HomeMy WebLinkAbout1982-21 Initiating a Special and Local Improvement Project for the Vail Lionshead Mall and Adjacent Area1 ~~
RESOLUTION #21
SERIES OF 1.982)
rITEMNq('~" G
DATE: /~ 'S' ~°Z
A RESOLUTION INITIATING A SPECIAL AND
LOCAL IMPROVEMENT PROJECT FOR THE VAIL
LIONSHEAD MALL AND ADJACENT AREA; DIRECTING
THE TOWN MANAGER TO HOLD ADMINISTRATIVE
HEARINGS AND OTHER PROCEDURES FOR THE
IItiPLEMENTATION THEREOF; RATIFYING AND
APPROVING WORK PREVIOUSLY DONE BY THE
ADMINISTRATION ON SAID SPECIAL AND LOCAL
IMPROVEMENT PROJECT; AND SETTING FORTH
DETAILS IN RELATION THERETO.
WHEREAS, it is the opinion of the Town Council that certain
improvements should be made to the Vail Lionshead Mall and surrounding
areas; and
WHEREAS, said improvements are necessary to protect and preserve
public areas and ways within the Town; and
WHEREAS, said project is necessary for the full and complete
use and enjoyment of the private property in the Lionshead area;
an d
WHEREAS, it is the belief of the Town Council. that said
improvements will confer special benefits of a local nature on
the private property inthe Vail Lionshead area; and
BE IT RESOLVED AND ORDERED BY THE TOWN COUNCIL OF THE TOWN OF
VAIL, COLORADO, THAT:
J~. There is hereby initiated by this Resolution a special and
local improvement project to construct and instill certain improve-
ments to the Vail Lionshead Mall and surrounding areas, including,
but not limited to, replacing paving in major areas of the mall, re-
locating planting areas, providing new focal points of interest,
unifying and upgrading utility systems, providing emergency access
to all areas of the mall, instilling a cascading fountain, a
sculpture plaza, a new lighting system, benches, kiosks, planters,
bicycle racks, drinking fountains, anti other amenities, and generally
improving the aesthetic quality of the mall and its surrounding area.
2. The Town Manager or his authorized agents are hereby
directed to proceed with the project by holding such adminis~tra~ive
hearings and investigations as they may deem necessary or appropra_ate
l ~
I.
to inform affected property owners about the project and the
assessments proposed and to obtain their reactions thereto, to
implement the project, and to recommend to the Town Council for
its consideration and adoption the manner of construction and
installation of the project, the extent of the project, the portion,
if any, of the cost of the project to be paid by the Town, the method
of assessing all or a portion of the cost of the project against the
properties in the vicinity thereof specially benefited thereby, the
portion of the cost of the project to be paid by special. assessments,
and any further recommendations that the Town Manager may deem
appropriate.
3. The Town Council hereby ratifies and approves any hearings,
work, or proceedings previously carried out by the Town Manager or
his authorized agents in relation to the project.
4. This Resolution shall take effect immediately upon its
adoption.
INTRODUCED, PASSED, ADOPTED, A~~TD APPROVED THIS 5th day of
October, 3982.
TOWN OF VAIL, COLORADO
Ro ne E. Slifer Ma ~'r 'Y ~ Y
ATTEST:
j~,
Colleen M. Kline, own Clerk
2-
Cauncil Member ~. ter. ~ ~ ~~C___~ seconded the motion,
and the question being upon the passage and adoption of the
Resolution, the roll was called with the following result:
Council Members Voting "Yes": Rod Slifer
Chuck Anderson
Paul Johnson
Herman Stauffer
Ronald Todd
Gail Wahrlich
Bill Wi1to
Council Members Voting "No":
A majority of the Council Members present having voted in
favor of the passage and adoption of the Resolution, the Mayor
thereupon declared the Resolution duly passed and adopted.
Thereupon, after consideration of other business to come
before the Council, the meeting was adjourned.
r .~~~ . ~.
TOWN) Mayor / - - ~
SEAL}
Attest:
1 ~
TOW (/
f/( '
6-
STATE OF COLORADO )
COUNTY OF EAGLE ) ss.
TOWN OF VAIL }
I, Colleen M. Kline, the Town Clerk of the Town of Vail,
Colorado, do hereby certify that the attached copy of Resolution
No. ~l , Series 1982, is a true and correct copy; that said
Resolution was passed and adopted by the Town Council at a
regular meeting thereof held at the Vail Municipal Building, the
regular meeting place of the Town Council in the Town, on~..
Tuesday, the 5th day of October, 1982; and that true copies of -
said Resolution have been duly executed and authenticated by the
signatures of the Mayor of the Town of Vail and myself, as Town '_
I
Clerk of the Town, sealed with the seal of the Town, and
numbered and recorded in the official records of the Town kept
for that purpose in my office. I further certify that the
foregoing pages 1 through 6, inclusive, constitute a true and
correct copy of the record of the proceedings of the Town
Council at its meeting of October 5, 1982, insofar as said
proceedings relate to said Resolution; that said proceedings
were duly had and taken; that the meeting was duly held; and
that the persons were present at said meeting as therein shown.
IN WITNESS WHEREOF, I have hereunto set my hand and the seal
of the Town of Vail, Colorado, this ~r day of `L11~, 1982.
s
TOWN} Town Clerk
tSEAL} Town of Vail, Colorado
7--
GAGE DAVISASSOCIATES GAGE DAVIS ASSOCIATES. INC.
910 TWEI•~TY EIGHTH STREET
PL.Mih'~X3 AtvD LANDSC1iPE ARC}-IITECTURE
MOUL DER. COLORADO 80303
isn'sl ~t•t7 1168
September 27, 1982
VAIL LIONSHEAD CONSTRUCTION BUDGET
I, Construction of Mall Areas 1,800,000
Overall Construction Costs Q00,000
a
2,00,000
II. Assessment District 1,000,000
General Obligation Bond 1,600,000
2,-1~00,000
a~b~~~90p
COSTS FOR ALL NEW PLAZA AREAS IN LIONSHEAD
LionsHead Center Mali
Clock Tower Square
LionsHead Court
LionsPride Court
Gondol a P,l aza
Landmark Mail
Southwest Mall Entry
test Mall Entry
East Mali Entry (to complete) .
Auxiliary Area Costs
TOTAL:1,800;000
OVERALL COSTS FOR LIONSHEAD MALL DEVELOPMENT
Utilities 190,~~17
Mohi 1 i zati on 95,3.08
Stockpiling ~57,x,
Master Electr•3cal System g8,gs5
Survey 28,532
Design & Engineering Fees 19D,212
Bond and Asszssment txnenses 150,000
TOTAL:800,000
i
GAGE DAViSASSOCfATES GAGE dAV1S ASSOCIATES, INC.
910 TWENTY EIGIiTH STREET
L = ^.-_--.- ~ _.,r~~,,,,,,~;60ULdER. COLORAdO $0303
PLANN~tdG A;d[i :.AfvD:iCAYr AFICNiTECTUflE
303- 449-1168 '
VAIL LIONSHEAD PLRZA: TOTAL ITEMIZED COST Page 1
Cost per Total Cost ~"_~,.
Task Units Quantity Uni t of Item ,.~:=±~
DEMOLITION
6" canc. slab SF 71,793_6.00 $420,758
Bomanite & standard
slab)
6" conc. curb LF 2,685 5.00 ].3,_425
around planters)
canc. stairs SF 3,172 5.00 15,860
Demolition Subtotal 460,043
I ~ -. _ . -sir
EARTHWORK
Rough grading SF 7
Trenching of planter LF
wall s
Excavation for new SF
steps
Grading for fountain Lump Sum
includes fill and
regrading}
COh:CRETE WORK
ivetiv cone, stairs ~ SF
Planter walls Face
1.5 average height} Foct
Retaining walls Face
Foat
2,727 0.84 G1,090
3,851 2.40 9,242
1,146 4.50 5,157
6440.00 6,440
arthwork Subtotal 81,929
2,630 25.00 65,750
4,239 31.00 131,437
1,573 18.OC?28,314
GAGE DAV9SASSOCIATES GAGE DAVIS ASSOCIATES. INC.
q50 TWENTY EIGHTH STREET
rrr.w..ar:.rr~~ .o.t...~~='+-=~•--=•~---«•- •~~
PLAi+iiAtJG Af~D i_AfvDSC.,F'E ARGiiTEG7URE
000LDER. GOLORADO 80303
1303) 44S•5568
VAIL LIONSHEAD PLAZA: TOTAL ITEh;IZED COST Page 2
Cost per Total Cast. r~~
Task Jni is Ruanti t.y 1lni t of Item -.
Conc. flat work SF 996 15.00 _14,940. ~'
Concrete tidork Subtotal 240,441
PAVING & SURFACING
6" sub base {for existing SF 17,438 0.74 12,904
planters being removed}
Patching existing SF 8,649 2.00 17,298
conc.
llnistone pavers SF 70,583 5.37 ~~379,568
utilizing existing
sub base}
Paving and Surfacing.
Subtotal ~ - $4J9,770
LANDSCAPING
2"Aspen ea.80 220.00 17,600
5'Blue Spruce ea.33 225,00 7,425
7'Blue Spruce ea.24 315.00 7,560
5`Lodgepole ea.24 175.00 4,200
7'l;adgepol a ea .25 245.00 6,125
9'Lodgepole ea.10 267.00 2,670
i
a
h
GAGE DAVISASSQCIATES
PLANNING AND LANDSCAPE gF~CMiTECTURE
GAGE DAVISASSOCIATES. iNC.
9t0 TWENTY EIGHTH STREET
80LiLbER, COLORADO 80303
303) 449-1188
PAIL LIDNSHEAD PLAZA: TOTAL ITEMIZED COST
Page ' 3
Cost per Total Cost
Task ~llni is Quanti t.y lJni t ~of Item
Specimen ea.lg 400.00 7,600 '
Specimen ea.6 500.00 3,000
Shrubs: 5 gallon ea.470 30.00 14,1OD
Ground Caver SF 9;055 1.75 15,846
Soil prep.Lump Sum 3,598
tine Grading Lump Sum l~ggg
Irrigation SF 23,132 0.60 13,879 „
Landscaping Subtotal 105,952
MISCELLANEOUS
Gondola Plaza fountain Lump Sum 151,250
Lighting ea.30 ~2,000.00 60,000
Speciality lighting ea.50 2DD.D0 10,000
Benches ea.40 425.00 B,OOD
Drinking fountains ea.0~1,600.OD 0_
Trash containers ea,7 400.00 Z,'80D
Signage Lump Sum 9 800
Kiosk ea.2 13,000.00 26,000
Bicycle Racks ea.2 500.00 1,000
Movable planters ea.0_1,OOD.OD 0--
Hand rails (for steps)LF L2~4D.00 9,36D
Tree grates ea.4-600.00 0-
Flag poles ea.8 1,000.00 8,000
t
y
r ^~~~,u, o ~„~'.,:oi.a ~~. _, :.;°,~,._ d .,,
i,,,
C;hGE DAVIS ASSOCIATES, 1NC.
GAGEDAViSASSOCIAT~S Se10 TWENTY EIGHTH STREF7
1zi."-__t. .. •..~,.-..~ ~
tDULDER, COLORADO 80343
PLAlJNi^ki AND IANUSCAPE AACNITECTURE
u)'S! 419 1166
VAIL LIONSHEAD PLAZA: TOTAL ITEMIZED CAST Page 4
Toi:al Cost
Task Units Quantity Cost aer unit of Item
Gondola Plaza Lump Sum $40,000.00 $40,000
sculpture
Bus shelter ea. 2 32,000.00 64,000
Miscellaneous Subtotal: $400,210
Auxiliary Areas $101,655
Grand Total $1,$00,000