HomeMy WebLinkAbout05. Dobson Arena VEAC Slide Deck 12.12.12Dobson Arena Renovation – Program
Update
| Vail economic Advisory Council
December 12, 2023
2
The Vision
Dobson Arena has evolved over the years from a pond, to a pond with stands to an
ice/events arena that has seen relatively minor updates over the years.
The Dobson Arena is a key component to the fabric of the Vail Community hosting a
rapidly growing sports community anchored by Ice Hockey as well as an event space for
key community events for over 40 years.
The facility is in dire need of an upgrade to bring the Mechanical, Electrical and Plumbing
up to code and current sustainable performance requirements
The facility must be able to function well for the next 50 years offering improved access,
bathrooms and amenities for patrons and the facility must be upgraded structurally to
ensure a responsible lasting update. As well, this plan must consider that the Dobson
will serve the community well into the future.
Dobson Arena Update – December 12, 2023
2
Dobson Arena Update – December 12, 2023
APPROVED OPTION
ENHANCED SURROUNDING SITE
NEW ROOF OVER EXISTING BUILDING PERIMETER
NEW MECHANICAL ELECTRICAL PLUMBING SYSTEMS
CREATE 6 NEW LOCKEROOMS + 2 OFFICIALS LOCKERS
ADD ADDITIONAL RESTROOM CAPACITY TO MEET CODE
NEW SOUTH AND WEST ENTRANCES
ADD NEW SOUTH FIXED SEATING
REPLACE ICE PLANT AND FLOOR SYSTEMS
NEW AMMENITY SPACES FOR FLEX USE
GU0
GU0
Site Plan
GU0
Overall Site PlanGU0
Total Budget of recommended Program on 8/1/23 $55,391,549
Budget Update - Cost Breakdown by Phase
Base Program + Accepted 8/1/23 Alternates $42,909,059
Expanded Schematic Design Program $1,661,013
Escalation/Contingency/Indirect Offsets ($1,661,013)
Total Estimated Construction Cost including Escalation of 7.09% $42,909,058
Soft Costs Including Owner's Contingency $11,482,491
Temp Ice Contribution $1,000,000
Total Budget of recommended Program on 12/5/23 $55,391,549
Dobson Arena Update – December 12, 2023
Aug. 25 –Sep.
27, 2023
Entitlement Specialist
Feb 7. –July 16,
2024
Design Development Phase
Feb. 7, 2024
Contractor Start
Feb. 20, 2024
Town Council Approve SD’s
move to DD’s
Apr. 2, 2024
Town Council 50%
DD/Entitllement Authorization
to Seek PEC/DRB Approval
July 16, 2024
Town Council Approval of DD
Price and Design; Permission to
move to CD’s
July 17– Feb.
27, 2024
Construction Documents
Feb. 18, 2024
Town Council Approval of Final
GMP & Approval to Award
Feb. 20, 2025 –
Mar. 2, 2027
Construction Phase
Dobson Arena Update – December 12, 2023
Project Milestones
2
Next steps include:
1. Issuing and RFP to General Contractors on December 11, 2023
2. Further defining sustainability funding opportunities through
available grants for the whole building
3. Reconciling our Approach and Budget after Initial Contractor Response to RFP
Submittals have been reviewed
4. Review reconciled project cost, budget and scope
5. Present General Contractor CM/GC recommendation to Town Council
6. Direct reconciled project scope to proceed to Design
Development, Entitlement submittal and review
Dobson Arena Update – December 12, 2023
2
Any Questions and Thank You
Dobson Arena Update – December 12, 2023