Design Review Board
ACTION FORM
Department of Community Development
75 South Frontage Road, Vail, Colorado 81657
tel: 970.479.2139 fax: 970.479.2452
web: www.vailgov.com
Project Name: VAILS FRONT DOOR CHANGE DRB Number: DRB060168
Project Description:
Change to approved plans as documented on the revised building permit plan set.
Participants:
OWNER LODGE PROPERTIES INC
C/O THE LODGE AT VAIL
174 E GORE CREEK DR
VAIL CO 81657
APPLICANT BRAUN ASSOCIATES, INC
225 MAIN STREET, SUITE G - 002
EDWARDS
CO 81632
License: 0000001546
05/18/2006
05/18/2006 Phone: 970-926-7575
Project Address: 174 GORE CREEK DR VAIL Location:
VAILS FRONT DOOR
Legal Description: Lot: A Block: 5-C Subdivision: VAIL VILLAGE FILING 1
Parcel Number: 2101-082-2300-9
Comments:
BOARD/STAFF ACTION
Motion By: Action: STAFFAPR
Second By:
Vote: Date of Approval: 06/01/2006
Conditions:
Cond: 8
(PLAN): No changes to these plans may be made without the written consent of Town of
Vail staff and/or the appropriate review committee(s).
Cond: 0
(PLAN): DRB approval does not constitute a permit for building. Please consult with
Town of Vail Building personnel prior to construction activities.
Cond:201
DRB approval shall not become valid for 20 days following the date of approval.
Cond:202
Approval of this project shall lapse and become void one (1) year following the date
C of final approval, unless a building permit is issued and construction is commenced
and is diligently pursued toward completion.
Planner: George Ruther DRB Fee Paid: $20.00
- Application for Design Review
Department of Community Development
- - 75 South Frontage Road, Vail, Colorado 81657
TO11A, OF li11L tel: 970.479.2139 fax: 970.479.2452
web: www.ci.vail.co.us
General Information:
All projects requiring design review must receive approval prior to submitting a building permit application. Please
refer to the submittal requirements for the particular approval that is requested. An application for Design Review
cannot be accepted until all required information is received by the Community Development Department. The
project may also need to be reviewed by the Town Council and/or the Planning and Environmental Commission.
Design review approval lapses unless a building permit is issued and construction commences within
one year of the approval.
Descr'ption~of the Request: IY\Lrc rc~,` ~ev" e f,
Location of the Proposal: Lot: Block: Subdivision:
Physical Address:
Parcel No.: 2- k t.) 012-7 Sad Z~ (Contact Eagle Co. Assessor at 970-328-8640 for parcel no.)
Zoning: S ~G s e--~ SS
Name(s) of Owner(s): k s
AP%k
Mailing Address: o d o
Owner(s) Signature(s):
Name of Applicant:
Mailing Address:
is kto Phone: `6-151335
Fax:
E-mail Address:
A
Type of Review and Fee:
❑ Signs
❑ Conceptual Review
❑ New Construction
❑ Addition
❑ Minor Alteration
(multi-family/commercial)
❑ Minor Alteration
(single-family/duplex)
m- Changes to Approved Plans
❑ Separation Request
eSsr{SI L e-aO.inAA Gs
$50 Plus $1.00 per square foot of total sign area.
No Fee
$650 For construction of a new building or demo/rebuild.
$300 For an addition where square footage is added to any residential or
commercial building (includes 250 additions & interior conversions).
$250 For minor changes to buildings and site improvements, such as,
reroofing, painting, window additions, landscaping, fences and
retaining walls, etc.
$20 For minor changes to buildings and site improvements, such as,
reroofing, painting, window additions, landscaping, fences and
retaining walls, etc.
520 For revisions to plans already approved by Planning Staff or the
Design Review Board.
No Fee
For Office-Use Only: (I~q -t
Fee Paid: Check No : - 45 - By-
Application Date: • c~~a r jZ
Planner: ~ie t u :
- - - - -
$ Phone: %'A S Z3 S S
V
I-Iri
0
r
D
col
n -B RAL I N
\tiS0 LA rrS, INC.
LAND PLANNING & COMMUNITY DEVELOPMENT
May 1, 2006
Mr. George Ruther, Chief of Planning
Town of Vail
Department of Community Development
75 South Frontage Road
Vail, CO 81632
RE: Vail's Front Door
Dear George:
The purpose of this letter is to follow-up on our meeting of April 271" at which time we
reviewed the latest plans for Vail's Front Door. Specifically, we reviewed construction
plans which in many cases depicted details that varied from approved DRB plans. In
virtually every case these refinements were either minor in nature or were consistent with
the originally design intent of approved DRB plans.
In this regard, attached you will find a DRB application for changes to approved plans for
the Front Door. All proposed changes are reflected on the plan set titled TOV Review
Submittal dated April 24, 2006.
Please do not hesitate to contact me with any questions you may have. Thank you again
for your ongoing assistance with this project.
Sincerely,
Thomas A. Braun
CC: Jack Hunn
Jay Peterson
Robert Fitzgerald
Opal Building • 225 Main Street • Suite G-2 • Edwards, CO 81632
970-926-7575 • 970-926-7576 fax • www.braunassociates.com
TOWN OF VAIL, COLORADO Statement
Statement Number: R060000627 Amount: $20.00 05/18/200601:15 PM
Payment Method: Check Init: JS
Notation: 4298/BRAUN
ASSOCIATES
Permit No: DRB060168 Type: DRB-Chg to Appr Plans
Parcel No: 2101-082-2300-9
Site Address: 174 GORE CREEK DR VAIL
Location: VAILS FRONT DOOR
Total Fees: $20.00
This Payment: $20.00 Total ALL Pmts: $20.00
Balance: $0.00
ACCOUNT ITEM LIST:
Account Code Description Current Pmts
DR 00100003112200 DESIGN REVIEW FEES 20.00
C
C
c
DRB - Resubmittal
Architectural keynotes:
General - Cover Sheet
G1. Revised sheet index
G2. Updated code summary
G3. Updated square footage summaries
General - Site
S I. Revised Chalets walls, stairs, walkways, drainage and grading to accommodate fire
protection egress
S2. Revised Chalets transformer location
S3. Revised site drainage along the west side of the Chalets and south to the mountain
road
S4. Revised site drainage along the south end of the ski yard
Sheet SD 1.03A\B\C
1. Stairs added/ walk realigned
2. Stairs removed
3. Walk realigned/ stairs to southern patio moved to south
4. Fire access stairs added between walkways
5. Stair added/ connection to walkway north of building 1
6.. Patio reconfigured/ entrance location moved (Patios were redesigned on a 4'-0"
module and as to accommodate structural columns) Patio elevations adjusted as a
result of finish floor elevations; stairs adjusted accordingly.
7. Walk realigned/ stairs redistributed
8. Patio reconfigured/ entrance location moved
9. Retaining wall added
10. Retaining wall added/ egress well created at unit 5B
1.1. Patio reconfigured
12. Patio reconfigured
13. Patio entrance location moved
14. Walkway added along road
15. Patio entrance location moved
16. Stairs removed
17. Patio reconfigured/ entrance location moved
18. Retaining wall added
AP*NI 19. Walk realigned/ stairs redistributed
20. Patio reconfigured
21. Patio reconfigured
22. Electrical transformer moved across the road from unit 3A
23. Patio reconfigured
24. Walkway added
25. Retaining wall moved to perimeter of patio
26. Retaining wall realigned/ railing added
27. Balcony shape adjusted; depth reduced
28. Patio/ planting area/ egress stairs added
29. Electrical transformer added
30. Safety rail added/ moved
31. Ventilation louvers added
32. Retaining wall added
33. Second hot tub located west of pool
34. Elevated planter bed removed
35. Railing added
36. Retaining wall/ stairs reconfigured
37. Walkway removed
38. Cooling tower added
39. Mechanical exhaust grate added
40. Mechanical louver added
41. Building 6 moved 2'-9" to east
42. Hot tub shape and location adjusted
43. Stairs along service road redesigned with regular steps
44. Pool patio elevation adjusted to accommodate new restroom finish floor
elevations
45. Retaining wall added
46. Stairs removed
47. Planting island reconfigured/ ramp removed
48. Gate removed
49. Additional stairs added
50. Entrance area rearranged/ ramp added
51. Planter reconfigured/ planter wall relocated
52. Fence/ trees relocated
53. Road/ garage entry realigned
54. Planting reconfigured
55. Planting reconfigured
56. Planting reconfigured
57. Fire hydrant added
58. New egress added
Sheet SD 1.05A\B\C
1. Street light added
2. Stair lights added
3. Stair lights added
4. Street lights removed
5. Street light removed
6. Lights added
7. Lights added/ locations adjusted
8. Lights added to retaining wall
9. Lights added to retaining wall
10. Stair lights added
11. Walkway lights moved south of walk
12. Walkway lights moved north of walk
13. Walkway lights moved north of walk
14. Lights added
15. Light added
16. Light added
17. Light moved
18. Light moved
Building A - Parking Garage & Loading Dock
Al. Revised plan layout.
A2. Added gallery connection between Lodge at Vail and Lodge Tower. See sheets
S2.01 and S2.02
A3. Added additional information
A4. Revised stone cap sloping due to coordination with grading.
A5. Revised stone veneer walls from two to one. (Previously approved by DRB)
Building B - Lodge at Vail Spa and Guestroom Addition
B l. Revised plan layout.
B2. Added gallery connection between Lodge at Vail and Lodge Tower. See sheets
52.01 and S2.02
B3. Added additional information
B4. Revised ridge height due to constructability issues.
B5. Added copper gutter and downspout.
B6. Continuation of stucco in lieu of wood siding.
B7. Replaced fireplace chimney with direct vent system.
B8. Deleted window. (to comply with Code requirement - proximity to relocated
Transformer)
B9. Revised windows layout.
B 10. Revised door layout.
B 11. Removed wood balcony railing due to constructability issues.
B 12. Revised wood railing decoration and trim, see added info on S2.02.
B13. Proposed grease exhaust stack in existing chase.
B14. Removed Utility add-on.
B15. Updated scope of work this area. (added doors in existing guestrooms at proposed
Balcony)
B16. Added door.
C
C Building C - Vail Alpine Ski Club
C 1. Revised plan layout.
C2. Added additional information. 7
C3. Added copper gutter and downspout and snow guards.'
C4. Revised chimney location.
C5. Removed chimney.
C6. Added chimney element to account for clear hoistway of elevator.
C7. Revised/updated exposed timber rafters / beams.
C8. Revised windows layout. GG~-
C9. Revised door layout.
00-1 t G
C 10. Refined design and details.
C11. Coordination with DRB approved material's Board.
C 12. Coordinated with Landscaping / Civil.
C 13. Coordinated with Structural.
C14. Coordinated with Mechanical.
C 15. Added architectural exterior lighting.
C 16. Lowered roof ridge to coordinate with building elevations.
C 17. Added enclosed space for fire control room.
Buildin D - Skier Services / Vista Bahn Park
D 1 a. Revised plan to coordinate with exterior building elevations.
Dlb. Added exterior door.
D2. Added additional information.
D3. Added prefinished metal gutter and downspout.
D4. Not used.
D5. Revised windows layout to coordinate with plans.
D6. Revised door layout to coordinate with plans.
D7. Added exposed timber rafters / beams.
D8. Not used.
D9. Refined to coordinate with building elevations and/or details.
D10. Coordinated with DRB approved material's Board.
D 11. Coordinated with Landscaping / Civil.
D12. Coordinated with Structural.
D 13. Coordinated with Mechanical.
D 14. Updated portion of exterior building elevation to coordinate with the plan and other
building elevations.
D 15. Lowered ATMs to comply with accessibility requirements.
D 16. Coordinated exhaust (mechanical) chimney on northwest elevation with southwest
elevation.
Building E - The Chalets at the Lodge at Vail
E 1. Revised garage entry. P& to
E2. Revised plan layout.
CA
E3. Revised eave and ridge heights per grading (revisions).
E4. Revised roof drainage.
E5. Revised copper chimney cap.
E6. Revised structural system and faux structure.
E7. Revised transom location.
E8. Added copper kitchen exhaust vent.
E9. Revised elevator smoke relief vent.
E10. Added mechanical vent.
E11. Revised window size.
E12. Revised elevation to show wall beyond.
E13. Revised elevation to show lower level egress door.
E14. Added light fixture location, fixture previously approved by DRB.
E15. Revised entry door elevation.
E16. Revised grade line per grading revisions.
E17. Added boiler flue exhaust.
E18. Added egress/light well.
E 19. Revised roof per elevator coordination.
E20. Added boiler intake louver.
E21. Added window.
E22. Revised Duplex 6 garage entry.
E23. Added mechanical air intake.
E24. Added garage exhaust.
E25. Added modified bitumen roof material at large crickets.
E26. USFS land exchange.
E27. Added additional information.
E28. Revised ridge height per venting detail of roof tile.
E29. Added garage egress corridor.
U
Page 1 of 2
Tom Bi
From:
To:
Sent:
Attach:
Subject:
,aun
"Mary Hart" <MHart@harthowerton.com>
"Tom Braun" <tom@braunassociates.com>
Wednesday, April 26, 2006 2:20 PM
Louvers.pdf
VFD
Tom, here is an 11x17 pdf of the louvers.
Also we tallied the landscaping and hexes where we are (due to VRDC VE efforts and weight challenges for
the evergreens, please note there are some quantities that are LESS than what DRB approved.)
It wouldnt bother me to have to add some material !
drb approved
CD set
Total Evergreens:
63
55
Total Aspens:
235
291
Total Shrubs:
565
1,114
Total perennials:
5054
4056
On Marabou, have you had a chance to think about how is the color designation of the lots can be shown?
Please let Andrew know we would need it by tomorrow afternoon for hte meeting on Friday.
Thanks
Mary
Mary Hart