HomeMy WebLinkAboutB06-0018-Plan Review CommentsColorado Ins ecfiionഀ
AGENCYഀ
REVIEWED BYഀ
J U L 10 2006ഀ
COLORADO INSPECTIONഀ
AGENCYഀ
COLORADO INSPECTION AGENCY PLAN REVIEW COMMENTSഀ
TO: Contractor Architectഀ
Hyder Construction 4220ഀ
Doug Thompson Randy Hartഀ
EMAIL: dthomson(a).hyderinc.com rhart .4240arch.comഀ
FAXഀ
NUMBER OF PAGES:ഀ
20ഀ
FROM:ഀ
Matthew Royerഀ
DATE:ഀ
03/10/2006ഀ
BUILDING PERMITഀ
B06-0018ഀ
OWNERS NAME:ഀ
Vail Resorts Co.ഀ
SITE ADDRESS:ഀ
Building A and Siteഀ
SUBDIVISION:ഀ
Mill Creekഀ
OCCUPANCY GROUP:ഀ
S-2ഀ
TYPE OF CONSTRUCTION:ഀ
I-Aഀ
NUMBER OF STORIES:ഀ
3ഀ
Engineerഀ
Monroe & Newell Engഀ
The design documents submitted for this project have been reviewed for compliance with the locallyഀ
adopted codes and amendments. The following comments must be addressed before a buildingഀ
permit is issued.ഀ
For processing:ഀ
Please submit (2) complete sets of revised construction documents containing the requestedഀ
information or plan revisions with all revisions clouded or otherwise identified.ഀ
Please respond in writing to each comment by marking the attached list or creating aഀ
response letter. Indicate which plan sheet detail specification or calculation shows theഀ
requested information Please send revisions to the attention of the plans examiner with theഀ
building permit application number noted.ഀ
Responses such as "will comply with code" are not adequate. Revised drawings mustഀ
clearly show code compliance.ഀ
A RESPONSE LETTER MUST BE INCLUDED WITH THE REVISED PLAN SUBMITTAL.ഀ
Please be sure to include on the resubmittal the engineer's or architect's "wet" stamp, signature,ഀ
registration number and date on the cover page of any structural calculations, all structural detailsഀ
and structural sheets of the plans For commercial or multi-family projects all sheets of the plansഀ
must be stamped.ഀ
C:\Documents and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018. DOC Page 1 of 20ഀ
BUILDING DEPARTMENT COMMENTS:ഀ
Common Project Comments: (CPC are attached to each permit comment letter)ഀ
1. Land Swap with US Forest Service must be complete prior to final approval and issuance of theഀ
Building Permit.ഀ
2. When plans are resubmitted for review; complete sets of plans for each building which includes theഀ
addendum sheets. Separate addendum packets will not be accepted and approved for initialഀ
permitting.ഀ
3. Preliminary plan review meetings had discussion regarding the submittal of Memorandum ofഀ
Understandings (MOU). MOU's defined in these meetings would be "used to define or clarify the useഀ
of a code section, agreement to the installation of a system not covered specifically by the code orഀ
clarify the use or component of a building. None of the agreed upon MOU's were submitted forഀ
review. Please provide the following MOU's for review:ഀ
a) Use of assumed property lines and fire separation distance.ഀ
b) Fire command roomഀ
c) Smoke management systemsഀ
d) Opening between parking garage and Lodge Tower parking garageഀ
e) Fire separation between the new building and existing buildingsഀ
f) Use of 508.2 for creating separate buildings as it relates to each buildingഀ
g) The separation between One Vail Place and new Skier Servicesഀ
4. Preliminary plan review submittal meetings had discussion regarding the submittal of Administrativeഀ
Modifications (AM). AM's as defined in these meetings would be based on International Buildingഀ
Code Section 104.10. Where practical difficulties are involved in carrying out the provision of thisഀ
code, a modification to the code may be granted by the building official after justification that theഀ
modification will not lesson health, accessibility, life and fire safety, or structural requirements. Theഀ
following AM's have been discussed and are being implemented into the plans. Please provide theഀ
following or amend plans accordingly to comply with the code.ഀ
a) Separation between Chalet buildingsഀ
b) Elimination of elevator smoke doors at residential levels of the Chalet buildingsഀ
5. Be sure to amend the Fire & Life Safety Report as necessary when changes are made to the plansഀ
that may affect the discussions made by the Report.ഀ
6. Provide a precise site plan showing exact locations of assumed property lines. If locations of assumedഀ
property lines are close enough to exterior walls to require rating of walls and opening protection,ഀ
provide details.ഀ
7. Fire and Life Safety Report states the use of 1 hour fire walls per IBC Table 705.4. This table doesഀ
not allow for 1 hour fire walls anywhere. Please clarify.ഀ
8. Fire walls are called out in the fire and life safety report to separate buildings. What is the purposeഀ
and use of the fire walls and the separations? Is it to separate property owners?ഀ
It appears that fire separation distances are being used to determine the ratings for the wallsഀ
identified as fire walls between the different building and spaces. Our interpretation of this section isഀ
that once the 3 hour separation is used to make a separate building then everything that is notഀ
separated by a fire wall per 705.4 will be considered as one building.ഀ
9. Accessibility requirements do not appear to be included within any plan for this project. Pleaseഀ
amend plans to include the following:ഀ
a) Accessible parking spaces and loading zones.ഀ
b) Accessible route from the parking and loading zones to the buildings.ഀ
c) Accessible routes to each building on the site which are required to be accessible.ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018. DOC Page 2 of 20ഀ
d) Signage details for parking, striping, routes, restrooms, etc.ഀ
e) Restroom details for fixtures, grab bars and accessories.ഀ
10. Amend plans to include stair signage plan, details and identify the location of the signage. Many ofഀ
the exit enclosures require the occupants to travel up to get to exit discharge. Clearly identify theഀ
direction of travel to the exit discharge.(IBC 1019.1.6)ഀ
11. Amend plans to include gates located at the level of exit discharge to eliminate occupants of theഀ
building from entering an enclosure and passing by the level of exit discharge. (IBC 1019.1.6)ഀ
12. Elevator door which do not open into a lobby need to be provided with a smoke control door inഀ
accordance with IBC Section 715.3.5.3ഀ
13. Clearly identify the location of safety glazing per IBC Chapter 24 either in the window schedule or onഀ
the plan.ഀ
14. The size of main elevator cars used for fire/emergency access needs to be determined by the Townഀ
of Vail Building and Fire Departments. Standard 24" x 76" required by code will not accommodate theഀ
stretchers used by emergency personnel. Please confirm the required size.ഀ
Architectural Comments:ഀ
Site Comments:ഀ
15. Coordinate pool equipment room in Bldg B with pool piping shown on Site Plan sheet W1.0ഀ
16. Provide compliant barrier to pool and spa areas. Change detail reference to L207. L208 is used forഀ
pool coping as called out on L202.ഀ
17. Fence shown on L207 shows the bottom of the fence to far above grade. Max distance betweenഀ
grade and bottom of fence 2 inches. (IBC 3109.4)ഀ
18. Sheet L202 references sheet L209, but this sheet does not exist. Please amend plan.ഀ
19. Amend plans to show gates compliant with the pool barrier requirements. (IBC 3109.4.1.7)ഀ
20. Boulder wall used at waterfall of pool shall not be climbable or an approved barrier shall extendഀ
around boulder wall. Show detail of wall or amend barrier to encompass this area.ഀ
21. Some of the exterior stairs from the lift ticket area only show handrails on one side. Amend plans toഀ
show handrails on both sides of all stairs throughout the site. (IBC 1109.11)ഀ
22. Sheet L102 for the chalets show some exterior stair locations with handrails on only one side. Handഀ
rails are required on both sides of stairs per 1009.11 2003 IBC.ഀ
23. Sheet L102 calls out Stairs and Handrails on sheet L107. Sheet L07 does not exist.ഀ
24. Sheet L202 calls out fireplace detail on L208. This detail is on L207. Correct drawings to specifyഀ
which sheet fireplace detail is located.ഀ
25. Sheet L207 states exterior gas fireplace. Provide manufacturers listing for exterior gas appliance. Alsoഀ
Sheet L202 has wood storage next to the fireplace called out as gas. Clarify.ഀ
26. Detail for all exterior stairs does not meet profile requirement of 1009.3.2 IBC 2003.ഀ
CADocuments and Settings\mroyer\My Documents\Plan ReviewWront Door\tov-b06-0018. DOC Page 3 of 20ഀ
27. There are changes in elevation of one step coming from west side of ski club down to walkway thatഀ
require a handrail unless tread depth of elevation change is the same or greater than the dimensionഀ
of a required landing. (IBC 1009)ഀ
28. Sheet L302 calls out stair and handrail details on L307. There are no stair and handrail details onഀ
L307. Clarify.ഀ
29. Amend plans to include all component which will be required and specified within the Administrativeഀ
modification for the opening between the Parking Garage (2 places) and the existing Lodge Tower.ഀ
The existing Lodge Tower plan has identified the parking garage as Type I-B. This needs to be takenഀ
into consideration when exercising IBC section 508.2. Same type of construction was used during theഀ
pre-submittal meetings that discussed the separation. Please address the type of constructionഀ
separation and opening protection accordingly. Please coordinate plans and design with the Lodgeഀ
Tower designers.ഀ
Mechanical Comments:ഀ
30. Provide positive pressure and outside air to valet booth. (IMC 404.3)ഀ
31. How is pool and spas being heated? There are no boilers shown in equipment room in bldg B. onഀ
P201.ഀ
32. Where is the gas piping for the fountain coming from? Sheet L308 is referenced and does not exist.ഀ
33. Spec Manual calls out CO detector to send alarm to panel at 35 PPM. If this setting also activatesഀ
exhaust fans it must be lowered to 25 PPM per 2003 IMC sec 404. Show compliance with 2003 IMCഀ
for fan activation.ഀ
Plumbing Comments:ഀ
34. Clarify where continuation of plumbing for pool to equipment room is shown.ഀ
Electrical Comments:ഀ
35. TVSS needs to have short circuit rating equal to or greater than available fault current. Provide ratingഀ
and calculation for TVSS. (NEC 285.6)ഀ
36. Provide nameplate information for generator. (NEC 445.13)ഀ
37. Feeder 50 to panel SLW should be 45.ഀ
38. Panels SLID, W and E not identified on panel schedule pages.ഀ
39. Panic hardware required on electrical room (A109) doors. (NEC 110.26(C)(2))ഀ
40. Feeder 51 must be 2"C minimum. (NEC table 5 and 4)ഀ
41. Grounding electrode conductors need to be bonded at both ends if installed in metallic conduit. (NECഀ
250.92(A)(3))ഀ
42. Maintain clearances around electrical equipment. (NEC 110.26 & 450.21)ഀ
43. Provide performance test in accordance with NEC 230.95(C) for GFCI service equipment.ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018.DOC Page 4 of 20ഀ
44. Are electrical rooms being separated with fire rated assemblies in lieu of the sprinkler system in thatഀ
room?ഀ
Energy Code Review:ഀ
Envelope Com Checkഀ
45. The IECC requires all conditioned spaces to be included in the building envelope. The parking garageഀ
and storage areas are being heated. We are unable to determine the areas used in the COM checkഀ
for conditioned spaces. Provide calculations for all areas used in the envelope COM check. If theഀ
parking garage is not considered a conditioned space then vestibules are required for spaces that areഀ
conditioned and open into the garage. (IECC 802.3.6)ഀ
Mechanical Com Checkഀ
46. The mechanical system list is incomplete for all areas which have conditioned space. Please provideഀ
more information.ഀ
47. Provide load calcs. per 1997 ASHRAE fundamentals or equivalent.ഀ
Electrical Energy Checkഀ
48. There is insufficient information to show compliance with IECC section 805.5.ഀ
Site Structural Comments:ഀ
Note: structural comments are numbered "S1,S2...... and are also given a designation with regards to the topic, as follows:ഀ
DC = design criteria; F= foundations; D = drawings; C = structural calculations; LS = lateral system.ഀ
Site Comments:ഀ
S1. D Specs 02925 appear to indicate that construction of EPS should not be done under "highഀ
winds", however wind speed is not defined. Suggest place notes regarding this requirement on theഀ
drawings and potential mitigating construction measures.ഀ
S2. D Specs also indicate combustibility and fire retardant be used - suggest plate notes to thisഀ
effect on the drawings.ഀ
S3. D SF101: verify lower strength EPS is correctly shown what appears to be underneath the Skiഀ
Club, Volume 4 drawings. Seems a higher strength is required for bearing.ഀ
S4. D SF sheets: It seems a finished elevation @ top of EPS would be useful for construction, it isഀ
not clear how the elevation will be correctly achieved with the current drawings.ഀ
S5. F SF sheets: verify pavement / subgrade above the EPS under roadway (20 psi) has beenഀ
designed to span between HS-20 tires, or depth is sufficient to distribute loads such that 20 psi is aഀ
sufficient strength under the roadway.ഀ
S6 F SF sheets: It appears EPS fill has not been designed underneath Volume 6 Chalet (Bldg E).ഀ
It is not clear how backfill is intended to be placed at these structures; in some locations Bldg E bearsഀ
half on the concrete tunnel and half on presumably engineered soil backfill. Please confirm that Bldg.ഀ
C:\Documents and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018. DOC Page 5 of 20ഀ
E bears on engineered backfill. Verify deflection compatibility of Bldg. E bearing on top of tunnel andഀ
backfill and associated differential deflection.ഀ
S7 DC Sheet L202: FOR to verify that various landscaping structures such as boulders, ponds,ഀ
stone walls, pavers, and other superimposed dead loads have been appropriately considered in theഀ
structural design; verify any concentrated bearing on EPS filler (i.e. such as due to any retainingഀ
walls, 6/1_205, or massive stone structures, 3/L.208, etc.)ഀ
S8 F 7/L.207: verify EPS will not be damaged over time due to fireplace heat.ഀ
S9 D A/W4.8: verify reinforcing at base of liftഀ
Building A Structural Comments:ഀ
Note: structural comments are numbered "S1,S2...... and are also given a designation with regards to the topic, as follows:ഀ
DC = design criteria; F= foundations; D = drawings; C = structural calculations; LS = lateral system.ഀ
General Structural Comment: Due to the inherent connectivity between the various structures in this project, there may beഀ
comments from this Volume's details in other Volume's comments, and vice versa. Note also that this review and eventualഀ
approval does not permit the violations of any section of the building code, or any other ordinance or State law.ഀ
S1. DC S001 Note that City of Vail requires 90 mph basic wind speed (IBC 2003, ASCE 7-02, 3sഀ
gust wind speed). It appears 100 mph basic wind speed was used in the designs, pleaseഀ
verify / confirm (typical all project volumes).ഀ
S2. F Soils report, page 33-34 recommends against supporting the parking structure on aഀ
combination of natural soils and bedrock, due to guaranteed differential settlement betweenഀ
the two supporting materials. The soils report goes on to recommend that foundation bearingഀ
elevation be lowered to allow the entire foundation to be supported by bedrock, or aഀ
combination spread footing (on bedrock) and deep foundation system (on natural soils) toഀ
reduce differential settlement. The structural drawings indicate "footing elevations may needഀ
to be lowered due to soil conditions." This note is unclear, if bearing on bedrock is required,ഀ
please change the note to clearly state this requirement. If bearing on bedrock is not requiredഀ
throughout, please explain the structural design philosophy used to mitigate the differentialഀ
settlement issue.ഀ
S3. F Soils report, page 26-27 discusses temporary and permanent dewatering for this site.ഀ
Appears that the vault and sump basin on S101, approx. @ grids 12.8/L.5 is part of theഀ
dewatering system. 12 ft. deep is unclear, provide a top of mat slab elevation. Consider theഀ
need for a hatch in the structural lid, provide reinforcing around the hatch. Provide structuralഀ
lid for precast sump (if not provided by manufacturer) . Note that lids over sumps seem toഀ
require HS-20 or other truck loading not the typical 50 psf garage loading - verify this loadingഀ
has been coordinated and will be verified in the review of the precast sump pit. Verifyഀ
buoyant forces vs. self weight.ഀ
S4. F Soils report, page 38, items 7 & 8 discusses underpinning of existing structures adjacent toഀ
new construction. Please discuss how the existing structures will be supported duringഀ
construction and permanently. Verify that vertical surcharge loading has been applied to theഀ
below grade permanent foundation walls and parking structure as appropriate. Verifyഀ
underpinning system does not conflict with the new foundations for this parking structure.ഀ
S4A F Calculations (p. FW5) don't appear to include soil full height at existing building. This appearsഀ
correct west of gridline 18, as slab on grade / offices will be constructed here, however westഀ
C:\Documents and Settings\mroyer\My Documents\Plan ReviewWront Door\tov-b06-0018. DOC Page 6 of 20ഀ
of the ski club foundation walls, there appears to be soil for two stories tall, creating a twoഀ
span condition at some exterior concrete walls. Verify soil backfill height and verifyഀ
calculations. Provide calcs for 2-story at-rest retaining wall conditions. See also commentഀ
S4B.ഀ
S4B. F/ LS It appears that the ramp at the south end, as well as the permanent shoring at the southഀ
side create an unbalanced lateral soil loading at the parking structure, at the upper parkingഀ
level, and lid level. Verify that concrete diaphragm and concrete shear walls below have beenഀ
designed to resist this unbalanced soil lateral loading. Verify drag loads / connections fromഀ
diaphragms to concrete walls. Provide calculations.ഀ
S4C. F/LS It seems that the parking structure compressible material is required between theഀ
permanent shoring wall and the parking structure to allow the two systems to behaveഀ
independently, and to avoid the permanent soil retaining system from loading the parkingഀ
structure. Details 13&14/S004 do not indicate this is being done. Also, it appears fromഀ
13/S004 that the new concrete walls will be constructed directly against the permanentഀ
shoring system, which it seems would move into the structure over time. Please comment.ഀ
S5. D S001: Column Schedule. Schedule includes (2) line items "Configuration". These variousഀ
configurations do not seem to be defined anywhere in the documents.ഀ
S6 D S001: Column Schedule. Reinf. Lap splices are shown for f'c = 5000 psi. However concreteഀ
general notes indicates concrete with f'c = 3500 & 4000. Lap splices for these lower strengthsഀ
are longer than those for f'c = 5000. Please check.ഀ
S7 D S001:Typical Column Details do not seem to be cut in the documents. Also, alternateഀ
longitudinal bars must be supported by the corner of a tie and bars spaced greater than 6"ഀ
clear must also be supported by the corner of a tie. (ACI 318 7.10.5.3)ഀ
S8 D S001: Section 1 Stud Rail Detail. Section AA indicates the rails extend several inches into theഀ
column. These extensions into the columns is not required, besides they will foul on theഀ
column vertical rebar.ഀ
S9 D S002: Beam Reinforcing Layout.:ഀ
a) Provide dimensions should be provided for all rebar cut off points. (1/4 span points do notഀ
align with rebar end locations).ഀ
b) It appears a cantilever layout is required- see comment S163.ഀ
S10 D S002:Section 1. Section 1 is cut thru Bm B10 on Sheet S108.ഀ
a) Section does not accurately show bars per schedule (bot bars are too many, top bars notഀ
shown).ഀ
b) Is the top part of what could be part of B10 included in 50" vert depth? Does not appearഀ
dowels to slab / beam above would meet shear flow requirements (VQ/1), please confirm.ഀ
If top part of the beam is indeed part of the beam B10, stirrups should be designed acrossഀ
the con'st joint to carry the full shear.ഀ
c) Verify only half T-beam width has been used for compression, due to slab step (dependsഀ
on answer to b) above)ഀ
d) It seems that bottom bars from the beam on the left side should extend a min 6" into theഀ
supporting beam, similar to slabs, per ACI 318 Figure 13.3.8.ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018. DOC Page 7 of 20ഀ
S11 D S002:Section 2. Section 2 is cut thru BM B12 on Sht S108ഀ
a) Bottom & top bars do not match those shown in the beam schedule.ഀ
b) Stirrups through the horiz const joint should be designed to carry the full shear, pleaseഀ
confirm.ഀ
c) Details 1 and 2 appear at odds, some clarifying notes are required to define the requiredഀ
dimensions in each case.ഀ
S12 D S002: Section 4 & 5.ഀ
a) See comment S11, similarഀ
b) Dowels from supporting beam to supported beam are not identified. It appears that theseഀ
dowels much carry the entire beam reaction thru shear friction, please confirm. See Skiഀ
Club (Vol 4) comment S29.ഀ
S13 D S002: Beam Schedule: Please check number of top & bot rebar with beam widths & ACI minഀ
clearances i.e. beam B18 (ACI 318 7.6).ഀ
S14 D S003: PB1 & PB2 PB 1-1 & PB7-2 and PB 8-1 and P138-2 continuous spans which are notഀ
clearly represented in your PT layout, however calculations seem to satisfy continuous beamഀ
design. Please verify that beams are represented correctly on the drawings. Tendon drapeഀ
transition is not clear, P137-1 and P138-1 shows same drapes at both ends which areഀ
interpreted as conflicting with the drapes given at the left ends of P137-2 and P138-2. Pleaseഀ
verify drawings and PT beam schedule.ഀ
S15 D S003: P139 & PB10 with variable depths appear to be missing PT info. Also, because of theഀ
variable depths the A dimension will not be valid at both ends of the beams. It is suggestedഀ
that a dimension J be added. Please consider and revise as necessary to meet code.ഀ
S16 - not usedഀ
S17 D S004: Section 1. Indicates what appears to be a layer of free draining granular material belowഀ
the S06. This material is not otherwise defined? Pis define, typical all sections. Verify ifഀ
vapor retarder is required.ഀ
S18 D S004: Section 9. Will 3'-0 square isolation pour fit around column, please verify.ഀ
S19 F S004: Section 10. Is drainage a consideration in the structural design for retaining wallഀ
(typical all walls)? Verify Lateral pressures include hydrostatic pressures as req'd, the garageഀ
extends well below the measured water table per soils report. Also, wall scales 1'-2 thk, butഀ
plan says 1'6. Which is correct?ഀ
S20 F S004: Section 11, 12, 14. Footing rebar is not identified, pis verify. Define rebar length &ഀ
spice length. (Typ as occurs)ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018. DOC Page 8 of 20ഀ
a .ഀ
S21 F,D S001: concrete general notes: consider using air entrainment at loading dock slabs and otherഀ
garage level concrete that will be exposed to weather- clarify notes as required.ഀ
S22 F,D S004: Section 5, 6. Provide min horiz. Reinforcing in fndn. Walls (ACI 318 14.3).ഀ
S23 F,D S005: Section 1.ഀ
a) The area between these walls appears to be occupied by concrete stair, not a SOG at theഀ
low level shown in this section. Check building code for max number of risers allowedഀ
without an intermediate landing.ഀ
b) Outside wall scales V-6, is shown as V-10 on plan? Inside wall scales V-2 is shown V-4ഀ
on plan?ഀ
c) Do the dowels from the footing extend to the top of the wall as indicated - verify graphics.ഀ
S24 F S005: Section 2. Horizontal rebar in wall not indicated.ഀ
S25 D S005: Section 3. Are #5 @ 4'-0 in the CMU Vertical or Horiz? This notation occurs typicallyഀ
@ most CMU, please clarify.ഀ
S26 F S005: Section 4. Same as section 3. Top rebar short way in this strup ftg's not defined, verifyഀ
req'd.ഀ
S27 D not used.ഀ
S28 D S005: Section 8. Define what appears to be a beam w/ties over a wall opening into the airഀ
tunnel.ഀ
S29 D S005: Section 9. It's very tight to use (2) layers of rebar in an 8" thk wall. Verify tolerancesഀ
are practical and verify ACI tolerances & Min cover are met (ACI 318 7.6 & 7.7)ഀ
S30 F S005: Section 10. Consider drainage behind this retain. Wall. Either weep holes or contഀ
drain to daylight.ഀ
S31 F S005: Section 10, 11. Where are elevation of the ledges defined? #8 is not developed for fullഀ
tension capacity over V-1" embedment -verify reinf.ഀ
S32 F S005: Section 10, 11. Verify details 9, 10, 11 are cut on plan. Verify top of retaining walls areഀ
shown.ഀ
S33 D S005: Section 12. Indicate rebar in this section.ഀ
S34 F S101: Bldg A fndn plan. Provide a section @ west - most wall on this sheet; add gridlines.ഀ
S35 F S101: Provide a foundation section thru the east wall adjacent to the tempഀ
retaining wall at the 12'-9 footing projection. The footing, reinf, thickness, is not defined.ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018.DOC Page 9 of 20ഀ
S36 D S101: What is elevation of SOG in the vicinity of 12.3 & L.5 (Loading Dock)? Provideഀ
max/min elevations on plan.ഀ
S37 D S101: Detail 6/S005 cut at the stair wall near Q.5 10.8 is not correct. Fix callout.ഀ
S38 D S101: Detail 6/S005 cut at the stair wall near L.5 16.5 in not correct. Fix callout.ഀ
S39 D S101: What is the top of footing elevation at the elevator near L.5 16.5? Is the combinedഀ
footing below the stair and col C14 all at this lower elevation? If so, define backfill SOG @ഀ
stair (detail cut 6/S005 is incorrect?). The 3'-0 detail at east side of stair is not well placed toഀ
define dimensions.ഀ
S40 D S101: Bldg A fndn plans. Missing detail ID @ 10.8 K @ footing.ഀ
S41 F S101: Bldg A fndn plans. There are (2) columns, C1 & C3 on an F17 footing (west side ofഀ
sht) which may or may not be in the footing schedule. This footing scales 11' x 16'. The C3ഀ
cols on lines 14.3 & 12.9 are on F11 footing which are 16'-3 & 16-3. This does not lookഀ
consistent. Please clarify drawings.ഀ
S42 D S101: Bldg A fndn plans. None of the foundation walls or foundations off grid appear to haveഀ
dimensions. Indicate on plan where dimensions can be found (i.e Arch drawings).ഀ
S43 F S101: Bldg A fndn plans. Footing F22 is not in your footing schedule.ഀ
S44 F S101: Bldg A fndn plans. Footing F19 thru F22 are called out on plans but are not included inഀ
the footing schedule. Revise footing schedule.ഀ
S45 F S101: Bldg A fndn plans. Footings F16& F17 seemed to have been graphically combined inഀ
the footing schedule so as to be unreadable. Revise footing schedule.ഀ
S46 F S101: Bldg A fndn plans. Reinforcing in F1 not indicated. Provide reinf.ഀ
S47 F S101: Bldg A fndn plans. Footings at (3) C3 columns on line Q3 are not identified on the plan.ഀ
S48 D S101: Bldg A fndn plans. Seems you need an elevator separator beam between the doubleഀ
elevator near 10.8 Q.5; please verify (typical all double car shafts).ഀ
S49 F S101: Bldg A fndn plans. Ftg F18 in footing schedule reinf. is not noted top, bot or whichഀ
way?ഀ
S50 D 7/S302: verify spacing of 3'-0" on embed - seems large for a 24k truck loading - also pleaseഀ
verify L4x4x3/8 for the max 24k truck point loadingഀ
S51 D S101.5 Much of this sheet is identified on S102 - suggest provide gridlines & match lines forഀ
clarity.ഀ
S52 F S101.5 Provide sections (details) @ curved retaining walls, NW area.ഀ
S53 F S101.5 The conc wall on line R is dimensioned as 1'-6 on the west and 1'-2 on the east end?ഀ
Fix dimensions (seems 1-'6" is correct.)ഀ
S54 D S101.5 Section 10/S004 at the wall @ S.W. side appears to be incorrect.ഀ
C\Documents and Settings\mroyerNy Documents\Plan Review\Front Door\tov-b06-0018. DOC Page 10 of 20ഀ
S55 F S101.5 It appears that you have anew footing below a C9 col that extends a significantഀ
distance below an existing bldg. Pis check, or design & show underpinning as required.ഀ
S56 F S101.5 Verify 23'-4" wall/slab step @ ramp entrance (8162'-8" to 8186'-0"); Detail 2/S005ഀ
does not show this. Fix dimensions/clarify.ഀ
S57 F S101.5 Show ftg rebar/section at CMU "C" wall @ existing bldg.ഀ
S58 F S102 Provide section thru new chase North of line R. Provide details at junction with existingഀ
concrete chase.ഀ
S59 D S102: Section 6/S003 cut near line U.5 in the NE part of the sheet is incorrect.ഀ
S60 D S102 Provide grid lines for unidentified col. Lines, or provide dimensions.ഀ
S61 F S103 General Comment: Wall strip foundation reinforcement does not appear to be calledഀ
Out anywhere on this or other sheets? Pis provide or clarify drawings.ഀ
S62 F S103 Sand and oil interceptor needs further definition: footing; walls; lid; location.ഀ
S63 F S103 Need detail thru 1'-6" thk wall near line 17 & @ sections thru 1'-6" conc wall @ westഀ
end of area.ഀ
S64 D S103 Openings seem to be shown south of the cols @ the gridline one bay North of theഀ
exterior wall. Are these openings thru the SOG below or openings overhead? Pis clarify.ഀ
S65 F S103 Verify Min 48" frost depth is achieved @ exterior/exposed loading dock areas - someഀ
footing elevations are not identified, ref. detail 5/S004 also. Consider corrosion of SOG reinf.ഀ
due to salts & temp effects.ഀ
S66 C Wall beam calculations B1-B84 contain much information that the drawings S201, S202, S203ഀ
do not seem to reflect. For example, calcs page B16 shows different top and bottomഀ
reinforcing, as well as a seemingly very important pilaster below a large beam, and #5x60"ഀ
diagonal bars at corners and pockets. The pilaster is not detailed on the structural drawings.ഀ
Please coordinate required reinforcing per calculations with the drawings, drawings appearഀ
incomplete.ഀ
S66a D Wall beams typically have a slab connecting in at the top of the beam, providing lateralഀ
bracing of the compression flange, however at the bottom of the wall beam, typically no slabഀ
exists. Verify that sufficient lateral bracing restraint is provided at negative moment regionsഀ
where the bottom of the wall beam is in compression, i.e. WB4 at the intermediate columnഀ
support.ഀ
S66b D WB4, S202: verify #8 stirrups at the supported beam perpendicular to the wall - the radius onഀ
these bars is quite large such that they can not be placed as drawn, and it is not clear whatഀ
the purpose is for these bars is. Section 16/S302 cut on plan at this location does not showഀ
these #8 stirrups.ഀ
S66c D 16/302: W134 detail: verify direction of shear friction hook; as bar elongates concrete cover willഀ
burst out at this location if not extraordinarily well developed. See ACI figure R11.9.2 (similarഀ
to corbels). Verify hook development length in the wall and development length into theഀ
beam, this information needs to be shown in the detail.ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018. DOC Page 11 of 20ഀ
S66d. D S202: W134 elevation apparently defines the top & bottom beam reinf. req'd for all beams:ഀ
Suggest place the required rebar on all elevations; note calculations B17 show 10 #10ഀ
bottom, and (8) #10 top, different than called out on S202, please verify reinforcing. Also,ഀ
calcs do not seem to reflect the large notch in the main span; this notch needs dimensions forഀ
depth, width, and location along span.ഀ
S67 D S104 slab to wall connectors are not detailed. Pis show a detail. See comment S66c.ഀ
S68 D S104/S201 Thickness of wall beams (WB#) is not shown on plans or on wall elevations.ഀ
Suggest provide wall beam thicknesses on plan.ഀ
S69 D S104 Bms @ line L are not identified - show on plans.ഀ
S70 D S104 This is the first sheet where "wall beams" are identified. The drawings do not identifyഀ
which way the elevations are taken. These elevations are also do not include grid lines whichഀ
could be used for orientation. These graphics could lead to erroneous interpretation, pleaseഀ
check. See comment S66.ഀ
S71 D S104 Defining sections seem required thru these wall beams. Note that there are no fullഀ
height sections cut thru these very important wall beams, please consider.ഀ
S72 D S105 Regarding the various 5" slab on grade over existing building North of line 9, suggestഀ
clarify if this a new or existing slab. Indicate if demo of (E) SOG is req'd - verify any demoഀ
does not compromise the existing structure.ഀ
S72 D S105 Additional rebar shown in 12" slab @ line 21.3. Is this "typ" additional reinf typ @ lineഀ
21.3 or line N or typ at all lines within the 12" slab area? If typ @ all lines within 12" slabഀ
shouldn't the bottom lengths very depending on the spacing of the columns.ഀ
S73 D S105 New 8" SOG south of L: do you want control joints? If so please define the spacingഀ
and depthഀ
S74 D S105 Seems you need a defining section thru the top of the conc wall at the north tunnel wallഀ
at rectangular columns / PT beam / flat slab / vertical wall intersection btwn N & L.ഀ
S75 D S105 Does section 6/S004 apply at what appears to be a loading dock north of Line R nearഀ
line 25? Verify.ഀ
S76 D S105 Pis provide a section thru the trench drain north of line R at the west end. See previousഀ
comment re: wall slab step.ഀ
S77 D S105 Col/bm details at lines 24, 23, & 22 seem complicated. A section or description isഀ
required for checking.ഀ
S78 D S105 Area south of line L has 6" steel studs @ V-4 o/c. What structural sheathingഀ
is on top of these steel studs? Define/detail connection to CMU & conc walls.ഀ
S79 D S106 Section 5/S302: Cut thru a conc wall in the NW area of this sheet appears to beഀ
incorrect in that it does not represent plan conditions. Pis Clarify.ഀ
S80 D S106 Beams B18 scales 36" wide, however bm schedule says 42"? Pis clarify.ഀ
S81 D S107 Refer to wall beam WB4.ഀ
a) Plan says bot wall @ 8168'-6 but elevation on sht S202 says bot of wall is @ 8169'-0.ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018. DOC Page 12 of 20ഀ
b) A conc col near the north end of W134 is not orthogonal to the beam. Rather, it is on aഀ
skew to the wall. This situation requires a detail: col rebar.ഀ
S82 D S107 Should wall beam WB8 framing between WB8 & WB5 be corrected to read W136?ഀ
S84 D S108 Galy. Gating @ skier services does not include snow drift from bldg geometry . Pisഀ
Verify.ഀ
S85 D S108 There seems to be a pool btwn R & N @ west end - How deep? Verify water loads areഀ
considered.ഀ
S86 D S108 There seems to be 8 or 9 conc bms @ slab step & @ pool edge in the west end of thisഀ
floor that do not have a mark or design? Call out beams; provide section @ step.ഀ
S87 D S108 Is beam B24-9 followed by B24-10 or is the short bm a cantilever. Does this cantileverഀ
bm support the skewed unidentified beam? Pis clarify.ഀ
S88 D S108 Is the 18" thk slab near 16.5 @ P reinforced with #6 @ 12" ea way top and bottom asഀ
stated in note 4 on sht S105? Added reinf. Is shown at one col & is said to be typical on n/sഀ
col. Lines, however it is unclear if this means typical @ e/w col lines or typ in each direction?ഀ
Pis clarify.ഀ
S89 D S108 A type stud rails are shown at one col. Are these stud rails typ at cols; clarify.ഀ
S90 D S108 North West area: There seems to be a missing east/west beam between (2)ഀ
unidentified conc. Beams; clarify.ഀ
S91 D S108 Verify shear friction for 100% of shear loads for the following beams (see ski clubഀ
comments)ഀ
B11 -Span 1 & Span 3ഀ
B10 -Span 1ഀ
B12 -Span 1ഀ
B9 - South End.ഀ
(Ref. 16/S302) Verify dowel development length - seems also vert dowel should be turnedഀ
downwards, ref. comment S66c.ഀ
S92 D S108 It is unclear what supports intersecting bms B6 with B11, span 1, at slab edgeഀ
illustrated by detail 9/S303?ഀ
S93 D S108 Verify Edge Strip reinf @ cantilever edge is defined, see 9/S303.ഀ
S94 D S109 Bm @ west end of pool is not identified?ഀ
S95 D S109 Bms B13, B14, B15 - Span 1 are cantilevered from B13, B14, B15 Span 2 instead ofഀ
as noted in the beam schedule- please verify schedule.ഀ
S96 D S109 Detail 14/S301 is cut on S109. This detail seems to define new steel framing as wellഀ
existing framing to be removed:ഀ
a) Detail 13/S301 Appears to be a section thru this area however is not referenced anywhereഀ
- cut 13/S301 on plan or detail.ഀ
b) Dims @ 3 places 14/S301 is cut appear different; are these the same detail & framing?ഀ
Please verify.ഀ
c) Verify W16 frames into (E) W12ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018. DOC Page 13 of 20ഀ
d) Provide Load for TS hanger.ഀ
S97 D S109 A prestressed beam near line 19 is identified as (2) PB9; seems this beam should beഀ
one PB similar to PB36; consider differential deflection btwn (2) PB9 & adjacent PB6.ഀ
S98 D S109 PB1 is identified as 30 x 60 in the schedule on S003. PB2 is identified as 20 x 28" inഀ
that schedule. These beam sizes appear very different sizes. Also, these beams appearഀ
continuous yet they are detailed as (2) single spans, verify performance will be as expected atഀ
center support. Also, the plan width scales 42" wide while the width of PB1 is 30" and PB2 isഀ
20" in the schedule. These & other PT bm designs should be checked & corrected as req'd.ഀ
S99 D S110 General Comment: Seems several details @ various sloping & stepping bearingഀ
conditions are req'd to ensure a complete load path & shear transfer. Consider axialഀ
shortening of Pt bms vs. restraint from monolithic slab & walls above and below.ഀ
S100 D S110 Outside foundation walls at the east end of building are shaded which I think, indicatedഀ
that the wall extends up past the plane of this framing plan, which is confusing as it seemsഀ
this plan represents the "lid" or top framing plan. Pis clarify. Detail PT beam to wall conn. &ഀ
slab to wall conn.ഀ
S101 D S110 Seems the PT dead ends or stressing ends need to be detailed because of the skewedഀ
angle btwn the PT beam and the wall - detail or explain.ഀ
S101 D S110 PB8-1 & PB8-2, PB7-1 & PB 7-2 are obviously 2 span continuous beams. However theഀ
PB schedule does not provide PT or mild steel arrangements for 2 span bms? Pis verify.ഀ
S102 D S110 Call out (2) conc bms spanning east & west between PB 7-2 bms are not identified, forഀ
ski club support.ഀ
S103 D S110 There seems to be a major step/trench (2) PB1 beams bear line 11.1 This dropഀ
requires an explanatory detail. Also, it seems obvious that the PB1 beams on each side ofഀ
the drop should not be the same as PB1 beams with a full tee beam flange. Pis check.ഀ
S104 D S110 Two PB11 beams, single span, seem to bear on a conc wall at a right angle bend in theഀ
wall. It would appear that the 320k tension will act to tear the rt angle wall apart. Suggest theഀ
FOR check. (Near 9.7)ഀ
S105 - not usedഀ
S106 D S201 These elevations do not seem to indicate construction joints or allowable lap spliceഀ
locations. If this info is critical. It is the EOR's responsibility to indicate this on the dwgs perഀ
ACI 301.ഀ
S107 D S201 Wall Beam WB1: Special rebar is req'd above and below the large wall opening. Detailഀ
14/S302 indicates 8 hz bars in the bottom of the wall. This is contradicted on shts S202ഀ
where 15410 in (3) layers are mentioned. Verify rebar T & B. Note it seems that the wallഀ
acts more like coupling beams and tension/compression columns @ this large opng - designഀ
for shear and combined bending and axial loads.ഀ
S108 D S201 Wall Beams WB2,WB3: Special rebar above & below openings (sim to WB1). Openingഀ
shown scales 6'x 6', plan says 5'x5'- coordinate plan and elevation.ഀ
S109 D S201 Show detail @ intersection of WB3 & WB4ഀ
CADocuments and Settings\mroyerWy Documents\Plan Review\Front Door\tov-b06-001 8. DOC Page 14 of 20ഀ
S110 D/C S201-3 Verify wall beams consider ACI provisions for deep beams regarding nonlinearഀ
distribution of strain and lateral buckling (ACI 318 10.7. 1) - calculations do not appear toഀ
consider these provisions.ഀ
S110a C deep beam calcs, B12 assumes that shear strength is 10*sgrt f'c, however the calculation ofഀ
Vc +Vs is not provided. Quick calculations show that typical shear reinforcement of #4 @ 9"ഀ
O.C. vertical and #4 @ 12" O.C. vertical are roughly 6*sgrt f'c. This typically does not appearഀ
to cause a problem with shear capacity, however for certain beams (WB11, calcs p. B49) thisഀ
seems to cause an overstressed condition. Also, the phi factor does not seem to have beenഀ
applied, f=0.75 for shear. Please review calcs and increase shear reinforcing as required.ഀ
S111 D S202 Elevation says (15) #10 bot in 3 rows. Verify this amount of bot steel will fit in all walls.ഀ
Sim. for (10) #10 top.ഀ
S112 D S202 WB5: Do the interior columns extend up from 8168'-0? See 13/S002 Bldg D.ഀ
S113 D S202 WB7: What is special reinforcing is req'd @ double openings in the wall above 8182.-6?ഀ
(ties, T&B bars); sim @ center column btwn doorways- these elements need individualഀ
designs and details as columns and beams - calcs p. B30-34 do not show these designs.ഀ
S114 D S202 WB8: The right side of this elevation seems to transition to a footing supportedഀ
retaining wall on the plan. This is not shown on the elevation. Pis modify detail if W138 isഀ
integral w/retaining wall.ഀ
S115 D S203. WB11 Verify 5'-0" long hooks @ end - verify this satisfies ACI 12.12.4ഀ
S116 D S301 Detail 5:ഀ
a) This is a good standard detail for reinf in a one way slab, however this detail is notഀ
referenced on the plans anywhere. Pis coordinate this detail w/plan reinf.ഀ
b) This detail does not show reinf perp to slab span - provide temp & shrinkage reinf..ഀ
S117 D S301 Section 6: Two layers of reinf in an 8" thk wall is trough to fit & maintain cover &ഀ
spacing - pls verify (typical as occurs).ഀ
S118 D S301 Section 9: Is this CMU wall, fully grouted, per CMU gen'I notes? Pls. clarify dtl.ഀ
S119 D S301 Section 10: Refers to see plan - Nothing shown on plan - coordinate plan and detail.ഀ
S120 D S301 Section 13: This appears to be an incomplete detail re: rebar in CMU, elevations,ഀ
grouting etc - reference 14/S301 as appropriate.ഀ
S121 D S301 Detail 14: See comments above, similar.ഀ
S122 D S302 Section 1 & plan sheets: Please add wall thickness, preferably on the plan; call outഀ
dowels @ center - need to transfer out of plane shear from soil lateral loads and in-planeഀ
shear loads (as applies).ഀ
S123 - not usedഀ
S124 D S302 Section 6: Many dowels not specified? Grouting? It appears that the lower slab isഀ
hanging from the upper tee beam const. however bars do not appear adequately developedഀ
for tension.ഀ
C:\Documents and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-001 8. DOC Page 15 of 20ഀ
S125 D S302 Section 9: Detail refers to plan -there is nothing on plans. Horiz wall beam reinf doesഀ
not match 12/S302? Verify.ഀ
S126 D S302 4/S302: #5 Dowel is not developed on either end (Ldh or Ld); also hook turnedഀ
upwards will blow out conc corner. Roughen for shear friction.ഀ
S127 D S302 Sections 12&13:ഀ
a) Bot rebar shows 18 bars, not consistent with wall elev.ഀ
b) Wall beam shown, not detailedഀ
c) Show dimensionsഀ
d) Verify #8 hooks; legs do not appear developed. #8 radius is not shown to scale.ഀ
S128 - not usedഀ
S129 D S302 Section 14: Define bot steelഀ
S130 D S302 Section 15: Define rebarഀ
S131 D S302 Section 15: Suggest pocket the wall for more positive beam bearing instead of tensionഀ
hanger See also S126.ഀ
S132 D S303 Section 2: Refers to "re plan", there is nothing shown on plans - please verify.ഀ
S133 - not usedഀ
S134 D S303 Section 5: Detail not drawn per scheduled beams on plan, beams are not the sameഀ
depth, revise detail. Consider mild top steel @ support.ഀ
S135 D S303 Section 6: Appears to be a beam, however the bot rebar is not identified. Stirrup hooksഀ
are not realistically shown, please verify.ഀ
S136 D S303 Section 7: Plan S108 says this is wall beam 5 which appears to be 12" thk; pleaseഀ
clarify if this is a beam or a wall beam. What is top & bot reinf shown. What are beamഀ
stirrups shown?ഀ
S137 D S303 Section 8ഀ
a) This section indicates a wall of various thicknesses without actually dimensioning wallഀ
thickness.ഀ
b) Various rebar is shown with very long hooks that are not identified.ഀ
c) A Hz beam appears below the bearing level of the tee beam on the left. No definition ofഀ
this beam is furnished. Doweled to the top PT beam are not identified.ഀ
d) FOR please review & clarify detailഀ
S138 D S303 Section 9: This is a confusing section - is this slab cantilevered from interior or a colഀ
strip? Define reinforcing. Call out expansion anchor embedmentഀ
S139 D S303 Section 10: Reinf is not defined. Pis define. Verify slab to wall beam dowel/shearഀ
friction.ഀ
S140 D S303 Section 11: Reinf dowels to concrete pad are not specified. Pis specify; anchor W16ഀ
skids to pad for wind and seismic loads for equipment.ഀ
CADocuments and Settings\mroyer\My DocumentsMan Review\Front Door\tov-b06-0018. DOC Page 16 of 20ഀ
S141 D 13/S303: Define expansion anchor size spacing, edge distance - verify that top of CMU doesഀ
not cause edge distance issues. Verify if expansion anchor is stainless, indicate as such ifഀ
req'd.ഀ
S142 D 14/S303: Please specify rebar and dimensions.ഀ
S143 DC S001: Appears ground snow load is required for ground level lid design, in lieu of roof snowഀ
load used: pg = 100/.7=143 psf. Please verify.ഀ
S144 C Transfer loads from buildings above the parking garage appear to be conservatively taken asഀ
the exterior soil load plus the snow / truck load. Please verify all point loads and line loadsഀ
are accounted for and transferred through to the footings.ഀ
S145 D,C S110: Transfer beams for building C located between consecutive PT beams are not calledഀ
out on plans. Please provide details and calculations for all such beams.ഀ
S146 D,C S108: At the 18" thick concrete slab the specified amount of reinforcement does not matchഀ
the calculations. It appears the top and bottom continuous reinforcement is not specified onഀ
the plans. Please verify.ഀ
S147 D,C S104: The calculations for the 12" thick concrete slab (page S44) indicate punching shearഀ
reinforcement is required at column 9 (grids 0.7-14.3). Please verify and provide theഀ
appropriate shear reinforcement.ഀ
S148 D S001: The tie spacing for column C9 exceeds the requirements of ACI. Please verify. (ACIഀ
318 7.10.5.2.)ഀ
S149 DC It appears that the PT stressing ends are not encapsulated. Per ACI all tendons exposed toഀ
corrosive environments need to be encapsulated with a water tight membrane. Please verifyഀ
PT general notes. (ACI 318 18.16.4)ഀ
S150 DC Please provide a Post-Tensioning Specification section.ഀ
S151 C Calculations for the B12 span3 do not match the drawings. Please verify.ഀ
S152 C Please verify the long term deflection for beam B18 meets ACI tolerances.ഀ
S153 C,D S109: East and west pool beams are not specified on plans. Please provide calculations andഀ
detail for the specified beams.ഀ
S154 - not usedഀ
S155 D S109: The beam at the entrance of the tunnel near grids R.5-25.5 is not scheduled. Pleaseഀ
specify mild reinforcement, shear reinforcement, and PT tendons.ഀ
S156 D S001: The general notes specify where to splice continuous reinforcement in walls andഀ
beams. Please clarify top and bottom reinforcement for walls, consider using inside face andഀ
outside face (I.F. and O.F.).ഀ
S157 D Per the general notes it is unclear where to splice the continuous reinforcement in theഀ
structural slabs. Please clarify. See also S116.ഀ
S158 C S110: The calculations for the PB1 PT beams did not account for the steps near grid lineഀ
11.1. The two beams adjacent to the steps can only account for one compression flangeഀ
C:\Documents and Settings\mroyer\My Documents\Plan ReviewWront Door\tov-b06-001 8. DOC Page 17 of 20ഀ
(high side of the step only). Please provide calculations verifying the two PB1 beams haveഀ
adequate reinforcement and strength providing they only have a one-sided compressionഀ
flange.ഀ
S159 C,D S109: Please schedule reinforcement for beams PB9 and P131 0. Please provide calculationsഀ
for these beams accounting for a one sided compression flange.ഀ
S160 D Detail at stair cores reference the wrong detail. Please provide a detail through the stair coresഀ
specifying the reinforcement.ഀ
S161 - not usedഀ
S162 D Is the wall beam reinforcement continuous at corners. If so please provide details for cornerഀ
reinforcement and lap splices. Congestion may be a problem at these locations.ഀ
S163 C,D S002: In the cantilever portions of beams B4, B13, B14, and B15 ACI requires ties be spacedഀ
<_3db for the development length of the top reinforcement. Please provide a detail at cantileverഀ
beam sections to clarify the stirrups in these locations per the beam schedule call out for ties.ഀ
(ACI 318 12.5.4)ഀ
S164 D S301: In section 13 a CMU wall is shown under the cantilever portion of the structural slab. Ifഀ
CMU is not designed to take the weight of the structural slab, a slip connection is requiredഀ
between the CMU wall and the slab to allow for long term deflections in the slab, pleaseഀ
provide a detail.ഀ
S165 D S108: Please clarify where plan note 6 occurs by hatching the specific areas and verify allഀ
calculations take the extra soil weight into account.ഀ
S166 D Concrete cover and fire ratings are not clearly specified on plans. Please verify allഀ
reinforcement coverage meet the required fire ratings.ഀ
S167 C,D S002: Section 3 indicates the one-way slab reinforcement spanning perpendicular to theഀ
beam is located below the longitudinal reinforcement for the beam. Refer to calculations pageഀ
R4. The beams are reinforced with #4 stirrups and #6 top bar giving a d of the slab equal toഀ
d=8-(1.5+1/2+6/8+(5/8)/2)=4.9". A d=6.5" was used in the calculations. If the d=4.9" is usedഀ
the provide amount of top reinforcement does not provide a ~Mn>_Mu. There are severalഀ
locations where calculations were not provided for all one-way slabs spanning betweenഀ
beams. Please verify all one-way slabs spanning between beams identifying the appropriateഀ
d distance for the negative moments and positive moments. Consider all conditionsഀ
specifically where #10 bar is called out in the one-way slabs.ഀ
S168 D Demo plan, D101 appears to show that an existing column / bearing wall between levels 0ഀ
and level 1, approx. @ grids 20.8 / will remain, however this is not completely clear on theഀ
architectural or structural drawings. Please confirm existing column remains, or provideഀ
design for column transfer beam. Please confirm walls removed @ existing building are nonഀ
load bearing.ഀ
S168 LS Soil restraint will be removed at the south and east faces of the existing South Lodge Condo,ഀ
during construction (excavation and demolition) and in the final condition (due to 2" gapഀ
between slabs at grade level, per note on S109). This seems to create an unbalanced lateralഀ
load situation at this existing building, due to lateral soil loads acting upon the north and westഀ
faces of the building. Provide calculations to show the existing South Lodge has a lateral loadഀ
path due to lateral soil loads during and after construction, or confirm that this issue will beഀ
coordinated by the contractor (permanent shoring @ existing structure, etc).ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-001 8. DOC Page 18 of 20ഀ
S169 S105 Column missing at grid 17/Lഀ
S170 S109 Grid intersection 23.2/N elevation of B22 and P133 beam is not apparent. Referring toഀ
Section 6 S303, it is not apparent if beam B22 is measured from the bottom of PB3 or B24.ഀ
The column at this intersection is shown supporting both the PB3 and B22 beams but theseഀ
beams are shown on the detail to be at different elevations. Provide column connectionഀ
detail, and all elevations of PB3 and B22.ഀ
S171 S108 grid intersection 21.3/L, the elevation of the 12" slab north of beams B22 and B21 can not beഀ
determined. On plan the P134 and P65 beams are shown higher than the 12" slab to the northഀ
as indicated by a step symbol; however, section 7 on S303 shows the PT beams lower thanഀ
the slab. Please provide on plan: elevations of the north slab adjacent to the supportingഀ
beams B22 and B21, and elevations of the PT beams and non-PT supporting beams. Alsoഀ
please correlate these elevations to detail 7 on S303. Please provide the reinforcing detail atഀ
grid intersection 21.3/L showing interfacing of reinforcing for P1310,1322-5, B21-1, the columnഀ
below, and the slabs.ഀ
S172 S109 Please indicate if a specific pour sequence is intended or required to satisfy designഀ
assumptions.ഀ
S173 S109 Please clarify if elastic shortening has been considered due to post-tensioningഀ
S174 S109 S003 provide calculations and conformance to AC1318 section 18.13 Post-tensioned tendonഀ
anchorage zones.ഀ
S175 S110 P131 requires approximately 38 tendons to achieve the final effective force of 1015k. Pleaseഀ
provide detail of anchorages and tendon profile to get the drapes specified consideringഀ
congestion of bursting, shear and flexural reinforcing. Please specify if multi strandഀ
anchorages are intended. The initial dead load seams to be overbalanced. Please indicate ifഀ
stage stressing is required.ഀ
S176 S001 and general. Reinforcing cover appears to be specified only on S001. Calculations providedഀ
in Ram Concept format does not indicate cover used considering layering of reinforcing in twoഀ
directions. Confirm either specific sequencing is specified or the calculations allow forഀ
flexibility in reinforcing sequencing.ഀ
S177 C U24 and PT7 shows #9 top bars needed. Please verify development. For the PT7 case, theഀ
boundary conditions suggest pinned condition. Clarify the top bars at this location per theഀ
calculations.ഀ
S178 C M10. Please provide reinforcing covers used in the calculations.ഀ
S179 C M10 beam 1-3 calls for 20410 top left side. B27-3 on S002 calls for a lesser amount ofഀ
17#10. Please provide justification for the reduced reinforcing from the calculated amount.ഀ
S180 C/D M7 and M8 shows reaction moments where connected to the BM22. Provide calculations forഀ
BM22 considering torsional effects. Also section 6 on S303 does not appear to address thisഀ
fixity. See S135.ഀ
S181 C M6 shows column heights of 40 feet. With the increased column lengths the columnഀ
moments are reduced. Please provide justification for modeling the columns extremely long.ഀ
Please provide a reference for the column design considering applied moments from the floorഀ
designs shown on M1 and M14.ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018. DOC Page 19 of 20ഀ
S182 C S105 M24-M27 Calculations appear to conclude #5 top and bot reinforcing. The plans showഀ
#6 top and bot with #5 add bars. The spacing on the plan appears to specify much moreഀ
reinforcing than the calculations conclude. Is there another load case or condition thatഀ
controls? It is not clear if the added reinforcing shown at 21.3/N is to be used at all columnഀ
locations including the short spans on grid L.5.ഀ
S183 C F6 shows f'c = 5000psi S001 specifies f'c = 4000psi for the footings- verify footings have beenഀ
designed per plans.ഀ
S184 D Building C S102: Please verify transfer load from column above for beam 5. See commentഀ
S12 Volume #4 Ski Club. Please verify deflections and strength of beam.ഀ
S185 D Building C S102: Please provide splice positions for top and bottom continuous reinforcementഀ
for the one way slab.ഀ
Please refer to the cover sheet for information and instructions for resubmitting plans. The recheck of plansഀ
usually occurs within 3-5 working days of plan re-submittal. In order to avoid delays please check all requestedഀ
information is included with the resubmitted plans.ഀ
Contact Person:ഀ
Matthew Royerഀ
Building Official/ Project Managerഀ
Colorado Inspection Agencyഀ
970-328-1790ഀ
matt. royer(a)coinspect.comഀ
Plans Examiners and Engineers:ഀ
Barry Kramer- Building Officialഀ
Todd Dunkin- Electrical Plans Examinerഀ
Dennis Lohmeier- Plumbing Plans Examinerഀ
Duskin Lowe- Plans Examinerഀ
James P. Horne, P.E., S.E. - Structural Review Project Managerഀ
C\Documents and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018. DOC Page 20 of 20ഀ
COLORADO INSPECTION AGENCY PLAN REVIEW COMMENTSഀ
TO: Contractorഀ
Hyder Constructionഀ
Doug Thompsonഀ
EMAIL: dthompson@hyderinc.comഀ
Architectഀ
4240ഀ
Randy Hartഀ
rhart@4240a.rch.comഀ
Engineerഀ
Monroe & Newell Engഀ
FAXഀ
NUMBER OF PAGES:ഀ
FROM:ഀ
DATE:ഀ
BUILDING PERMITഀ
OWNERS NAME:ഀ
SITE ADDRESS:ഀ
SUBDIVISION:ഀ
OCCUPANCY GROUP:ഀ
TYPE OF CONSTRUCTION:ഀ
NUMBER OF STORIES:ഀ
20ഀ
Matthew Royerഀ
03/10/2006ഀ
B06-0018ഀ
Vail Resorts Co.ഀ
Building A and Siteഀ
Mill Creekഀ
S-2ഀ
I-Aഀ
3ഀ
The design documents submitted for this project have been reviewed for compliance with the locallyഀ
adopted codes and amendments. The following comments must be addressed before a buildingഀ
permit is issued.ഀ
For processing:ഀ
Please submit (2) complete sets of revised construction documents containing the requestedഀ
information or plan revisions with all revisions clouded or otherwise identified.ഀ
Please respond in writina to each comment by markina the attached list or creating aഀ
response letter. Indicate which plan sheet, detail, specification, or calculation shows theഀ
reauested information. Please send revisions to the attention of the plans examiner with theഀ
building permit application number noted.ഀ
Responses such as "will comply with code" are not adequate. Revised drawings mustഀ
clearly show code compliance.ഀ
A RESPONSE LETTER MUST BE INCLUDED WITH THE REVISED PLAN SUBMITTAL.ഀ
Please be sure to include on the resubmittal the engineer's or architect's 'Wet" stamp, signature,ഀ
registration number and date on the cover page of any structural calculations, all structural detailsഀ
and structural sheets of the plans. For commercial or multi-family projects all sheets of the plansഀ
must be stamped.ഀ
C:\DOCUME-I\dhopp\LOCALS-I\Temp\A Site -Response to ToV-b06-0018.DOC Page I of Iഀ
BUILDING DEPARTMENT COMMENTS:ഀ
Common Project Comments: (CPC are attached to each permit comment letter)ഀ
1. Land Swap with US Forest Service must be complete prior to final approval and issuance of theഀ
Building Permit.ഀ
The agreement was signed on January 18th, 2006 and is now in a 45 day review period.ഀ
2. When plans are resubmitted for review; complete sets of plans for each building which includes theഀ
addendum sheets. Separate addendum packets will not be accepted and approved for initialഀ
permitting.ഀ
Plans have been modified and are to be resubmitted for the Town of Vail Building and Fireഀ
Department review, approval and issuance of a permit.ഀ
3. Preliminary plan review meetings had discussion regarding the submittal of Memorandum ofഀ
Understandings (MOU). MOU's defined in these meetings would be "used to define or clarify the useഀ
of a code section, agreement to the installation of a system not covered specifically by the code orഀ
clarify the use or component of a building. None of the agreed upon MOU's were submitted forഀ
review. Please provide the following MOU's for review:ഀ
a) Use of assumed property lines and fire separation distance.ഀ
b) Fire command roomഀ
c) Smoke management systemsഀ
d) Opening between parking garage and Lodge Tower parking garageഀ
e) Fire separation between the new building and existing buildingsഀ
f) Use of 508.2 for creating separate buildings as it relates to each buildingഀ
g) The separation between One Vail Place and new Skier Servicesഀ
A Memorandum of Understanding dated April 3, 2006 addressing these issues has been completedഀ
and will be submitted to the Building, Fire Department and Colorado Code Inspection for review andഀ
approval.ഀ
4. Preliminary plan review submittal meetings had discussion regarding the submittal of Administrativeഀ
Modifications (AM). AM's as defined in these meetings would be based on International Buildingഀ
Code Section 104.10. Where practical difficulties are involved in carrying out the provision of thisഀ
code, a modification to the code may be granted by the building official after justification that theഀ
modification will not lesson health, accessibility, life and fire safety, or structural requirements. Theഀ
following AM's have been discussed and are being implemented into the plans. Please provide theഀ
following or amend plans accordingly to comply with the code.ഀ
a) Separation between Chalet buildingsഀ
b) Elimination of elevator smoke doors at residential levels of the Chalet buildingsഀ
A Request for Administrative Modification dated April 3, 2006 addressing these issues has beenഀ
completed and will be submitted to the Building, Fire Department and Colorado Code Inspection forഀ
review and approval.ഀ
5. Be sure to amend the Fire & Life Safety Report as necessary when changes are made to the plansഀ
that may affect the discussions made by the Report.ഀ
An updated Life Safety Report for The Vail Front Door Buildings A, B, C and D dated April 3, 2006ഀ
has been completed and coordinated with the G - Series Code Drawings. This report andഀ
attachments will be submitted to the Building, Fire Department and Colorado Code Inspection forഀ
review and approval.ഀ
6. Provide a precise site plan showing exact locations of assumed property lines. If locations of assumedഀ
property lines are close enough to exterior walls to require rating of walls and opening protection,ഀ
provide details.ഀ
4240 has updated the G - Series Code Drawings indicating the locations of property lines andഀ
assumed property lines.ഀ
C:\DOCUME- I\dhopp\LOCALS-1\Temp\A Site - Response to ToV-b06-0018.DOC Page 2 of 2ഀ
7. Fire and Life Safety Report states the use of 1-hour fire walls per IBC Table 705.4. This table doesഀ
not allow for 1 hour fire walls anywhere. Please clarify.ഀ
The Life Safety Report has been modified to reflect the approach taken for the building separations.ഀ
As indicated in the report numerous meetings were held with the building and fire departmentഀ
identifying buildings, construction types and openings. The buildings and proximity to the propertyഀ
lines will not meet the prescriptive requirements of the building code. The design team has identifiedഀ
on the G - Series Code Drawings that the project will use a variety of 3-hour horizontal and verticalഀ
fire resistive separations as well as 2-hour and 1-hour occupancy separation walls. This approach ofഀ
compartmentation with the use of automatic sprinkler protection and detection though-out will notഀ
compromise the life safety of the occupants.ഀ
8. Fire walls are called out in the fire and life safety report to separate buildings. What is the purposeഀ
and use of the fire walls and the separations? Is it to separate property owners?ഀ
It appears that fire separation distances are being used to determine the ratings for the wallsഀ
identified as fire walls between the different building and spaces. Our interpretation of this section isഀ
that once the 3 hour separation is used to make a separate building then everything that is notഀ
separated by a fire wall per 705.4 will be considered as one building.ഀ
The Life Safety Report has been modified to reflect the approach taken for the building separations.ഀ
As indicated in the report numerous meetings were held with the building and fire departmentഀ
identifying buildings, construction types and openings. The buildings and proximity to the propertyഀ
lines will not meet the prescriptive requirements of the building code. The design team has identifiedഀ
on the G - Series Code Drawings that the project will use a variety of 3-hour horizontal and verticalഀ
fire resistive separations as well as 2-hour and 1-hour occupancy separation walls. This approach ofഀ
compartmentation with the use of automatic sprinkler protection and detection though-out will notഀ
compromise the life safety of the occupants.ഀ
9. Accessibility requirements do not appear to be included within any plan for this project. Pleaseഀ
amend plans to include the following:ഀ
a) Accessible parking spaces and loading zones.ഀ
b) Accessible route from the parking and loading zones to the buildings.ഀ
c) Accessible routes to each building on the site which are required to be accessible.ഀ
d) Signage details for parking, striping, routes, restrooms, etc.ഀ
e) Restroom details for fixtures, grab bars and accessories.ഀ
The drawings have been modified to show accessible parking spaces and loading zones, accessibleഀ
routes and confirmed that restroom details for fixtures, grab bars and accessories has been provided.ഀ
All signs related to accessibility are listed in a separate contract with the client and will be a deferredഀ
submittal to the building for review and approval.ഀ
10. Amend plans to include stair signage plan, details and identify the location of the signage. Many ofഀ
the exit enclosures require the occupants to travel up to get to exit discharge. Clearly identify theഀ
direction of travel to the exit discharge.(IBC 1019.1.6)ഀ
The design team will modify the drawings to reflect required stair signage and directional signage. Itഀ
would be the intent of the design team to identify with the fire department additional egress signage orഀ
directional signage to ensure occupants will be directed to a an egress stair/passage way and to aഀ
public way.ഀ
11. Amend plans to include gates located at the level of exit discharge to eliminate occupants of theഀ
building from entering an enclosure and passing by the level of exit discharge. (IBC 1019.1.6)ഀ
Gates have been added to the plans to meet this requirement and direct occupants to the exterior orഀ
from continuing below or above a level of exit discharge.ഀ
12. Elevator door which do not open into a lobby need to be provided with a smoke control door inഀ
accordance with IBC Section 715.3.5.3ഀ
None of the elevators penetrate more than 3 stories. Thus, smoke control and venting is not required.ഀ
C:\DOCUME-I\dhopp\LOCALS-1\Temp\A Site - Response to ToV-b06-0018.DOC Page 3 of 3ഀ
13. Clearly identify the location of safety glazing per IBC Chapter 24 either in the window schedule or onഀ
the plan.ഀ
Bldg. B: Per A610 for window types with tempered glazing and reference building elevations forഀ
location of such window types.ഀ
Bldg. C: Per A610 & A611, tempered glazing is indicated at/in the following locations:ഀ
- within 24" of door edges that are less than 60" AFF.ഀ
- within units that have panes greater than 9 s.f.ഀ
- and in units that are within 18" of the floor.ഀ
See the updated window schedule that shows additional tempered glazing for units with panesഀ
greater than 9 s.f.ഀ
Bldg D: Per A610, tempered glazing is indicated at/in the following locations:ഀ
- within 24" of door edges that are less than 60" AFF.ഀ
- within units that have panes greater than 9 s.f.ഀ
- and in units that are within 18" of the floor.ഀ
See the updated window schedule that shows additional tempered glazing for units with panesഀ
greater than 9 s.f.ഀ
Bldg. E. Per A610 for window types with tempered glazing and reference building elevations forഀ
location of such window types.ഀ
14. The size of main elevator cars used for fire/emergency access needs to be determined by the Townഀ
of Vail Building and Fire Departments. Standard 24" x 76" required by code will not accommodate theഀ
stretchers used by emergency personnel. Please confirm the required size.ഀ
The elevator cabs are currently designed to comply with the standard stretcher requirement asഀ
adopted by the code. In the case of the Chalets the elevator serves 4 levels or 3 stories. Based onഀ
that interpretation the stretcher accessible would not be required. The design team is providing aഀ
stretcher accessible elevator to each unit beyond what would be required by code. The currentഀ
elevators will be 2474 inches.ഀ
Architectural Comments:ഀ
Site Comments:ഀ
15. Coordinate pool equipment room in Bldg B with pool piping shown on Site Plan sheet W1.0ഀ
The pool piping information on W1.0 is directed to the pool equipment room detailed on sheet W2.0.ഀ
Sheet W0.0 shows the piping corridor routes from the pool to the equipment room.ഀ
16. Provide compliant barrier to pool and spa areas. Change detail reference to L207. L208 is used forഀ
pool coping as called out on L202.ഀ
Detail sheet numbers have been corrected to correspond with plan call-outs.ഀ
17. Fence shown on L207 shows the bottom of the fence to far above grade. Max distance betweenഀ
grade and bottom of fence 2 inches. (IBC 3109.4)ഀ
Details have been revised to show 2" clearance.ഀ
18. Sheet L202 references sheet L209, but this sheet does not exist. Please amend plan.ഀ
Detail sheet numbers have been corrected to correspond with plan call-outs.ഀ
19. Amend plans to show gates compliant with the pool barrier requirements. (IBC 3109.4.1.7)ഀ
Details have been revised to show 2" clearance.ഀ
C:\DOCUME-I\dhopp\LOCALS-I\Temp\A Site - Response to ToV-b06-0018.DOC Page 4 of 4ഀ
20. Boulder wall used at waterfall of pool shall not be climbable or an approved barrier shall extendഀ
around boulder wall. Show detail of wall or amend barrier to encompass this area.ഀ
The stone veneer wall with fence has been redesigned to extend behind the waterfall and provide aഀ
continuous barrier between the sidewalk and the waterfall. See sheet L202ഀ
21. Some of the exterior stairs from the lift ticket area only show handrails on one side. Amend plans toഀ
show handrails on both sides of all stairs throughout the site. (IBC 1109.11)ഀ
Stair areas have been revised to show handrails on both sides.ഀ
22. Sheet L102 for the chalets show some exterior stair locations with handrails on only one side. Handഀ
rails are required on both sides of stairs per 1009.11 2003 IBC.ഀ
Stairs have been revised to show handrails on both sides.ഀ
23. Sheet L102 calls out Stairs and Handrails on sheet L107. Sheet L07 does not exist.ഀ
Detail sheet numbers have been corrected to correspond with plan call-outs.ഀ
24. Sheet L202 calls out fireplace detail on L208. This detail is on L207. Correct drawings to specifyഀ
which sheet fireplace detail is located.ഀ
Detail sheet numbers have been corrected to correspond with plan call-outs.ഀ
25. Sheet L207 states exterior gas fireplace. Provide manufacturers listing for exterior gas appliance. Alsoഀ
Sheet L202 has wood storage next to the fireplace called out as gas. Clarify.ഀ
Manufactures listing information is called on detail 7, sheet L-208. Wood storage call-out on L202 hasഀ
been changed to blanket storage.ഀ
26. Detail for all exterior stairs does not meet profile requirement of 1009.3.2 IBC 2003.ഀ
Nosing design on sheet L106, detail 10 has been changed from a beveled edge nosing to a squareഀ
condition.ഀ
27. There are changes in elevation of one step coming from west side of ski club down to walkway thatഀ
require a handrail unless tread depth of elevation change is the same or greater than the dimensionഀ
of a required landing. (IBC 1009)ഀ
A handrail on both sides of the steps has been added.ഀ
28. Sheet L302 calls out stair and handrail details on L307. There are no stair and handrail details onഀ
L307. Clarify.ഀ
Detail sheet numbers have been corrected to correspond with plan call-outs.ഀ
29. Amend plans to include all component which will be required and specified within the Administrativeഀ
modification for the opening between the Parking Garage (2 places) and the existing Lodge Tower.ഀ
The existing Lodge Tower plan has identified the parking garage as Type I-B. This needs to be takenഀ
into consideration when exercising IBC section 508.2. Same type of construction was used during theഀ
pre-submittal meetings that discussed the separation. Please address the type of constructionഀ
separation and opening protection accordingly. Please coordinate plans and design with the Lodgeഀ
Tower designers.ഀ
See Memorandum of Understanding... As discussed with the TOV Fire Department at severalഀ
meetings, a water curtain will be provided at the connection of the Lodge Tower parking garage andഀ
the new Building A Parking Garage. This opening between these two buildings is located on theഀ
property line and a cross easement agreement has been executed between the Lodge Tower andഀ
Vail Front Door owners. Prescriptively in accordance with the building code this opening would not beഀ
permitted. If the opening were permitted the protection of the opening would normally be done with aഀ
90-minute fire shutter. Because of the difficulty of maintaining access should the fire shutter beഀ
activate it was agreed to by the building and fire department to protect the opening with a water washഀ
from the sprinkler system. The water curtain shall be designed to provide a density of 3 gallons perഀ
C:\DOCUME-I\dhopp\LOCALS-I\Temp\A Site - Response to ToV-b06-0018.DOC Page 5 of 5ഀ
minute per lineal foot across the opening. This protection will be from a closed sprinkler head waterഀ
curtain and not a deluge system. The sprinkler heads at the opening will be spaced 6 feet on centerഀ
and within 12 inches of the opening. The water curtain is to be located on the Vail Front Door side ofഀ
the opening. Additionally, a rate compensating heat detector is being provided on both sides of theഀ
opening from the adjacent fire alarm systems for notification of an alarm condition at either Lodgeഀ
Tower the Vail Front Door. The contractor through the sub-contractor will prepare shop drawings andഀ
construction sequencing for the modifications to the fire protection system for this special protection.ഀ
The shop drawings and construction sequencing will be reviewed and approved by BCERഀ
Engineering for submittal to the TOV Fire Department for their review and approval during the shopഀ
drawing permit process.ഀ
Mechanical Comments:ഀ
30. Provide positive pressure and outside air to valet booth. (IMC 404.3)ഀ
Outside air has been added, see Bldg. C, sheet M101.ഀ
31. How is pool and spas being heated? There are no boilers shown in equipment room in bldg B. onഀ
P201.ഀ
Refer to Bldg. B, sheet M101 P, keynote # 3.ഀ
32. Where is the gas piping for the fountain coming from? Sheet L308 is referenced and does not exist.ഀ
ABS could not find reference to sheet L308. Refer to Bldg. D, response # 29.ഀ
33. Spec Manual calls out CO detector to send alarm to panel at 35 PPM. If this setting also activatesഀ
exhaust fans it must be lowered to 25 PPM per 2003 IMC sec 404. Show compliance with 2003 IMCഀ
for fan activation.ഀ
ABS could not find reference to 35 PPM in specification. See 15975 3.13 D. for sequence (fans areഀ
activated at 9 PPM).ഀ
Plumbing Comments:ഀ
34. Clarify where continuation of plumbing for pool to equipment room is shown.ഀ
The pool design is by STO Design and all plumbing piping for pools and spas shall be provided byഀ
them, with the exception of make-up water and backwash discharge standpipe, which ABS hasഀ
supplied in the pool equipment room.ഀ
Electrical Comments:ഀ
35. TVSS needs to have short circuit rating equal to or greater than available fault current. Provide ratingഀ
and calculation for TVSS. (NEC 285.6)ഀ
Calculations for available fault current at TVSS and specification of short circuit rating have beenഀ
added, see sheet E002.ഀ
36. Provide nameplate information for generator. (NEC 445.13)ഀ
Nameplate information will not be available until contractor selects generator manufacturer.ഀ
Specification section 16403 1.04 has been revised to add a note that submittals shall includeഀ
nameplate rating as designated in NEC section 445.13.ഀ
37. Feeder 50 to panel SLW should be 45.ഀ
Feeder has been upsized to compensate for voltage drop.ഀ
38. Panels SLD, W and E not identified on panel schedule pages.ഀ
Panel SLD is shown on Bldg D sheet E004. Panels SLW and SLE have been added to bldg A sheetഀ
E004.ഀ
CADOCUME-I\dhopp\LOCALS-1\Temp\A Site - Response to ToV-b06-0018.DOC Page 6 of 6ഀ
39. Panic hardware required on electrical room (A109) doors. (NEC 110.26(C)(2))ഀ
A note has been added to sheet E201 to require panic hardware. 4240 needs to revise architecturalഀ
documents as necessary.ഀ
40. Feeder 51 must be 2"C minimum. (NEC table 5 and 4)ഀ
Feeder 51 has been revised to be a 2" conduit.ഀ
41. Grounding electrode conductors need to be bonded at both ends if installed in metallic conduit. (NECഀ
250.92(A)(3))ഀ
Specification section 16450-2.02 has been revised to add the following note. "Grounding electrodeഀ
conductors shall be bonded at both ends if installed in metallic conduit per NEC 250.92(A)(3)."ഀ
42. Maintain clearances around electrical equipment. (NEC 110.26 & 450.21)ഀ
The following general note has been to Sheet E002. "ELECTRICAL EQUIPMENT MUST FIT IN THEഀ
SPACE PROVIDED AND MEET ALL CLEARANCE REQUIREMENTS PER NEC 110.26 & 450.21.ഀ
REFER TO PLANS FOR SPACE ALLOCATION".ഀ
43. Provide performance test in accordance with NEC 230.95(C) for GFCI service equipment.ഀ
Specification section 16065-2.02-5 has been revised to add the following note. "Provide performanceഀ
test in accordance with NEC 230.95(C) for GFCI service equipment."ഀ
44. Are electrical rooms being separated with fire rated assemblies in lieu of the sprinkler system in thatഀ
room?ഀ
Electrical rooms are sprinkled.ഀ
Energy Code Review:ഀ
Envelope Corn Checkഀ
45. The IECC requires all conditioned spaces to be included in the building envelope. The parking garageഀ
and storage areas are being heated. We are unable to determine the areas used in the COM checkഀ
for conditioned spaces. Provide calculations for all areas used in the envelope COM check. If theഀ
parking garage is not considered a conditioned space then vestibules are required for spaces that areഀ
conditioned and open into the garage. (IECC 802.3.6)ഀ
The only conditioned space in this building is the Dock Office. See attached Envelope Complianceഀ
Certificate for compliance. Radiant heating of Dock and Valet area are allowed per ASHRAE 90.1-ഀ
2004, Section 6.5.8.1. The ceiling plenums that are shown, for heating of plumbing piping fromഀ
above, are included in the related buildings' Envelope Compliance Certificate's (Bldg's B & D). Theഀ
lower level of the Ski Club (Bldg. C) has a vestibule between the conditioned spaces and the garage.ഀ
All other spaces adjacent to the garage fall into exception # 2 or 4 of IECC 802.3.6; they are allഀ
equipment rooms or are less than 3,000 sq. ft. in area.ഀ
Mechanical Corn Checkഀ
46. The mechanical system list is incomplete for all areas which have conditioned space. Please provideഀ
more information.ഀ
See attached Envelope Compliance Certificate for Dock Office only.ഀ
47. Provide load calcs. per 1997 ASHRAE fundamentals or equivalent.ഀ
See attached Load Calcs for your reference.ഀ
Electrical Energy Checkഀ
48. There is insufficient information to show compliance with IECC section 805.5.ഀ
ABS Response: Buildings A, C and D share a common electrical service. The combined lightingഀ
wattage for this service is within compliance, see original letter issued with Com Check calculations.ഀ
Due to limitations within the Com Check program the three calculations could not be combined. Thisഀ
was due to the garage not being eligible to be calculated as an individual space. In an effort to bringഀ
C:\DOCUME-I\dhopp\LOCAL'>-t\Temp\A Site -Response to ToV-b06-0018.000 Page 7 of 7ഀ
Building C closer to individual compliance the lighting load has been reduced from 18,797 watts toഀ
17,013 watts on the modified drawings. See the modified Com Check report for Building C.ഀ
Site Structural Comments:ഀ
Note: structural comments are numbered "S1,S2,..." and are also given a designation with regards to the topic, as follows:ഀ
DC = design criteria; F= foundations; D = drawings; C = structural calculations; LS = lateral system.ഀ
Site Comments:ഀ
S1. D Specs 02925 appear to indicate that construction of EPS should not be done under "high winds",ഀ
however wind speed is not defined. Suggest place notes regarding this requirement on the drawingsഀ
and potential mitigating construction measures. ✓ഀ
Specifications have been revised to read " High Winds over 20 MPH" ClaSaotഀ
S2. D Specs also indicate combustibility and fire retardant be used - suggest plate notes to this effectഀ
on the drawings.ഀ
Specifications for project are submitted to Foam Molders for manufacturing of material. Required byഀ
Federal Law to include Flame Retardant in this type of application. c(c&eA,ഀ
S3. D SF101: verify lower strength EPS is correctly shown what appears to be underneath the Ski Club,ഀ
Volume 4 drawings. Seems a higher strength is required for bearing.ഀ
The EPS placed under the Ski Services is only for filler material. This is not bearing the G cdl ✓ഀ
foundation/footing for the structure. Placing fill materialഀ
S4. D SF sheets: It seems a finished elevation C top of EPS would be useful for construction, it is notഀ
clear how the elevation will be correctly achieved with the current drawings.ഀ
Next Submittal has the depth of the top of the EPS detailed. The thickness/depth of the top layer willഀ
outline the various elevations.ഀ
S5. F SF sheets: verify pavement / subgrade above the EPS under roadway (20 psi) has been designedഀ
to span between HS-20 tires, or depth is sufficient to distribute loads such that 20 psi is a sufficientഀ
strength under the roadway.ഀ
Calculations verify the 20 psi is sufficient under roadways with an eight inch slab thickness. If the slabഀ
is reinforced then the density can be decreased dependirlg on the amount of reinforcement used.ഀ
n/a7k C'35 fLe ~s Of t(ara- vet/ ca~~d°uMഀ
S6 F SF sheets: It appears EPS fill has not been designed underneath Volume 6 Chalet (Bldg E). It isഀ
not clear how backf ill is intended to be placed at these structures; in some locations Bldg E bears halfഀ
on the concrete tunnel and half on presumably engineered soil backfill. Please confirm that Bldg. Eഀ
bears on engineered backfill. Verify deflection compatibility of Bldg. E bearing on top of tunnel andഀ
backfill and associated differential deflection.ഀ
In this application the EPS is placed to reduce vertical loading on the underground structure fromഀ
landscaping features. The foundation system of Building E has been designed to accommodate theഀ
fact that part of the building is bearing on the concrete tunnel and a portion of the building will be /ഀ
placed on soil. ✓ഀ
S7 DC Sheet L202: FOR to verify that various landscaping structures such as boulders, ponds, stoneഀ
walls, pavers, and other superimposed dead loads have been appropriately considered in theഀ
structural design; verify any concentrated bearing on EPS filler (i.e. such as due to any retainingഀ
walls, 6/1-205, or massive stone structures, 3/L.208, etc.) C oref f'ഀ
Worst case is 4.0 diameter boulder. EPS calculations verify stability under this situation. rഀ
38 F 7/L.207: verify EPS will not be damaged over time due to fireplace heat.ഀ
With three feet of material distance between the Fireplace and the EPS material there is enough heatഀ
dissipation to decrease the chances of deformation due to heat.ഀ
S9 D A/W4.8: verify reinforcing at base of liftഀ
C:\DOCUME-1\dhopp\LOCAIS-1\Temp\A Site - Response to ToV-b06-0018.DOC Page 8 of 8ഀ
The reinforcement at the base of the handicap lift is sufficient to adequately anchor the lift andഀ
support the max vertical load of 470 lbs. All that is required per the manufacturer's specific-a~tlion is aഀ
concrete footing and STO has provided the rebar in addition to this requirement. Ci, VAഀ
Building A Structural Comments:ഀ
See attached Structural Comments from Monroe & Newell Engineers.ഀ
Contact Person.ഀ
Matthew Royerഀ
Building official/ Project Managerഀ
Colorado Inspection Agencyഀ
970-328-1790ഀ
m tt.roWr@coinspect.comഀ
Plans Examiners and Engineers:ഀ
Barry Kramer- Building Officialഀ
Todd Dunkin- Electrical Plans Examinerഀ
Dennis Lohmeier- Plumbing Plans Examinerഀ
Duskin Lowe- Plans Examinerഀ
James P. Horne, P.E., S.E. - Structural Review Project Managerഀ
C:\DOCUME-I\dhopp\LOCAI -I\Temp\A Site - Response to ToV-b06-0018.DOC Page 9 of 9ഀ
Colorado Ins ecdonഀ
AGENCYഀ
COLORADO INSPECTION AGENCY PLAN REVIEW COMMENTSഀ
2nd review comments are shown below the original comment in bold italics. Comments that wereഀ
addressed have been removed from the list.ഀ
TO: Contractor Architectഀ
Hyder Construction 4220ഀ
Doug Thompson Randy Hartഀ
EMAIL: dthomson(a)-hyderinc.com rhart(a)-4240arch.comഀ
FAXഀ
NUMBER OF PAGES:ഀ
18ഀ
FROM:ഀ
Matthew Royerഀ
DATE:ഀ
05/08/2006ഀ
BUILDING PERMITഀ
B06-0018ഀ
OWNERS NAME:ഀ
Vail Resorts Co.ഀ
SITE ADDRESS:ഀ
Building A and Siteഀ
SUBDIVISION:ഀ
Mill Creekഀ
OCCUPANCY GROUP:ഀ
S-2ഀ
TYPE OF CONSTRUCTION:ഀ
I-Aഀ
NUMBER OF STORIES:ഀ
3ഀ
Engineerഀ
Monroe & Newell Engഀ
The design documents submitted for this project have been reviewed for compliance with the locallyഀ
adopted codes and amendments. The following comments must be addressed before a buildingഀ
permit is issued.ഀ
For processing:ഀ
Please submit (5) complete sets of revised construction documents containing the requestedഀ
information or plan revisions with all revisions clouded or otherwise identified.ഀ
Please respond in writina to each comment by marking the attached list or creating aഀ
response letter. Indicate which plan sheet, detail, specification, or calculation shows theഀ
reauested information. Please send revisions to the attention of the plans examiner with theഀ
building permit application number noted.ഀ
Responses such as "will comply with code" are not adequate. Revised drawings mustഀ
clearly show code compliance.ഀ
A RESPONSE LETTER MUST BE INCLUDED WITH THE REVISED PLAN SUBMITTAL.ഀ
Please be sure to include on the resubmittal the engineer's or architect's "wet" stamp, signature,ഀ
registration number and date on the cover page of any structural calculations, all structural detailsഀ
and structural sheets of the plans. For commercial or multi-family projects all sheets of the plansഀ
must be stamped.ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018.2. DOC Page 1 of 18ഀ
BUILDING DEPARTMENT COMMENTS:ഀ
Common Project Comments: (CPC are attached to each permit comment letter)ഀ
3. Preliminary plan review meetings had discussion regarding the submittal of Memorandum ofഀ
Understandings (MOU). MOU's defined in these meetings would be "used to define or clarify the useഀ
of a code section, agreement to the installation of a system not covered specifically by the code orഀ
clarify the use or component of a building. None of the agreed upon MOU's were submitted forഀ
review. Please provide the following MOU's for review:ഀ
a) Use of assumed property lines and fire separation distance.ഀ
b) Fire command roomഀ
c) Smoke management systemsഀ
d) Opening between parking garage and Lodge Tower parking garageഀ
This item should be submitted as an Administrative Modification.ഀ
e) Fire separation between the new building and existing buildingsഀ
f) Use of 508.2 for creating separate buildings as it relates to each buildingഀ
This may be an Administrative Modification depending on writing and design.ഀ
g) The separation between One Vail Place and new Skier Servicesഀ
This item should be submitted as an administrative Modification.ഀ
4. Preliminary plan review submittal meetings had discussion regarding the submittal of Administrativeഀ
Modifications (AM). AM's as defined in these meetings would be based on International Buildingഀ
Code Section 104.10. Where practical difficulties are involved in carrying out the provision of thisഀ
code, a modification to the code may be granted by the building official after justification that theഀ
modification will not lesson health, accessibility, life and fire safety, or structural requirements. Theഀ
following AM's have been discussed and are being implemented into the plans. Please provide theഀ
following or amend plans accordingly to comply with the code.ഀ
a) Separation between Chalet buildingsഀ
b) Elimination of elevator smoke doors at residential levels of the Chalet buildingsഀ
c) Opening between parking garage and Lodge Tower parking garage. When writing thisഀ
modification be sure to use the correct Type 1B construction type for Lodge Tower.ഀ
Please amend G sheets to correctly identify the Lodge Tower as Type IB construction.ഀ
d) The separation between One Vail Place and new Skier Servicesഀ
5. Be sure to amend the Fire & Life Safety Report as necessary when changes are made to the plansഀ
that may affect the discussions made by the Report.ഀ
As discussed in the meeting on 0510212006; the Fire and Life Safety Report, Memorandums ofഀ
Understanding and Administrative Modifications will be reformatted for clarification and easeഀ
of understanding.ഀ
6. Provide a precise site plan showing exact locations of assumed property lines. If locations of assumedഀ
property lines are close enough to exterior walls to require rating of walls and opening protection,ഀ
provide details.ഀ
Please show the location of the actual property line between the new Spa and the Lodgeഀ
Tower. Sheet G016 shows an assumed property line between these two buildings at 5'6" fromഀ
the Spa and 21' 11 " from the Lodge Tower. As a result of this assumed property line, theഀ
Lodge Tower would need a rated wall and protected openings. Please clarify?ഀ
Chalet property lines are also a concern. During the 0510212006 meeting we were told toഀ
reference G026 for location of property lines. This sheet shows the Chalet buildings crossingഀ
over or placed on the property lines. Please clarify.ഀ
7. Fire and Life Safety Report states the use of 1 hour fire walls per IBC Table 705.4. This table doesഀ
not allow for 1 hour fire walls anywhere. Please clarify.ഀ
CADocuments and Settings\mroyer\My Documents\Plan ReviewWront Door\tov-b06-0018.2. DOC Page 2 of 18ഀ
The Fire and Life Safety Report was modified in an attempt to clear this issue. This somewhatഀ
still remains. We understand the intent after the last revision. Please clarify based on theഀ
example below. For instance:ഀ
Page 17 of the April 3 Fire and Life Safety Report has a table regarding separations betweenഀ
buildings. I would like to use the 3rd item in the table as an example. Table States-ഀ
Description: Mid-Level Parking garage/ Spa for Lodge at Vail Lower Level; Separation Reason:ഀ
Spa Construction Type; Occupancy Group: S-2 Type IA; Fire Ratin_g: 1 hour Occupancyഀ
Separation Wall.ഀ
Based on the plan, the Lodge at Vail is Type IA, the parking garage is Type IA. The reason forഀ
separation is not really type of construction because they are both the same type. The reasonഀ
for the separation is occupancy. The Fire Rating isn't an occupancy separation wall becauseഀ
this doesn't exist in the IBC; the plan is actually shown correctly as a 1 hour barrier.ഀ
I believed the confusion was coming from the table (Fire and Life Safety Report) saying oneഀ
thing and the plans showing another. Please clarify.ഀ
9. Accessibility requirements do not appear to be included within any plan for this project. Pleaseഀ
amend plans to include the following:ഀ
a) Accessible parking spaces and loading zones.ഀ
b) Accessible route from the parking and loading zones to the buildings.ഀ
c) Accessible routes to each building on the site which are required to be accessible.ഀ
d) Signage details for parking, striping, routes, restrooms, etc.ഀ
e) Restroom details for fixtures, grab bars and accessories.ഀ
This packet is normally not a deferred submittal. Amend plans and specification for allഀ
required signage per IBC Section 1110.ഀ
Show the location of required Site Signage on sheet C37.0 (signage plan).ഀ
The response states that parking spaces were provided. 2 were located on the plans. Pleaseഀ
respond with sheet numbers and locations of which all accessible parking spaces can beഀ
found. Also, include the parking calculations used to determine the required number ofഀ
spaces. The space and loading zone shown on sheet A106 needs to be dimensioned. Be sureഀ
to include the required number of accessible spaces and van accessible spaces.ഀ
When the plan shows the location of inaccessible entrances and the required number ofഀ
accessible parking spaces then the accessible routes will be reviewed for code compliance.ഀ
The routes may need to be identified on a separate sheet or sheets to be clearly represented.ഀ
10. Amend plans to include stair signage plan, details and identify the location of the signage. Many ofഀ
the exit enclosures require the occupants to travel up to get to exit discharge. Clearly identify theഀ
direction of travel to the exit discharge.(IBC 1019.1.6)ഀ
We were unable to locate the signage if it was provided with this submittal. Please provide orഀ
respond with the location in which to find this information.ഀ
11. Amend plans to include gates located at the level of exit discharge to eliminate occupants of theഀ
building from entering an enclosure and passing by the level of exit discharge. (IBC 1019.1.6)ഀ
The response states that gates have been added. Provide written response of where theseഀ
gates were added. What sheets were modified?ഀ
12. Elevator door which do not open into a lobby need to be provided with a smoke control door inഀ
accordance with IBC Section 715.3.5.3ഀ
CADocuments and Settings\mroyerNy Documents\Plan ReviewWront Door\tov-b06-0018.2. DOC Page 3 of 18ഀ
The Chalet Building elevators penetrate more then 3 stories which would require smokeഀ
control. Please amend plans accordingly. This was a topic at the 0510212006 meeting and mayഀ
be handled by an Administrative Modification.ഀ
14. The size of main elevator cars used for fire/emergency access needs to be determined by the Townഀ
of Vail Building and Fire Departments. Standard 24" x 76" required by code will not accommodate theഀ
stretchers used by emergency personnel. Please confirm the required size.ഀ
This has been a topic of discussion at various 42401Town of Vail meetings. The question isഀ
not whether or not you are compliant with the letter of the code, but whether or not you haveഀ
coordinated with the Town of Vail Fire Department regarding the elevator sizes. This buildingഀ
is unique in design with regard to emergency access. This is one of the smoke managementഀ
and other conditions within this project that are being provide above and beyond the code.ഀ
The Fire Department is looking at several items in respect to performance. The comment hereഀ
is to verify that coordination is occurring with the Fire Department to ensure they haveഀ
adequate emergency access. The topic has surfaced because the stretchers used by theഀ
Town of Vail emergency personnel are larger than the code required size for stretchers.ഀ
Architectural Comments:ഀ
Site Comments:ഀ
17. Fence shown on L207 shows the bottom of the fence to far above grade. Max distance betweenഀ
grade and bottom of fence 2 inches. (IBC 3109.4)ഀ
Please amend detail 2/L208. In one location this detail shows 3-314" at the bottom of theഀ
barrier.ഀ
19. Amend plans to show gates compliant with the pool barrier requirements. (IBC 3109.4.1.7)ഀ
Clearly show gate as self-latching, show location of latch and protection of the latch if locatedഀ
less than 54" above the walking surface.ഀ
28. Sheet L302 calls out stair and handrail details on L307. There are no stair and handrail details onഀ
L307. Clarify.ഀ
Handrail shown in detail 3IL307 must be gripable and comply with IBC section 1009.11.3.ഀ
Amend plan to clearly show this handrail is compliant.ഀ
29. Amend plans to include all component which will be required and specified within the Administrativeഀ
modification for the opening between the Parking Garage (2 places) and the existing Lodge Tower.ഀ
The existing Lodge Tower plan has identified the parking garage as Type I-B. This needs to be takenഀ
into consideration when exercising IBC section 508.2. Same type of construction was used during theഀ
pre-submittal meetings that discussed the separation. Please address the type of constructionഀ
separation and opening protection accordingly. Please coordinate plans and design with the Lodgeഀ
Tower designers.ഀ
This comment was discussed in the 0510212006 meeting with 42140, BCER, Town of Vail andഀ
Colorado Inspection Agency. An Administrative Modification will be created to clarify theഀ
opening and equivalencies provided to allow this opening on the property line between theഀ
two buildings. This Administrative Modification must be consistent with the Modificationഀ
created by the Lodge Tower. It was discussed that one document be created that is signedഀ
and agreed upon by both property owners.ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018.2. DOC Page 4 of 18ഀ
Mechanical Comments:ഀ
32. Where is the gas piping for the fountain coming from? Sheet L308 is referenced and does not exist.ഀ
Amend plans to show the location of a gas shutoff valve near the fire pit.ഀ
Energy Code Review:ഀ
Envelope Com Checkഀ
The Town of Vail recently established the heating degree days and cooling degree days for aഀ
base of 65 degrees. The numbers provided are:ഀ
Heating degree days (base 65 degree F): 9826ഀ
Cooling degree days (base 65 degree F): 3ഀ
1 apologize for the notice of these numbers; however I have been instructed to pass thisഀ
information on and require modification of the Envelop Compliance Certificate and design.ഀ
Amend reports to reflect the design criteria established by the Town of Vail.ഀ
Site Structural Comments:ഀ
Note: structural comments are numbered "S1,S2...... and are also given a designation with regards to the topic, as follows:ഀ
DC = design criteria; F= foundations; D = drawings; C = structural calculations; LS = lateral system.ഀ
Site Comments:ഀ
S5. F SF sheets: verify pavement / subgrade above the EPS under roadway (20 psi) has beenഀ
designed to span between HS-20 tires, or depth is sufficient to distribute loads such that 20 psi is aഀ
sufficient strength under the roadway.ഀ
KMA, 515106: Note, sheet C35.0 shows a 6" roadway slab, please verify adequacy.ഀ
S7 DC Sheet L202: FOR to verify that various landscaping structures such as boulders, ponds,ഀ
stone walls, pavers, and other superimposed dead loads have been appropriatelyഀ
considered in the structural design; verify any concentrated bearing on EPS filler (i.e.ഀ
such as due to any retaining walls, 6/1-205, or massive stone structures, 3/L.208, etc.)ഀ
M&N Response:ഀ
These issues have been discussed with the EPS Designer and the Landscape Designer.ഀ
The retaining walls were designed based on the allowable bearing pressure on the EPS.ഀ
The designer of the boulder walls will need to be informed of these allowables also.ഀ
KL&A, 5/5/06: See also comment in Volume 1 section. No calculations have been provided atഀ
this time. We assume that bearing capacity and stability of landscaping or stone structuresഀ
designed by others will be reviewed and checked by the FOR during the submittal process.ഀ
Comment closed.ഀ
Building A Structural Comments:ഀ
Note: structural comments are numbered "S1,S2...... and are also given a designation with regards to the topic, as follows:ഀ
DC = design criteria; F= foundations; D = drawings; C = structural calculations; LS = lateral system.ഀ
General Structural Comment: Due to the inherent connectivity between the various structures in this project, there may beഀ
comments from this Volume's details in other Volume's comments, and vice versa. Note also that this review and eventualഀ
approval does not permit the violations of any section of the building code, or any other ordinance or State law.ഀ
C\Documents and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018.2. DOC Page 5 of 18ഀ
S4. F Soils report, page 38, items 7 & 8 discusses underpinning of existing structures adjacent toഀ
new construction. Please discuss how the existing structures will be supported duringഀ
construction and permanently. Verify that vertical surcharge loading has been applied to theഀ
below grade permanent foundation walls and parking structure as appropriate. Verifyഀ
underpinning system does not conflict with the new foundations for this parking structure.ഀ
M&N Response:ഀ
Underpinning of existing structures is responsibility of General Contractor. Surchargesഀ
from vertical loading was included in design of new, below structural walls.ഀ
KL&A, 515106: No surcharges seem to have been included in the lateral pressures inഀ
the calculations. Surcharges are shown acting vertically but the horizontal loads areഀ
not increased, please indicate where these calculations are located.ഀ
S4A F Calculations (p. FW5) don't appear to include soil full height at existing building. This appearsഀ
correct west of gridline 18, as slab on grade / offices will be constructed here, however westഀ
of the ski club foundation walls, there appears to be soil for two stories tall, creating a twoഀ
span condition at some exterior concrete walls. Verify soil backfill height and verifyഀ
calculations. Provide calcs for 2-story at-rest retaining wall conditions. See also commentഀ
S4B.ഀ
M&N Response:ഀ
Please refer to the calculations sheet FW1 for a "key". The calc on FW5 applies to the northഀ
foundation wall from west of grid 25 to grid 17. The only two-story retaining walls are alongഀ
the south wall per "F", "J", and "I" in the key.ഀ
KL&A, 5/5/06: Please address the unbalanced soil lateral load issue. Describe theഀ
lateral load path at the intermediate slab. We suggest holding a meeting to discussഀ
and resolve this issue, as needed.ഀ
S41B. F/ LS It appears that the ramp at the south end, as well as the permanent shoring at the southഀ
side create an unbalanced lateral soil loading at the parking structure, at the upper parkingഀ
level, and lid level. Verify that concrete diaphragm and concrete shear walls below have beenഀ
designed to resist this unbalanced soil lateral loading. Verify drag loads / connections fromഀ
diaphragms to concrete walls. Provide calculations.ഀ
M&N Response:ഀ
The permanent shoring will resist the unbalanced soil loading. The permanent shoringഀ
is to be designed and detailed by an engineer of the shoring subcontractor.ഀ
KL&A, 5/5/06: This response does not address the issue. FW45 & FW67 show twoഀ
span walls, please explain how the center reaction is transmitted to the supporting soil.ഀ
Verify load to middle parking level acting southwards from the north walls isഀ
transmitted to the perimeter walls and cores with appropriate lateral connectionsഀ
(dowels, shear friction, foundation bearing pressure due to moments in short walls,ഀ
etc.). We suggest holding a meeting to discuss and resolve this issue, as needed.ഀ
S4C. F/LS It seems that the parking structure compressible material is required between theഀ
permanent shoring wall and the parking structure to allow the two systems to behaveഀ
independently, and to avoid the permanent soil retaining system from loading the parkingഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018.2.DOC Page 6 of 18ഀ
structure. Details 13&14/S004 do not indicate this is being done. Also, it appears fromഀ
13/S004 that the new concrete walls will be constructed directly against the permanentഀ
shoring system, which it seems would move into the structure over time. Please comment.ഀ
M&N Response:ഀ
Section 14/S004 occurs within the building with no shoring. Section 13/S004 is the onlyഀ
section that has the wall cast against permanent shoring. M&N's design and detailing wereഀ
completed per direction from the General Contractor and Shoring Contractor.ഀ
KL&A, 5/5/06:This response does not address the issue. Please confirm that the wallsഀ
were designed for lateral soil loads where not adjacent to permanent shoring walls.ഀ
S5. D S001: Column Schedule. Schedule includes (2) line items "Configuration". These variousഀ
configurations do not seem to be defined anywhere in the documents.ഀ
M&N Response:ഀ
These configurations are nomenclature used by CRSI. We have added notes to the scheduleഀ
to clarify.ഀ
KL&A, 5/5/06: FOR please verify cross-tie in one direction only @ 4F tie configurationഀ
on S001.ഀ
S19 F S004: Section 10. Is drainage a consideration in the structural design for retaining wallഀ
(typical all walls)? Verify Lateral pressures include hydrostatic pressures as req'd, the garageഀ
extends well below the measured water table per soils report. Also, wall scales 1'-2 thk, butഀ
plan says 1'6. Which is correct?ഀ
M&N Response:ഀ
A permanent dewatering system is to be provided so the hydrostatic pressure does not needഀ
to be accounted for. Drawings are not necessarily to scale nor should they be scaled forഀ
dimensions. Written dimensions shall govern.ഀ
KL&A, 5/5/06:Closed regarding hydrostatic pressure & scaling issues. Verify edgeഀ
distance for shear friction dowel from wall to footing. It appears dowel will burst outഀ
the back of the wall. Please verify. Similar at 11,12,13/S004.ഀ
S21 F,D S001: concrete general notes: consider using air entrainment at loading dock slabs and otherഀ
garage level concrete that will be exposed to weather- clarify notes as required.ഀ
M&N Response:ഀ
Concrete for slabs on grade in tunnel parking garage and loading dock will be noted asഀ
needing to have 6% to 8% air entrainment.ഀ
KL&A, 5/5/06: This does not appear to have been noted on the drawings. FOR toഀ
coordinate communicating this decision with the contractor. Comment Closed.ഀ
S24 F S005: Section 2. Horizontal rebar in wall not indicated.ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018.2. DOC Page 7 of 18ഀ
M&N Response:ഀ
Please refer to revised plan.ഀ
KL&A, 5/5/06: Rebar does not meet ACI minimum of 0.002 (ACI 14.3.3)ഀ
S31 F S005: Section 10, 11. Where are elevation of the ledges defined? #8 is not developed for fullഀ
M&N Response:ഀ
Elevations of ledges are shown on the plans.ഀ
KL&A, 5/5/06: Address development at 10/S005 vertical bar.ഀ
S39 D S101: What is the top of footing elevation at the elevator near L.5 16.5? Is the combinedഀ
footing below the stair and col C14 all at this lower elevation? If so, define backfill SOG @ഀ
stair (detail cut 6/S005 is incorrect?). The 3'-0 detail at east side of stair is not well placed toഀ
define dimensions.ഀ
M&N Response:ഀ
Please refer to the revised plans and section.ഀ
KL&A, 5/5/06: Note it is not clear where the 5 foot thick tower crane footing ends /ഀ
begins and how the mat footing and other adjacent monolithic footings tie together,ഀ
suggest revisit this area. FOR please coordinate these issues as required, commentഀ
closed.ഀ
S49 F S101: Bldg A fndn plans. Ftg F18 in footing schedule reinf. is not noted top, bot or whichഀ
way?ഀ
M&N Response:ഀ
Please refer to revised plans.ഀ
KL&A, 5/5/06: Plans have not been changed.ഀ
S61 F S103 General Comment: Wall strip foundation reinforcement does not appear to be calledഀ
Out anywhere on this or other sheets? Pis provide or clarify drawings.ഀ
M&N Response:ഀ
Please refer to item S20.ഀ
KL&A, 515/06:ഀ
S65 F S103 Verify Min 48" frost depth is achieved @ exterior/exposed loading dock areas - someഀ
footing elevations are not identified, ref. detail 5/S004 also. Consider corrosion of SOG reinf.ഀ
due to salts & temp effects.ഀ
M&N Response:ഀ
The loading dock is interior heated space.ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-W-0018.2. DOC Page 8 of 18ഀ
KL&A, 5/5/06: Consider slab reinforcing corrosion due to salts and moisture fromഀ
vehicles at the slab on grade and at flat plate slabs at all levels. Ref. ACI Ch. 4:ഀ
increased cover, increased use of pozzolans, epoxy coated rebar, epoxy coating onഀ
driving surface, etc. Please comment.ഀ
S66 C Wall beam calculations 131-1384 contain much information that the drawings S201, S202, S203ഀ
do not seem to reflect. For example, calcs page B16 shows different top and bottomഀ
reinforcing, as well as a seemingly very important pilaster below a large beam, and #5x60"ഀ
diagonal bars at corners and pockets. The pilaster is not detailed on the structural drawings.ഀ
Please coordinate required reinforcing per calculations with the drawings, drawings appearഀ
incomplete.ഀ
M&N Response:ഀ
Please refer to the revised wall beam elevations and calculations.ഀ
KL&A, 5/5/06: Diagonal bars and details @ wall to column connection are still notഀ
detailed, please review. Sheet S201, ref: "typical wall intersection detail." Ref.ഀ
comment S109.ഀ
S66a D Wall beams typically have a slab connecting in at the top of the beam, providing lateralഀ
bracing of the compression flange, however at the bottom of the wall beam, typically no slabഀ
exists. Verify that sufficient lateral bracing restraint is provided at negative moment regionsഀ
where the bottom of the wall beam is in compression, i.e. W134 at the intermediate columnഀ
support.ഀ
M&N Response:ഀ
Per PCA notes for deep flexural members, all the wall beams are adequately braced toഀ
satisfy ACI provisions. Refer to attached calculations.ഀ
KL&A, 5/5/06: We feel that PCA guidelines do not apply to conventionally reinforcedഀ
concrete structures. ACI 10.7 states specifically that lateral torsional buckling andഀ
nonlinear strain distribution need to be considered. ACI References are given, of theseഀ
10.22, the Park and Paulay text seems a more appropriate reference. We suggestഀ
holding a meeting to discuss and resolve this issue, as needed.ഀ
S66c D 16/302: W134 detail: verify direction of shear friction hook; as bar elongates concrete cover willഀ
burst out at this location if not extraordinarily well developed. See ACI figure R11.9.2 (similarഀ
to corbels). Verify hook development length in the wall and development length into theഀ
beam, this information needs to be shown in the detail.ഀ
M&N Response:ഀ
Please refer to the General Notes on S001 for development length information. Note: Dueഀ
to head height constraints, dowels cannot be turned down.ഀ
KL&A, 5/5/06: Development into beam is insufficient: Ld = 48" for bottom barsഀ
(which may not be accurate as a great number of bars are required and no position isഀ
shown in the detail), and 2'-9" at most is provided with a 4'-0" horizontal leg. Also atഀ
the hooked end, Ldh = 19", larger than the V-5" available. Shear friction calculationsഀ
appear to consider the reinforcing fully developed on each side of the joint. Pleaseഀ
revisit the beam to wall and slab to wall details for adequate rebar development.ഀ
S67 D S104 slab to wall connectors are not detailed. Pls show a detail. See comment S66c.ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018.2. DOC Page 9 of 18ഀ
M&N Response:ഀ
Please refer to section 4/S302 and section cut at grid N.1 near grid 12.9.ഀ
KL&A, 515/06: Ref. S66c: verify rebar development.ഀ
S72 D S105 Additional rebar shown in 12" slab @ line 21.3. Is this "typ" additional reinf typ @ lineഀ
21.3 or line N or typ at all lines within the 12" slab area? If typ @ all lines within 12" slabഀ
shouldn't the bottom lengths very depending on the spacing of the columns.ഀ
M&N Response:ഀ
Please refer to revised plan.ഀ
KL&A, 5/5/06: Plans are not revised, please address.ഀ
S73 D S105 New 8" SOG south of L: do you want control joints? If so please define the spacingഀ
and depthഀ
M&N Response:ഀ
Provide control joints per General Note 5.C/S001 except sawcut on 1" deep. Generalഀ
Contractor to provide proposed layout.ഀ
KL&A, 5/5/06: Verify 1" depth is shown on the drawings, see S65 regarding rebarഀ
corrosion.ഀ
S74 D S105 Seems you need a defining section thru the top of the conc wall at the north tunnel wallഀ
at rectangular columns / PT beam / flat slab / vertical wall intersection btwn N & L.ഀ
M&N Response:ഀ
See new Section 20/S301.ഀ
KL&A, 5/5/06: See S91 regarding shear friction dowels.ഀ
S77 D S105 Col/bm details at lines 24, 23, & 22 seem complicated. A section or description isഀ
required for checking.ഀ
M&N Response:ഀ
See new Section 21/S301.ഀ
KL&A, 5/5/06: See S91 regarding shear friction dowels. Column is not shown, addressഀ
column / beam detail.ഀ
S78 D S105 Area south of line L has 6" steel studs @ 1'-4 o/c. What structural sheathingഀ
is on top of these steel studs? Define/detail connection to CMU & conc walls.ഀ
M&N Response:ഀ
Refer to revised plans.ഀ
KL&A, 5/5/06: Address connections of beams and deck in 8/S302.ഀ
C\Documents and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018.2. DOC Page 10 of 18ഀ
S79 D S106 Section 5/S302: Cut thru a conc wall in the NW area of this sheet appears to beഀ
incorrect in that it does not represent plan conditions. Pis Clarify.ഀ
M&N Response:ഀ
There is a section cut for 15/S302 in the area described.ഀ
KL&A, 5/5/06: Call out rebar in 15/S302. Verify dowel for 50 plf guardrail loading.ഀ
S91 D S108 Verify shear friction for 100% of shear loads for the following beams (see ski clubഀ
comments)ഀ
611 -Span 1 & Span 3ഀ
B10 -Span 1ഀ
B12 -Span 1ഀ
B9 - South End.ഀ
(Ref. 16/S302) Verify dowel development length - seems also vert dowel should be turnedഀ
downwards, ref. comment S66c.ഀ
M&N Response:ഀ
See response to Comment S66C.ഀ
B11 - Span 1 is designed as a cantilever section so it is not meant to be supported onഀ
its left side. B11 - Span 3 is supported 100% by shear friction transfer as well as B-9ഀ
South End. B-10 and B-12 are supported by the ledge that exists in WB4, but can beഀ
supported 100% by shear friction. See revised calculations. Dowel developmentഀ
length should be determined by the parameters set forth by the General Notes onഀ
S001.ഀ
KL&A, 5/5/06: Detail 16/S302 says (9) #9; calculation shows (14) #10 for B11, (12) #9 forഀ
B9, and (8) #10 for B10. Calculations and drawings appear to conflict. Suggest use aഀ
schedule for dowels required at all beams supported by shear friction. Nothing isഀ
called out at the west end of B11 on S104. Verify all beam dowels and connections.ഀ
See also comment S66c.ഀ
S92 D S108 It is unclear what supports intersecting bms B6 with 1311, span 1, at slab edgeഀ
illustrated by detail 9/S303?ഀ
M&N Response:ഀ
Detail 9/S303 is on the 8183'-6" level. Refer to Section 5/S002 for B6 to 1311ഀ
connection.ഀ
KL&A, 5/5/06: The issue is the support of the west end of B11, span 1. Pleaseഀ
comment.ഀ
S94 D S109 Bm @ west end of pool is not identified?ഀ
M&N Response:ഀ
Refer to item S86ഀ
KL&A, 5/5/06: S108 & 109: beams at the west and east ends of the pool are still notഀ
identified (3'-0" wide). Please verify.ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018.2. DOC Page 11 of 18ഀ
S95 D S109 Bms B13, B14, B15 - Span 1 are cantilevered from B13, B14, B15 Span 2 instead ofഀ
as noted in the beam schedule- please verify schedule.ഀ
M&N Response:ഀ
This area where the cantilever beams are located has been revised completely forഀ
construction sequencing. See revised S102, S105, and S109.ഀ
KL&A, 5/5/06: Beam schedule S002 still shows a cantilever span, please verifyഀ
schedule is correct.ഀ
S96 D S109 Detail 14/S301 is cut on S109. This detail seems to define new steel framing as wellഀ
existing framing to be removed:ഀ
a) Detail 13/S301 Appears to be a section thru this area however is not referencedഀ
anywhere - cut 13/S301 on plan or detail.ഀ
b) Dims @ 3 places 14/S301 is cut appear different; are these the same detail &ഀ
framing? Please verify.ഀ
c) Verify W16 frames into (E) W12ഀ
d) Provide Load for TS hanger.ഀ
M&N Response:ഀ
a) Please refer to revised drawing.ഀ
b) Refer to architectural drawings for actual layout. Layout to be field verified.ഀ
C) The W16 frames into the (E) W12.ഀ
d) 6000lbsഀ
KL&A, 5/5106:ഀ
a) Comment closed.ഀ
b) FOR to coordinate, comment closed.ഀ
C) Please verify, this is a difficult connection with the load criteria on the generalഀ
notes, S001. Comment closed.ഀ
d) This is required on the drawings for connection design. Alternatively, call out aഀ
weld. FOR to coordinate, comment closed.ഀ
S102 D S110 Call out (2) conc bms spanning east & west between PB 7-2 bms are not identified, forഀ
ski club support.ഀ
M&N Response:ഀ
Beams will be Type "134" from schedule on S002.ഀ
KL&A, 5/5/06: Please identify the beams on plan with the B4 keyed note.ഀ
S104 D S110 Two PB11 beams, single span, seem to bear on a conc wall at a right angle bend in theഀ
wall. It would appear that the 320k tension will act to tear the rt angle wall apart. Suggest theഀ
FOR check. (Near 9.7)ഀ
M&N Response:ഀ
The beam will be shifted to the west. (Note: This did not get revised on the 4/3/06ഀ
drawings but will be coordinated with future addendum.)ഀ
KL&A, 5/5106: FOR to coordinate, comment closed.ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018.2. DOC Page 12 of 18ഀ
S107 D S201 Wall Beam WB1: Special rebar is req'd above and below the large wall opening. Detailഀ
14/S302 indicates 8 hz bars in the bottom of the wall. This is contradicted on shts S202ഀ
where 15410 in (3) layers are mentioned. Verify rebar T & B. Note it seems that the wallഀ
acts more like coupling beams and tension/compression columns @ this large opng - designഀ
for shear and combined bending and axial loads.ഀ
M&N Response:ഀ
Details are general and are not intended to show specific items unless specificallyഀ
called out. See attached calculations.ഀ
KL&A, 5/5/06: Shear stirrups are required by new calcs. Also, it seems column ties areഀ
required per ACI chapter 10 (stirrups plus cross ties per typical column details). Callഀ
out ties on the drawings, suggest provide a section through WB1 at the opening.ഀ
Extend stirrups into the supporting wall for a distance "d" at the lower beam, minimum.ഀ
S109 D S201 Show detail @ intersection of WB3 & WB4ഀ
M&N Response:ഀ
Please refer to revised Sheet S201 for detail. (Note: #9 Hooked bars should extend toഀ
far face of wall. To be coordinated on future addendum.)ഀ
KL&A, 5/5/06: FOR to coordinate, comment closed. See S66.ഀ
S110 D/C S201-3 Verify wall beams consider ACI provisions for deep beams regarding nonlinearഀ
distribution of strain and lateral buckling (ACI 318 10.7.1) - calculations do not appear toഀ
consider these provisions.ഀ
M&N Response:ഀ
Wall beams meet the required ACI provisions for deep beams as required above. Seeഀ
additional calculations.ഀ
KL&A, 5/5/06: Please explain which reference is used in the calcs (i.e. Figure 2, Figureഀ
3). See comment S66a.ഀ
S110a C deep beam calcs, B12 assumes that shear strength is 10*sgrt f'c, however the calculation ofഀ
Vc +Vs is not provided. Quick calculations show that typical shear reinforcement of #4 @ 9"ഀ
O.C. vertical and #4 @ 12" O.C. vertical are roughly 6*sgrt f'c. This typically does not appearഀ
to cause a problem with shear capacity, however for certain beams (WB11, calcs p. B49) thisഀ
seems to cause an overstressed condition. Also, the phi factor does not seem to have beenഀ
applied, f=0.75 for shear. Please review calcs and increase shear reinforcing as required.ഀ
M&N Response:ഀ
Shear reinforcing for wall beams was reviewed and verified. Please refer to revisedഀ
wall beam elevations.ഀ
KL&A, 5/5/06: There appears to be no change in shear reinforcement on the drawings.ഀ
Please show numerically what the quick numbers we have calculated above areഀ
missing, and that shear capacity of WB11 and other beams is sufficient. No newഀ
calculations for shear appear to have been provided.ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018.2. DOC Page 13 of 18ഀ
S113 D S202 WB7: What is special reinforcing is req'd @ double openings in the wall above 8182.-6?ഀ
(ties, T&B bars); sim @ center column btwn doorways- these elements need individualഀ
designs and details as columns and beams - calcs p. B30-34 do not show these designs.ഀ
M&N Response:ഀ
Please refer to revised wall beam elevations.ഀ
KL&A, 5/5/06: This does not appear to have been addressed in the drawings. Theഀ
calculations presentation is not clear and we can not locate any new calculations forഀ
this. Please check.ഀ
S115 D S203. WB11 Verify 5'-0" long hooks @ end - verify this satisfies ACI 12.12.4ഀ
M&N Response:ഀ
Development lengths are to be determined during the shop drawing process perഀ
General Notes on S001 and are not to be scaled off the elevations.ഀ
KL&A, 5/5/06: Verify ACI 12.12.4 is satisfied with a standard hook at all locations at wallഀ
ends, as this is what will be provided if a length is not specified.ഀ
S126 D S302 4/S302: #5 Dowel is not developed on either end (Ldh or Ld); also hook turnedഀ
upwards will blow out conc corner. Roughen for shear friction.ഀ
M&N Response:ഀ
Dowel has development length. Calculations for shear friction do not requireഀ
roughening.ഀ
KL&A, 5/5/06: See S91 (S126 closed).ഀ
S132 D S303 Section 2: Refers to "re plan", there is nothing shown on plans - please verify.ഀ
M&N Response:ഀ
This section should be cut on S109 near Grid L.5-22 and Grid R-24. This revision to S109 willഀ
be added in the future addendum.ഀ
KL&A, 5/5/06: FOR to coordinate, comment closed.ഀ
S143 DC S001: Appears ground snow load is required for ground level lid design, in lieu of roof snowഀ
load used: pg = 100/.7=143 psf. Please verify.ഀ
M&N Response:ഀ
Roof framing is designed to comply with the Town of Vail amendments to the 2003ഀ
1 BC.ഀ
KL&A, 515/06: We understand that the Town of Vail has been made aware of thisഀ
comment, and has decided that the roof snow load is applicable to the garage lidഀ
structure, as designed. Comment closed.ഀ
S145 D,C S110: Transfer beams for building C located between consecutive PT beams are not calledഀ
out on plans. Please provide details and calculations for all such beams.ഀ
M&N Response:ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018.2.DOC Page 14 of 18ഀ
Please refer to revised plans.ഀ
KL&A, 5/5/06: Comment closed (See comment S102)ഀ
S147 D,C S104: The calculations for the 12" thick concrete slab (page S44) indicate punching shearഀ
reinforcement is required at column 9 (grids 0.7-14.3). Please verify and provide theഀ
appropriate shear reinforcement.ഀ
M&N Response:ഀ
See revised plan.ഀ
KL&A, 5/5/06: Type B stud rails are based on 20" thick slab, please provide stud railsഀ
for 12" thick slab.ഀ
S150 DC Please provide a Post-Tensioning Specification section.ഀ
M&N Response:ഀ
The concrete specification with our General Notes on S001 provide the requiredഀ
information.ഀ
KL&A, 5/5/06: We feel that additional direction is required from the EOR, such asഀ
testing requirements, contractor qualifications, submittal requirements (i.e. provideഀ
bursting steel, etc.), references, material standards. FOR please review and makeഀ
revisions to the specs or general notes as deemed necessary. Comment closed.ഀ
S151 C Calculations for the B12 span3 do not match the drawings. Please verify.ഀ
M&N Response:ഀ
B12 span3 does match the drawings on S002.ഀ
KL&A, 5/5/06: Calculation on pages R56 and R57 indicate a larger section for B12 spanഀ
3 than the document show.ഀ
S155 D S109: The beam at the entrance of the tunnel near grids R.5-25.5 is not scheduled. Pleaseഀ
specify mild reinforcement, shear reinforcement, and PT tendons.ഀ
M&N Response:ഀ
Refer to revised beam schedule on S002, revised plan sheet S109, and attachedഀ
calculations.ഀ
KL&A, 5/5/06: Please identify the beam on plan with a keyed note.ഀ
S165 D S108: Please clarify where plan note 6 occurs by hatching the specific areas and verify allഀ
calculations take the extra soil weight into account.ഀ
M&N Response:ഀ
The "hatched" areas referenced in Note 6 are on the east and west sides of the 16-0" wideഀ
roadway that is on top of the structural slab/beams from the upper level (8184'-0") at Grid L-ഀ
10.8 down to the lower Level (8168'-2") at Grid Q.5-12.3. This information will be shownഀ
on the future addendum.ഀ
CADocuments and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-001 8.2. DOC Page 15 of 18ഀ
KL&A, 5/5/06: FOR to coordinate, comment closed.ഀ
S171 S108 grid intersection 21.3/L, the elevation of the 12" slab north of beams B22 and B21 can not beഀ
determined. On plan the PB4 and PB5 beams are shown higher than the 12" slab to the northഀ
as indicated by a step symbol; however, section 7 on S303 shows the PT beams lower thanഀ
the slab. Please provide on plan: elevations of the north slab adjacent to the supportingഀ
beams B22 and B21, and elevations of the PT beams and non-PT supporting beams. Alsoഀ
please correlate these elevations to detail 7 on S303. Please provide the reinforcing detail atഀ
grid intersection 21.3/L showing interfacing of reinforcing for P1310,1322-5, B21-1, the columnഀ
below, and the slabs.ഀ
M&N Response:ഀ
These elevations are provided on the plans. Please reference sheet S109 and elevationഀ
noted on S108 near grid 16.4.ഀ
KL&A, 5/5/06: Please verify this information is changed on the drawings, we canഀ
not find the elevations and information requested. FOR to coordinate, commentഀ
closed.ഀ
S174 S109 S003 provide calculations and conformance to AC1318 section 18.13 Post-tensioned tendonഀ
anchorage zones.ഀ
M&N Response:ഀ
These calculations can not be completed or provided until the specific characteristics of theഀ
anchorage devices are determined during the shop drawing phase. Specific reinforcingഀ
requirements shall be determined by the P.T. shop drawings for review by the Engineer ofഀ
Record.ഀ
KL&A, 5/5/06: Submittal requirements are not shown on the drawings. See S150.ഀ
S174 is considered closed, FOR to coordinate.ഀ
S175 S110 P131 requires approximately 38 tendons to achieve the final effective force of 1015k. Pleaseഀ
provide detail of anchorages and tendon profile to get the drapes specified consideringഀ
congestion of bursting, shear and flexural reinforcing. Please specify if multi strandഀ
anchorages are intended. The initial dead load seams to be overbalanced. Please indicate ifഀ
stage stressing is required.ഀ
M&N Response:ഀ
See response to Comment S174. Multi-strand anchorages may be required by post-ഀ
tensioning subcontractor. Stage stressing is not required. The immediate load conditions areഀ
part of the load cases check in the RAM Concept Program.ഀ
KL&A, 5/5/06: See S174, comment closed.ഀ
S177 C U24 and PT7 shows #9 top bars needed. Please verify development. For the PT7 case, theഀ
boundary conditions suggest pinned condition. Clarify the top bars at this location per theഀ
calculations.ഀ
M&N Response:ഀ
Please refer to the revised plans.ഀ
C\Documents and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018.2. DOC Page 16 of 18ഀ
KL&A, 5/5/06: Please provide a specific reference to the revised drawings that you areഀ
referring to, nothing appears to have been revised. Provide calcs showing requiredഀ
development and that this development is consistent with 8/S303 & 4/S303.ഀ
S178 C M10. Please provide reinforcing covers used in the calculations.ഀ
M&N Response:ഀ
2" cover was used in design.ഀ
KL&A, 515/06: It seems the cover required should be shown on the drawings, pleaseഀ
verify.ഀ
S180 C/D M7 and M8 shows reaction moments where connected to the BM22. Provide calculations forഀ
BM22 considering torsional effects. Also section 6 on S303 does not appear to address thisഀ
fixity. See S135.ഀ
M&N Response:ഀ
See the attached calculations indicating that the torsion induced into the beam BM22 by theഀ
2.8 kft end moment from Beam B24-1 is less than the torsional moment below which torsionഀ
can be neglected. (The end moment for Beam B23-1 is even smaller). Refer to the Beamഀ
Reinforcing Schedule on S002 for the "D" reinforcing for B23-Span 1. The schedule will beഀ
revised in the next addendum to include the same "D" reinforcing for Beam B24-Span 1 asഀ
Beam B23-Span 1.ഀ
KL&A, 5/5/06: FOR to coordinate, comment closed.ഀ
S181 C M6 shows column heights of 40 feet. With the increased column lengths the columnഀ
moments are reduced. Please provide justification for modeling the columns extremely long.ഀ
Please provide a reference for the column design considering applied moments from the floorഀ
designs shown on M1 and M14.ഀ
M&N Response:ഀ
The program used assumes 100% fixity at the columns and does not consider crackedഀ
sections. This does not hold up to engineering judgment, therefore, the columns have beenഀ
modeled longer.ഀ
KL&A, 5/5/06: M1 through M133 midlevel and lid calculations: forces used for columnഀ
design is not clear. Provide calculations showing how forces (axial & moment) haveഀ
been derived, design calculations are not clear. Summarize and explain the designഀ
approach, method, and location of each slab design.ഀ
Please refer to the cover sheet for information and instructions for resubmitting plans. The recheck of plansഀ
usually occurs within 3-5 working days of plan re-submittal. In order to avoid delays please check all requestedഀ
information is included with the resubmitted plans.ഀ
Contact Person:ഀ
Matthew Royerഀ
C:\Documents and Settings\mroyer\My Documents\Plan Review\Front Door\tov-b06-0018.2. DOC Page 17 of 18ഀ
Building Official/ Project Managerഀ
Colorado Inspection Agencyഀ
970-328-1790ഀ
matt.rover(aD-coinspect.comഀ
Plans Examiners and Engineers:ഀ
Barry Kramer- Building Officialഀ
Todd Dunkin- Electrical Plans Examinerഀ
Dennis Lohmeier- Plumbing Plans Examinerഀ
Duskin Lowe- Plans Examinerഀ
James P. Horne, P.E., S.E. - Structural Review Project Managerഀ
CADocuments and Settings\mroyerNy Documents\Plan Review\Front Door\tov-b06-0018.2. DOC Page 18 of 18ഀ
COLORADO INSPECTION AGENCY PLAN REVIEW COMMENTSഀ
2~d review comments are shown below the original comment in bold italics. Comments that wereഀ
addressed have been removed from the list.ഀ
TO: Contractorഀ
Hyder Constructionഀ
Doug Thompsonഀ
EMAIL: dthompson(@hyderinc.comഀ
Architectഀ
4240ഀ
Randy Hartഀ
rha rt(a-)4240a rch. comഀ
Engineerഀ
Monroe & Newell Engഀ
FAX:ഀ
NUMBER OF PAGES:ഀ
FROM:ഀ
DATE:ഀ
BUILDING PERMITഀ
OWNERS NAME:ഀ
SITE ADDRESS:ഀ
SUBDIVISION:ഀ
OCCUPANCY GROUP:ഀ
TYPE OF CONSTRUCTION:ഀ
NUMBER OF STORIES:ഀ
18ഀ
Matthew Royerഀ
05/08/2006ഀ
B06-0018ഀ
Vail Resorts Co.ഀ
Building A and Siteഀ
Mill Creekഀ
S-2ഀ
I-Aഀ
3ഀ
The design documents submitted for this project have been reviewed for compliance with the locallyഀ
adopted codes and amendments. The following comments must be addressed before a buildingഀ
permit is issued.ഀ
For processing:ഀ
Please submit (5) complete sets of revised construction documents containinq the requestedഀ
information or plan revisions with all revisions clouded or otherwise identifiedഀ
Please respond in writing to each comment by marking the attached list or creating aഀ
response letter. Indicate which plan sheet, detail specification or calculation shows theഀ
requested information. Please send revisions to the attention of the plans examiner with theഀ
building permit application number noted.ഀ
Responses such as "will comply with code" are not adequate. Revised drawings mustഀ
clearly show code compliance.ഀ
A RESPONSE LETTER MUST BE INCLUDED WITH THE REVISED PLAN SUBMITTAL.ഀ
Please be sure to include on the resubmittal the engineer's or architect's "wet" stamp signatureഀ
registration number and date on the cover page of any structural calculations all structural detailsഀ
and structural sheets of the plans. For commercial or multi-family projects all sheets of the plansഀ
must be stamped.ഀ
= Previously answered 05/23/06 as part of partial "Grading and Excavation Permit" package.]ഀ
Page I of 9ഀ
► 3. Preliminary plan review meetings had discussion regarding the submittal of Memorandum ofഀ
Understandings (MOU). MOU's defined in these meetings would be "used to define or clarify the useഀ
of a code section, agreement to the installation of a system not covered specifically by the code orഀ
clarify the use or component of a building. None of the agreed upon MOU's were submitted forഀ
review. Please provide the following MOU's for review:ഀ
a) Use of assumed property lines and fire separation distance.ഀ
Refer BCER May 23, 2006 Memorandum of Understanding: Item #3, Pg. 3.ഀ
b) Fire command roomഀ
Refer BCER May 23, 2006 Memorandum of Understanding: Item #2, Pg. 2.ഀ
c) Smoke management systemsഀ
Refer BCER May 23, 2006 Memorandum of Understanding: Item #1, Pg. 2.ഀ
d) Opening between parking garage and Lodge Tower parking garageഀ
This item should be submitted as an Administrative Modification.ഀ
Refer BCER Administrative Modification #1 dated May 23, 2006.ഀ
e) Fire separation between the new building and existing buildingsഀ
This item should be submitted as an Administrative Modification.ഀ
Refer BCER Administrative Modification #2 dated May 23, 2006.ഀ
f) Use of 508.2 for creating separate buildings as it relates to each buildingഀ
This may be an Administrative Modification depending on writing and design.ഀ
Refer BCER May 23, 2006 Memorandum of Understanding: Item #4, Pg. 4.ഀ
g) The separation between One Vail Place and new Skier Servicesഀ
This item should be submitted as an administrative Modification.ഀ
Refer BCER Administrative Modification #2 dated May 23, 2006.ഀ
► 4. Preliminary plan review submittal meetings had discussion regarding the submittal of Administrativeഀ
Modifications (AM). AM's as defined in these meetings would be based on International Buildingഀ
Code Section 104.10. Where practical difficulties are involved in carrying out the provision of thisഀ
code, a modification to the code may be granted by the building official after justification that theഀ
modification will not lesson health, accessibility, life and fire safety, or structural requirements. Theഀ
following AM's have been discussed and are being implemented into the plans. Please provide theഀ
following or amend plans accordingly to comply with the code.ഀ
a) Separation between Chalet buildingsഀ
Refer BCER Administrative Modification #2 dated May 23, 2006.ഀ
b) Elimination of elevator smoke doors at residential levels of the Chalet buildingsഀ
Refer BCER Administrative Modification #2 dated May 23, 2006.ഀ
c) Opening between parking garage and Lodge Tower parking garage. When writing thisഀ
modification be sure to use the correct Type IB construction type for Lodge Tower.ഀ
Please amend G sheets to correctly identify the Lodge Tower as Type 1B construction.ഀ
Refer BCER Administrative Modification #1 dated May 23, 2006.ഀ
Construction Type has been modified to `I-B' - refer revised sheet G016.ഀ
d) The separation between One Vail Place and new Skier Servicesഀ
Refer BCER Administrative Modification #2 dated May 23, 2006.ഀ
e) Fire separation between the new building and existing buildingsഀ
Refer BCER Administrative Modification #2 dated May 23, 2006.ഀ
= Previously answered 05/23/06 as part of partial "Grading and Excavation Permit" package.]ഀ
Page 2 of 9ഀ
► 5. Be sure to amend the Fire & Life Safety Report as necessary when changes are made to the plansഀ
that may affect the discussions made by the Report.ഀ
As discussed in the meeting on 0510212006; the Fire and Life Safety Report, Memorandums ofഀ
Understanding and Administrative Modifications will be reformatted for clarification and easeഀ
of understanding.ഀ
BCER has reformatted the Life Safety Report, Memorandum of Understanding andഀ
Administrative Modifications to help clarify the requirements of the project.ഀ
► 6. Provide a precise site plan showing exact locations of assumed property lines. If locations of assumedഀ
property lines are close enough to exterior walls to require rating of walls and opening protection,ഀ
provide details.ഀ
Please show the location of the actual property line between the new Spa and the Lodgeഀ
Tower. Sheet G016 shows an assumed property line between these two buildings at 5'6" fromഀ
the Spa and 21' 11 " from the Lodge Tower. As a result of this assumed property line, theഀ
Lodge Tower would need a rated wall and protected openings. Please clarify?ഀ
Sheet G016 has been revised to show the South Lodge Tower's ACTUAL property line -ഀ
Building B is approximately 25' away from this property line. According to IBC Table 602,ഀ
exterior walls of Type IA Construction, with Groups other than H, between 10' and 30', wouldഀ
require 1-hour fire-resistance rating (as indicated on sheet G016). Within that wall, IBC Tableഀ
704.8 would permit a maximum area of exterior wall opening (unprotected) of 45%, with `Noഀ
Limit' on protected openings. Since that wall only has only one door/opening, the maximumഀ
area of opening has not been exceeded.ഀ
Chalet property lines are also a concern. During the 0510212006 meeting we were told toഀ
reference G026 for location of property lines. This sheet shows the Chalet buildings crossingഀ
over or placed on the property lines. Please clarify.ഀ
The Project Boundary w/ USFS Land Exchange has been noted on sheets G022 through G027.ഀ
Lot 1 and Lot 2 of the Mill Creek Subdivision and the USFS Land Exchange parcel are bothഀ
owned by the `Permit Applicant'. VRDC's, in the future, plans on replatting this areaഀ
eliminating the `internal' property line(s).ഀ
► 7. Fire and Life Safety Report states the use of 1 hour fire walls per IBC Table 705.4. This table doesഀ
not allow for 1 hour fire walls anywhere. Please clarify.ഀ
The Fire and Life Safety Report was modified in an attempt to clear this issue. This somewhatഀ
still remains. We understand the intent after the last revision. Please clarify based on theഀ
example below. For instance:ഀ
Page 17 of the April 3 Fire and Life Safety Report has a table regarding separations betweenഀ
buildings. I would like to use the 3'd item in the table as an example. Table States-ഀ
Description: Mid-Level Parking garage/ Spa for Lodge at Vail Lower Level; Separation Reason:ഀ
Spa Construction Type; Occupancy Group: S-2 Type JA; Fire Rating: 1 hour Occupancyഀ
Separation Wall.ഀ
Based on the plan, the Lodge at Vail is Type JA, the parking garage is Type IA. The reason forഀ
separation is not really type of construction because they are both the same type. The reasonഀ
for the separation is occupancy. The Fire Rating isn't an occupancy separation wall becauseഀ
this doesn't exist in the IBC; the plan is actually shown correctly as a 1 hour barrier.ഀ
I believed the confusion was coming from the table (Fire and Life Safety Report) saying oneഀ
thing and the plans showing another. Please clarify.ഀ
This has been removed from the Vail's Front Door Life Safety Report dated May 23, 2006.ഀ
= Previously answered 05/23/06 as part of partial "Grading and Excavation Permit" package.]ഀ
Page 3 of 9ഀ
► 9. Accessibility requirements do not appear to be included within any plan for this project. Pleaseഀ
amend plans to include the following:ഀ
a) Accessible parking spaces and loading zones.ഀ
Refer new sheets G050 thru G052 for `Accessibility Plans', and G056 for `Accessibilityഀ
Details'.ഀ
b) Accessible route from the parking and loading zones to the buildings.ഀ
Refer new sheets G050 thru G054 for `Accessibility Plans', and G056 for `Accessibilityഀ
Details'.ഀ
c) Accessible routes to each building on the site which are required to be accessible.ഀ
Refer to new sheets G050 thru G055 for `Accessibility Plans', and G056 forഀ
`Accessibility Details'.ഀ
d) Signage details for parking, striping, routes, restrooms, etc.ഀ
See `Signage' response below.ഀ
e) Restroom details for fixtures, grab bars and accessories.ഀ
Refer new sheets G056 and G057 for `Accessibility Details'. Refer also G055 for `Lodgeഀ
at Vail Guestroom Accessibility Plan'.ഀ
This packet is normally not a deferred submittal. Amend plans and specification for allഀ
required signage per IBC Section 1110.ഀ
An overall `graphically-consistent' Signage Package is planned that would include all front-of-ഀ
house, back-of-house, and Code required signage. In that regard, the Permit Applicant wouldഀ
request that the complete Signage Package be submitted later as a "Deferred Submittal" asഀ
previously indicated (refer "VII. DEFERRED SUBMITTALS", Item 10, Sheet G006). Theഀ
Signage Package, when submitted, will comply with all IBC requirements as well as Sectionഀ
1110.ഀ
Show the location of required Site Signage on sheet C37.0 (signage plan).ഀ
Required `traffic' signage appears on sheet C37.0. Additional `accessibility' signage will beഀ
provided with the Signage Package described above.ഀ
Parking within the Front Door project consists of `Valet' parking stalls, `Assigned' Lodgeഀ
South Condominium (LSC) stalls, `Loading Dock' stalls, and `Employee' parking stalls - thereഀ
are no `open to the public' parking stalls within the Front Door project. Valet stalls occur at theഀ
lower level (refer new sheet G050) and lower-mid level (refer new sheet G051). Loading Dockഀ
stalls also occur at the lower-mid level. Assigned LSC parking stalls occur at the lower mid-ഀ
level and are provided by Agreement between VRDC and the LSC, replacing at-grade stallsഀ
lost due to construction of Building A - a total of 15 stalls required (refer new sheet G051).ഀ
Employee parking stalls occur at the upper-mid level (refer new sheet G052).ഀ
Combining the number of parking stalls within Valet and Employee parking areas (NOTഀ
including Loading Dock or LSC stalls - since Dock stalls are not required to be included, andഀ
LSC stalls have been included in Klipp's parking calculations under a separate Project), theഀ
calculations indicate a need for six accessible stalls (refer new sheet G050 for excerpt of IBCഀ
Table 1106.1). With six accessible stalls being required, one of those stalls will be `vanഀ
accessible' (refer IBC 1106.5). The six accessible stalls (five car and one van) have beenഀ
divided equally between the three parking `levels' in the Garage - two car stalls at the lowerഀ
level Ski Club valet, one car and one van stall at the lower-mid level Lodge at Vail valet, andഀ
two car stalls at the upper-mid level employee. As well, since the lower level Ski Club valetഀ
parking can be publicly accessed, a passenger loading zone has been incorporated per IBCഀ
1106.7.3. [Note: We feel the location of the passenger loading zone is permitted even if aഀ
three-point turn is required to exit the area. As well, the location of the westerly HC stall isഀ
permitted since the valet stall just `behind' the HC stall could be `emptied' by the Valetഀ
Attendant if the HC driver returned to leave - as the Attendant is only a few feet away]. Aഀ
= Previously answered 05/23/06 as part of partial "Grading and Excavation Permit" package.]ഀ
Page 4 of 9ഀ
passenger loading zone should not be required at the Lodge at Vail valet parking area sinceഀ
the public will NEVER drive into that valet parking area - as the Lodge at Vail valet serviceഀ
occurs at the Lodge's front door / porte cochere (the car is driven into the valet parking areaഀ
by the Attendant, not the `public'). Refer new sheets G050 thru G052.ഀ
Also, include the parking calculations used to determine the required number of spaces.ഀ
An excerpt of IBC Table 1106.1 "Accessible Parking Spaces" has been indicated on new sheetഀ
G050; hi-lighting the need for 6 accessible spaces as described above - with one of thoseഀ
spaces being van accessible as required.ഀ
The space and loading zone shown on sheet A106 needs to be dimensioned.ഀ
The stall and loading zone have now been dimensioned. Refer revised sheet A/A106.ഀ
Be sure to include the required number of accessible spaces and van accessible spaces.ഀ
See response above relative to excerpt of IBC Table 1106.1 indicated on new sheet G050.ഀ
When the plan shows the location of inaccessible entrances and the required number ofഀ
accessible parking spaces then the accessible routes will be reviewed for code compliance.ഀ
The routes may need to be identified on a separate sheet or sheets to be clearly represented.ഀ
New sheets have been provided indicating the location of HC stalls and passenger loadingഀ
zones - as well as accessible routes and accessible entries. Refer new sheets G050 throughഀ
G055.ഀ
10. Amend plans to include stair signage plan, details and identify the location of the signage. Many ofഀ
the exit enclosures require the occupants to travel up to get to exit discharge. Clearly identify theഀ
direction of travel to the exit discharge.(IBC 1019.1.6)ഀ
We were unable to locate the signage if it was provided with this submittal. Please provide orഀ
respond with the location in which to find this information.ഀ
"Directional" exit signage will be provided in the overall `graphically-consistent' Signageഀ
Package described in Item 9 above.ഀ
11. Amend plans to include gates located at the level of exit discharge to eliminate occupants of theഀ
building from entering an enclosure and passing by the level of exit discharge. (IBC 1019.1.6)ഀ
The response states that gates have been added. Provide written response of where theseഀ
gates were added. What sheets were modified?ഀ
Gate has been added to Bldg B/Spa Stair BS02 at Level 8177'-8" (refer Bldg B/A102 & 2 &ഀ
3/A701).ഀ
► 12. Elevator door which do not open into a lobby need to be provided with a smoke control door inഀ
accordance with IBC Section 715.3.5.3ഀ
The Chalet Building elevators penetrate more then 3 stories which would require smokeഀ
control. Please amend plans accordingly. This was a topic at the 0510212006 meeting and mayഀ
be handled by an Administrative Modification.ഀ
Refer BCER Memorandum of Understanding dated May 23, 2006: Item #1, Pg. 2.ഀ
= Previously answered 05/23/06 as part of partial "Grading and Excavation Permit" package.]ഀ
Page 5 of 9ഀ
14. The size of main elevator cars used for fire/emergency access needs to be determined by the Townഀ
of Vail Building and Fire Departments. Standard 24" x 76" required by code will not accommodate theഀ
stretchers used by emergency personnel. Please confirm the required size.ഀ
This has been a topic of discussion at various 42401Town of Vail meetings. The question isഀ
not whether or not you are compliant with the letter of the code, but whether or not you haveഀ
coordinated with the Town of Vail Fire Department regarding the elevator sizes. This buildingഀ
is unique in design with regard to emergency access. This is one of the smoke managementഀ
and other conditions within this project that are being provide above and beyond the code.ഀ
The Fire Department is looking at several items in respect to performance. The comment hereഀ
is to verify that coordination is occurring with the Fire Department to ensure they haveഀ
adequate emergency access. The topic has surfaced because the stretchers used by theഀ
Town of Vail emergency personnel are larger than the code required size for stretchers.ഀ
In previous, various discussions with Charlie Davis and Mike McGee, there were no specificഀ
directions provided for the `entire' Front Door project, relative to providing elevator cabsഀ
capable of handling 24" x 80" stretchers (since the Front Door - unlike The Arrabelle and Theഀ
Ritz - is spread out over a large horizontal area with no one [or two] elevator[s] accessingഀ
each individual Building). There WERE specific discussions about the Residential Buildingsഀ
needing to provide additional "at-grade" emergency access, which is why walks and stepsഀ
between Buildings 1 & 3, and 2 & 4 were added - providing access to the very top of `the hill'ഀ
from the Access Road below. At those Meetings, direction was given to make all 13ഀ
Residential elevators (Elevator Nos. 8 thru 20) `side-opening' (instead of the previouslyഀ
indicated `center-opening') in order to meet the Code required 24" x 76" stretcher. As well,ഀ
Commercial Elevator Nos. 1 (Ski Club passenger) and 6 (Spa passenger) were revised to `side-ഀ
opening' per those directions.ഀ
In a Meeting held in Vail 13 February 2006, attended by numerous interested parties -ഀ
including Wayne Martin/NWCCOG, Charlie Davis, Peter Brandeis/Eagle County Healthഀ
Services, Steve Rondinelli/BCER, Jeff Marsh/Lerch Bates, Randy Hart/4240 and Matt Royer/CIAഀ
- it was discussed and decided that the Front Door would not have to meet the 24" x 80"ഀ
stretcher size, again, due to it's "sprawling" nature.ഀ
All that being said, there are only 3 elevators throughout the entire project that are not, at aഀ
minimum, 24" x 76" stretcher accessible - Elevator Nos. 5 (Ski Club `valet') and 21 & 22 (Skierഀ
Services `valet') - because they provide access to only 2 back-of-house floors each. On theഀ
other hand, 3 Commercial freight elevators (Elevator Nos. 2 [Ski Club] and 3 & 4 [Skierഀ
Services]) are large enough to handle the 24" x 80" stretcher - as is. ALL elevators, except theഀ
3 `valet' elevators will have the "Star of Life" insignia.ഀ
A better way to understand the `emergency access' options to the individual Buildings is toഀ
look at it as described below:ഀ
Building A:ഀ
• Parking Garages & Loading Dock (All Lower Levels) - Access through Tunnel.ഀ
Building B:ഀ
• Spa Front-of-House (Level 1) - Access through existing at-grade Lodge at Vail Lobby, andഀ
new Door B104.ഀ
• Spa Back-of-House (Level 1) - Access through Spa front-of-house, and Elevator No. 2 fromഀ
Loading Dock (24" x 76" stretcher).ഀ
• Spa Front-of-House (Level 2) - Access through Spa front-of-house Elevator No. 6 (24" xഀ
76" stretcher), and Ground Level `roundabout' to the south.ഀ
• Guestrooms (All Levels) - Access through existing Lodge at Vail existing Guestroomഀ
corridors.ഀ
= Previously answered 05/23/06 as part of partial "Grading and Excavation Permit" package.]ഀ
Page 6 of 9ഀ
Building C:ഀ
• Locker Room (Lower Level) - Access through Ski Club Valet Parking Garage, and Elevatorഀ
No. 1 (24" x 76" stretcher) from Ground Level `roundabout'.ഀ
• Ski Storage (Mid Level) - Access by Elevator No. 1 (24" x 76" stretcher) from Lower Levelഀ
Locker Room, and Ground Level `roundabout'.ഀ
• Great Room (Ground Level) - Access by Elevator No. 1 (24" x 76" stretcher) from Lowerഀ
Level Locker Room, and Ground Level `roundabout'.ഀ
Building D:ഀ
• Skier Services Back-of-House; including One Vail Place (Lower Level) - Access by Elevatorഀ
Nos. 4 & 5 (24" x 80" stretcher) from Loading Dock, and Ground Level public Plazaഀ
northeast of Building D.ഀ
• Public Areas and Back-of-House Offices (Ground Level) - Access by Elevator Nos. 4 & 5ഀ
(24" x 80" stretcher) from Loading Dock, and Ground Level public Plaza northeast ofഀ
Building D.ഀ
Building E:ഀ
• Residences (All Levels) - Access by individual Unit elevators (Nos. 8 through 20 - 24" xഀ
76" stretcher) from Lower Level Residential Parking Garage, and at-grade walks and stepsഀ
for front door and terrace access.ഀ
As one can see, there are multiple `emergency access points' from multiple Levels throughoutഀ
the project - for this reason, it was felt that we were ok with complying with the 2003 IBCഀ
3002.4 requirements - without having to provide for the 80" long stretcher.ഀ
Architectural Comments:ഀ
Site Comments:ഀ
17. Fence shown on L207 shows the bottom of the fence to far above grade. Max distance betweenഀ
grade and bottom of fence 2 inches. (IBC 3109.4)ഀ
Please amend detail 2/L208. In one location this detail shows 3-314" at the bottom of theഀ
barrier.ഀ
Pool and Spa Enclosure: Revised dimension between finish grade and bottom of fence onഀ
section to read at 2"maximum distance (refer to 2/1-208).ഀ
19. Amend plans to show gates compliant with the pool barrier requirements. (IBC 3109.4.1.7)ഀ
Clearly show gate as self-latching, show location of latch and protection of the latch if locatedഀ
less than 54" above the walking surface.ഀ
Pool and Spa Fence Enclosure Gate: Added gate latch with latch protection surround asഀ
required (refer to 1/1-208).ഀ
28. Sheet L302 calls out stair and handrail details on L307. There are no stair and handrail details onഀ
L307. Clarify.ഀ
Handrail shown in detail 3IL307 must be gripable and comply with IBC section 1009.11.3.ഀ
Amend plan to clearly show this handrail is compliant.ഀ
Handrail: Added railing section to clarify handrail dimensions (refer to 3/1_307).ഀ
= Previously answered 05/23/06 as part of partial "Grading and Excavation Permit" package.]ഀ
Page 7 of 9ഀ
► 29. Amend plans to include all component which will be required and specified within the Administrativeഀ
modification for the opening between the Parking Garage (2 places) and the existing Lodge Tower.ഀ
The existing Lodge Tower plan has identified the parking garage as Type I-B. This needs to be takenഀ
into consideration when exercising IBC section 508.2. Same type of construction was used during theഀ
pre-submittal meetings that discussed the separation. Please address the type of constructionഀ
separation and opening protection accordingly. Please coordinate plans and design with the Lodgeഀ
Tower designers.ഀ
This comment was discussed in the 0510212006 meeting with 42140, BCER, Town of Vail andഀ
Colorado Inspection Agency. An Administrative Modification will be created to clarify theഀ
opening and equivalencies provided to allow this opening on the property line between theഀ
two buildings. This Administrative Modification must be consistent with the Modificationഀ
created by the Lodge Tower. It was discussed that one document be created that is signedഀ
and agreed upon by both property owners.ഀ
Refer BCER Administrative Modification #1 dated May 23, 2006.ഀ
Mechanical Comments:ഀ
32. Where is the gas piping for the fountain coming from? Sheet L308 is referenced and does not exist.ഀ
Amend plans to show the location of a gas shutoff valve near the fire pit.ഀ
The gas supply is located on sheet Bldg D/P103. The gas supply shut-off valve within theഀ
automatic ignition box is located adjacent to the fire pit (refer to 4/1-308. )ഀ
Energy Code Review:ഀ
Envelope Corn Checkഀ
The Town of Vail recently established the heating degree days and cooling degree days for aഀ
base of 65 degrees. The numbers provided are:ഀ
Heating degree days (base 65 degree F): 9826ഀ
Cooling degree days (base 65 degree F): 3ഀ
1 apologize for the notice of these numbers; however I have been instructed to pass thisഀ
information on and require modification of the Envelop Compliance Certificate and design.ഀ
Amend reports to reflect the design criteria established by the Town of Vail.ഀ
The Town of Vail currently approves the computer program COM Check as an Energy Codeഀ
Calculation method. COM Check will not allow the user to change the heating or coolingഀ
degree-days. They are automatically inserted when the town of Vail is chosen. Therefore, theഀ
calculations will remain as submitted originally. Per conversation between Jay Watson (ABSഀ
Engineers) and Matt Royer (CIA), it is understood that this is acceptable to the ToV for thisഀ
project.ഀ
Site Structural Comments:ഀ
Note: structural comments are numbered "S1,S2...... and are also given a designation with regards to the topic, as follows:ഀ
DC = design criteria; F= foundations; D = drawings; C = structural calculations; LS = lateral system.ഀ
Site Comments:ഀ
S5.F SF sheets: verify pavement / subgrade above the EPS under roadway (20 psi) has beenഀ
designed to span between HS-20 tires, or depth is sufficient to distribute loads such that 20ഀ
psi is a sufficient strength under the roadway.ഀ
KL&A, 515106: Note, sheet C35.0 shows a 6" roadway slab, please verify adequacy.ഀ
Pavement section has been revised to read as 8" thickness. See revised sheet C35.0.ഀ
Calculations for the loading requirements are included in the Expanded Polystyreneഀ
Explanation Report by AES (dated 04/03/06).ഀ
S7 DC Sheet L202: FOR to verify that various landscaping structures such as boulders, ponds,ഀ
stone walls, pavers, and other superimposed dead loads have been appropriatelyഀ
= Previously answered 05/23/06 as part of partial "Grading and Excavation Permit" package.]ഀ
Page 8 of 9ഀ
't %ഀ
considered in the structural design; verify any concentrated bearing on EPS filler (i.e.ഀ
such as due to any retaining walls, 6/1-205, or massive stone structures, 31.208, etc.)ഀ
KL&A, 515106: See also comment in Volume 1 section. No calculations have beenഀ
provided at this time. We assume that bearing capacity and stability of landscaping orഀ
stone structures designed by others will be reviewed and checked by the FOR duringഀ
the submittal process. Comment closed.ഀ
See attached Structural Comments from Monroe & Newell Engineers.ഀ
Building A Structural Comments:ഀ
See attached Structural Comments from Monroe & Newell Engineers.ഀ
Please refer to the cover sheet for information and instructions for resubmitting plans. The recheck of plansഀ
usually occurs within 3-5 working days of plan re-submittal. In order to avoid delays please check all requestedഀ
information is included with the resubmitted plans.ഀ
Contact Person:ഀ
Matthew Royerഀ
Building Official/ Project Managerഀ
Colorado Inspection Agencyഀ
970-328-1790ഀ
matt. royer(cDcoinspect.comഀ
Plans Examiners and Engineers:ഀ
Barry Kramer- Building Officialഀ
Todd Dunkin- Electrical Plans Examinerഀ
Dennis Lohmeier- Plumbing Plans Examinerഀ
Duskin Lowe- Plans Examinerഀ
James P. Horne, P.E., S.E. - Structural Review Projectഀ
Managerഀ
= Previously answered 05/23/06 as part of partial "Grading and Excavation Permit" package.]ഀ
Page 9 of 9ഀ
REVIEWS BYഀ
~Pഀ
` COLORADO INSPECTIONഀ
torado Inspect)ഀ
AGENCYഀ
May 26, 2006ഀ
Charlie Davis, Building Officialഀ
Town of Vail Community Developmentഀ
75 South Frontage Road, Vail, CO 81657ഀ
RE: Front Door Grading and Excavation Permitഀ
Charlie:ഀ
Colorado Inspection Agency has reviewed the documents submitted as requested from theഀ
meeting and comment letter dated 05/18/2006. These documents were reviewed for complianceഀ
for the release and approval of Grading, Excavation and Shoring of the Front Door Project Site.ഀ
The documents submitted have clarified the outstanding issues that were identified by Coloradoഀ
Inspection Agency and Town of Vail Building, Planning, Public Works and Fire Department.ഀ
Conditions of this approval to allow grading, excavation and shoring are as follows:ഀ
1. This approval is for grading, excavation and shoring of the site. Permits which areഀ
granted partial approval for this work are B06-0018, B06-0022.ഀ
2. Additional plan review fees will be assessed to these permits and payment is requiredഀ
prior to release of permit. Email regarding the additional fees has been included with thisഀ
document.ഀ
3. Complete Building permit fees for permit B06-0018 and B06-0022 will need to be paidഀ
prior to release of grading and excavation permit.ഀ
4. Submittal dates for remainder of plan review comments and full building permit approvalഀ
have been established by Vail Resorts. The letter stating the dates has been included withഀ
this document for reference.ഀ
a. Complete VFD Building A, B, C & D response will be submitted for review noഀ
later than June 19, 2006.ഀ
b. Complete VFD Building E response will be submitted for review no later thanഀ
July 10, 2006.ഀ
5. Reference to the International Residential Code needs to be removed from the Fire andഀ
Life Safety Report and Administrative Modification for the Building E- Chalets. Pageഀ
12, 13 and 16 all make reference to this code of which is not applicable. This wasഀ
discussed with Steve Rondinelli on May 26, 2006 and agreement was made that thisഀ
FLS/Admin Mod. will be modified with the full building permit submittal to referenceഀ
section 708 of the International Building Code.ഀ
Colorado Inspection Agency p: 970.328.1790ഀ
1286 Chambers Avenue, # 101 f: 970.328.1791ഀ
Eagle, Colorado 81631ഀ
Colorado Inspection Agency recommends approval to move forward with Grading, Excavationഀ
and Shoring with the submittal dates and conditions listed above. There are several issues stillഀ
remaining to be resolved prior to release of a full building permit.ഀ
Please do not hesitate to contact me with any question or clarification.ഀ
Sincerely,ഀ
Matthew Royer, Building Officialഀ
matt.royer@coinspect.comഀ
Colorado Inspection Agencyഀ
1286 Chambers Avenue, #101ഀ
Eagle, Colorado 81631ഀ
p: 970.328.1790ഀ
f: 970.328.1791ഀ
-2-ഀ
wഀ
v C) wഀ
May 23, 2006ഀ
N-Ir, Charlie Davis,ഀ
Chief Bi.filding Officialഀ
I,)cy rr of Vail C'ot"trirluriky Ivey elopmeni.ഀ
75 South Frontage Roadഀ
V aH. Cpl M 657,.ഀ
RE: Vail*s From Door Pry jectഀ
Plan Check Response- Tinic l,a.ineഀ
Dow Chadire.ഀ
The purpose tai this t.i.)rI-i:sl'rcri.dente is to cat dirze be Mike dwt VZINC.'. thrt>lI,gh ourഀ
`yichi*e.. t o Record 4240 :~rclrite~ rtire.s v.,ill be submittingഀ
of Plan t".`he conni-ric uts. The si-Abject Nan Check c r me-rats rvere received fry>F£r C.I.A..ഀ
Wyyvcn Friday May 5 & Monday eta 8, 20Mഀ
It our itricrrti,riz to Irat}y ide ilrrec , et-wt<itrt 4d ' ra °rt gs and espouse' packages forഀ
the iiirki sated ENca a.itirroC:irrd ng, Permit directlyter latt Royer otC"TA- via F"f £ x :rye'ഀ
imd morning Wednesday May 24. 2006 mith a copy of th transmittal to you al thatഀ
.t.rrc l: „I`Ire r"espun es "iil be to the condensed list of items received at our ineeting ofഀ
1 twin 3y My IS, 34706° Per oui t' ee-r ng o lay 18. 2000, it is otu ianderst;tl3tling, that it"ഀ
the comm-,ent ri sl)crnscs are acceptable and that items requested (via emai 15,1 NA j6ഀ
1211M) by O vin Kassirrcl, To V Linginc:er, are era sfied, that a E c avation'Gradinഀ
f':t,i d , ill be issued for VI'D Building A E on or beforc IMay 3020Wഀ
C'i mpicte I'' ii, Check Chn-anents for X= F-D Buitdin s A, B. C & D y i;, t-,c S,.t;trrmed toഀ
yo" Office Oil or be lore . c:tlc i 9, 2C)O6. V RDC:`, is hopeful that the full Building Pertrtitsഀ
it F !3z ll{ :i? + A, 13., C AC D vviH lrti:° irisucd in a Hinny inwiner. so Ily' & C`tr.rstrtiWo $ canഀ
mair,ta.irr !h 6t11 :i"s:ititl7 schedule. '.`RDC" yvould greatly ;i)nprc.:iat : the r°"z:k i , Cat theഀ
Building Perim for Build "a;,=, It first. to € and clr:_ hle, impacts v.-itih. Buildings A, C 1.)ഀ
tttl lc yaഀ
toഀ
I=i.Wy, A is mu itlteirt to stet ndt coinplete Ilan Chtck responses for Boil inL, on or-ഀ
be t)re my W, 21?f')6. Our 'rear Wds the additional tiRIC W! lUblt;it I3t.rluin E, iS neededഀ
to add c ss the concerns relMed to 113C C;'rt: liner I I issues noted and discussed in tr.irഀ
Ifwwta'ng of May K 2006, As noted above VRL)C: is antic;iptin a ti wly kwe of hieഀ
V. %50.wഀ
.ii .t 1 i we' "T" M. A no T-tti € t up? I", a . Amp k.o I?=1e"' . R a.Mഀ
5 sഀ
a sഀ
4Mഀ
i M& x Kmd ..-c;,ഀ
VAIL RESORT -ഀ
VROI ' and our AtWhmt,Conlracior Teams W "C hm`t', ut in real daw-'s to -Submit theഀ
I ,.HO .S Iva clwk rnespo$ sLs for di Nei}fit" of az . E y$~ &iL~7:: ~ 3 "c 13T ~3t IY ~ IIZ`~~ as 'SL Y l1 asഀ
as >'T EFL e%'t3r't; I"x'`~°e+:it. ddx,itik !i iat, ~ഀ
tic: i:3ai £3tltl€ttt~~ ~ . h"_ i"~T $ ;~'a'a`si f_S7 .dl;.it2~.i: Q A t.=+: ,.ii;.aഀ
4 iftbrt titat you and the ter TOV Officials have txtc idk~d to the Project in % ;o°<rim!ഀ
Sonic ChatIetIgiIIg, s'stle.S I"eI.ited to @'v`uu,-ig our l3wil i;Ia PC 3t !IoIIid c ,.'tഀ
questions or re-q&-%, additional info `Iliation, f~ free ::ontac, m ~3rs aഀ
I lard copies are a% ailable upon ri,:qUCM.ഀ
of &ttW `Tഀ
Vail Rc,~ortsഀ
Do u L ~'ix# m l1li Cഀ
Mau Ro4rKIAഀ
Tom 1"Co tarsi Sat.dot"Kil"•`l°t.)V Pfit,.ഀ
0ഀ
4ഀ
Matt Roverഀ
From:ഀ
Charlie Davis [CDavis@vailgov.com]ഀ
Sent:ഀ
Thursday, May 18, 2006 4:09 PMഀ
To:ഀ
dthompson@hyderinc.com; JACKH@vailresorts.com; rcaudel@vailresorts.comഀ
Cc:ഀ
Matt Royer; Joseph Sutherഀ
Subject:ഀ
Assesed Fast Track Fees For Front Doorഀ
Good Afternoon,ഀ
As promised here is the breakdown of additional fees that we discussed in this morningsഀ
meeting. Due to the fact that a request has been made to release partial permits forഀ
excavation and shoring work, we have assessed a fast track fee on the following:ഀ
B06-0018 Building "A" permitഀ
Current plan check fee = $66,894.17ഀ
Fast Track plan check fee = $102,914.10 Fees paid to date = $66,894.17 Balance due atഀ
time of partial permit release = $138,973.03 (excludes rec. amenities fee)ഀ
B06-0022 Building "E" master permitഀ
Current plan check fee = $10,087.02ഀ
Fast Track plan check fee = $15,518.50ഀ
Fees paid to date = $10,087.02ഀ
Balance due at time of partial release = $19,452.98 (excludes rec.ഀ
amenities fee)ഀ
The good news is: We only need to assess this fee on the two above listed permits and notഀ
the nine permits that was discussed this morning.ഀ
Thank you all for your cooperation this morning. It was a pleasure to work through theseഀ
difficult issues without any additional burdens.ഀ
Please contact me with any questions.ഀ
Best Regards,ഀ
Charlie Davisഀ
Chief Building Officialഀ
Town of Vailഀ
970-479-2142ഀ
cdavis@vailgov.comഀ
1ഀ
sഀ
REVIEWED BYഀ
COLORADO INSPECTIONഀ
AGENCYഀ
The items listed below were taken from the original plan review comment letters and secondഀ
review comment letters. It is our opinion that these items could drastically impact the designഀ
and constructability of this project. The comments listed are the issues that have beenഀ
identified and need to be resolved prior to the release of a Grading and Excavation Permit.ഀ
See original comment letters for the complete list.ഀ
The comments listed are separated by Permit number, Building and Volume.ഀ
As well as the comments listed below, the Building Official must give final approvalഀ
to proceed with a partial permit. That approval will be based on a recommendationഀ
from Colorado Inspection Agency, Town of Vail Planning, Public Works and Fireഀ
Departments. Conditions established by all parties must be satisfied prior toഀ
recommendations for approval will be granted. The list below is not a complete listഀ
by all departments. This list was generated by Colorado Inspection for only Codeഀ
related issues.ഀ
Release of a partial permit may be granted with conditions and a timeline for all otherഀ
plan review comments to be complete.ഀ
This list below was generated prior to the 05/18/2006 9:30 a.m. meeting to be held atഀ
the Town of Vail with Town Officials, Vail Resorts and Applicant. Other concerns/ഀ
requirements may be generated as a result of this meeting.ഀ
Permit Number B06-0018- Building A and Site- Volume I and IIഀ
3. Preliminary plan review meetings had discussion regarding the submittal ofഀ
Memorandum of Understandings (MOU). MOU's defined in these meetings would beഀ
"used to define or clarify the use of a code section, agreement to the installation of aഀ
system not covered specifically by the code or clarify the use or component of aഀ
building. None of the agreed upon MOU's were submitted for review. Please provideഀ
the following MOU's for review:ഀ
a) Use of assumed property lines and fire separation distance.ഀ
b) Fire command roomഀ
c) Smoke management systemsഀ
d) Opening between parking garage and Lodge Tower parking garageഀ
This item should be submitted as an Administrative Modification.ഀ
e) Fire separation between the new building and existing buildingsഀ
This item should be submitted as an Administrative Modification.ഀ
f) Use of 508.2 for creating separate buildings as it relates to each buildingഀ
This may be an Administrative Modification depending on writing andഀ
design.ഀ
g) The separation between One Vail Place and new Skier Servicesഀ
This item should be submitted as an administrative Modification.ഀ
-1-ഀ
Vail's Front Door Projectഀ
Outstanding Comments for release of partial permit to allow for grading and excavation.ഀ
4. Preliminary plan review submittal meetings had discussion regarding the submittal ofഀ
Administrative Modifications (AM). AM's as defined in these meetings would be basedഀ
on International Building Code Section 104.10. Where practical difficulties are involvedഀ
in carrying out the provision of this code, a modification to the code may be granted byഀ
the building official after justification that the modification will not lesson health,ഀ
accessibility, life and fire safety, or structural requirements. The following AM's haveഀ
been discussed and are being implemented into the plans. Please provide the followingഀ
or amend plans accordingly to comply with the code.ഀ
a) Separation between Chalet buildingsഀ
b) Elimination of elevator smoke doors at residential levels of the Chalet buildingsഀ
c) Opening between parking garage and Lodge Tower parking garage. Whenഀ
writing this modification be sure to use the correct Type IB constructionഀ
type for Lodge Tower. Please amend G sheets to correctly identify theഀ
Lodge Tower as Type IB construction.ഀ
d) The separation between One Vail Place and new Skier Servicesഀ
e) Fire separation between the new building and existing buildingsഀ
5. Be sure to amend the Fire & Life Safety Report as necessary when changes are madeഀ
to the plans that may affect the discussions made by the Report.ഀ
As discussed in the meeting on 0510212006; the Fire and Life Safety Report,ഀ
Memorandums of Understanding and Administrative Modifications will beഀ
reformatted for clarification and ease of understanding.ഀ
6. Provide a precise site plan showing exact locations of assumed property lines. Ifഀ
locations of assumed property lines are close enough to exterior walls to require rating ofഀ
walls and opening protection, provide details.ഀ
Please show the location of the actual property line between the new Spa and theഀ
Lodge Tower. Sheet G016 shows an assumed property line between these twoഀ
buildings at 5'6" from the Spa and 21'11" from the Lodge Tower. As a result ofഀ
this assumed property line, the Lodge Tower would need a rated wall andഀ
protected openings. Please clarify?ഀ
Chalet property lines are also a concern. During the 0510212006 meeting we wereഀ
told to reference G026 for location of property lines. This sheet shows the Chaletഀ
buildings crossing over or placed on the property lines. Please clarify.ഀ
7. Fire and Life Safety Report states the use of 1 hour fire walls per IBC Table 705.4. Thisഀ
table does not allow for 1 hour fire walls anywhere. Please clarify.ഀ
The Fire and Life Safety Report was modified in an attempt to clear this issue.ഀ
This somewhat still remains. We understand the intent after the last revision.ഀ
Please clarify based on the example below. For instance:ഀ
Page 17 of the April 3 Fire and Life Safety Report has a table regardingഀ
separations between buildings. I would like to use the 3rd item in the table as anഀ
example. Table States- Description: Mid-Level Parking garage/ Spa for Lodge atഀ
Vail Lower Level; Separation Reason: Spa Construction Type; Occupancy Group:ഀ
S-2 Type IA; Fire Rating: 1 hour Occupancy Separation Wall.ഀ
-2-ഀ
Vail's Front Door Projectഀ
Outstanding Comments for release of partial permit to allow for grading and excavation.ഀ
Based on the plan, the Lodge at Vail is Type IA, the parking garage is Type IA.ഀ
The reason for separation is not really type of construction because they are bothഀ
the same type. The reason for the separation is occupancy. The Fire Rating isn'tഀ
an occupancy separation wall because this doesn't exist in the IBC; the plan isഀ
actually shown correctly as a 1 hour barrier.ഀ
I believed the confusion was coming from the table (Fire and Life Safety Report)ഀ
saying one thing and the plans showing another. Please clarify.ഀ
9. Accessibility requirements do not appear to be included within any plan for this project.ഀ
Please amend plans to include the following:ഀ
a) Accessible parking spaces and loading zones.ഀ
b) Accessible route from the parking and loading zones to the buildings.ഀ
c) Accessible routes to each building on the site which are required to beഀ
accessible.ഀ
d) Signage details for parking, striping, routes, restrooms, etc.ഀ
e) Restroom details for fixtures, grab bars and accessories.ഀ
This packet is normally not a deferred submittal. Amend plans and specificationഀ
for all required signage per IBC Section 1110.ഀ
Show the location of required Site Signage on sheet C37.0 (signage plan).ഀ
The response states that parking spaces were provided. 2 were located on theഀ
plans. Please respond with sheet numbers and locations of which all accessibleഀ
parking spaces can be found. Also, include the parking calculations used toഀ
determine the required number of spaces. The space and loading zone shown onഀ
sheet A106 needs to be dimensioned. Be sure to include the required number ofഀ
accessible spaces and van accessible spaces.ഀ
When the plan shows the location of inaccessible entrances and the requiredഀ
number of accessible parking spaces then the accessible routes will be reviewedഀ
for code compliance. The routes may need to be identified on a separate sheet orഀ
sheets to be clearly represented.ഀ
12. Elevator door which do not open into a lobby need to be provided with a smoke controlഀ
door in accordance with IBC Section 715.3.5.3ഀ
The Chalet Building elevators penetrate more then 3 stories which would requireഀ
smoke control. Please amend plans accordingly. This was a topic at theഀ
0510212006 meeting and may be handled by an Administrative Modification.ഀ
29. Amend plans to include all component which will be required and specified within theഀ
Administrative modification for the opening between the Parking Garage (2 places) andഀ
the existing Lodge Tower. The existing Lodge Tower plan has identified the parkingഀ
garage as Type I-B. This needs to be taken into consideration when exercising IBCഀ
section 508.2. Same type of construction was used during the pre-submittal meetingsഀ
that discussed the separation. Please address the type of construction separation andഀ
opening protection accordingly. Please coordinate plans and design with the Lodgeഀ
Tower designers.ഀ
This comment was discussed in the 0510212006 meeting with 42140, BCER, Townഀ
of Vail and Colorado Inspection Agency. An Administrative Modification will beഀ
created to clarify the opening and equivalencies provided to allow this opening onഀ
the property line between the two buildings. This Administrative Modificationഀ
-3-ഀ
Vail's Front Door Projectഀ
Outstanding Comments for release of partial permit to allow for grading and excavation.ഀ
must be consistent with the Modification created by the Lodge Tower. It wasഀ
discussed that one document be created that is signed and agreed upon by bothഀ
property owners.ഀ
Permit Number B06-0019 Building B Volume IIIഀ
16. Clearly define the separation between existing and new addition. (Fire separationഀ
between I-A and III-A construction).ഀ
This item will be reviewed with the Fire and Life Safety submitted that will occurഀ
as part of the 0510212006 meeting.ഀ
29. What is the size of the day tank for the back-up generator, quantity and classification ofഀ
liquid and means for filling tank? This is shown on Building A plans & Building B plans.ഀ
Currently a diesel generator is shown on the plans. H occupancy?ഀ
Provide specifications and documentation for the generator which will include theഀ
size of the tank.ഀ
Permit Number B06-0020 - Building C - Volume IVഀ
20. Except as permitted in Section 402.4.6, openings in exit enclosures other thanഀ
unexposed exterior openings shall be limited to those necessary for exit access to theഀ
enclosure from normally occupied spaces and for egress from the enclosure. Doorഀ
C106 on A102 and door C227 on sheet A103 are not allowed in the exit enclosure.ഀ
(1019.1.1 IBC)ഀ
Response says to see MOU. Please identify document, page and paragraphഀ
where this information can be found. We were unable to locate this information.ഀ
Permit Number B06-0021 - Building D - Volume Vഀ
18. How does the three hour firewall described in the LSR separating the lower level of Oneഀ
Vail Place from the new Skier Services Building comply with section 705 IBC 2003. Theഀ
wall must continue to and terminate above the roof.ഀ
Any designs which are shown on the plans and do not comply with the code mustഀ
be applied for in the form of an Administrative Modification and not aഀ
Memorandum of Understanding as described in the response. If it is not possibleഀ
to construct this wall as described and required by the Building Code then submitഀ
an Administrative Modification clearly identifying the issues, code sections, andഀ
alternative construction, safeguards to fire and life safety and justification for theഀ
modification. It was agreed in the 0510212006 meeting that if compliance with theഀ
IBC then this will be submitted for review as an Administrative Modification.ഀ
-4-ഀ
Vail's Front Door Projectഀ
Outstanding Comments for release of partial permit to allow for grading and excavation.ഀ
Permit Number B06-0022 through B06-0029 - Building E - Volume VIഀ
21. The LSR states that there will be a 3 hour fire separation from the parking garage to theഀ
residential units both horizontally and vertically. The vertical separation is shown as aഀ
one hour on the plans and the parking garage does not have a complete separationഀ
from the mechanical room on the floor above. Sheet G023 and 024 don't show stairഀ
ES02 as a rated assembly nor does it list a wall type. Sheet M010 shows the wall typeഀ
as an "R" wall assembly which is shown as a 2 hour wood framed party wall on sheet Aഀ
600. If the ceiling of the parking garage is being used for the 3 hour separation then theഀ
stairs going to the 2nd floor mechanical room from the garage and the large opening forഀ
the garage ventilation must be protected. Add opening protection to the garage ceilingഀ
below the mechanical room or revise plans showing extent of three hour separation toഀ
include ceiling of mechanical room.ഀ
Detail the required fire separation where R-3 residential units are adjacent to S-2ഀ
parking garage. Clarify whether the separation is driven by the difference inഀ
occupancies or the different types of construction. Also if any portions of theseഀ
vertical walls support the 3 hour separation as referenced in Section 508.2 thenഀ
the walls must have the same rating as the floor assembly. Include in responseഀ
required protection of openings based on wall construction.ഀ
23. Addendum # 1 has changed location of rated walls separating the parking garage fromഀ
adjoining spaces. Addendum has added separation to the storage areas in the garageഀ
but not the elevator machine rooms. The elevator machine rooms do however have 90ഀ
min rated doors shown on the schedule. The now rated storage rooms don't haveഀ
protected openings. Coordinate door schedule with wall construction for all spaces beingഀ
separated from the parking garage.ഀ
Detail fire separation or absence thereof at adjoining spaces (elevator machineഀ
rooms, residential storage units, trash room) and S-2 parking garage. Firstഀ
submittal showed no separation, addendum showed fire-rated partitions andഀ
second submittal has removed the fire separation again. Reference the codeഀ
sectionsഀ
30. Provide smoke door assemblies per section 715.3.5.3 at all elevators doors.ഀ
Response referenced sheet A700 and A701. There are no notes on these sheets toഀ
address this. Revise response to reference correct sheets.ഀ
34. Life Safety Report references the construction of the party wall between units asഀ
providing additional protection because the wall is being constructed as a two hourഀ
assembly. LSR states that the wall will continue to and terminate at the underside of theഀ
roof sheathing. This detail is not reflected on the plans in fact it is shown stopping theഀ
wall at the underside of the rafters. Please coordinate the plans with the LSR continuingഀ
the wall to the roof sheathing. Provide detail for roof ventilation as wall to deck willഀ
eliminate ridge vent.ഀ
❑ LSR also states that they are utilizing section 705.7 of the 2003 IBC for combustibleഀ
members entering the rated assembly at the party wall. The referenced sectionഀ
(705.7) is part of section 705 "Fire Walls". This section is a very prescriptiveഀ
commentary on the construction of fire walls one of which "705.3" states "Fire Wallsഀ
shall be of any approved noncombustible materials. Section 705.7 is not applicableഀ
-5-ഀ
Vail's Front Door Projectഀ
Outstanding Comments for release of partial permit to allow for grading and excavation.ഀ
to the assembly being shown on the plans because of the combustible framingഀ
members used in the construction of the wall. Revise plans removing all framingഀ
members from entering the party wall or change the construction of the wall to meetഀ
section 705.3.ഀ
The Chalet residences are not exempt from the requirements of accessible units. Perഀ
IBC Section 3104.2 exception 2 requires that connected buildings shall be consideredഀ
as one building for the purpose of calculating the number of type B units is required byഀ
IBC Chapter 11. Amend plan to comply with Chapter 11. Provide all details,ഀ
specifications, parking, accessible routes, etc. which would clearly show complianceഀ
with IBC for accessibility.ഀ
The LSR still states that the 2-hour fire rated wall will extend to and terminate atഀ
the underside of the roof deck but that is not reflected on the plans. In fact theഀ
fire-wall is interrupted at each floor level by framing members and then stops atഀ
the underside of the rafters. Determine what type of wall will be constructed,ഀ
identify it per code section and detail its construction to meet the codeഀ
requirements.ഀ
34aഀ
Reference to section 705.7 in the Ad Min Mod has been removed. Determine whatഀ
type of wall will be constructed, identify it per code section and detail itsഀ
construction to meet the code requirements.ഀ
34bഀ
As a result of the meeting held on 05102106 designer will determine feasibility ofഀ
having all units comply with the Type B provisions on ANSI 117.1 1998 forഀ
accessibility.ഀ
58. Note 11 sheet A 155 # 6 of the revision to documents states "revised location ofഀ
elevator `08"". Sheet A 155 Floor Plan: unit 5C level 3 shows elevator 16, 17 andഀ
18 with no reference to elevator 8. This same comment applies to Note mm sheetഀ
A 157 revision to documents Revise statement to address correct elevator orഀ
sheetഀ
-6-ഀ
Vail's Front Door Projectഀ
Outstanding Comments for release of partial permit to allow for grading and excavation.ഀ
05/18/2006ഀ
REVIEWED BYഀ
vUL _Ur )Jഀ
COLORADO INSPECTIONഀ
AGENCYഀ
The items listed below were taken from the original plan review comment letters and second reviewഀ
comment letters. It is our opinion that these items could drastically impact the design and constructabilityഀ
of this project. The comments listed are the issues that have been identified and need to be resolvedഀ
prior to the release of a Grading and Excavation Permit.ഀ
See original comment letters for the complete list.ഀ
The comments listed are separated by Permit number, Building and Volume.ഀ
As well as the comments listed below, the Building Official must -give final approval to proceedഀ
with a partial permit. That approval will be based on a recommendation from Colorado Inspectionഀ
Agency Town of Vail Planning, Public Works and Fire Departments. Conditions established byഀ
all parties must be satisfied prior to recommendations for approval will be granted. The list belowഀ
is not a complete list by all departments. This list was generated by Colorado Inspection for onlyഀ
Code related issues.ഀ
Release of a partial permit may be granted with conditions and a timeline for all other plan reviewഀ
comments to be complete.ഀ
This list below was generated prior to the 05/18/2006 9:30 a.m. meeting to be held at the Town ofഀ
Vail with Town Officials, Vail Resorts and Applicant. Other concerns/ requirements may beഀ
generated as a result of this meeting.ഀ
Permit Number B06-0018- Buildinq A and Site- Volume I and IIഀ
3. Preliminary plan review meetings had discussion regarding the submittal of Memorandum ofഀ
Understandings (MOU). MOU's defined in these meetings would be "used to define or clarify the useഀ
of a code section, agreement to the installation of a system not covered specifically by the code orഀ
clarify the use or component of a building. None of the agreed upon MOU's were submitted forഀ
review. Please provide the following MOU's for review:ഀ
a) Use of assumed property lines and fire separation distance.ഀ
Refer BCER May 23, 2006 Memorandum of Understanding: Item #3, Pg. 3.ഀ
,/b) Fire command roomഀ
Refer BCER May 23, 2006 Memorandum of Understanding: Item #2, Pg. 2.ഀ
,,~6) Smoke management systemsഀ
Refer BCER May 23, 2006 Memorandum of Understanding: Item #1, Pg. 2.ഀ
✓ d) Opening between parking garage and Lodge Tower parking garageഀ
This item should be submitted as an Administrative Modification.ഀ
/ Refer BCER Administrative Modification#1 dated May 23, 2006.ഀ
/e) Fire separation between the new building and existing buildingsഀ
This item should be submitted as an Administrative Modification.ഀ
Refer BCER Administrative Modification#2 dated May 23, 2006.ഀ
f) Use of 508.2 for creating separate buildings as it relates to each buildingഀ
This may be an Administrative Modification depending on writing and design.ഀ
Refer BCER May 23, 2006 Memorandum of Understanding: Item #4, Pg. 4.ഀ
,/g) The separation between One Vail Place and new Skier Servicesഀ
This item should be submitted as an administrative Modification.ഀ
Refer BCER Administrative Modification#2 dated May 23, 2006.ഀ
-1-ഀ
Vail's Front Door Project - Outstanding Comments for release of partial permit to allow for grading and excavation.ഀ
4. Preliminary plan review submittal meetings had discussion regarding the submittal of Administrativeഀ
Modifications (AM). AM's as defined in these meetings would be based on International Buildingഀ
Code Section 104.10. Where practical difficulties are involved in carrying out the provision of thisഀ
code, a modification to the code may be granted by the building official after justification that theഀ
modification will not lesson health, accessibility, life and fire safety, or structural requirements. Theഀ
following AM's have been discussed and are being implemented into the plans. Please provide theഀ
following or amend plans accordingly to comply with the code.ഀ
a) Separation between Chalet buildingsഀ
_ഀ
Refer BCER Administrative Modification#2 dated May 23, 20 6.ഀ
b) Elimination of elevator smoke doors at residential levels of the Cha ?ഀ
Refer BCER Administrative Modification#2 dated May 23, 2006.ഀ
vd~ Opening between parking garage and Lodge Tower parking garage. When writing thisഀ
modification be sure to use the correct Type 1B construction type for Lodge Tower.ഀ
Please amend G sheets to correctly identify the Lodge Tower as Type 1B construction.ഀ
Refer BCER Administrative Modification#1 dated May 23, 2006.ഀ
Construction Type has been modified to `I-B' - refer revised sheet G016.ഀ
o/d) The separation between One Vail Place and new Skier Servicesഀ
/ Refer BCER Administrative Modification#2 dated May 23, 2006.ഀ
v'b) Fire separation between the new building and existing buildingsഀ
Refer BCER Administrative Modification#2 dated May 23, 2006.ഀ
/Be sure to amend the Fire & Life Safety Report as necessary when changes are made to the plansഀ
that may affect the discussions made by the Report.ഀ
As discussed in the meeting on 0510212006; the Fire and Life Safety Report, Memorandums ofഀ
Understanding and Administrative Modifications will be reformatted for clarification and easeഀ
of understanding.ഀ
BCER has reformatted the Life Safety Report, Memorandum of Understanding andഀ
Administrative Modifications to help clarify the requirements of the project.ഀ
4. Provide a precise site plan showing exact locations of assumed property lines. If locations of assumedഀ
property lines are close enough to exterior walls to require rating of walls and opening protection,ഀ
provide details.ഀ
Please show the location of the actual property line between the new Spa and the Lodgeഀ
Tower. Sheet G016 shows an assumed property line between these two buildings at 5'6" fromഀ
the Spa and 21' 11" from the Lodge Tower. As a result of this assumed property line, theഀ
Lodge Tower would need a rated wall and protected openings. Please clarify?ഀ
Sheet G016 has been revised to show the South Lodge Tower's ACTUAL property line -ഀ
Building B is approximately 25' away from this property line. According to IBC Table 602,ഀ
exterior walls of Type IA Construction, with Groups other than H, between 10' and 30', wouldഀ
require 1-hour fire-resistance rating (as indicated on sheet G016). Within that wall, IBC Tableഀ
704.8 would permit a maximum area of exterior wall opening (unprotected) of 45%, with 'Noഀ
Limit' on protected openings. Since that wall only has only one door/opening, the maximumഀ
area of opening has not been exceeded.ഀ
Chalet property lines are also a concern. During the 0510212006 meeting we were told toഀ
reference G026 for location of property lines. This sheet shows the Chalet buildings crossingഀ
over or placed on the property lines. Please clarify.ഀ
The Project Boundary w/ USFS Land Exchange has been noted on sheets G022 through G027.ഀ
Lot 1 and Lot 2 of the Mill Creek Subdivision and the USFS Land Exchange parcel are bothഀ
owned by the `Permit Applicant'. VRDC's, in the future, plans on replatting this areaഀ
eliminating the `internal' property line(s).ഀ
-2-ഀ
Vail's Front Door Project - Outstanding Comments for release of partial permit to allow for grading and excavation.ഀ
ire and Life Safety Report states the use of 1 hour fire walls per IBC Table 705.4. This table doesഀ
not allow for 1 hour fire walls anywhere. Please clarify.ഀ
The Fire and Life Safety Report was modified in an attempt to clear this issue. This somewhatഀ
still remains. We understand the intent after the last revision. Please clarify based on theഀ
example below. For instance:ഀ
Page 17 of the April 3 Fire and Life Safety Report has a table regarding separations betweenഀ
buildings. I would like to use the 3'd item in the table as an example. Table States-ഀ
Description: Mid-Level Parking garage/ Spa for Lodge at Vail Lower Level; Separation Reason:ഀ
Spa Construction Type; Occupancy Group: S-2 Type IA; Fire Ratin_g: 1 hour Occupancyഀ
Separation Wall.ഀ
Based on the plan, the Lodge at Vail is Type IA, the parking garage is Type IA. The reason forഀ
separation is not really type of construction because they are both the same type. The reasonഀ
for the separation is occupancy. The Fire Rating isn't an occupancy separation wall becauseഀ
this doesn't exist in the IBC; the plan is actually shown correctly as a 1 hour barrier.ഀ
I believed the confusion was coming from the table (Fire and Life Safety Report) saying oneഀ
thing and the plans showing another. Please clarify.ഀ
This has been removed from the Vail's Front Door Life Safety Report dated May 23, 2006.ഀ
9. Accessibility requirements do not appear to be included within any plan for this project. Pleaseഀ
amend plans to include the following:ഀ
✓a) Accessible parking spaces and loading zones.ഀ
Refer new sheets G050 thru G052 for `Accessibility Plans', and G056 for `Accessibilityഀ
Details'.ഀ
Jb) Accessible route from the parking and loading zones to the buildings.ഀ
Refer new sheets G050 thru G054 for `Accessibility Plans', and G056 for `Accessibilityഀ
Details'.ഀ
1c) Accessible routes to each building on the site which are required to be accessible.ഀ
Refer to new sheets G050 thru G055 for `Accessibility Plans', and G056 forഀ
`Accessibility Details'.ഀ
d Signage details for parking, striping, routes, restrooms, etc.ഀ
See `Signage' response below.ഀ
e) Restroom details for fixtures, grab bars and accessories.ഀ
Refer new sheets G056 and G057 for `Accessibility Details'. Refer also G055 for `Lodgeഀ
at Vail Guestroom Accessibility Plan'.ഀ
This packet is normally not a deferred submittal. Amend plans and specification for allഀ
required signage per IBC Section 1110.ഀ
An overall `graphically-consistent' Signage Package is planned that would include all front-of-ഀ
house, back-of-house, and Code required signage. In that regard, the Permit Applicant wouldഀ
request that the complete Signage Package be submitted later as a "Deferred Submittal" asഀ
previously indicated (refer "VII. DEFERRED SUBMITTALS", Item 10, Sheet G006). Theഀ
Signage Package, when submitted, will comply with all IBC requirements as well as Sectionഀ
1110.ഀ
✓Show the location of required Site Signage on sheet C37.0 (signage plan).ഀ
Required `traffic' signage appears on sheet C37.0. Additional `accessibility' signage will beഀ
provided with the Signage Package described above.ഀ
Parking within the Front Door project consists of `Valet' parking stalls, `Assigned' Lodgeഀ
South Condominium (LSC) stalls, `Loading Dock' stalls, and `Employee' parking stalls -thereഀ
are no `open to the public' parking stalls within the Front Door project. Valet stalls occur at theഀ
lower level (refer new sheet G050) and lower-mid level (refer new sheet G051). Loading Dockഀ
stalls also occur at the lower-mid level. Assigned LSC parking stalls occur at the lower mid-ഀ
level and are provided by Agreement between VRDC and the LSC, replacing at-grade stalls lostഀ
-3-ഀ
Vail's Front Door Project - Outstanding Comments for release of partial permit to allow for grading and excavation.ഀ
due to construction of Building A - a total of 15 stalls required (refer new sheet G051).ഀ
Employee parking stalls occur at the upper-mid level (refer new sheet G052).ഀ
Combining the number of parking stalls within Valet and Employee parking areas (NOTഀ
including Loading Dock or LSC stalls - since Dock stalls are not required to be included, andഀ
LSC stalls have been included in Klipp's parking calculations under a separate Project), theഀ
calculations indicate a need for six accessible stalls (refer new sheet G050 for excerpt of IBCഀ
Table 1106.1). With six accessible stalls being required, one of those stalls will be `vanഀ
accessible' (refer IBC 1106.5). The six accessible stalls (five car and one van) have beenഀ
divided equally between the three parking `levels' in the Garage - two car stalls at the lowerഀ
level Ski Club valet, one car and one van stall at the lower-mid level Lodge at Vail valet, andഀ
two car stalls at the upper-mid level employee. As well, since the lower level Ski Club valetഀ
parking can be publicly accessed, a passenger loading zone has been incorporated per IBCഀ
1106.7.3. [Note: We feel the location of the passenger loading zone is permitted even if aഀ
three-point turn is required to exit the area. As well, the location of the westerly HC stall isഀ
permitted since the valet stall just `behind' the HC stall could be `emptied' by the Valetഀ
Attendant if the HC driver returned to leave - as the Attendant is only a few feet away]. Aഀ
passenger loading zone should not be required at the Lodge at Vail valet parking area sinceഀ
the public will NEVER drive into that valet parking area - as the Lodge at Vail valet serviceഀ
occurs at the Lodge's front door / porte cochere (the car is driven into the valet parking areaഀ
by the Attendant, not the `public'). Refer new sheets G050 thru G052.ഀ
Also, include the parking calculations used to determine the required number of spaces.ഀ
An excerpt of IBC Table 1106.1 "Accessible Parking Spaces" has been indicated on new sheetഀ
V G050; hi-lighting the need for 6 accessible spaces as described above - with one of thoseഀ
spaces being van accessible as required.ഀ
VI'T'he space and loading zone shown on sheet A106 needs to be dimensioned.ഀ
The stall and loading zone have now been dimensioned. Refer revised sheet A/A106.ഀ
/~e sure to include the required number of accessible spaces and van accessible spaces.ഀ
See response above relative to excerpt of IBC Table 1106.1 indicated on new sheet G050.ഀ
When the plan shows the location of inaccessible entrances and the required number ofഀ
/ accessible parking spaces then the accessible routes will be reviewed for code compliance.ഀ
V The routes may need to be identified on a separate sheet or sheets to be clearly represented.ഀ
New sheets have been provided indicating the location of HC stalls and passenger loadingഀ
zones - as well as accessible routes and accessible entries. Refer new sheets G050 throughഀ
G055.ഀ
,9,Elevator door which do not open into a lobby need to be provided with a smoke control door inഀ
accordance with IBC Section 715.3.5.3ഀ
The Chalet Building elevators penetrate more then 3 stories which would require smokeഀ
control. Please amend plans accordingly. This was a topic at the 0510212006 meeting and mayഀ
be handled by an Administrative Modification.ഀ
Refer BCER Memorandum of Understanding dated May 23, 2006: Item #1, Pg. 2.ഀ
VI 9. Amend plans to include all component which will be required and specified within the Administrativeഀ
modification for the opening between the Parking Garage (2 places) and the existing Lodge Tower.ഀ
The existing Lodge Tower plan has identified the parking garage as Type 1-13. This needs to be takenഀ
into consideration when exercising IBC section 508.2. Same type of construction was used during theഀ
pre-submittal meetings that discussed the separation. Please address the type of constructionഀ
separation and opening protection accordingly. Please coordinate plans and design with the Lodgeഀ
Tower designers.ഀ
-4-ഀ
Vail's Front Door Project - Outstanding Comments for release of partial permit to allow for grading and excavation.ഀ
This comment was discussed in the 0510212006 meeting with 42140, BCER, Town of Vail andഀ
Colorado Inspection Agency. An Administrative Modification will be created to clarify theഀ
opening and equivalencies provided to allow this opening on the property line between theഀ
two buildings. This Administrative Modification must be consistent with the Modificationഀ
created by the Lodge Tower. It was discussed that one document be created that is signedഀ
and agreed upon by both property owners.ഀ
Refer BCER Administrative Modification#1 dated May 23, 2006.ഀ
/ Permit Number B06-0019 Building B Volume IIIഀ
16. Clearly define the separation between existing and new addition. (Fire separation between I-A and III-ഀ
A construction).ഀ
This item will be reviewed with the Fire and Life Safety submitted that will occur as part of theഀ
0510212006 meeting.ഀ
Refer BCER Administrative Modification#2 dated May 23, 2006.ഀ
What is the size of the day tank for the back-up generator, quantity and classification of liquid andഀ
means for filling tank? This is shown on Building A plans & Building B plans. Currently a dieselഀ
generator is shown on the plans. H occupancy?ഀ
Provide specifications and documentation for the generator which will include the size of theഀ
tank.ഀ
The generator is part of the Buildings A/C/D electrical service design, and is not part ofഀ
Building B. The generator will have a diesel fuel day tank with 8 hours of fuel capacity asഀ
noted on the Building A/C/D electrical one line diagram and in Specification Section 16403.ഀ
Exact tank capacity and dimensions will not be available until equipment submittals areഀ
provided by the Contactor. Per literature available for the specified generator, the unit willഀ
require 24.1 gal/hour running at full load; which equates to 192.8 gallon for 8 hours of run time.ഀ
Permit Number B06-0020 - Building C - Volume IVഀ
VL0. Except as permitted in Section 402.4.6, openings in exit enclosures other than unexposed exteriorഀ
openings shall be limited to those necessary for exit access to the enclosure from normally occupiedഀ
spaces and for egress from the enclosure. Door C106 on Al 02 and door C227 on sheet Al 03 areഀ
not allowed in the exit enclosure. (1019.1.1 IBC)ഀ
Response says to see MOU. Please identify document, page and paragraph where thisഀ
information can be found. We were unable to locate this information.ഀ
See item #6 in Memorandum of Understanding document for clarification.ഀ
/ Permit Number B06-0021 - Building D - Volume Vഀ
481 How does the three hour firewall described in the LSR separating the lower level of One Vail Placeഀ
from the new Skier Services Building comply with section 705 IBC 2003. The wall must continue toഀ
and terminate above the roof.ഀ
Any designs which are shown on the plans and do not comply with the code must be appliedഀ
for in the form of an Administrative Modification and not a Memorandum of Understanding asഀ
described in the response. If it is not possible to construct this wall as described and requiredഀ
by the Building Code then submit an Administrative Modification clearly identifying the issues,ഀ
code sections, and alternative construction, safeguards to fire and life safety and justificationഀ
for the modification. It was agreed in the 0510212006 meeting that if compliance with the IBCഀ
then this will be submitted for review as an Administrative Modification.ഀ
Refer BCER Administrative Modification#2 dated May 23, 2006.ഀ
-5-ഀ
Vail's Front Door Project - Outstanding Comments for release of partial permit to allow for grading and excavation.ഀ
- 13unaina t - volumeഀ
2~! The LSR states that there will be a 3 hour fire separation from the parking garage to the residentialഀ
units both horizontally and vertically. The vertical separation is shown as a one hour on the plans andഀ
the parking garage does not have a complete separation from the mechanical room on the floorഀ
above. Sheet G023 and 024 don't show stair ES02 as a rated assembly nor does it list a wall type.ഀ
Sheet MO 10 shows the wall type as an "R" wall assembly which is shown as a 2 hour wood framedഀ
party wall on sheet A 600. If the ceiling of the parking garage is being used for the 3 hour separationഀ
then the stairs going to the 2nd floor mechanical room from the garage and the large opening for theഀ
garage ventilation must be protected. Add opening protection to the garage ceiling below theഀ
mechanical room or revise plans showing extent of three hour separation to include ceiling ofഀ
mechanical room.ഀ
Detail the required fire separation where R-3 residential units are adjacent to S-2 parkingഀ
garage. Clarify whether the separation is driven by the difference in occupancies or theഀ
different types of construction. Also if any portions of these vertical walls support the 3 hourഀ
separation as referenced in Section 508.2 then the walls must have the same rating as the floorഀ
assembly. Include in response required protection of openings based on wall construction.ഀ
See revised sheets G023, G024, G028, A103, A600 and Building E Door Schedule.ഀ
• Detail of required fire separation is provided on revised sheet G023. In addition, seeഀ
revised sheets A103 and A600 for revised wall ratings and wall types relative to fireഀ
separation revisions made to sheet G023.ഀ
• Clarification has been provided for compliance with occupancy separation, separationഀ
of construction types, and compliance with 2003 IBC Section 508.2 for ratedഀ
construction supporting rated assembly above. See added designation for 3-hr fireഀ
rated construction supporting 3-hr fire rated assembly above on sheet G023, G024, andഀ
G028.ഀ
• See revised door schedule which reflects 3-hr protection for openings in the 3-hr fireഀ
rated wall.ഀ
• Regarding the previously questioned opening in the garage ceiling to the mechanicalഀ
room above, see revised sheet G023 and G024.ഀ
Per 2003 IBC Section 707.2, openings through a floor/ceiling assembly are NOTഀ
required to be protected by a shaft enclosure complying with this section, if theഀ
opening complies with Exception 7. Exception 7 requires that the floor opening complyഀ
with the following:ഀ
7.1. Does not connect more than two stories.ഀ
7.2. Is not part of the required means of egress system except as permitted inഀ
Section 1019.1.ഀ
7.3. Is not concealed within the building construction.ഀ
7.4. Is not open to a corridor in Group I and R occupancies.ഀ
7.5. Is not open to a corridor on nonsprinklered floors in any occupancy.ഀ
7.6. Is separated from floor openings serving other floors by constructionഀ
conforming to required shaft enclosures.ഀ
The opening between the Residential Garage Parking Level and the Cooling Towerഀ
Room, on the Mechanical Level above, complies with Exception 7. Therefore theഀ
opening is not required to be protected.ഀ
3. Addendum # 1 has changed location of rated walls separating the parking garage from adjoiningഀ
spaces. Addendum has added separation to the storage areas in the garage but not the elevatorഀ
machine rooms. The elevator machine rooms do however have 90 min rated doors shown on theഀ
schedule. The now rated storage rooms don't have protected openings. Coordinate door scheduleഀ
with wall construction for all spaces being separated from the parking garage.ഀ
Detail fire separation or absence thereof at adjoining spaces (elevator machine rooms,ഀ
residential storage units, trash room) and S-2 parking garage. First submittal showed noഀ
separation, addendum showed fire-rated partitions and second submittal has removed the fireഀ
separation again. Reference the code sectionsഀ
-6-ഀ
Vail's Front Door Project - Outstanding Comments for release of partial permit to allow for grading and excavation.ഀ
See revised sheet G023, G024, A103, and Door Schedule.ഀ
The Storage Rooms are being classified as Incidental Use Areas per 2003 IBC Sectionഀ
302.1.1. The S-1 Storage Rooms are incidental to the S-2 Residential Parking Garage. rഀ
An automatic fire-extinguishing system is being provided to the S-1 Storage Rooms.ഀ
Therefore, per Table 302.1.1, the S-1 storage rooms are not required to be separatedഀ
om the S-2 Residential Parking Garage. `1:ഀ
The Trash Room is a Waste Collection Room that is being classified as an Incidentalഀ
Use Areas per 2003 IBC Section 302.1.1. The Trash Room is incidental to the S-2ഀ
Residential Parking Garage. An automatic fire-extinguishing system is being providedഀ
to the Trash Room. Therefore, per Table 302.1.1, the Trash Room is not required to beഀ
eparated from the S-2 Residential Parking Garage.ഀ
Per 2003 IBC Section 3006.4, elevator machine rooms shall be enclosed withഀ
construction having a fire-resistance rating not less than the required rating of theഀ
hoistway enclosure served by the machinery. Therefore, elevator machine rooms areഀ
enclosed a rating not less than 2-hr.ഀ
The private garages for residences 6A and 6B are Incidental Use Areas per 2003 IBCഀ
Section 302.1.1. The private garage space is incidental to its respective residence.ഀ
Therefore, per Table 302.1.1, with an automatic fire extinguishing system, a one-hourഀ
separation is required between the private garage and its respective residence.ഀ
0. Provide smoke door assemblies per section 715.3.5.3 at all elevators doors.ഀ
Response referenced sheet A700 and A701. There are no notes on these sheets to addressഀ
this. Revise response to reference correct sheets.ഀ
Refer BCER Memorandum of Understanding May 23, 2006: Item #1, Pg. 2.ഀ
/4. Life Safety Report references the construction of the party wall between units as providing additionalഀ
protection because the wall is being constructed as a two hour assembly. LSR states that the wall willഀ
continue to and terminate at the underside of the roof sheathing. This detail is not reflected on theഀ
plans in fact it is shown stopping the wall at the underside of the rafters. Please coordinate the plansഀ
with the LSR continuing the wall to the roof sheathing. Provide detail for roof ventilation as wall toഀ
deck will eliminate ridge vent.ഀ
The LSR still states that the 2-hour fire rated wall will extend to and terminate at the undersideഀ
of the roof deck but that is not reflected on the plans. In fact the fire-wall is interrupted at eachഀ
floor level by framing members and then stops at the underside of the rafters. Determine whatഀ
type of wall will be constructed, identify it per code section and detail its construction to meetഀ
the code requirements.ഀ
Refer BCER Fire & Life Safety Report and Administrative Modification - Building E, Residentialഀ
Chalets: Pg. 12.ഀ
LSR also states that they are utilizing section 705.7 of the 2003 IBC for combustible membersഀ
entering the rated assembly at the party wall. The referenced section (705.7) is part of sectionഀ
705 "Fire Walls". This section is a very prescriptive commentary on the construction of fireഀ
walls one of which "705.3" states "Fire Walls shall be of any approved noncombustibleഀ
materials. Section 705.7 is not applicable to the assembly being shown on the plans becauseഀ
of the combustible framing members used in the construction of the wall. Revise plansഀ
removing all framing members from entering the party wall or change the construction of theഀ
wall to meet section 705.3.ഀ
Reference to section 705.7 in the Ad Min Mod has been removed. Determine what typeഀ
of wall will be constructed, identify it per code section and detail its construction toഀ
meet the code requirements.ഀ
Refer BCER Fire & Life Safety Report and Administrative Modification - Building E,ഀ
Residential Chalets: Pg. 12.ഀ
-7-ഀ
Vail's Front Door Project - Outstanding Comments for release of partial permit to allow for grading and excavation.ഀ
b. The Chalet residences are not exempt from the requirements of accessible units. Per IBCഀ
Section 3104.2 exception 2 requires that connected buildings shall be considered as oneഀ
building for the purpose of calculating the number of type B units is required by IBC Chapterഀ
11. Amend plan to comply with Chapter 11. Provide all details, specifications, parking,ഀ
accessible routes, etc. which would clearly show compliance with IBC for accessibility.ഀ
As a result of the meeting held on 05102106 designer will determine feasibility of havingഀ
all units comply with the Type B provisions on ANSI 117.1 1998 for accessibility.ഀ
Refer BCER May 23, 2006 Memorandum of Understanding: Item #5, Pg. 4.ഀ
Relative to `Type B' provisions, a Meeting was held Thursday 18 May 2006 with theഀ
appropriate Town of Vail and Front Door Design Team members to discuss the IBCഀ
Chapter 11 ICC/ANSI All 17.1-1998 issue. It was decided that in order to obtain theഀ
`Grading & Excavation Permit' through this specific CIA Commentary (now dated 18ഀ
May 2006), the Permit Applicant would describe the direction the Design Team wouldഀ
be taking in complying with IBC Chapter 11. That description, as well as the logic used,ഀ
is described below.ഀ
While many sections of IBC Chapter 11 were discussed, the consensus focused onഀ
provisions of section 1107.6.3 `Group R-3' and 1107.7 `General exceptions'-ഀ
specifically 1107.7.2, 1107.7.3 and 1107.7.4.ഀ
Section 1107.7.2 `Multistory units' states that multistory units (dwelling or sleeping)ഀ
without elevators are not required to have `Type B' units - but that if an elevator isഀ
provided, and if that elevator provides access to only one level - then that one levelഀ
shall "be accessible and contain a toilet facility". At the Chalets, elevator access couldഀ
only be achieved at the "lower levels" (generally the Junior Master Suite and Multi-ഀ
Purpose levels) due to the Town of Vail Zoning height restrictions and other siteഀ
impracticalities - requiring us to provide an intermediate landing between the top twoഀ
levels (Kitchen/Dining and Living Room level at the top; Senior Master Suite level justഀ
below).ഀ
Section 1107.7.3 `Elevator service to the lowest story with units' exempts access to theഀ
upper levels as long as access is provided to the lower levels serviced by an elevator.ഀ
At the Chalets, as described above, the lower levels requiring access would be theഀ
Junior Master Suite and Multi-Purpose levels. In following the requirements of sectionഀ
1107.7.2, an accessible toilet facility must be provided on those levels. It also must beഀ
noted that the IBC Commentary states that "if an elevator is utilized to provide accessഀ
to only the lowest level containing dwelling or sleeping units, this building would notഀ
be considered an `elevator' building".ഀ
Section 1107.7.4 `Site impracticality' describes under what conditions the requiredഀ
number of Type B units is permitted to be reduced - stating that "Type B units may beഀ
reduced to a percentage which is equal to the percentage of the entire site havingഀ
grades, prior to development, which are less than 10 percent". At the Chalets, theഀ
entire pre-developed Chalet site is over 10 percent slope - though `Condition V statesഀ
that no matter how steep the site, a minimum of 20 percent of the units would still needഀ
to be `accessible'. In that regard, of the 13 Chalet units, 2.6 units (13 x 20% [.20] = 2.6,ഀ
rounding up to 3) would need to be `accessible' - 3 units that would then continue toഀ
comply with sections 1107.7.2 and 1107.7.3 as described above.ഀ
In conclusion, 3 out of the 13 Chalet units will provide `access' as described above -ഀ
including parking stalls and routes to those 3 units within the Residential parkingഀ
garage (following ICC/ANSI A117.1-1998 sections 1003.1 through 1003.11 - exceptഀ
1003.12 'Kitchens'- and section 1004). While we have a good idea as to which 3 unitsഀ
-8-ഀ
Vail's Front Door Project - Outstanding Comments for release of partial permit to allow for grading and excavation.ഀ
will provide the necessary `access', we will provide that documentation later in theഀ
`Building Permit Responses' portion of CIA's commentary. As discussed in the 18 Mayഀ
2006 Meeting, we assume that for the `Excavation Permit', the description of our `intent'ഀ
is adequate for issuing the Permit.ഀ
ഀ
If Note 11 sheet A 155 # 6 of the revision to documents states "revised location of elevator '08'ഀ
Sheet A 155 Floor Plan: unit 5C level 3 shows elevator 16, 17 and 18 with no reference toഀ
elevator 8. This same comment applies to Note mm sheet A 157 revision to documents Reviseഀ
statement to address correct elevator or sheetഀ
See revised sheets A151, A153, A155, and A157.ഀ
• Note "revised location of elevator 08" is incorrect. The note should have read "revisedഀ
location of elevator 18". Elevator 18 has been clouded on appropriate sheets. Refer toഀ
sheets A151, A153, A155, and A157.ഀ
-9-ഀ
Vail's Front Door Project - Outstanding Comments for release of partial permit to allow for grading and excavation.ഀ
REVIEWS BD Yഀ
J U L 1 0 2006ഀ
ENGINEERING, INC.ഀ
MEMORANDUM OF UNDERSTANDING REQUESTഀ
Vail Front Door Projectഀ
Vail, Coloradoഀ
Modified May 23, 2006ഀ
April 3, 2006ഀ
ONഀ
VAIL FRONT DOOR - VAIL, COLORADOഀ
1. SMOKE MANAGEMENT SYSTEM (STAIR and ELEVATOR HOISTWAY)ഀ
2. FIRE COMMAND ROOMഀ
3. USE OF ASSUMED PROPERTY LINES AND FIRE SEPARATIONഀ
4. USE OF 508.2 FOR CREATING SEPARATE BUILIDNGSഀ
5. ACCESSIBILITY REQUIREMENTS IN RESIDENTIAL CHALETSഀ
6. DOOR OPENINGS INTO SKI CLUB EXIT ENCLOSUREഀ
This document supercedes all previously submitted fire protection and life safety documentsഀ
related to the Vail Front Door Project. Previous documents produced by Rolf Jensen andഀ
Associates Inc (RJA) will not be in effect. Effective March 11, 2006 BCER Engineering, Inc.ഀ
(BCER) will be the fire protection and life safety consulting engineers of record for the project.ഀ
INTRODUCTIONഀ
This Memorandum of Understanding (MOU) request is the documentation of several meetingsഀ
and discussions with the Town of Vail Building and Fire Department. The intent of thisഀ
correspondence is to "document" how the design team will comply with the requirements of theഀ
adopted building, fire code and amendments as adopted by the Town of Vail. This documentഀ
differs from the Request for Administrative Modification process in that we are not requestingഀ
any variance from the adopted building and fire codes. This document should be a reference toഀ
and complement the Life Safety Report and Construction Documents prepared by the designഀ
team. Once signed by all parties (signature page) the described portions of the Fire Protectionഀ
and Life Safety code requirement are considered to be clarification of the building or fire codeഀ
FCCJL1ircmcnts for the design and construction of the Vail Front Door Project in Vail, Colorado.ഀ
-1-ഀ
1. SMOKE MANAGEMENT SYSTEM (STAIR AND ELEVATOR HOISTWAY)ഀ
The building is not considered a high-rise structure, however, meetings with the TOVഀ
Fire Department identified that fire department access was limited and that performanceഀ
based approach was taken for this complex. This required a smoke management system toഀ
augment the fire department access. The smoke management system will include theഀ
pressurization of Stair #CSOI and Elevator #I in Building C. Building C is the Ski Clubഀ
Building located in the center of the Vail Front Door Complex. This stair and elevatorഀ
will provide access to all levels of the complex. The stairs and elevator are located nearഀ
the fire command room and the fire department staging area on the exterior of theഀ
building.ഀ
Stairwell Enclosures - The smoke management system for the designatedഀ
stairwell enclosure will consist of a pressurization fan for the designated stairwellഀ
will be activated automatically upon fire alarm activation (water-flow orഀ
detection). The system will be designed such that during operation the doors intoഀ
the stairwell will not require more than 30-pounds of force to open, regardless ofഀ
the barometric pressures of the environment. We discussed that the system willഀ
not need to be designed to any minimum pressure differential such as 0.05 inchesഀ
of water column but it would be enough to keep the stairwell positive in relationഀ
to adjacent spaces. A smoke management system will to be designed by a fireഀ
protection engineer and submitted to the fire department for their review andഀ
approval.ഀ
Elevator Hoist-way - The smoke management system for the designated elevatorഀ
hoist-ways will consist of a pressurization fan for the elevator shafts activatedഀ
upon fire alarm activation (water-flow or detection). The smoke managementഀ
system will not need to be designed to any minimum pressure differential.ഀ
However, the system will be designed to keep the elevator positive in relation toഀ
the adjacent spaces or elevator lobbies. The positive pressure will extend beyondഀ
the hoist-way into the elevator lobbies or adjacent corridors. It is intended that theഀ
smoke management system will prevent smoke from migrating from floor toഀ
floor via the identified elevator hoist-way or stair enclosure.ഀ
• Emergency Power and Control - The smoke management system will beഀ
connected to the building emergency power system since this is a life safetyഀ
system. The smoke management system will also be manually controlled fromഀ
the fire command center utilizing an approved smoke control panel.ഀ
2. FIRE COMMAND ROOMഀ
At numerous meetings with the TOV fire department, the design team presented the fireഀ
department access and the location of the fire command room. The TOV fire departmentഀ
agreed the building was not a high-rise but requested that a fire command be provided. Itഀ
was agreed to by the team that the fire command center would be located near theഀ
-2-ഀ
entrance of Building C or the Alpine Club near the main entrance. Further clarificationഀ
from the fire department also required that the fire command room would not be sharedഀ
with any other function and would require direct access to the exterior via the stairഀ
enclosure. The currently approved location provides a central response point for the fireഀ
department staging area with access to stairs serving the building and an elevator servingഀ
all levels of the building complex. The fire command room location has been approvedഀ
and also communicates to the stair enclosure. Although a normally non-occupied roomഀ
cannot communicate to a stair enclosure the access from the exterior into the stairഀ
enclosure is a desirable condition and acceptable to the fire department. Listed below areഀ
the components that will be included in the fire command room:ഀ
• Annunciators for the fire alarm system.ഀ
• Fire Fighter Smoke Control Panelഀ
• Public address, voice communication system status and controls.ഀ
• A direct dial telephone.ഀ
• A table for reviewing building plans and schematic diagrams.ഀ
• Schematic building plans, including typical floor plans, egress drawings, fireഀ
protection systems, smoke control diagrams, fire-fighting equipment and fireഀ
department access.ഀ
• Keys to access all portions of the building.ഀ
3. USE OF ASSUMED PROPERTY LINES AND FIRE RESISTIVE SEPARATIONഀ
The design team has had numerous meetings with the Town of Vail Building and Fireഀ
Department regarding the Vail Front Door Complex. From the initial meetings it wasഀ
identified that the buildings will communicate below grade via the parking garage andഀ
that there would be mixing of construction type and fire resistive separation requirementsഀ
between buildings. The G-Series code sheets identify the proposed and required fireഀ
resistive separations. These separations include both 3-hour vertical and horizontal fireഀ
resistive separations that are intended to compartment the buildings both vertically andഀ
horizontally. Additionally, there are occupancy separation fire resistive walls that separateഀ
occupancies. The design team has evaluated the property line setbacks to both legal andഀ
assumed property lines and have provided fire resistive separation where required. Seeഀ
the G-Series Code Sheets for details related to assumed property lines and fire resistiveഀ
separations.ഀ
-3-ഀ
4. USE OF 508.2 FOR CREATING SEPARATE BUILDINGSഀ
The design team has utilized Section 508.2 of the International Building Code to separateഀ
the building below grade from the buildings above grade. BCER has submitted a requestഀ
for an administrative modification defining the separation of the S-2 Parking Garageഀ
below the Residential Chalet portion of the building. Additionally, that request alsoഀ
includes the separation between the Lodge Tower Parking Garage and the Vail Frontഀ
Door Parking Garage. See Administrative Modification Request dated April 3, 2006 andഀ
modified on May 15, 2006. From the initial meetings with the Town of Vail Building,ഀ
Fire Department and Colorado Inspection Agency it was identified that the buildings willഀ
communicate below grade via the parking garage and that there would be mixing ofഀ
construction types and fire resistive separation requirements between buildings. Attachedഀ
are code sheets identifying the proposed and required fire resistive separations. Theseഀ
separations include both vertical and horizontal fire resistive separations that are intendedഀ
to compartment the buildings both vertically and horizontally. Additionally, there areഀ
occupancy separation fire resistive walls that separate occupancies. See the G-Seriesഀ
Code Sheets for details related to assumed property lines and fire resistive separations.ഀ
5. ACCESSIBILITY REQUIREMENTS IN RESIDENTIAL CHALETSഀ
The Chalets consist of five duplex residential structures and one triplex residentialഀ
structure (total of 13 dwelling units resembling detached single family residences)ഀ
residing above a subterranean parking garage for private vehicles. The residentialഀ
structures are identified from north to south as Building 1 and 2 on the west end, Buildingഀ
3 and 4 in the center, and Building 5 (triplex) and 6, which actually are situated next toഀ
each other with 5 being west of 6. Portions of building 5 are above portions of theഀ
Building 6 private parking garage. Building 6 does not have access to the subterraneanഀ
private residential parking garage. A corner of Building 5 and a portion of Building 6ഀ
reside above the Tunnel of the new Building A Parking Garage and Loading Dock. Inഀ
total, the subterranean private residential parking garage and the residential structures areഀ
approximately 75,700 ft2 in area. The residential structures are considered R or simply aഀ
residential occupancy classification with the subterranean private residential parkingഀ
garage considered a S-2 occupancy classification.ഀ
The private residential parking garage and the private garage for Building 6 are accessedഀ
from Vail Road via a road residing above the Tunnel of the new Building A Parkingഀ
Garage and Loading Dock, leading to a roundabout in front of the new Building C Skiഀ
Club. Beyond the roundabout, another road provides access to the existing One Vail Placeഀ
parking garage.ഀ
All but two residential structures will be four-levels with three stories above grade. Oneഀ
residential unit within Building 5 and one residential unit within Building 6 will haveഀ
only three levels. The lowest levels are all at different elevations. The residentialഀ
structures are located on top of, and on the side of the private residential parking garageഀ
that serves them. The private residential parking garage has a second level mechanicalഀ
-4-ഀ
equipment room serving the residential structures with utilities metered separately.ഀ
Each of the residential units will be equipped with an elevator. Buildings 2 and 4 areഀ
accessed from the private residential parking garage via elevator, while Buildings 1, 3 andഀ
5 are accessed directly without use of an elevator. Building 6 has its own private garage.ഀ
As each of the residential structures lowest levels begin at different elevations, the heightഀ
of each elevator shaft varies to accommodate the elevation of the floors each shaft serves.ഀ
Due to the varying elevations of each residential structure, some Buildings actually haveഀ
structural void spaces. These void spaces are to be protected by one or multiply means ofഀ
NPFA 13 approved methods of protecting void spaces. (See G021).ഀ
The private residential parking garage and the separate residential structures above will beഀ
constructed under the provisions of the 2003 editions of the International Codes and theഀ
Town of Vail Amendments. The facility will not be treated as one overall building inഀ
regards to construction type and allowable areas as separation by firewalls or fireഀ
resistive construction is planned to be utilized.ഀ
The private residential parking garage is occupied with parking of private motorizedഀ
vehicles and storage for each residential unit, accessible from the residential parkingഀ
garage. The private residential parking garage is also occupied with incidental use areasഀ
such as a trash room, mechanical and electrical rooms, storage rooms, and Fire Commandഀ
room for the Chalets.ഀ
The residential units are most like a single-family residential unit. Section 310 of theഀ
2003 IBC defines the various residential occupancies as follows:ഀ
➢ R-1 is reserved for residential occupancies where occupants are transient inഀ
nature; The Vail Front Door Residential Chalets are not this type of occupancyഀ
R-2 is reserved for residential occupancies containing more than two dwellingഀ
units where the occupants are permanent in nature; The Vail Front Doorഀ
Residential Chalets are a series of duplexes separated by a two-hour fire resistiveഀ
walls with one unit being a triplex residential unit.ഀ
➢ R-3 is reserved for residential occupancies where the occupants are permanent inഀ
nature and not classified as R-1, R-2, R-4 or 1, and where buildings do not containഀ
more than two dwelling units. The Vail Front Door Residential Chalets are aഀ
series of duplexes separated by a two-hour fire resistive wall with one unit being aഀ
triplex residential unit.ഀ
➢ R-4 is reserved for residential occupancies arranged as residential care/assistedഀ
living facilities. The Vail Front Door Residential Chalets are not this type ofഀ
occupancy.ഀ
Section 310.2 of the 2003 IBC defines residential or dwelling unit as a single unitഀ
providing complete, independent living facilities for one or more persons, includingഀ
permanent provisions for living, sleeping, eating, cooking, and sanitation. The residentialഀ
or dwelling structures "closely resemble" five, stand-alone duplex (two-family) and oneഀ
triplex residential buildings. Due to the resemblance to stand-alone duplex residentialഀ
-5-ഀ
buildings and the definitions of R occupancies as well as a dwelling unit, the design teamഀ
recommends classification of each of the individual residential or dwelling structures asഀ
residential occupancy that most closely resembles a Group R-3 Occupancy.ഀ
Chapter 11 of the International Building Code regulates Accessibility requirements for allഀ
occupancies. Section 1107.6.2 and 1107.6.3 identifies provisions for when Type Bഀ
accessible units are required. In both R-2 Multi-family residences and R-3 Single-familyഀ
residences, where there are four or more residential dwelling units or sleeping unitsഀ
intended to be occupied as a residence in a single structure.ഀ
Since none of the residential structures have more than four residential units, and they areഀ
separated from each other and the subterranean private parking garage by fire resistiveഀ
construction it would be our opinion that the accessibility requirements for Chapter 11ഀ
may not apply.ഀ
These interpretations as well as the accessibility requirements were discussed onഀ
September 22, 2005 and October 13, 2005 with the Town of Vail Building and Fireഀ
Department and Colorado Inspection Agency (Town of Vail P Party Building Codeഀ
Consultants). The consensus of those meetings was that the residential duplexes andഀ
triplex, although appearing like a R2 Occupancy "look, act and feel like detachedഀ
residential structures". Again supporting that the accessibility requirements of Chapter 11ഀ
of the IBC would not be enforced.ഀ
It would also be our interpretation that if the accessibility requirements were notഀ
applicable in Section 1107.6 for residential occupancies, then other requirements outlinedഀ
in the section would not be applicable.ഀ
As indicated in the October 13, 2005 meeting this interpretation was to be documentedഀ
through the Memorandum of Understanding Process. This item is considered thatഀ
documentation.ഀ
The design team had another meeting with the Town of Vail Building Official andഀ
Colorado Inspection Agency on May 18, 2006 to again discuss the accessibility issue andഀ
requirements for meeting the intent of the accessibility requirements of the IBC.ഀ
Discussion evolved between all parties resulting in making 3 units Type B or adaptable.ഀ
The units would have limited areas or levels complying with adaptability based on accessഀ
to the residential units; access from the parking garage via an elevator. Some of the unitsഀ
do not have direct access from the residential parking garage to elevators serving theഀ
residential units without going up stairs.ഀ
There was consensus between all parties that providing access from the parking garage toഀ
the lowest levels of 3 units, and making those levels Type B adaptable only, wasഀ
acceptable. That approach was based on utilizing Section 1107.7.4 Site Impracticality toഀ
residential units of the IBC as the basis for the limited number of accessible/adaptableഀ
units. Lastly, Vail Resorts was going to contact the owners of the potential Type Bഀ
adaptable units to let them know that their unit was going to have levels that would meetഀ
-6-ഀ
those requirements of the IBC for accessibility/adaptability.ഀ
There was consensus between all parties at the meeting held May 18, 2006 and thoseഀ
signing this Memorandum of Understanding that all the residential units would not beഀ
required to meet the Type B adaptability requirements. This interpretation would meet theഀ
intent of accessibility requirements of the IBC.ഀ
6. DOOR OPENINGS INTO SKI CLUB EXIT ENCLOSUREഀ
Item #20 of the building department review comments for Building C or Ski Clubഀ
indicated that Doors C106 (sheet A102) and Door C227 (sheet A103) opened into the exitഀ
stair enclosure. IBC Section 402.4.6 limits exits into exit stair enclosures to thoseഀ
necessary for exit access to the enclosure from normally occupied spaces or rooms.ഀ
Although these doors would not normally be permitted into the exit enclosure, the roomsഀ
they serve are the Fire Command Room and the Fire Valve Room Serving the majority ofഀ
the complex. Access to these rooms was provided as agreed to in several meetings withഀ
the building and fire department. The fire department felt strongly that access to the Fireഀ
Command and Fire Valve Room was essential at this central location and primaryഀ
response point to the complex. The fire department indicated that they would not congestഀ
the exit stair, impeding the path of exiting occupants. The location of the fire valve roomഀ
and fire command room and the associated fire department operations will not eitherഀ
impede access to or egress from the building complex. Additionally, this exit stair isഀ
being provided with a smoke management system as described in item #1 of thisഀ
Memorandum of Understanding.ഀ
RECOMMENDATIONഀ
This MOU in conjunction with the current design documents provides a level of protection andഀ
life safety that meets the intent and spirit of the Code and therefore does not create a hazardousഀ
condition to the occupants of the building. The results of this document are also consistent withഀ
the meetings held with the Town of Vail Building and Fire Department and are intended toഀ
document the construction documents and clarify any special requirements that are in the currentഀ
design.ഀ
Prepared by:ഀ
BCER Engineering, Inc.ഀ
Stephen Rondinelli, AIAഀ
Director of Fire Protection and Life Safetyഀ
-7ഀ
SIGNATURE PAGEഀ
Vail Front Door - Vailഀ
Request for Memorandum of Understandingഀ
May 23, 2006ഀ
Prepared by:ഀ
BCER Engineering, Inc.ഀ
May 23, 2006ഀ
Stephen Rondinelli, AIA Dateഀ
Director of Fire Protection and Life Safetyഀ
Concurred by:ഀ
44LW~ഀ
May 23, 2006ഀ
42/40 - Architect of Recordഀ
Dateഀ
Owner Representativeഀ
Vail Resortsഀ
Approved by:ഀ
Dateഀ
Charlie Davis Dateഀ
Town of Vail Chief Building Officialഀ
Mike McGee Dateഀ
Vail Fire and Emergency Services Fire Marshalഀ
ATTACHMENTS: G - Series Code Drawingsഀ
-8-ഀ