, the proposed design would substantially increase the mass of the overall building by adding
a fourth floor on the west wing, which is a cause for concern.
J�+-�q�
—
Y
_
J�+-�q�
—
Proposed West Wing Expansion Existing Central Wing Proposed East Wing
VVMC Unifying Architectural Design Concept As Viewed from West Meadow Drive
Below are
photos of
the
present
structure
as
compared
with the
proposed
redevelop
ment:
Existing Landscape and Architecture of West Wing Above
Proposed Expansion of West Wing
With a new entrance proposed on the South Frontage Road, the West Wing would become the back side of the VVMC complex. The
proposed design would, however, make West Meadow Drive more "commercialized" by pushing out toward the edge of the street and
eliminating existing landscaping which currently makes the existing West Wing more compatible with the West Meadow Drive
residential neighborhood.
Proposed West Wing bump -out infringes on landscaped area necessary to retain compatibility with adjoining residential neighborhood.
Views of existing and proposed (below) expansion of the VVMC West Wing surface parking lot to be included in redevelopment of Evergreen Hotel.
The Vail PEC has just held its first public discussion of a zoning proposal to allow this project to go forward. While the Vail Homeowners
Association supports the expansion of the Medical Center, it believes that it should be done in a way that is responsible and in keeping
with the overall qualities of the existing neighborhood. As presently proposed, there are several aspects of the development that could be
substantially improved. The proposed West Wing expansion building would move the building to within 3.5 feet of the property line
creating a wall effect four stories high.
While a fourth floor would not necessarily render the design objectionable, the VHA believes that the expansion should be compatible
and harmonized with the present buildings and the overall aesthetics of the neighborhood. Unfortunately the present plans would
eliminate significant landscaping - a number of large, mature trees - that serve to integrate the VVMC into the surrounding neighborhood.
The VHA recommends that any zoning approval should be conditioned upon maintaining the present Meadow Drive setbacks and
landscaping or even increase the landscaping to soften the industrial nature of the building and make it more compatible with the
established characteristics of this section of West Meadow Drive.
The VHA also recommends that the design of the West Wing should be harmonized with the existing structure so that there is a unifying
theme in the overall structure as opposed to the hodgepodge of styles that has evolved on the medical center's campus over the past 45
years. The unifying design theme is a recommendation of the proposed VVMC Master Plan.
Extend Snow Melt System for West Meadow Dr TOV Pedestrian Route:
Participants at the PEC hearing recommended the need to include VVMC in
the Town of Vail's (TOV) snow melt system serving the pedestrian walkway
on the north side of West Meadow Drive. With increasing frequency, clients
of the VVMC regularly use the West Meadow Drive public pedestrian
walkways for rehabilitation therapy. The number of pedestrians on West
Meadow Drive public walkways traversing between Vail Village and
Lionshead commercial centers has greatly increased in recent years as well.
The Vail Homeowners Association notes that the Town of Vail is
exponentially increasing the urban density of the West Meadow Drive
neighborhood to the degree that it is now on par with major new
redevelopments in Vail Village and Lionshead. Yet, the Town has not
committed to provide the same level of public improvements such as
providing snow -melted pedestrian walkways as it has already installed
throughout the Vail Village and Lionshead neighborhoods.
Mechanical Equipment Noise: The West Wing expansion provides for the
relocation of exterior ground level mechanical building ventilation
equipment on West Meadow Drive. The noise from this equipment has, for
years, been a major source of irritation and complaint from adjacent residents
and passersby. The mechanical equipment issue is an example of the lack of
foresight and coordinated design of the existing VVMC complex. The
offending mechanical equipment was installed after the completion of the
West Wing due to a lack of forethought on the part of ventilation engineers.
The neighborhood and Homeowners Association places a high priority on
ensuring, in the VVMC master plan, that similar oversights do not occur in
the future development of the VVMC facilities.
Crutching on Nonsnow-melted West Meadow Drive TOV Walkway
The VVMC Central Wing and West Meadow Drive Streetscape illustrates how trees and landscape have been used to harmonize the existing West Wing with
the residential neighborhood.
Design is Critical to Maintain Compatibility: The VVMC West Wing Expansion eliminates large trees which have served to harmonize
6
the medical buildings with the adjacent residential neighborhood. Changes are being requested to soften the institutional appearance of the
proposal in an effort to restore a higher degree of aesthetic compatibility with the adjoining West Meadow Drive tourism circulation
corridor and residential neighborhood. The correct design, scale and appearance of new development along West Meadow Drive is
essential in maintaining a high standard of guest and residential experience in this important link between the Town's two commercial
tourism centers.
Urbanizing the West Meadow Drive Neighborhood: The proposed VVMC/Evergreen Hotel land swap and subsequent redevelopment
of the Evergreen Hotel would eliminate the large surface parking currently used by VVMC by conveying it to the Evergreen Hotel. In
return, VVMC would receive hotel land fronting on the South Frontage Road, which allows all VVMC traffic to enter its campus from the
frontage road. A change to the Evergreen Hotel zoning, based upon the land exchange with VVMC, is to be heard by the PEC on March
9th. The PEC is considering tabling the hearing until April 13th since involved parties are continuing discussions regarding the proposed
land exchange. The parking lot would be replaced with a new hotel building being suggested by development interests as being larger
than the Solaris complex in Vail Village. Future phases of the medical center could be of a similar size as shown below. The Vail
Homeowners Association believes that priority must be given to continuing the practice, begun with the new Four Seasons Hotel, of
stepping down the height of structures built along the north side of West Meadow Drive so that views to the mountains beyond are
preserved.
Shown is VVMC density potential resulting from land exchange with the Evergreen Hotel.
Quick Links
Special Events Calendar
Local Media Links
Visit VHA Website
What's on Your Mind? Send Your Comments
Contact the Editor
View Our Newsletter Archives
VHA Newsletter Reprint Policy
VHA Collaborative Consensus Guidelines
Production Credits
Content Editors:
Larry Stewart, Gail Galvin Ellis, PsyD
Copy Editing & Distribution:
Elizabeth Bailey, General Partner
Books Plus
books_plus more@msn.com
Copyright (0 2015 Vail Homeowners Association
All Rights Reserved
www.vailhomeowners.com
Forward this email
�F*4Jna ul�su
This email was sent to wcampbell@vailgov.com by vha0)vail.net
Rapid removal with SafeUnsubscribeTM Privacy Policy.
C&Btadcarfi2a, 11
!ry -t F( tU tr: d.o
Vail Homeowners Association P. O. Box 238 Vail CO 81658-0238
Warren Campbell
From: George Ruther
Sent: Wednesday, March 04, 2015 8:13 AM
To: Warren Campbell; Council Dist List
Subject: Fwd: Ramifications of VVHA expansion
See the attached letter regarding VVMC master plan. This will be entered into the public record for the meeting
on the 17th.
Thanks,
George Ruther, AICP
Director of Community Development
Town of Vail
(970) 376-2675
Sent from my iPad
Begin forwarded message:
From: Kathie Dudzinski <bikeski2mac.com>
Date: March 3, 2015 at 4:18:32 PM MST
To: " gruther2vailgov.com" <gruther2vailgov.com>
Cc: Jim Lamont <vvhagvail.net>, Jim Lamont & Joan Norris <jflamontgvail.net>, "Dr. Roger
& April Steinert" <roger2drsteinert.com>, " emily.tamberino2vvmc.com"
<emily.tamberinogvvmc.com>, VVMC News <buildgvvmc.com>
Subject: Ramifications of WHA expansion
To Town of Vail,
Vail Homeowners Association
Skaal Hus I Condominium Association
To all concerned:
We have reviewed emails from VVMC, the recent VHA email and the included PEC meeting
minutes re the mass, height and property line so close to W Meadow Dr.
Not much was emphasized regarding the expansion to the south of the East Wing trying to make
room for an indoor turn around for a 30' truck.
It makes no sense to have loading and delivery on the south side of the building.
As we have many times stated in writing, we remain adamantly against commercial traffic on
West Meadow Dr. which is THE only pedestrian/ bicycle link between Vail Village and
Lionshead.
We agree also that a high building without separation via landscape would be overpowering to
the average pedestrian, but the proximity of the sidewalk to ice overhangs would make its use
treacherous. (It would make walking hazardous even with heated sidewalks or even without
crutches!) Please add our voices to those who have already discussed these concerns.
Kathie and Paul Dudzinski
Skaal Hus 94
141 W. Meadow Drive
Ad Name: 10968160A
Customer: TOWN OF VAIL/PLAN DEPT/COMM
Your account number is- 1 OP2P 33
vail Daily
PROOF OF PUBLICATION
STATE OF COLORADO }
}SS.
COUNTY OF EAGLE }
I, Don Rogers, do solemnly swear that I am a qualified
representative ofthe Vail Daily. That the same Daily newspaper
printed, in whole or in part and published in the County
of Eagle, State of Colorado, and has a general circulation
therein; that said newspaper has been published continuously
and uninterruptedly in said County of Eagle for a period of
more than fifty-two consecutive weeks next prior to the first
publication of the annexed legal notice or advertisement and
that said newspaper has published the requested legal notice
and advertisement as requested.
The Vail Daily is an accepted legal advertising medium,
only for jurisdictions operating under Colorado's Home
Rule provision.
That the annexed legal notice or advertisement was
published in the regular and entire issue of every
number of said daily newspaper for the period of 1
consecutive insertions; and that the first publication of said
notice was in the issue of said newspaper dated 2/20/2015 and
that the last publication of said notice was dated 2/20/2015 in
the issue of said newspaper.
In witness whereof, I have here unto set my hand this day,
02/23/2015.
General Man ager/Publisher/Editor
Vail Daily
Subscribed and sworn to before me, a notary public in and for
the County of Eagle, State of Colorado this day 02/23/2015.
� 2M 4,& 9. -V-�
Pamela J. Schultz, Notary Public
My Commission expires: November 1, 2015
�pRY PUe/
' PAMELA J.
SCHULTZ
9�� COt-SRP$
My Commismn Expires 11/0112015
THIS ITEM MAY AFFECT YOUR PROPERTY
PUBLIC NOTICE
NOTICE IS HEREBY GIVEN that the Planning and
Environmental Commission of the Town of Vail will
hold a public hearing in accordance with section
12-3-6, Vail Town Code, on March 9, 2015 at 1:00
pm in the Town of Vail Municipal Building.
A request for a final review of a major exterior al-
teration or modification, pursuant to Section
12-7H-7, Major Exterior Alterations or Modifica-
tions, Vail Town Code, to allow for a change to the
approved mix of residential unit types, and a re-
quest for final review of an amended conditional
use permit, pursuant to Section 12-7H-3, Permit-
ted and Conditional Uses: First Floor or Street Lev-
ee, Section 12-7H-4, Permitted and Conditional Us-
es; Second Floor and Above, Vail Town Code, to
allow for a reduction in the number of timeshare
units, located at 705 West Lonshead Circle/Lot 1,
Strata Vail, and setting forth details in regard
thereto. (PEC150006, PEC150007)
Applicant: Lionshead Inn LLC, represented by
Mauriello Planning Group
Planner: Warren Campbell
The applications and information about the propos-
als are available for public inspection during office
hours at the Town of Vail Community Develop-
ment Department, 75 South Frontage Road. The
public is invited to attend site visits. Please call
970-479-2138 for additional information.
Sign language interpretation is available upon re-
quest, with 24-hour notification. Please call
970-479-2356, Telephone for the Hearing Im-
paired, for information.
Published February 20, 2015 in the Vail Daily.
(10968160)
Ad Name: 11007342A
Customer: TOWN OF VAIL/PLAN DEPT/COMM
Your account number is- 1OP2P 33
PLANNING AND ENVIRONMENTAL
COMMISSION
1:00pm
March 9, COUNCIL
TOWN COUNCIL CHAMBERS
/ PUBLIC WELCOME
75S. Frontage Road - Vail, Colorado, 81657
Vail Daily
MEMBERS PRESENT MEMBERS ABSENT
PROOF OF PUBLICATION
STATE OF COLORADO }
1 ss
i
COUNTY OF EAGLE }
I, Don Rogers, do solemnly swear that I am a qualified
representative ofthe Vail Daily. That the same Daily newspaper
Site Visit: None
25 minutes
1.A request fora final review of a major exterior
alteration or modification, pursuant to Section
12-7H-7, Major Exterior Alterations or Modifica-
tions, Vail Town Code, to allow for a change to the
approved mix of residential unit types, and a re -
quest for final review of an amended conditional
use permit, pursuant to Section 12-7H-3, Permit -
ted and Conditional Uses: First Floor or Street Lev-
el, Section 12-7H-4, Permitted and Conditional Us -
es; Second Floor and Above, Vail Town Code, to
allow for a reduction in the number of timeshare
units, located at 705 West Lionshead Circle/Lot 1,
Strata Vail, and setting forth details in regard
thereto. (PEC150006, PEC150007)
Applicant: Lionshead Inn LLC, represented by
Mauriello Planning Group
Planner: Warren Campbell
printed, in whole or in part and published in the County
of Ea le State of Colorado and has a eneral circulation
g , , g
therein; that said newspaper has been published continuously
ed uninterruptedly in said County of Eagle for a period of
more than fifty-two consecutive weeks next prior to the first
Ubllcatlon of the annexed legal notice or advertisement and
P g
that said newspaper has published the requested legal notice
and advertisement as requested.
ACTION:
MOTION: SE OND:VOTE:
90 minutes
2.A request for final review of an amendment to a
conditional use permit, pursuant to Section
12-9C-3, Conditional Uses, Vail Town Code, for an
existing healthcare facility, amending the develop-
ment plan to allow for an additional floor plate on
the west wing, located at 181 West Meadow Drive
and 108 South Frontage Road West (Vail Valley
Medical Center)/Lots E, F, and 10 Vail Village Fil-
ing 2, Lot 2E, Block 1, Vail Lionshead Filing 1 and
Lot D-2, A Resubdivision of Lot D, Vail Village Fil-
ing 2 (PEPEC1
Applicant: Vail Valley Medical Center, represented
by Braun Associates
Planner: Warren Campbell
The Vail Daily is an accepted legal advertising medium,
only for jurisdictions operating under Colorado's Home
Rule provision.
That the annexed legal notice or advertisement was
published in the regular and entire issue of every
number of said dailynewspaper for the period of I
h 1�er h
consecutive insertions; and that the first publication of said
ACTION:
MOTION: SECOND: VOTE:
CONDITION(S):
3.A request for a recommendation to the Vail Town
Council for an amendment to the Lionshead Rede-
velopment Master Plan, pursuant to Sectionn2.82.8,,
Adoption and Amendment of the Master Plan, Li -
onshead Redevelopment Master Plan, to amend
the Detailed Plan Recommendations for the Ever-
green Lodge at Vail, located at 250 South Front-
age Road West/Lot 2W, Block 1, Vail Lionshead
Filing 2, and setting forth details in regard thereto.
(PEC140044)
Applicant: Evergreen Lodge at Vail, represented by
Mauriello Planning Group
Planner: Warren Campbell
ACTION: Table to April 13, 2015
MOTION:SECOND:VOTE:
notice was in the issue of said newspaper dated 3/6/2015 and
4.Approval of February 23, 2015 minutes
MOTION: SECOND: VOTE:
that the last publication of said notice was dated 3/6/2015 in
5.Information Update
the issue of said newspaper.
6.Adjournment
MOTION: SECOND: VOTE:
In witness whereof I have here unto set m hand this da
y y,
03/06/2015.
General Maner/Publisher/Editor
g
Vail Dail y
The applications and information about the propos-
are available for public inspection during -
lar lar office hours at the Town of Vail Communityy DeDe-
velopment Department, 75 South Frontage Road.
The public is invited to attend the project orienta-
tion and the site visits that precede the public
hearing in the Town of Vail Community Develop-
ment Department. Times and order of items are
approximate, subject to change, and cannot be re-
lied upon to determine at what time the Planning
and Environmental Commission will consider an
item. Please call (970) 479-2138 for additional in -
formation. Sign language interpretation is available
upon request with 24-hour notification. Please call
(970) 479-2356, Telephone for the Hearing Im-
paired, for information.
Subscribed and sworn to before me, a notary public in and for
the County of Eagle, State of Colorado this day 03/06/2015.
Community Development Department
Published March 6, 2015 in the Vail Daily.
(1107342)
� 2m.&& 9. -V-�
Pamela J. Schultz, Notary Public
My Commission expires: November 1, 2015
�pRY PUe/
' PAMELA J.
SCHULTZ
9�� COt-SRP$
My Commismn Expires 11/0112015