HomeMy WebLinkAboutB06-0019 Comments/Structuralsrഀ
COLORADO INSPECTION AGENCY PLAN REVIEW COMMENTSഀ
TO: Contractorഀ
Hyder Constructionഀ
Doug Thompsonഀ
EMAIL: dthompson@hyderinc.comഀ
Architectഀ
4240ഀ
Randy Hartഀ
rhart@4240arch.comഀ
Engineerഀ
Monroe & Newell Engഀ
FAXഀ
NUMBER OF PAGES:ഀ
FROM:ഀ
DATE:ഀ
BUILDING PERMITഀ
OWNERS NAME:ഀ
SITE ADDRESS:ഀ
SUBDIVISION:ഀ
OCCUPANCY GROUP:ഀ
TYPE OF CONSTRUCTION:ഀ
NUMBER OF STORIES:ഀ
10ഀ
Matthew Royerഀ
03/10/2006ഀ
B06-0019 PST c)(0 `0C,49ഀ
Vail Resorts Co.ഀ
Building Bഀ
Mill Creekഀ
R-1, S-2, B, A-3ഀ
I-Aഀ
3ഀ
The design documents submitted for this project have been reviewed for compliance with the locallyഀ
adopted codes and amendments. The following comments must be addressed before a buildingഀ
permit is issued.ഀ
For processing:ഀ
Please submit (2) complete sets of revised construction documents containing the requestedഀ
information or plan revisions with all revisions clouded or otherwise identified.ഀ
Please respond in writing to each comment by marking the attached list or creating aഀ
response letter. Indicate which plan sheet, detail, specification, or calculation shows theഀ
reauested information. Please send revisions to the attention of the plans examiner with theഀ
building permit application number noted.ഀ
Responses such as "will comply with code" are not adequate. Revised drawings mustഀ
clearly show, code compliance.ഀ
A RESPONSE LETTER MUST BE INCLUDED WITH THE REVISED PLAN SUBMITTAL.ഀ
Please be sure to include on the resubmittal the engineer's or architect's "wet" stamp, signature,ഀ
registration number and date on the cover page of any structural calculations, all structural detailsഀ
and structural sheets of the plans. For commercial or multi-family projects all sheets of the plansഀ
must be stamped.ഀ
CADOCUME-I\dhopp\LOCALS-I\Temp\B - Response to ToV-b06-0019.DOCഀ
Page I ofഀ
BUILDING DEPARTMENT COMMENTS:ഀ
Common Project Comments: (CPC are attached to each permit comment letter)ഀ
1. Land Swap with US Forest Service must be complete prior to final approval and issuance of theഀ
Building Permit.ഀ
The agreement was signed on January 18'h, 2006 and is now in a 45 day review period.ഀ
2. When plans are resubmitted for review; complete sets of plans for each building which includes theഀ
addendum sheets. Separate addendum packets will not be accepted and approved for initialഀ
permitting.ഀ
Plans have been modified and are to be resubmitted for the Town of Vail Building and Fireഀ
Department review, approval and issuance of a permit.ഀ
3. Preliminary plan review meetings had discussion regarding the submittal of Memorandum ofഀ
Understandings (MOU). MOU's defined in these meetings would be "used to define or clarify the useഀ
of a code section, agreement to the installation of a system not covered specifically by the code orഀ
clarify the use or component of a building. None of the agreed upon MOU's were submitted forഀ
review. Please provide the following MOU's for review:ഀ
a) Use of assumed property lines and fire separation distance.ഀ
b) Fire command roomഀ
c) Smoke management systemsഀ
d) Opening between parking garage and Lodge Tower parking garageഀ
e) Fire separation between the new building and existing buildingsഀ
f) Use of 508.2 for creating separate buildings as it relates to each buildingഀ
g) The separation between One Vail Place and new Skier Servicesഀ
A Memorandum of Understanding dated April 3, 2006 addressing these issues has been completedഀ
and will be submitted to the Building, Fire Department and Colorado Code Inspection for review andഀ
approval.ഀ
4. Preliminary plan review submittal meetings had discussion regarding the submittal of Administrativeഀ
Modifications (AM). AM's as defined in these meetings would be based on International Buildingഀ
Code Section 104.10. Where practical difficulties are involved in carrying out the provision of thisഀ
code, a modification to the code may be granted by the building official after justification that theഀ
modification will not lesson health, accessibility, life and fire safety, or structural requirements. Theഀ
following AM's have been discussed and are being implemented into the plans. Please provide theഀ
following or amend plans accordingly to comply with the code.ഀ
a) Separation between Chalet buildingsഀ
b) Elimination of elevator smoke doors at residential levels of the Chalet buildingsഀ
A Request for Administrative Modification dated April 3, 2006 addressing these issues has beenഀ
completed and will be submitted to the Building, Fire Department and Colorado Code Inspection forഀ
review and approval.ഀ
5. Be sure to amend the Fire & Life Safety Report as necessary when changes are made to the plansഀ
that may affect the discussions made by the Report.ഀ
An updated Life Safety Report for The Vail Front Door Buildings A, B, C and D dated April 3, 2006ഀ
has been completed and coordinated with the G - Series Code Drawings. This report andഀ
attachments will be submitted to the Building, Fire Department and Colorado Code Inspection forഀ
review and approval.ഀ
6. Provide a precise site plan showing exact locations of assumed property lines. If locations of assumedഀ
property lines are close enough to exterior walls to require rating of walls and opening protection,ഀ
provide details.ഀ
4240 has updated the G - Series Code Drawings indicating the locations of property lines andഀ
assumed property lines.ഀ
C:\DOCUME-I\dhopp\LOCALS-I\Temp\B - Response to ToV-b06-0019.DOC Page 2 of 2ഀ
Jഀ
7. Fire and Life Safety Report states the use of 1-hour fire walls per IBC Table 705.4. This table doesഀ
not allow for 1 hour fire walls anywhere. Please clarify.ഀ
The Life Safety Report has been modified to reflect the approach taken for the building separations.ഀ
As indicated in the report numerous meetings were held with the building and fire departmentഀ
identifying buildings, construction types and openings. The buildings and proximity to the propertyഀ
lines will not meet the prescriptive requirements of the building code. The design team has identifiedഀ
on the G - Series Code Drawings that the project will use a variety of 3-hour horizontal and verticalഀ
fire resistive separations as well as 2-hour and 1-hour occupancy separation walls. This approach ofഀ
compartmentation with the use of automatic sprinkler protection and detection though-out will notഀ
compromise the life safety of the occupants.ഀ
8. Fire walls are called out in the fire and life safety report to separate buildings. What is the purposeഀ
and use of the fire walls and the separations? Is it to separate property owners?ഀ
It appears that fire separation distances are being used to determine the ratings for the wallsഀ
identified as fire walls between the different building and spaces. Our interpretation of this section isഀ
that once the 3 hour separation is used to make a separate building then everything that is notഀ
separated by a fire wall per 705.4 will be considered as one building.ഀ
The Life Safety Report has been modified to reflect the approach taken for the building separations.ഀ
As indicated in the report numerous meetings were held with the building and fire departmentഀ
identifying buildings, construction types and openings. The buildings and proximity to the propertyഀ
lines will not meet the prescriptive requirements of the building code. The design team has identifiedഀ
on the G - Series Code Drawings that the project will use a variety of 3-hour horizontal and verticalഀ
fire resistive separations as well as 2-hour and 1-hour occupancy separation walls. This approach ofഀ
compartmentation with the use of automatic sprinkler protection and detection though-out will notഀ
compromise the life safety of the occupants.ഀ
9. Accessibility requirements do not appear to be included within any plan for this project. Pleaseഀ
amend plans to include the following:ഀ
a) Accessible parking spaces and loading zones.ഀ
b) Accessible route from the parking and loading zones to the buildings.ഀ
c) Accessible routes to each building on the site which are required to be accessible.ഀ
d) Signage details for parking, striping, routes, restrooms, etc.ഀ
e) Restroom details for fixtures, grab bars and accessories.ഀ
The drawings have been modified to show accessible parking spaces and loading zones, accessibleഀ
routes and confirmed that restroom details for fixtures, grab bars and accessories has been provided.ഀ
All signs related to accessibility are listed in a separate contract with the client and will be a deferredഀ
submittal to the building for review and approval.ഀ
10. Amend plans to include stair signage plan, details and identify the location of the signage. Many ofഀ
the exit enclosures require the occupants to travel up to get to exit discharge. Clearly identify theഀ
direction of travel to the exit discharge.(IBC 1019.1.6)ഀ
The design team will modify the drawings to reflect required stair signage and directional signage. Itഀ
would be the intent of the design team to identify with the fire department additional egress signage orഀ
directional signage to ensure occupants will be directed to a an egress stair/passage way and to aഀ
public way.ഀ
11. Amend plans to include gates located at the level of exit discharge to eliminate occupants of theഀ
building from entering an enclosure and passing by the level of exit discharge. (IBC 1019.1.6)ഀ
Gates have been added to the plans to meet this requirement and direct occupants to the exterior orഀ
from continuing below or above a level of exit discharge.ഀ
C:\DOCUME-I\dhopp\LOCALS-I\Temp\B - Response to ToV-b06-0019.DOC Page 3 of 3ഀ
12. Elevator door which do not open into a lobby need to be provided with a smoke control door inഀ
accordance with IBC Section 715.3.5.3ഀ
None of the elevators penetrate more than 3 stories. Thus, smoke control and venting is not required.ഀ
13. Clearly identify the location of safety glazing per IBC Chapter 24 either in the window schedule or onഀ
the plan.ഀ
Bldg. B: Per A610 for window types with tempered glazing and reference building elevations forഀ
location of such window types.ഀ
Bldg. C: Per A610 & A611, tempered glazing is indicated at/in the following locations:ഀ
- within 24" of door edges that are less than 60" AFF.ഀ
- within units that have panes greater than 9 s.f.ഀ
- and in units that are within 18" of the floor.ഀ
See the updated window schedule that shows additional tempered glazing for units with panesഀ
greater than 9 s.f.ഀ
Bldg D: Per A610, tempered glazing is indicated at/in the following locations:ഀ
- within 24" of door edges that are less than 60" AFF.ഀ
- within units that have panes greater than 9 s.f.ഀ
- and in units that are within 18" of the floor.ഀ
See the updated window schedule that shows additional tempered glazing for units with panesഀ
greater than 9 s.f.ഀ
Bldg. E: Per A610 for window types with tempered glazing and reference building elevations forഀ
location of such window types.ഀ
14. The size of main elevator cars used for fire/emergency access needs to be determined by the Townഀ
of Vail Building and Fire Departments. Standard 24" x 76" required by code will not accommodate theഀ
stretchers used by emergency personnel. Please confirm the required size.ഀ
The elevator cabs are currently designed to comply with the standard stretcher requirement asഀ
adopted by the code. In the case of the Chalets the elevator serves 4 levels or 3 stories. Based onഀ
that interpretation the stretcher accessible would not be required. The design team is providing aഀ
stretcher accessible elevator to each unit beyond what would be required by code. The currentഀ
elevators will be 24x74 inches.ഀ
Architectural Comments:ഀ
15. Locate and define intent of 3 hour firewalls and how these comply with section 508, 2003 IBC.ഀ
The design team has used a series of fire resistive walls and floor assemblies to separate theഀ
buildings based on construction type of the buildings and the required occupancy separation of theഀ
different occupancies and uses. From the initial meetings with the Town of Vail Building, Fireഀ
Department and Colorado Inspection Agency it was identified that the buildings will communicateഀ
below grade via the parking garage and that there would be mixing of construction type and fireഀ
resistive separation requirements between buildings. Attached are code sheets identifying theഀ
proposed and required fire resistive separations. These separations include both vertical andഀ
horizontal fire resistive separations that are intended to compartment the buildings both vertically andഀ
horizontally. Additionally, there are occupancy separation fire resistive walls that separateഀ
occupancies. See the G-Series Code Sheets for details related to assumed property lines and fireഀ
resistive separations. USE OF 508.2 FOR CREATING SEPARATE BUILDINGS The design team hasഀ
utilized Section 508.2 of the International Building Code in conjunction with the administrativeഀ
modification process. BCER has submitted a request for an administrative modification defining theഀ
separation of the S-2 Parking Garage below the Residential Chalet portion of the building. Seeഀ
Administrative Modification Request dated April 3, 2006. From the initial meetings with the Town ofഀ
Vail Building, Fire Department and Colorado Inspection Agency it was identified that the buildings willഀ
CADOCUME-I\dhopp\LOCALS-I\Temp\B -Response to ToV-b06-0019. DOC Page 4 of 4ഀ
communicate below grade via the parking garage and that there would be mixing of construction typeഀ
and fire resistive separation requirements between buildings. Attached are code sheets identifying theഀ
proposed and required fire resistive separations. These separations include both vertical andഀ
horizontal fire resistive separations that are intended to compartment the buildings both vertically andഀ
horizontally. Additionally, there are occupancy separation fire resistive walls that separateഀ
occupancies. See the G-Series Code Sheets for details related to assumed property lines and fireഀ
resistive separations.ഀ
16. Clearly define the separation between existing and new addition. (Fire separation between I-A and III-ഀ
A construction).ഀ
The design team has used a series of fire resistive walls and floor assemblies to separate theഀ
buildings based on construction type of the buildings and the required occupancy separation of theഀ
different occupancies and uses. From the initial meetings with the Town of Vail Building, Fireഀ
Department and Colorado Inspection Agency it was identified that the buildings will communicateഀ
below grade via the parking garage and that there would be mixing of construction type and fireഀ
resistive separation requirements between buildings. Attached are code sheets identifying theഀ
proposed and required fire resistive separations. These separations include both vertical andഀ
horizontal fire resistive separations that are intended to compartment the buildings both vertically andഀ
horizontally. Additionally, there are occupancy separation fire resistive walls that separateഀ
occupancies. See the G-Series Code Sheets for details related to assumed property lines and fireഀ
resistive separations. USE OF 508.2 FOR CREATING SEPARATE BUILDINGS The design team hasഀ
utilized Section 508.2 of the International Building Code in conjunction with the administrativeഀ
modification process. BCER has submitted a request for an administrative modification defining theഀ
separation of the S-2 Parking Garage below the Residential Chalet portion of the building. Seeഀ
Administrative Modification Request dated April 3, 2006. From the initial meetings with the Town ofഀ
Vail Building, Fire Department and Colorado Inspection Agency it was identified that the buildings willഀ
communicate below grade via the parking garage and that there would be mixing of construction typeഀ
and fire resistive separation requirements between buildings. Attached are code sheets identifying theഀ
proposed and required fire resistive separations. These separations include both vertical andഀ
horizontal fire resistive separations that are intended to compartment the buildings both vertically andഀ
horizontally. Additionally, there are occupancy separation fire resistive walls that separateഀ
occupancies. See the G-Series Code Sheets for details related to assumed property lines and fireഀ
resistive separations.ഀ
17. Define amount and type of acid shown in pool equipment room in skier services building on sheetഀ
P201.ഀ
The amount and type of acid shown in pool equipment room on sheet W2.0 (P201 not an STOഀ
document) is 55 gallons or Muriatic Acid diluted with water at a 4:1 ratio (4 parts water: 1 part Muriaticഀ
Acid).ഀ
18. Provide a precise site plan showing exact locations of assumed property lines. If locations of assumedഀ
property lines are close enough to exterior walls to require rating of walls and opening protection,ഀ
provide details. The following locations may require protection based on assumed property lines. Theഀ
south and west wall of building B, north wall of building C, and the east wall of the south Vail Condos.ഀ
See sheets G016 thru G019 for revised plan information.ഀ
19. Provide detail for exterior wall types based on type of construction. Building is shown as Type I-Aഀ
construction which will require 3 hour exterior bearing walls. The details on sheet S002 don't reflectഀ
protection of structural members. Please clarify and amend plan accordingly.ഀ
Plan has been revised accordingly. See 24/S002 for additional information.ഀ
CADOCUME- I \dhopp\LOCALS- I\Temp\B - Response to ToV-b06-0019.DOC Page 5 of 5ഀ
20. Clarify classification of spa foyer, offices and accessory rooms called out on sheet GO 16 as A-3ഀ
occupancies.ഀ
Classification has been revised to `Spa/Health Club' on sheet G016. In the 2003 IBC Commentary aഀ
Health Club is listed a an A-3 Occupancy. The SPA most closely resembles a Health Club and designഀ
team has designated this area as a A-3 Occupancy.ഀ
21. Does corridor 13188 need to be an exit passageway or horizontal exit? Stair B501 discharges into thisഀ
hallway. Provide analysis to verify requirements. This protection must be continuous from verticalഀ
exit enclosure to exit discharge. Openings into these spaces are limited to those required for exitingഀ
from normally occupied spaces. Components of other trades (plumbing, mechanical and electrical)ഀ
are also limited to those required for the enclosure.ഀ
This corridor is not a horizontal exit. This is an existing exit passageway. 4240 will add a vestibule toഀ
separate the electrical room and reasonably comply with this requirement.ഀ
22. Does corridor B221 and associated stairs need to be an exit passageway or horizontal exit? Stairഀ
B501 discharges into this hallway. Provide analysis to verify requirements. This protection must beഀ
continuous from vertical exit enclosure to exit discharge. Openings into these spaces are limited toഀ
those required for exiting from normally occupied spaces. Components of other trades (plumbing,ഀ
mechanical and electrical) are also limited to those required for the enclosure.ഀ
It is the intent to extend the 2 hour walls to the exterior and there are no non-occupied rooms exitingഀ
into this exit passageway.ഀ
23. Clarify detail on sheet A400 & A404 called out as X/XXXXഀ
Details refer to 2/A508 on drawing A400 and 1/A508 on drawing A404.ഀ
24. Check all details referencing guard height. Detail 5 on Sheet A 700 shows guard height at 34 inches.ഀ
Min 42 inches required. (IBC 1012)ഀ
Section 5/A700 shows guard height at 42" as is related 3/A700.ഀ
25. Show compliance with ANSI A117.1-1998 for restrooms 6193, B196, 13128 and B142 on sheet A301ഀ
and B205 and B206 Sheet A304. The lavatory can not be within the clear floor space for the waterഀ
closet.ഀ
Restrooms B193, 13196, 13128 and B142 on sheet A301 and B205 and B206 on sheet A304 areഀ
compliant with ANSI A117.1-1998.ഀ
26. Amend plans to show clear floor space for a parallel approach to the showers shown on sheet A301ഀ
rooms 8191 and 13192. Alcove requirements needs to be 60" (ANSI 305.7)ഀ
HC showers B191 and B197 on sheet A301 are compliant with ANSI 305.7.ഀ
27. Show compliance with ANSI section 1003 for type B units at Suite 310 and 320 as required by sectionഀ
1107.6.1 2003 IBC.ഀ
Bathrooms B313 & B323 are compliant (see sheet A305). And doors B301, B311A, B314, B323 areഀ
compliant (see sheets A102 & A305). These rooms when added will become part of the Lodge atഀ
Vail. Currently the Lodge at Vail is an existing condition and is assumed to comply with accessibleഀ
rooms. With the addition of the 5 new residential suites two have been modified to be Type B units.ഀ
28. Clarify note on sheet A 600 between detail 10 and 11. Note states that openings can be unprotected.ഀ
Table 715.3 2003 IBC requires these openings to have a 3/a hour rating.ഀ
Note on sheet A600 between wall types 10 and 11 complies with Table 715.3 2003 IBC by statingഀ
`with 3/a" hour rating openings'.ഀ
C:\DOCUME-I\dhopp\LOCALS-I\Temp\B - Response to ToV-b06-0019.DOC Page 6 of 6ഀ
29. What is the size of the day tank for the back-up generator, quantity and classification of liquid andഀ
means for filling tank? This is shown on Building A plans & Building B plans. Currently a dieselഀ
generator is shown on the plans. H occupancy?ഀ
Diesel fuel to run generator shall be below exempt amounts permitted by building and fire codes.ഀ
Therefore, the emergency generator room would not be considered `H' occupancy.ഀ
30. Type of construction for building requires roof to be 1 '/2 hour construction. Detail G sheet A 602 callsഀ
out 1 hour roof assembly. Revise plans to reflect required rating for roof and soffits.(IBC Table 601)ഀ
Detail G on sheet A602 for roof construction complies with IBC Table 601, and shows `1 '/2 hr roof'.ഀ
31. Ramp between corridor B106 and stair B108 must have a handrail on both sides.(IBC 1010.8)ഀ
Ramp on Corridor 13106 has handrails on both sides per IBC 1010.8 shown on sheets A302 andഀ
A303.ഀ
32. Exit discharge from door B104 has a change in elevation of 12 inches with two risers. Provideഀ
handrail on both sides. Handrail shall have extensions. (IBC 1009)ഀ
Exterior stair has handrails with extensions on both sides per IBC 1009, shown on sheet A302.ഀ
33. Provide exit analysis for corridor 13107. Exit path and ratings will be reviewed with the exit analysis.ഀ
This corridor is not a rated corridor but a non-rated hallway serving the Reception Area between theഀ
new and existing portions of the Lodge at Vail.ഀ
34. Identify exit path from corridor on Level 2 on sheet A102 that enters into stair BS02. Identify rating ofഀ
this exit path and stair enclosure.ഀ
The exit path has been clarified on Sheet A102 and the rating of the corridor is consistent with theഀ
stair enclosure rating.ഀ
35. Duct penetrations through the existing walls are not all protected with dampers. Some are protectedഀ
and some are not. Please clarify.ഀ
ABS revised their drawings. See sheets M101 and M102.ഀ
36. Provide accumulative exit load at Door 131 08C. Verify door swing and exit width.ഀ
The cumulative exit loading at Door 13108C has been reviewed and door swing and exit width areഀ
adequate. The door swing of door B108c from the exit stair will be changed to discharge occupantsഀ
from the stair towards the stair on the west end. The cumulative exit loading into the stair is 160.ഀ
Occupants would be coming from the existing International wing conference rooms. Note that the 2ഀ
hour fire wall that they pass through is an existing horizontal exit and the that occupants are thenഀ
occupants can either go through Door B1 08C or continue down the hallway to the main entrance.ഀ
See attached sketch.ഀ
37. Please include Level 1 in the exit analysis. This sheet does not appear to be included.ഀ
See sheets G030 thru G034 for exiting information.ഀ
38. Amend plan to comply with approach clearance to the door into the Steam Room 8147.ഀ
Door to Steam Room B147 complies with the approach clearance (18") per ANSI 404 on sheet A302.ഀ
39. Wall types shown separating units on sheet A304 terminates a 2 hour wall at a wall with noഀ
construction type designated. Revise walls to form a complete separation.ഀ
Only a one-hour fire resistive wall is required. A two-hour wall is shown for sound control.ഀ
40. Provide approach clearances (18") on the pull side of doors: B180, B1 77B, B1 77A, B122 and 13135.ഀ
(ANSI 404)ഀ
C:ADOCUME-I\dhoppALOCALS-I\TeropAB - Response to ToV-b06-0019.DOC Page 7 of 7ഀ
Doors 13180, 1317713, 13177A, 13122 and 13135 show approach clearances (18") on the pull side perഀ
ANSI 404 on sheets 1/A101 and 1/A301.ഀ
41. Provide drinking fountains on spa level sheet A101.ഀ
Restrooms on Spa level 1 are private (for members only); the Spa Owner will provide water perഀ
his/her operation. On Spa second floor close to restrooms B206 and B206 one ADA compliantഀ
Electrical Water Cooler is provided as shown on sheet A304.ഀ
42. Fireplaces that are capable of burning wood must be enclosed within 1 hour shaft. (TOVBR)ഀ
Spa and Guest Rooms fireplaces are provided with gas burning artificial logs; they have a direct ventഀ
system shown on sheet 1/A902 and 1/A201. See also VFD Commercial Manual - Section 10305ഀ
`Manufactured Fireplaces and flues' and Slifer Interior design Manual Sheet A-1.ഀ
43. Doors 13122 and 13135 need to have 18" on the pull side of the doorഀ
See response to comment #40.ഀ
Mechanical Comments:ഀ
44. Provide make-up air to chiller room M103ഀ
Make-up air has been added. Refer to sheet M101 of the Building A set.ഀ
45. Clearly show the fireplace venting for community room B150. Show the location of vent piping andഀ
location of the termination.ഀ
Direct vent systems shown on 1/A902 and 1/A201. See also VFD Commercial Specification Sectionഀ
10305 - Manufactured Fireplaces and Flues.ഀ
46. Provide specification/venting for fireplace which is next to hot tub in couple treatment room 13171.ഀ
Clearly show the location of vent piping and the location of vent termination.ഀ
See response to comment #45.ഀ
47. Provide protection of duct openings located at B106 corridor and 13109 corridor. Dampers are shownഀ
on one side of the corridor, but not the other.ഀ
Fire/smoke dampers have been shown in the 2-hour wall penetration. See sheet M101.ഀ
Electrical comments:ഀ
48. Identify detail note 4 on sheet DE101.ഀ
Detail note 4 has been eliminated from sheet DE101.ഀ
49. DE101 - (FACP, MDCA, 5th floor lodge disconnect) - Provide change over plan that will not affectഀ
existing building function of the Lodge.ഀ
The change over for MDCA and the fifth floor meter center is being completed under a separateഀ
permit.ഀ
50. Feeder 26 to Pool Panel (E002) is rated 230A - load is 255 and OCPD is 300A...change to feeder 24ഀ
for this so conductors are rated for load and next higher OCPD rating is acceptable. 215.2(A)(1)ഀ
The load for the pool panel has been reduced to 179 amps per pool consultant documents. The loadഀ
summary on sheet E002 has been revised, and the OCPD serving the pool panel has been reducedഀ
to 225A/3P.ഀ
51. SG-1, SG-2 to be protected at MFR recommendations-provide MFR instructions (sheets E001/002-ഀ
Steam Generator)ഀ
See modified Note #1 on Equipment Schedule, E001.ഀ
CADOCUME-I\dhopp\LOCALS-1\Temp\B - Response to ToV-b06-0019. DOC Page 8 of 8ഀ
52. Wiring in guestrooms to be other than NM - construction type per building code prohibits this wiringഀ
method. 334.10 and code analysisഀ
Specification Section 16110.3.01 has been modified to eliminate the use of NM cable.ഀ
53. Spa EPO's (E101) not to be less than 5' from spa (680.41)ഀ
See modified plan E101. EPO switches have been relocated and note has been added.ഀ
Energy Code Review Comments:ഀ
Envelope Corn Checkഀ
54. The roof area of the conditioned spaces that are covered by landscape infill material do not appear toഀ
be included in the com-check. Clarify.ഀ
See attached Envelope Compliance Certificate.ഀ
55. Identify plan sheets showing insulation at the slab on grade which would be required to allow aഀ
continuous R-value.ഀ
Insulation has been deleted from calculation. See attached Envelope Compliance Certificate.ഀ
56. Architectural plan sheets show a concrete tile roofing material rather than the metal roof with thermalഀ
breaks as referenced on the com-check. Detail roof type insulation and any required thermal breaks.ഀ
Reference to metal roof has been changed. See attached Envelope Compliance Certificate.ഀ
Mechanical Com Checkഀ
57. Provide HVAC load calcs per 1997 ASHRAE.Sഀ
See attached Load Calcs for your reference.ഀ
58. Indicate on plan sheets the approved methods of sealing the duct joints.ഀ
Duct joint sealing is covered in specification section 15880 2.01 C. & 15880 3.01 G & H.ഀ
59. Provide calculations showing compliance for outside air required by Chapter 403 of the 2003 IMC.ഀ
See outside air calculation matrix on sheet M101.ഀ
Structural Comments:ഀ
See attached Structural Comments from Monroe & Newell Engineers.ഀ
Contact Person:ഀ
Matthew Royerഀ
Building Official/ Project Managerഀ
Colorado Inspection Agencyഀ
970-328-1790ഀ
matt. royer@ coinspect.comഀ
Plans Examiners and Engineers:ഀ
Barry Kramer- Building Officialഀ
Todd Dunkin- Electrical Plans Examinerഀ
Dennis Lohmeier- Plumbing Plans Examinerഀ
Duskin Lowe- Plans Examinerഀ
James P. Horne, P.E., S.E. - Structural Review Project Managerഀ
C:\DOCUME-I\dhopp\LOCALS-I\Temp\B - Response to ToV-b06-0019.DOC Page 9 of 9ഀ
sഀ
lഀ
1ഀ
1ഀ
Iഀ
pഀ
Dഀ
sഀ
pഀ
oNഀ
3 r~ഀ
VAILഀ
S Fഀ
Oഀ
D O 4Rഀ
eഀ
sഀ
sഀ
Nഀ
ഀ
sഀ
wഀ
9ഀ
Mഀ
III llt oz o~ഀ
° ~ z aഀ
.L Yഀ
-il:~:~t;_';.i.ഀ
G9 ' Atഀ
fr ~ഀ
1 1ഀ
April 3, 2006ഀ
Monroe & Newellഀ
Engineers, Inc.ഀ
4240 Architectureഀ
1621 Eighteenth Street, Suite 200ഀ
Denver, CO 80202ഀ
Attn: Randy Hartഀ
Re: Vail's Front Door (M&N # 5500.02) Spa - Building Bഀ
BUILDING PERMIT B06-0019ഀ
Dear Mr. Hart:ഀ
Vail, Coloradoഀ
Denver, Coloradoഀ
Dillon, Coloradoഀ
The following are our responses to the structural portions of The Town of Vail Buildingഀ
Department comments for the above building, dated March 10, 2006. We have included theഀ
original comment with each response. Our responses are noted with "M&N Response".ഀ
S 1. C/DC Calcs p. RB2: Snow drifting / sliding loads do not appear to have been considered for theഀ
balconies, please verify these loads are accounted for.ഀ
M&N Response:ഀ
Roof framing is designed to comply with the Town of Vail amendments to the 2003ഀ
International Building Code. These amendments do not require an increase in loadingഀ
due to wind or valleys.ഀ
S2. F 1/5001 Rebar in elevator pit footing is not identified in the detail or on plan.ഀ
M&N Response:ഀ
Please refer to revised section.ഀ
.1'/A,ഀ
2006 Platinum Sponsorഀ
The Colorado Chapter ofഀ
The American Institute of Architectsഀ
www.monroe-newell.comഀ
1701 Wynkoop Street * Suite 200 • Denver, Colorado 80202ഀ
(303) 623-4927 • FAX (303) 623-6602 • email denverginonroe-newell.comഀ
S3. F I/SOOI Long way footing rebar in the exterior footing is not identified. Is detail 4/SOOIഀ
intended to be a typical detail for all strip footings? If so please reference 4/5001 as suchഀ
in other details and on plan.ഀ
M&N Response:ഀ
Please refer to revised section.ഀ
S4. F 2/5001 Gravel fill below SOG is not specified, verify drainage requirements per soilsഀ
report are coordinated with the other structures. Elevator sump in the pits seemsഀ
required.ഀ
M&N Response:ഀ
Slab on grade construction to be in accordance with the soils report per the General Noteഀ
Item 5A. Please refer to revised section.ഀ
S5. F 2/5001 Length and width dimensions are not on plans or the section, please provide.ഀ
M&N Response:ഀ
Please refer to revised section.ഀ
S6. F 1 O/5001 Show detail of how cast in place concrete stairs are supported at the concreteഀ
walls (ref. also 5101). Consider nosing & tread "L" bars for durability and freeze thawഀ
conditions.ഀ
M&N Response:ഀ
Please refer to revised sections and plans.ഀ
ST D I &2/5002 Sections identify 2" metal deck" while plans say 1 %2" deck- coordinate theഀ
drawings. Verify if deck is composite deck or non-composite deck. Verify also bottomഀ
flutes are wide enough to receive composite studs as required. Suggest galvanized &ഀ
vented deck on any slabs exposed to weather.ഀ
M&N Response:ഀ
Please refer to revised sections.ഀ
SBA.LS There do not appear to be any lateral analysis calculations in the submitted calcsഀ
package. Please submit lateral calculations for review. See comment S8 as well.ഀ
M&N Response:ഀ
Please refer to revised calculations.ഀ
S8. LS S I00 / calcs/ drawings IBC 3403.2 states basically that any additions /alterations toഀ
existing structures shall not increase forces in any existing structural element by moreഀ
than 5% without demonstrating current code compliance for such structural elements. Byഀ
inspection, this addition appears to be more than a 5% addition to the existing Lodge inഀ
terms of mass and exposed area for wind forces. Further, gravity loads have beenഀ
increased in some areas due to new steel framing supported on existing walls. Pleaseഀ
demonstrate by structural calculation that this %5 rule is not exceeded, or provideഀ
calculations for the following:ഀ
a) Details 24/S002, 22/S002, 6/S003, 10/S003, 13/S002: verify capacity of existingഀ
CMU and / or precast bearing walls. Verify allowable soil bearing pressure is notഀ
exceeded.ഀ
b) Details 4&5/S002: verify lateral out of plane capacity of existing walls has notഀ
been completely removed during demolition, that structure on opposite sideഀ
braces bearing walls out of plane and lateral diaphragm to wall connections haveഀ
not been compromisedഀ
c) It appears that lateral wind and seismic calculations are required for theഀ
completed entire Lodge building (existing plus new construction), as well as theഀ
local re-entrant corners in the addition itself, due to the IBC 5% rule notedഀ
above. This could be done demonstrating that as much or more lateral strengthഀ
and stiffness is added to the structure with the addition than previously existed,ഀ
however structural calculations are required to verify this. Check diaphragm /ഀ
drag forces through connections to the existing structure, verify soil pressure atഀ
ends of lateral shear walls, verify lateral drifts, and other typical lateralഀ
calculations.ഀ
M&N Response:ഀ
a) New loads being applied to the existing structure are similar to existing loads.ഀ
This is due to roughly the same footprint for the existing and new constructionഀ
therefore, the existing structure will need to resist no additional loading.ഀ
b) Demolition of existing wood kickers will increase out of plane capacity ofഀ
existing precast walls. Details 4&5/S002 will transfer no additional load toഀ
existing wall.ഀ
C) The addition shown on the structural plans has roughly the same footprint as theഀ
existing building that is to be demolished and therefore will add no additionalഀ
load to the existing structure. The new addition utilizes separate lateral systemഀ
to support itself therefore, no additional calculation on the existing structure areഀ
required.ഀ
S9. D S 101 Structural slab shown as "RE: Building A, S104..." shows many large steps inഀ
the finished elevation in Building B drawings, ref. line 12.0 near Q.6. No such steps areഀ
shown in the Building A package, Sheet 5104. Verify if these steps are accomplished byഀ
over framing of some kind, and how the finished raised floor elevation is supported.ഀ
Provide details of this over framing if our interpretation is correct.ഀ
M&N Response:ഀ
Please refer to revised plans and added section 15/S003.ഀ
S 10. D S 101 Verify point loads from any large tubs or masonry is considered in building Aഀ
slab design.ഀ
M&N Response:ഀ
Additional loads have been coordinated with Building "A" drawings and calculations.ഀ
S 11. D 7,8,9,10/S002 Seems open end CMU is required at the base instead of lintel blocksഀ
shown; also, no accessories are shown for supporting slab rebar: CRSI says accessoriesഀ
will not be furnished unless specifically required by contract documents. Verifyഀ
additional #4 @ 12" o.c. are positioned in the middle of slab on deck - seems theyഀ
should be in the low flutes?ഀ
M&N Response:ഀ
Please refer to revised sections.ഀ
S12. D 1/S001 General comment for project: verify horizontal reinforcing in CMU bearingഀ
walls is only the wire ladder reinforcing per general notes. No horizontal bars appear toഀ
be called out in CMU walls. Also, verify that these are typically partially grouted CMUഀ
walls above grade, per General Notes below grade CMU is fully grouted. Suggestഀ
clarify if CMU in the parking structure is fully grouted (this is below grade but still anഀ
interior condition... please clarify)ഀ
M&N Response:ഀ
Please refer to General Notes item 9D and revised plans.ഀ
S13. D 12/S002 the section indicates a steel beam supported by a connection below an 18"ഀ
concrete slab (per Building A drawings)- verify reaction used for this connection designഀ
includes column transfer loads from columns above (ie calcs p. FB 101, beams FB32,ഀ
FB30 are not included in the calculations, we can not verify that transfer loads have beenഀ
included.) Also, verify connection of embeds conforms to IBC Table 1912.2. Provideഀ
calculations.ഀ
M&N Response:ഀ
Please refer to revised calculations.ഀ
S14. D 9/S002 Design deck support connection at Bldg. A slab edge - should detail 6/S002 beഀ
referenced for use in 9/S002? Note also rebar between slab on metal deck and concreteഀ
slab at Bldg. A is not likely to be placed in this way due to formwork obstruction.ഀ
Suggest reconsider this detail.ഀ
M&N Response:ഀ
Please refer to revised section.ഀ
S15. C S102: calcs p FB26, floor beam FB 15: calc shows W 12x14, beam per plan inഀ
calculations (FB101) is W 14x35; beam per drawings is W 14x26 - please verify beamഀ
size per plan is correct.ഀ
M&N Response:ഀ
Beam per S 102 is correct. Please see revised calculation and key plan.ഀ
S 16.D S 102: beam W 12x 14 near grids 13.8/S.2 at south side of "open" area is not framed asഀ
such in calculations, FB 101. Seems a detail is required at east end of this beam @ഀ
existing structure.ഀ
M&N Response:ഀ
Please refer to revised plans, revised calculation and key plan.ഀ
S17. D 13/S002 Suggest 1" grout for full bearing under this base plateഀ
M&N Response:ഀ
Please refer to revised plans.ഀ
S18. D 14/5002 & 23/5002 Verify these sections are cut on plan - we can't locate them.ഀ
M&N Response:ഀ
14/5002 is cut on S 103. 23/5002 is added to S 101, please refer to revised plans.ഀ
S19. D 9/5003 We feel the steel fabricator can not design this steel to CMU connection: first,ഀ
there are no loads provided; second, this is not a standard steel to steel connection whereഀ
tables apply. Third, snow plus snow drift plus sliding snow must be used for loads, asഀ
applicable. At the very least, the FOR needs to design the embed at top of CMU, andഀ
also consider the moment cranked into the top of CMU wall by the eave beam. Provideഀ
calculations.ഀ
M&N Response:ഀ
Please refer to revised plans and calculations for embed plate. Shear connection to beഀ
per fabricator according to General Notes. Please refer to response to S 1 for snowഀ
loading.ഀ
520. D 10/5003 We can not locate calculations for this header connection. Verify grout in theഀ
cells adjacent to the new header is not required for the capacity: it is unclear how theseഀ
cells will be grouted prior to demolition without further direction on the detail. Further,ഀ
sequencing notes are required regarding temporary shoring (if these are bearing wallsഀ
above, loads are required to design the temporary shoring) Please address these issues.ഀ
M&N Response:ഀ
Please refer to revised calculations.ഀ
521. D 5003, trusses 1,2,and 3: There does not seem to be enough information on the drawingsഀ
to detail or fabricate these trusses; does not seem that calculations have been provided.ഀ
Verify trusses are laterally supported by the roof framing / roof deck.ഀ
M&N Response:ഀ
Please refer to revised plans and calculations.ഀ
522. D S 101 Clarify three elevations shown at two ramps near V.7/12.9- the info appears toഀ
conflict.ഀ
M&N Response:ഀ
Please refer to revised plans.ഀ
523. D 5102 Callout on v.7/13.9 for detail 11/5001: this detail does not exist.ഀ
M&N Response:ഀ
Please refer to revised plans.ഀ
S24. D S102 Seems a section is required at the beam/ CMU wall connection @ U.5/15.6: thisഀ
is a fairly complicated cantilevered area.ഀ
M&N Response:ഀ
Please refer to revised plans, added section 14/S003 and calculations.ഀ
S25. D S 101, S 102, S 103 Verify fire rating requirements for slabs on deck (deck and concreteഀ
alone appear to be unrated).ഀ
M&N Response:ഀ
Beams and decking receive sprayed on fireproofing per Architectural details. 4 '/z" slabഀ
meets all fire rating types.ഀ
S26. D 5102: detail 15/S002 cut on line 15.6 does not exist; detail cut through south wall ofഀ
building is not labeled, please fix these call outs.ഀ
M&N Response:ഀ
Detail 15/S002 is correctly labeled and detail is now included on S002. Detail on southഀ
wall not required. Please refer to revised plans.ഀ
S27. D S 103 Several references this sheet refer to 1" 18 ga. composite deck. We are not awareഀ
of such a deck that is commonly used (ie Vulcraft) - do you mean form deckഀ
(noncomposite)? Please clarify.ഀ
M&N Response:ഀ
Decking is 1 '/2" similar to other composite slabs. Please refer to revised plans.ഀ
S28. D S 103, note 8: #2 ties need a diagram or a defined bend shape. Verify #2 bars areഀ
commonly used in this instance, or specify 1/4" diameter wire.ഀ
M&N Response:ഀ
Please refer to revised plans.ഀ
S29. D S 103 provide CMU column calculations; verify requirements of MSJC for columns areഀ
satisfied. Are these column intended to act as lateral piers? If so, provide combinedഀ
lateral / gravity calculations for worst-case column / pier.ഀ
M&N Response:ഀ
Please refer to revised calculations.ഀ
S30.LS S104 Verify roof deck welding attachment specified on 5001 for lateral loads. Verifyഀ
attachment to existing building is sufficient for lateral load transfers expected from theഀ
new to existing building. Sections 6&11/S003 do not appear to attach the roof diaphragmഀ
to the existing floor diaphragm at all - seems a lateral connection or diaphragm chord isഀ
required. Provide calcs.ഀ
M&N Response:ഀ
New structure has separate lateral system therefore existing structure supports onlyഀ
gravity loading. Please refer to revised calculation.ഀ
S31. D S 104 / A200, A201: it appears that the existing building is much taller than this addition,ഀ
however it does not appear snow drift or sliding snow has been considered in theseഀ
designs. Further, please verify unbalanced snow loads have been considered for the newഀ
roof over the addition. (ASCE 7-02 7.6, 7.7, 7.9)ഀ
M&N Response:ഀ
Please refer to the response to Item S 1.ഀ
532. D 5701 Please identify several of the framing members that are not sized.ഀ
M&N Response:ഀ
Please refer to revised plans.ഀ
533. D 5701 Seems details are required at various "existing" and "precast" landings to showഀ
how stairs, landings, and walls interconnect.ഀ
M&N Response:ഀ
Please refer to revised plans.ഀ
S34. D 5701 Stair BS05: verify steel channels and precast landing is supported on the east sideഀ
by a 6" light gauge stud wall. Provide details.ഀ
M&N Response:ഀ
Precast stair is supported by masonry walls. Please refer to revised plan and addedഀ
section.ഀ
535. D D101-D102 Verify that existing structural elements will be shored for the full designഀ
loading at occupied space & roof above during demolition and construction, as directedഀ
by the FOR or other registered P.E. in Colorado. Gravity and lateral loads should beഀ
considered.ഀ
M&N Response:ഀ
The design for the temporary shoring is a Means and Methods question for the Generalഀ
Contractor therefore not part of the scope of work for the EOR. The General Contractorഀ
should hire a register Professional Engineer in Colorado to design a shoring system toഀ
carry existing design loading. This design may then be reviewed by the FOR forഀ
compliance to the project requirements.ഀ
End of Comment Responses.ഀ
If you have any questions or comments, please call.ഀ
Very truly yours,ഀ
MO ROE NEWELL ENGINEERS, INC.ഀ
Peter D. Monroe, P.E.ഀ
Principalഀ
Iഀ
Fഀ
Monroe & Newellഀ
Engineers, Inc.ഀ
STRUCTURAL ENGINEERING CALCULATIONSഀ
For:ഀ
Vail's Front Doorഀ
Building "B"ഀ
Spa Guestroom Suite Additionഀ
Permit B06-0019ഀ
Vail, Coloradoഀ
M&N #5500.02ഀ
Vail, Coloradoഀ
Denver, Coloradoഀ
Dillon, Coloradoഀ
These drawings and calculations are the property of Monroe & Newell En-rineers, Inc. Any use orഀ
reproductions of these calculations without the expressed written permission of Monroe & Newellഀ
Engineers, Inc. is strictly prohibited.ഀ
**P.E. stamp on sheet applies to the following calculation pages and indicates that have been reviewed.ഀ
This includes all sheets attached to this cover.ഀ
April 3, 2006ഀ
iW1~~iഀ
=1ഀ
2006 Platinum Sponsorഀ
The Colorado Chaptcr ofഀ
The American Institute of Architectsഀ
www.monroe-newelLcomഀ
1701 Wynkoop Street • Suite 200 • Denver, Colorado 80202ഀ
(303) 623-4927 • FAX (303) 623-6602 . email: denver@monroe-newelLcomഀ
_ '2.~._ഀ
Monroe & Newellഀ
Engineers, Inc.ഀ
PAM If.T 20,4-1 Milli, Rh-l Ml IP,ddM%ഀ
JOB i - _ഀ
SHEET NO. OF~ 'ഀ
CALCULATED BY DATEഀ
CHECKED BY DATEഀ
crniഀ
Monroe & Newell Engineers, inc. Title : Vail's Front Door - Spaഀ
1701 Wynkoop Street, Suite 200 Dsgnr: Arthur Ashworth, PEഀ
IT)ഀ
Description : Lodge Expansionഀ
Denver, CO 80202ഀ
303.623.4927 Scopeഀ
Fax: 303.623.6602ഀ
Job # 5500.02ഀ
Date: 12:21 PM, 31 MAR 06ഀ
, -7ഀ
Rev: 580009ഀ
User: KW-0606238, Ver5.8.0, 1-Dec-2003 Concrete Rectangular & Tee Beam Design Page 1ഀ
(0)1983-2003 ENERCALC Engineering Software 5500.ecw:Misc Iഀ
Description Exterior Stair support Beamഀ
General information Code Ref: ACI 318-02, 1997 UBC, 2003 IBC, 2003 NFPA 5000ഀ
Span 35 50 ft f'c 5,000 psiഀ
Depth 24.000 in Fy 60,000 psiഀ
Width 12.000 in Concrete Wt. 145.0 pcfഀ
Seismic Zone 0ഀ
End Fixity Pinned-Pinnedഀ
Beam Weight Added Internally Live Load acts with Short Termഀ
Reinforcingഀ
Rebar @ Center of Beam... Rebar @ Left End of Beam... Rebar @ Right End of Beam...ഀ
Count Size 'd' from Top Count Size 'd' from Top Count Size 'd' from Topഀ
#1 8 8 21.50in #1 in #1 inഀ
Note: Load factoring supports 2003 IBC and 2003 NFPA 5000 by virtue of their references to ACI 318-02 for concrete design.ഀ
Factoring of entered loads to ultimate loads within this program is according to ACI 318-02 C.2ഀ
Uniform Loadsഀ
v aഀ
Dead Load Live Load Short Termഀ
Star; Endഀ
#1 1.088 k 0.550 k k 0.000 ft 35.500 ftഀ
Beam Design OKഀ
Span = 35.50ft, Width= 12.00in Depth = 24.00inഀ
Maximum Moment : Muഀ
451.20 k-ftഀ
Allowable Moment: Mn*phiഀ
499.07 k-ftഀ
Maximum Deflectionഀ
-1.7101 inഀ
P.1axi .u.. Shear : Vuഀ
45.96 kഀ
Mഀ
ax Reaction @ Leftഀ
34.22 kഀ
Allowable Shear:. Vn*phiഀ
75.89 kഀ
Mഀ
ax Reaction @ Rightഀ
34.22 kഀ
Shear Stirrups...ഀ
Stirrup Area @ Section 0.440 iഀ
n2ഀ
Region 0:000ഀ
5.917ഀ
11.833ഀ
17.750 23.667ഀ
29.583 35.500 ftഀ
Max. Spacing 10.750ഀ
10.750ഀ
10.750ഀ
10.750 10.750ഀ
10.750 10.750 inഀ
Max Vu 45.959ഀ
34.164ഀ
17.082ഀ
16.675 16.675ഀ
33.757 45.552 kഀ
Bending & Shear Force Summaryഀ
Bending... Mn*Phiഀ
Mu, Eq. C-1ഀ
Mu, Eq. C-2ഀ
Mu, Eq. C-3ഀ
@ Center 499.07 k-ftഀ
451.20 k -ftഀ
338.40 k-ftഀ
195.37 k-ftഀ
@ Left End 0.00 k-ftഀ
0.00 k-ftഀ
0.00 k-ftഀ
0.00 k-ftഀ
@ Right End 0.00 k-ftഀ
0.00 k-ftഀ
0.00 k-ftഀ
0.00 k-ftഀ
Shear... Vn*Phiഀ
Vu, Eq. C-ഀ
Vu, Eq. C-,ഀ
Vu, Eq. C4ഀ
@ Left End 75.89 kഀ
45.96 kഀ
34.47 kഀ
19.90 kഀ
@ Right End 75.89 kഀ
45.55 kഀ
34.16 kഀ
19.72 kഀ
Deflectionഀ
Deflections...ഀ
Upwardഀ
Downwardഀ
DL + [Bm Wt]ഀ
0.0000 inഀ
at 0.0000 ftഀ
-1.2184 inഀ
at 17.7500ftഀ
DL + LL + [Bm Wt]ഀ
0.0000 inഀ
at 0.0000 ftഀ
-1.7101 inഀ
at 17.7500ftഀ
DL + LL + ST + [Bm Wt]ഀ
0.0000 inഀ
at 0.0000 ftഀ
-1.7101 inഀ
at 17.7500ftഀ
Reactions...ഀ
@ Leftഀ
@ Rightഀ
DL + [Bm Wt]]ഀ
24.459 kഀ
24.459 kഀ
DL + LL + [Bm Wt]ഀ
34.222 kഀ
34.222 kഀ
DL + LL + ST + [Em Wt]ഀ
34.222 kഀ
34.222 kഀ
-ഀ
ivionroe & Neweii Engineers, inc.ഀ
Title : Vail's Front Door - Spaഀ
Job # 5500.02ഀ
jഀ
1701 Wynkoop Street; Suite 200ഀ
Dsgnr: Arthur Ashworth, PEഀ
Date: 12:21 PM, 31 MAR 06ഀ
Denver, CO 80202ഀ
Description : Lodge Expansionഀ
ഀ
Jഀ
303.623.4927ഀ
Scopeഀ
Fax: 303.623.6602ഀ
Rev: 580009ഀ
User. 6238, Ver5.8.0, 7-Dec-2ഀ
ai1oc1.OAAI.onnv cnicervlഀ
003 Concrete Rectangularഀ
c~a,,~.eഀ
& Tee Beam Designഀ
Page 2 hഀ
SSOO.ecw:btiscഀ
Description Exterior Stair support Beamഀ
Section Analysisഀ
Evaluate Moment Capacity...ഀ
Centerഀ
Left Endഀ
Right Endഀ
X : Neutral Axisഀ
9.290 inഀ
0.000 inഀ
0.000 inഀ
a = beta' Xneutralഀ
7.432 inഀ
0.000 inഀ
0.000 inഀ
Compression in Concreteഀ
379.032 kഀ
0.000 kഀ
0.000 kഀ
Sum [Steel comp. forces]ഀ
0.000 kഀ
0.000 kഀ
0.000 kഀ
Tension in Reinforcingഀ
-379.200 kഀ
0.000 kഀ
0.000 kഀ
Find Max As for Ductile Failure...ഀ
X-Balancedഀ
12.724 inഀ
0.000 inഀ
0.0000 inഀ
Xmax = Xbal ' 0.75ഀ
9.543 inഀ
0.000 inഀ
0.000 inഀ
a-max = beta ' Xbalഀ
10.180 inഀ
0.000 inഀ
0.000 inഀ
Compression in Concreteഀ
389.369 kഀ
0.000 kഀ
0.000 kഀ
Sum [Steel Comp Forces]ഀ
0.000 kഀ
0.000 kഀ
0.000 kഀ
Total Compressive Forceഀ
389.369 kഀ
0.000 kഀ
0.000 kഀ
AS Max = Tot Force / Fyഀ
6.489 in2ഀ
0.000 in2ഀ
0.000 in2ഀ
Actual Tension Asഀ
6.320 OKഀ
0.000 OKഀ
0.000 OKഀ
Additional Deflection Calcsഀ
_ aഀ
Neutral Axisഀ
9.530 inഀ
~Mcrഀ
50.91 k-ftഀ
(grossഀ
13,824.00 in4ഀ
Ms:Max DL + LLഀ
303.72 k-ftഀ
!crackedഀ
9;977.53 in,^ഀ
R1 = (Ms:DL+LL)(v"Grഀ
0.168ഀ
Elastic Modulusഀ
4,030.5 ksiഀ
Ms:Max DL+LL+STഀ
303.72 k-ftഀ
Fr = 7.5 " f'cA.5ഀ
530.330 psiഀ
R2 = (Ms:DL+LL+ST)/Mcrഀ
0.168ഀ
Z:Crackingഀ
127.990 Winഀ
Leff... Ms(DL+LL)ഀ
9,995.647 in4ഀ
Leff... Ms(DL+LL+ST)ഀ
9,995.647 in4ഀ
Eff. Flange Widthഀ
12.00 inഀ
ACI Factors (per ACI 318-02, applied internally to entered loads) 101ഀ
-1 _ഀ
ACI C 1 & C 2 DLഀ
ഀ
1.400ഀ
ACI C 2 Group Factor 0.750 Add"I "1.4" Factor for Seismic 1.400ഀ
ACI C-1 & C-2 LLഀ
1.700ഀ
ACI C-3 Dead Load Factor 0.900 Add" l "0.9" Factor for Seismic 0.900ഀ
ACI C-1 & C-2 ST .ഀ
1.700ഀ
ACI C-3 Short Term Factor 1.300ഀ
....seismic = ST ` :ഀ
1.100ഀ
Monroe & Newell Engineers, inc. Title : Vail's Front Door - Spa job # 5500.02ഀ
1701 Wynkoop Street, Suite 200 Dsgnr: Arthur Ashworth, PE Date: 12:21 PM, 31 MAR 06ഀ
Denver, CO 80202 Description : Lodge Expansionഀ
303.623.4927 Scope:ഀ
Fax: 303.623.6602ഀ
mev: bdw`Jaഀ
User: KW-0606238, Ver5.8.0, 1-Dec-2003 Concrete Rectangular & Tee Beam Design Page 3 Iഀ
(c)1983.2003 ENERCALC Engineering Software 5500 ecw 11iscഀ
Description Exterior Stair support Beamഀ
Sketch & Diagramഀ
aഀ
50.3 355 7.10ഀ
10.65 !14.20 17.75 21.30 24.85 28.40 31.95 355038 , 1 355 9.10 10.65 i4.2017.75 21.30 2d.85 28.40 31.95 35.50ഀ
WfiIiiiiii; nnnrn6,r Ii, rn rnrn iirഀ
1.638k/II 2C+3-.ഀ
15 = _ഀ
lalഀ
uu0ഀ
7 -7ഀ
W .ഀ
u.0ഀ
iഀ
3n 4tഀ
i .20 17 :ഀ
- -ഀ
:15.13ഀ
Mu:Max=d51.20k-ftഀ
:30.26;ഀ
- -ഀ
;22.69 : -ഀ
Dmax = 1.71 Olinഀ
;-40.35ഀ
:ഀ
130 26 -ഀ
Rmax = 34.222kഀ
Rmax = 34 Load (k)ഀ
Loch e AI'nq f lember_(1ഀ
1ഀ
Shear Load (k) Location Along Member (ft)ഀ
~ഀ
Vu-Max=45.959kഀ
Vu Max= 20 5 710ഀ
0. a_ 14<I s i.-.0 24.85 28.40 31.95 3ഀ
1 2'.30 24.85 28.40 31.95 3550ഀ
55033840355 7.10 7065ഀ
406.081ഀ
304.56''.ഀ
360.96:ഀ
270.72' - -ഀ
-ഀ
315.84'ഀ
- -ഀ
236.88 - -ഀ
27072:ഀ
203.04ഀ
T25 60ഀ
169.20ഀ
80.1Eഀ
2ഀ
ReAumg Moment (k 1.t)ഀ
~J Location Along Member (ft) Jഀ
6e.-4,* Moment tk )t) ~ Location Along Member (ft)ഀ
Beare Sketchഀ
Stresseഀ
s for ACI C-1 Combinationഀ
Stresses for ACI C-2 Combinationഀ
?2.91 356 710 10.65 14.20 1 7.76 21 .30 24.95 28.40 31 95 35 50 3a '..155 ' 70ഀ
W.6 14.20 !17.7 21 30 24.85-A40 31.95 - 35.5C14- - 10 41C `120 !17,75-21 -0-24.35 2840 31.95-35.50ഀ
Cഀ
1321- r-_-ഀ
. 1=69ഀ
03ഀ
0.00ഀ
yഀ
13'8'.ഀ
"20.3-ഀ
.17.16.ഀ
,ഀ
She r load (klഀ
Shear Load W location elഀ
o.ഀ
'8.73ഀ
03. 3.55 7.10ഀ
10 6 I 2 0 _h 7 4_ AO' 31 95 35.6 303.723.55 7.70 10 5 ;I1 0 7._21 1 35 28.40" 3195 36.50 17ഀ
_13ഀ
10,ഀ
273.35 :ഀ
ഀ
273.35',;ഀ
.ഀ
.ഀ
242498! :ഀ
- _ഀ
24298. -ഀ
: ! ! Iഀ
212,60:___ഀ
212.60ഀ
_ഀ
782.23ഀ
-ഀ
]822: -ഀ
Shear Load O k r Location Along Member (ft)ഀ
161.86 -ഀ
191:ഀ
195.373.55 7.10 10.65 .1=1 J, 75 21 30 24.85 28.40 31.95ഀ
35.50ഀ
175.83!ഀ
-ഀ
91.1 °ഀ
60 7sഀ
60.-1ഀ
156301ഀ
3C 3'ഀ
.-137ഀ
138.76ഀ
Be .,Pഀ
e s 1'ഀ
11c `IC 9iഀ
5ഀ
s 0-5 t6ഀ
B 0vm o :-q - go..Al t hor oഀ
10 13674 lഀ
521 3C X185 2840-i'35ഀ
50ഀ
SSഀ
UJഀ
00 ~ഀ
N 7.22 - -ഀ
orഀ
.ഀ
.ഀ
=ഀ
nഀ
.ഀ
.oഀ
.ഀ
.ഀ
.ഀ
97ഀ
69ഀ
031ഀ
3;ഀ
.ഀ
78.75ഀ
0.68ഀ
:0.68ഀ
-0.86ഀ
!0.86 -ഀ
-ഀ
ഀ
-1.03 :ഀ
'1.03 .ഀ
39.07ഀ
-ഀ
- -ഀ
=120ഀ
-1.37 !ഀ
,ഀ
-1.37 .ഀ
_ഀ
54ഀ
s4 ! -ഀ
eeHdit Moment (k-ft) Location Along Member (ft)ഀ
Local "y" Deflection (in)ഀ
Location Along Member (ft)ഀ
Local "y" Deflection (in) Location Along Member (ft)ഀ
Stresses for ACI C-3 Combinationഀ
Stresses for Service Dead + Live Loadsഀ
Stresses for Dead+Live+Short Term Loadsഀ
L,ഀ
Nഀ
Gഀ
Cഀ
Oഀ
Oഀ
wഀ
Gഀ
G4ഀ
c'ഀ
Wഀ
C!]ഀ
rഀ
Q~ഀ
_Uഀ
a~ഀ
cഀ
• cഀ
Cഀ
Lഀ
f yഀ
tiഀ
Cഀ
aഀ
1ഀ
cഀ
cഀ
Qഀ
Cഀ
0ഀ
Qഀ
raഀ
zഀ
1n+ഀ
dഀ
Fഀ
Lഀ
Uഀ
tiഀ
t1ഀ
9ഀ
sഀ
O n'ഀ
0ഀ
cഀ
Glഀ
:Eഀ
Wഀ
Rഀ
Oഀ
Cഀ
3ഀ
0ഀ
0ഀ
@L i 3ഀ
q ,n ,bഀ
zNcoocoഀ
Cl r, Mഀ
ഀ
y .ഀ
cഀ
N M ~ ~ a 3 ~ - `eyഀ
~ O 4ഀ
rഀ
. 4ഀ
.i y.ഀ
P• 3 yF x xഀ
.s N Oഀ
q n toഀ
~M G1C0ഀ
~M f q xഀ
01 qഀ
M Mഀ
rഀ
=Oഀ
r ,ഀ
Oഀ
J Lഀ
v •~;v; oഀ
vഀ
vഀ
kM° M:-Oഀ
tox~o ~y,ZNtoxഀ
rnc+yഀ
.L~ N Gഀ
C T tഀ
M N ri xഀ
Mഀ
t'ഀ
3 nഀ
N CDഀ
v ~ഀ
Mഀ
CJ ~ഀ
~ Mഀ
Mഀ
C ~ഀ
Lഀ
~tഀ
aഀ
Oഀ
L.Lഀ
m ~ഀ
w~ഀ
I 1ഀ
ZN o~yഀ
My°xഀ
fഀ
4 ~ഀ
Y t~ഀ
"r G1ഀ
r` A ~ Nഀ
M t+ഀ
N Cഀ
r ~ l7 Qഀ
M q qഀ
M Mഀ
7ഀ
2002 Lat/Lon Lookup Output!ഀ
w-- " U S G Sഀ
ssreua fare charrgirt wandഀ
LOCATION 39.63992 Lat. -106.37400 Long.ഀ
The interpolated Probabilistic ground motion values, in %g,ഀ
at the requested point are:ഀ
10%PE in 50 yr 2%PE in 50 yrഀ
PGA 4.90 15.08ഀ
0.2 sec SA 10.47 28.41ഀ
1.0 sec SA 2.60 6.79ഀ
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -ഀ
SEISMIC HAZARD: Hazard by Lat/Lon. 2002ഀ
http://egint.er.us-s.gov/eq-men/egi-bin/find-11-2002-interp-06.cgiഀ
Page 1 of 1ഀ
12-ഀ
n~ഀ
3/30/2006ഀ
JOBഀ
'r Monroe & Newellഀ
Engineers, Inc. sHE_T NO. OFഀ
CALCULATED BY DATEഀ
CHECKED BY DATEഀ
ഀ
ഀ
ഀ
ഀ
Jഀ
.ഀ
iഀ
"lഀ
a.. :e leyഀ
ഀ
ഀ
ഀ
rഀ
✓,s _ഀ
ഀ
rഀ
z - 6 ~w [ഀ
ഀ
.ഀ
ഀ
ഀ
1 ?ഀ
/'I ~I r rrഀ
ഀ
ഀ
tഀ
.ഀ
ഀ
ഀ
tഀ
.............................f.........................................i..........ഀ
>ഀ
1ഀ
ഀ
ഀ
ഀ
...i.;...ഀ
ഀ
hഀ
lഀ
ഀ
Jഀ
ഀ
ഀ
ഀ
ഀ
.ഀ
.ഀ
ഀ
' j f { E iഀ
:ഀ
's !ഀ
1ഀ
.ഀ
ഀ
ഀ
:ഀ
ഀ
ഀ
...i.................._...............ഀ
_ഀ
-ഀ
ഀ
ഀ
ഀ
ഀ
ഀ
_ഀ
ഀ
.ഀ
,ഀ
.ഀ
1ഀ
ഀ
.ഀ
tഀ
ഀ
ഀ
yഀ
;ഀ
ഀ
ഀ
' _ _ഀ
tഀ
/ഀ
ഀ
ഀ
Lഀ
ഀ
yഀ
:ഀ
ഀ
:ഀ
i i 4......_.ഀ
ഀ
ഀ
ഀ
ഀ
i~ഀ
iഀ
I 'ഀ
ഀ
.ഀ
.ഀ
:ഀ
ഀ
;ഀ
ഀ
ഀ
.ഀ
k.!ഀ
r it^ഀ
ഀ
Monroe & Newellഀ
Engineers, Inc.ഀ
r'ഀ
JOBഀ
SHEET NO.ഀ
OFഀ
CALCULATED BY DATEഀ
CHECKED BY DATEഀ
SCALEഀ
ഀ
Cഀ
- rഀ
A....ഀ
ഀ
f jഀ
vഀ
rc t. iഀ
~ഀ
l 1. 6 44 a M iഀ
Y ~ഀ
- 1ഀ
ഀ
tഀ
aഀ
J n ny o~ഀ
tഀ
✓ rLഀ
_ , .ഀ
ഀ
ഀ
ഀ
I ~ഀ
`7 C 2ഀ
-71ഀ
..Yഀ
.ഀ
I eഀ
aഀ
ഀ
r^O _ .ഀ
.ഀ
ഀ
(tom jഀ
aഀ
ഀ
ഀ
1ഀ
PRODUCT 204-1 (Sing a Sheets) 2051 (Padded)ഀ
Monroe & Newellഀ
Engineers, Inc.ഀ
PRODUCT 204-1 (Single Sheets) 2051 (Padded)ഀ
JOB iiഀ
SHEET NO.ഀ
OFഀ
DATEഀ
CALCULATED BYഀ
CHECKED BYഀ
DATEഀ
Monroe & Newellഀ
Engineers, Inc.ഀ
SHEET NO.ഀ
CALCULATED BYഀ
OFഀ
DATEഀ
CHECKED BY DATEഀ
SCALEഀ
ഀ
ഀ
ഀ
ഀ
. : .ഀ
/7.. tഀ
Y.. -ഀ
. . .ഀ
.ഀ
ഀ
ഀ
~ Jഀ
lഀ
.ഀ
ഀ
ഀ
ഀ
ഀ
(ഀ
ഀ
pഀ
ഀ
`ഀ
Witഀ
J}ഀ
fഀ
,.AA ]ഀ
Yr'ഀ
I E Iഀ
3 u z? `ഀ
ഀ
ഀ
ഀ
ഀ
a =ഀ
ഀ
-ഀ
- ^.--_-_--.mഀ
- .ഀ
.ഀ
....................:_.._........._......._..i..............>.ഀ
itഀ
ഀ
ഀ
ഀ
ഀ
ഀ
ഀ
ഀ
tഀ
Iഀ
ഀ
ഀ
-ഀ
ഀ
ഀ
fഀ
Zഀ
ഀ
?ഀ
ഀ
ഀ
ഀ
_G C. :~.i~.i......,._ F~7~._.ഀ
PRODUCT 204-1 Single Sheets) 2059 (Padded)ഀ
jq Monroe & Newellഀ
Engineers, Inc.ഀ
PRODUCT 204-1 (Single Sheets) 205-1 (Padded)ഀ
JOBഀ
SHEET NO.ഀ
CALCULATED BYഀ
CHECKED BYഀ
OFഀ
DATEഀ
DATEഀ
MASONRY Concrete Masonry Design Systemഀ
National Concrete Masonry Associationഀ
Prjct: VFD - SPA Name: Arthur Ashworth, PEഀ
Topic: Masonry Wall Bending j Date: 04-03-06ഀ
Page: Chkd:ഀ
Design of a Reinforced Masonry Wall with Cut-of-Plane Loadsഀ
Using the 1999 MSJC ASD Design Codeഀ
Material and Construction Dataഀ
8 in. CMU, Partial grout, running bondഀ
Wall Weight = 48.4 psf (From Tables)ഀ
Type S mortar Masonry cement / Air-entrained PCL Mortar, Coarse Groutഀ
CMU Concrete Density= 115 pcfഀ
Unit Compressive Strength = 1900 psiഀ
f'm = 1500 psi (From Tables)ഀ
Em = 900f'm = 1350000 psiഀ
Wall Design Detailsഀ
TI Ilc'r ,ess = 7. oGS 11 I.ഀ
Height = 156 in. (Simply Supported Wail, Effective height = H)ഀ
x = 3.813 in.ഀ
#5 Bars, Grade 60ഀ
Reinforcement Spacing = 24 in. On-Centerഀ
Wall Support: Simply Supported Wallഀ
Specified Load Componentsഀ
Load P (lb) e (in)ഀ
W1(psf)ഀ
W2 (psf)ഀ
L (in)ഀ
h1 (in)ഀ
h2 (in)ഀ
Dead 0 0ഀ
0ഀ
0ഀ
0ഀ
0ഀ
156ഀ
Live 0 0ഀ
0ഀ
0ഀ
0ഀ
0ഀ
156ഀ
Soil 0 0ഀ
0ഀ
0ഀ
0ഀ
0ഀ
156ഀ
Fluid 0 0ഀ
0ഀ
0ഀ
0ഀ
0ഀ
156ഀ
Wind 0 0ഀ
0ഀ
0ഀ
0ഀ
0ഀ
156ഀ
Seismic 0 0ഀ
31.48ഀ
31.48ഀ
0ഀ
0ഀ
156ഀ
Roof 0 0ഀ
0ഀ
0ഀ
0ഀ
0ഀ
156ഀ
Rain 0 0ഀ
0ഀ
0ഀ
0ഀ
0ഀ
156ഀ
Snow 0 0ഀ
0ഀ
0ഀ
0ഀ
0ഀ
156ഀ
Controlling Load Casesഀ
MASONRY Concrete Masonry Design Systemഀ
National Concrete Masonry Associationഀ
Prjct: VFD - SPA i Name: Arthur Ashworth, PEഀ
Topic: Masonry Wall Bending Date: 04-03-06ഀ
j Page: Chkd:ഀ
Section Forces with Controlling Flexure and Axial Load--0.9D + Eഀ
x/H = 0.530 from bottom of wallഀ
V = -12.2772 lb/ftഀ
ML = 7951.4514 lb-in,/ftഀ
P = 266.152 lb/ft at en = 0 inഀ
MT = ML + Pen = 7951.4514 lb-in/ftഀ
Moment Capacity = 16748.7 lb-in/ft (1395.725 lb-ft/ft) at this axial loadഀ
Shear Capacity= 1324.5805 lb/ftഀ
The wall is adequate for these critical section forces.ഀ
Section Forces with Controlling Shearing Force--D + L + L- + S + R + Eഀ
x/H = 0.000 from bottom of wallഀ
V = 204.62 lb/ftഀ
ML = 0 lb-in./ftഀ
P=629.2 lb/ft at en=0inഀ
MT = ML + Pen = 0 lb-in/ftഀ
Moment Capacity = 17207.105 lb-in/ft at this axial loadഀ
Shear Capacity= 1324.5805 lb/ftഀ
The wall is adequate for these critical .section forces.ഀ
These were found to be load cases that controlled the design.ഀ
The flexural, shear and axial forces shown are those occuringഀ
at the critical section for the case controlled by flexure andഀ
at the critical section for the case controlled by shear.ഀ
The following design calculations are for the section with controlling bending momentഀ
Section Design Forces Usedഀ
V = -12.2772 Ib/ft (Computed from Loads)ഀ
ML = 7951.4514 lb-in./ft (Computed from Loads)ഀ
P = 266.152 lb/ft at e = 0 in (Computed from Loads)ഀ
;ഀ
Computed Design Valuesഀ
Note: 1/3 stress increase was usedഀ
Effective Width = 24 in.ഀ
Wah IM(Ith - A 4I'Q in nn nffnntkiaഀ
MASONRY Concrete Masonry Design Systemഀ
National Concrete Masonry Associationഀ
Prjct: VFD - SPA Name: Arthur Ashworth, PEഀ
Topic: Masonry Wall Bending ! Date: 04-03-06ഀ
Page: Chkd:ഀ
Allowable Shearing Force = 1324.58 lb/ftഀ
The wall is adequate in shearഀ
Required As = 0.1244 in2 each reinforced cell (0.06218 in2/ft) OKഀ
d = 3.813 in.ഀ
n = 21.48ഀ
kbalanced = 0.3092ഀ
ibalanced = 0.8969ഀ
k = 0.2263ഀ
j = 0.9246ഀ
rmax kCompression) = 41348.9 Ibs (20674.5 ibs/ft) OKഀ
P,~ (Tension) = 9920 Ibs (4960 Ibs/ft) OKഀ
I -11ഀ
The wall has adequate capacity.ഀ
Monroe & Newellഀ
Engineers, Inc.ഀ
rഀ
I-,ഀ
JOB 1lഀ
SHEET NO.ഀ
OF 5` L: 3ഀ
CALCULATED BY DATEഀ
CHECKED BY DATEഀ
SCALEഀ
_ഀ
iഀ
L-4 - ~Z,L1i'ഀ
I.ഀ
ഀ
G Pഀ
iഀ
55 "7 T ; jഀ
ഀ
.ഀ
ഀ
ഀ
ഀ
.ഀ
.ഀ
; .ഀ
tഀ
iഀ
r wഀ
Iഀ
c C 1 ~ ' f r"~ t Fഀ
k,s4. ISഀ
ഀ
jഀ
ഀ
nഀ
°ഀ
Q 1 ( Jഀ
4 . .ഀ
Lഀ
nഀ
1ഀ
_ഀ
,ഀ
ഀ
ഀ
ഀ
ഀ
aഀ
1ഀ
_ i .._i...ഀ
ഀ
.ഀ
ഀ
ChLഀ
_ഀ
Q~.......ഀ
ഀ
ഀ
1ഀ
ഀ
'ഀ
ഀ
-ഀ
1ഀ
.ഀ
.ഀ
ഀ
\0ഀ
AVഀ
€ C i €ഀ
ഀ
ഀ
tഀ
. .ഀ
ഀ
v .ഀ
ഀ
ഀ
ഀ
~ഀ
ഀ
~ rഀ
~ഀ
i Jഀ
ഀ
t~,cഀ
.ഀ
~ഀ
Tഀ
EA -r,ഀ
ഀ
.ഀ
.ഀ
Uഀ
iഀ
.ഀ
r~......ഀ
.ഀ
.ഀ
.ഀ
.ഀ
r~......ഀ
ഀ
.ഀ
ഀ
Jഀ
PRODUCT 204-1 (Single Sheels) 205-1 (Padded)ഀ
A Monroe & Newellഀ
Engineers, Inc.ഀ
PRODUCT 204-1 (Single Sheets) 205-1(PZdded)ഀ
If Cഀ
JOBഀ
SHEET NO.ഀ
CALCULATED BYഀ
CHECKED BYഀ
OF S;7,ഀ
DATEഀ
DATEഀ
4 • , TtNOഀ
O VATIO ER,FY)ഀ
4 5 14 .9ഀ
1 15ഀ
G 0 .1 s OPEt'1 -ഀ
_ W8 G eഀ
G,OX30 A - za B~ M(~ഀ
L/aNDI-ഀ
W12 _ _ഀ
ETഀ
(8116'-6 I0" X ._V, tOXL,ഀ
X2ഀ
STRINOER z I Y~ N MN UP _ -ഀ
COL-Uഀ
V, 2. . V4,DAIഀ
:''.I~i•ഀ
C 2~°v Wit' ..I,•'I;ഀ
V40 AIoഀ
_3 I/2") - - _ ,N,~ laഀ
( - Iഀ
13,'5`1 .,his- 81b2'ഀ
HSS 5X3X1/-4 4 t e.2a, TOഀ
P OF 4ഀ
~c•'ഀ
N RETEഀ
GOLUMN UP W1'4 TS 3X / M THIGH GOഀ
-i J I , .tt HANG gLAB E-_-'ഀ
_ : ?ell / :10 W,2X14 f'~jl 22 GA`O ►TEഀ
GpMPOS GICINOഀ
Ilia V 3ഀ
►-►SS 1/2 7E, t.,tETAI- pEഀ
,A q.,:'1 • • • aഀ
N UPഀ
i:::: c• GOLUMഀ
(8151..;, UPഀ
~.C~ _ F:::.::: X{axe?'•. MCP T? 3'-0 ' GOt-UI INഀ
HSS 5(3X1/4 , py •i 1.3_ .a~-- GOLU -ഀ
- 4ഀ
COLUMN UP W5 j~t~s}.:.: 18. y I t~rnJR FR~~ W l tom`ഀ
pT 1y~1 it- 1 O~ഀ
W q (22f 1~ 1ഀ
0 V4 (t4 (3ഀ
Gഀ
P:>1 ) TY IGA►- ~r S 4X4(1/2ഀ
Gpt_UMN UPഀ
Wtp~c►2 (818i' 12' HSഀ
►4ഀ
O V2ഀ
~p GA5T Iഀ
1 PLACEഀ
GONCR I toX~2 5 4X`4XP I _ -ഀ
STAIRSa ~v UMN U4 - tya ~,alഀ
REe SI La' " X53 Wlഀ
,g )CIO /0\3ഀ
ell,ഀ
5 Fch °(L2 q,a?,l ~L W12(I4ഀ
X12ഀ
WIO s W12~ -ഀ
S. Q 5 ~ ,r Tഀ
U ~ -ഀ
~ . c.~2 I r1 • _ഀ
; 1 1;ti~ 1 - SEC 11{r fv,'L'S t2 XIഀ
- - - r t tn110X p3 3_ഀ
-►4 Xf1 H 5 N -ഀ
- F 13 GOLUMഀ
yIlOX12 HSS 6(3X1/ഀ
- = S ~ N UPഀ
i 1 _ (I pLU WXj4ഀ
JA-ഀ
ഀ
R k 14A3 1a ' Gpt-UrtN Aj,lly UF' Iq Y16X~ 4 Iഀ
_ X 1ഀ
4 ( H U N W x►4 5 (3X1/s4 V4 A3 ~ ~ , f _ _ Isഀ
R W~ -4~il~w H~ ~~:7_~- - 1 I,~~X►O r bkഀ
• 1 ¢ O OPEN-.~------"ഀ
_j 1- 0ഀ
Mt3t UP - w~ - , JW-0, THkG4c rഀ
Q.6 OF TE 51-p6 1 - E ! ca 1~ഀ
- , 1 G, pNG ~1ഀ
Fp C.ഀ
'30 1 0 !3 r _ഀ
1 1 140'ഀ
1 _ഀ
- --Q '-4 ' O r - 11 Y~ഀ
~ i-1 - - IE5 1 aഀ
V ETE c~ഀ
Z 1ഀ
P eFT1 C, 1R01I r._=ഀ
~ `J 1 ~ ?a ,---~~-i I 1 1 ~ I \ TO, I ~ 1-~ vl ~ ~ഀ
Monroe & Newell Engineers, Inc. Title : Vail's Front Door - Spaഀ
1701 Wynkoop Street, Suite 200 Dsgnrl Arthur Ashworth, PEഀ
Denver, CO 80202 Description : Lodge Expansionഀ
303.623.4927 Scope:ഀ
Fax: 303.623.6602ഀ
Job # 5500.02ഀ
Date: 8:19AM, 3 APR 06ഀ
Rev: 580001 Page 1ഀ
User: KW-0606238, Ver5.8.0, 1-Dec-2003 Composite Steel Beamഀ
(c)1983.2003 ENERCALC Engineering Software 5500 acw Revised Calcsഀ
Description Floor Beam - FB15 - REVISEDഀ
Design Inputഀ
Code Ref: AISC 9th ASD 1997 UBC, 2003 IBC 2003 NFPA 5000 sഀ
`ഀ
Section Name W1-4X26 Fy 50.00 ksiഀ
Beam Span 10.000 ftഀ
f'c 3,500.00 psiഀ
Beam Spacing 15.000 ftഀ
Concrete Density 145.00 pcfഀ
Slab Thickness 4.500 inഀ
Stud Diameter 0.750 inഀ
Deck Rib Height 1.500 inഀ
Stud Height 3.000 inഀ
Rib Spacing 6.000 inഀ
Beam Weight Added Internallyഀ
Rib Width 1.750 inഀ
Using Partial Composite Actionഀ
Rib Orientation Parallelഀ
Elastic Modulus 29,000.00 ksiഀ
Beam Location Slab Both Sidesഀ
(applied before 75% curing)ഀ
Dead Loadsഀ
Full Span Uniform Loads...ഀ
Point Loads...ഀ
#1 0.525 k/ftഀ
#1 1.700 k 6.000ftഀ
# 2 k/ftഀ
# 2 1.640 k 6.000ftഀ
Live Loads ( applied after 75% curing)ഀ
Grill Span Uniform Loads... -ഀ
- `Pei- Loads...ഀ
#1 0.750 k/ftഀ
# 1 2.250 k 6.000 ftഀ
# 2 k/ftഀ
#2 2.250 k 6.000 ftഀ
Lഀ
fFFഀ
Summaryഀ
OK Shored & Unshoredഀ
Using: W14X26, Span = 10.00ft, Slab Thickness =ഀ
4.500in, Deckഀ
Rib Ht= 1.50in, Rib Spac= 6.00in, Rib Width= 1.75in w/ Slab Eഀ
Stress Checks for Shored & Unshored Cases...ഀ
@ Bottom of Beam Actual =ഀ
9,315.7 psiഀ
Allowable = 33,333.0 psi OKഀ
Unshored DL Stress Actual =ഀ
4,983.6 psiഀ
Allowable = 33,333.0 psi OKഀ
Actual Shear Stress Actual =ഀ
3,160.3 psiഀ
Allowable = 20,000.0 psi OKഀ
Unshored Stress Check....ഀ
(Mdl/Ss + MII/Strans) Actual = 10,340.9 psi Allowable = 45,000.0 psi OKഀ
MII / Strans(top) Actual = 220.3 psi Allowable = 1,575.0 psi OKഀ
Alternate Unshored Stress Check : (Mdl + MII) / Ss 11,728.5 38,000.0 psiഀ
Shored Concrete Stress Check (Mdl + M11) / (Strans:tcp ' n) 383.0 1,575.0 psiഀ
Shear Studs & Shear Transferഀ
Actual # Studs 4 per 1/2 beam spanഀ
Stud Capacity 8.75 k V'h : min 38.35 kഀ
Total req'd 1/2 Span 5studs Vh @ 100% 153.40k Vh : Used 35.00 kഀ
Zone 1 fromഀ
0.000 ftഀ
toഀ
2.000 ft , Useഀ
1 studsഀ
Zone 2 fromഀ
2.000 ftഀ
toഀ
4.000 ft , Useഀ
2 studsഀ
Zone 3 fromഀ
4.000 ftഀ
toഀ
6.000 It , Useഀ
1 studsഀ
Zone 4 fromഀ
6.000 ftഀ
toഀ
7.333 It , Useഀ
1 studsഀ
Zone 5 fromഀ
7.333 ftഀ
toഀ
8.667 it , Useഀ
1 studsഀ
Zone 6 fromഀ
8.667 ftഀ
toഀ
10.000 ft , Useഀ
2 studsഀ
Monroe & Newell Engineers, Inc. Title : Vail's Front Door - Spa Job # 5500.02ഀ
IT) 1701 Wynkoop Street, Suite 200 Dsgnr: Arthur Ashworth, PE Date: 8:19AM, 3 APR 06ഀ
Description : I odge Expansionഀ
Denver, CO 80202ഀ
303.623.4927 Scope:ഀ
Fax: 303.623.6602ഀ
ReV., 580001 Page 2 01ഀ
User: KW-0606238, Ver5.8.0, 1-Dec-2003 Composite Steel Beam 5500. ecw:Revised Calcsഀ
(-)1983-2003 ENERCALC Engineering Softwareഀ
Description Floor Beam - FB15 - REVISEDഀ
Deflectionsഀ
ഀ
. _ഀ
,ഀ
..v rഀ
I : Transformed 699.88 in4ഀ
sഀ
.ഀ
.ഀ
_ഀ
vഀ
Effective 462.2Ein4ഀ
Shoredഀ
Unshoredഀ
Before 75 % Curing 0.018 inഀ
(after shores removed) 0.033 inഀ
Construction Loads Only 0.000 inഀ
0.000 inഀ
After 75% Curing 0.024 inഀ
0.024 inഀ
Total Uncured Deflection 0.018 inഀ
L/6768.6ഀ
0.033 in L / 3587.2ഀ
Composite Deflection 0.042 inഀ
L/2874.1ഀ
0.057 in L / 2088.3ഀ
Reactionsഀ
maഀ
raഀ
Load Combinations... @ Leftഀ
@ Riqhtഀ
Dead + Constuction 4.09 kഀ
4.76 kഀ
Composite 5.55 kഀ
6.45 kഀ
Max DL + LL 9.64kഀ
11.21 kഀ
Analysis Valuesഀ
Maximum ivIlomentsഀ
a=ffective Flange Width...ഀ
Dead Load Alone 14.63 k-ft Fbഀ
: Allowഀ
33.00 psi Based on Beam Span 2.500 ftഀ
Dead + Const 14.63 k-ft n :ഀ
Strengthഀ
8.60 Based on Beam Spacing 15.000 ftഀ
Live Load Only 19.80 k-ft n :ഀ
Deflectionഀ
8.51ഀ
Dead + Live 34.43 k-ftഀ
Effective Width 2.500 ftഀ
Support Shearsഀ
Shear @ Leftഀ
9.64 kഀ
Shear @:Rightഀ
11.21 kഀ
Section Propertiesഀ
Section Nameഀ
W14X26ഀ
Depthഀ
13.910 inഀ
Ixx : Steel Sectionഀ
245.00 in4ഀ
Widthഀ
5.025 inഀ
I transformedഀ
697.88 in4ഀ
Flange Thickഀ
0.420 inഀ
Strans : topഀ
125.42 in3ഀ
Web Thickഀ
0.255 inഀ
Strans : botഀ
54.33 in3ഀ
Areaഀ
7.690 in2ഀ
Strans : eff @ botഀ
44.35 in3ഀ
Weightഀ
26.121 #/ftഀ
n'Strans : Ef @ topഀ
673.5 in3ഀ
I-steelഀ
245.00 in4ഀ
X-X Axis from Botഀ
12.85 inഀ
S steel : topഀ
35.23 in3ഀ
Vh @ 100%ഀ
153.40 kഀ
S steel : bottomഀ
35.23 in3ഀ
1ഀ
1ഀ
I II 1 ~tiഀ
ഀ
1_-.ഀ
II_ഀ
1 0 1 ~ Xഀ
1 t vഀ
11 / II aഀ
Iഀ
_ wഀ
1 0 ~ )ഀ
20~'r Fr ' ~ .Ip^^ഀ
I - 1ഀ
,ih,W. V' Iഀ
yooഀ
X10 t ' s 1ഀ
X+0 P (1ഀ
vieഀ
8X10 ca O Oഀ
+ X a k. c 1. sഀ
ഀ
IVFഀ
1 6ഀ
' rcr; 2fg~ `'..i 'ഀ
Cഀ
wt3~--' ~ bit a1 `y> , yilഀ
c,W{ sഀ
1 10Xഀ
- I...ഀ
1 ~ 1ഀ
1 iiN Oഀ
y.112•X1Aഀ
+ W8?oQ ^3 , Uഀ
_ 5 1ഀ
1 1~ tli~p~... ~ X v+ഀ
I _ U - lA ``,,`t U+ 1 1ഀ
O~ 1'Q 1^11_ -ഀ
1ഀ
1ഀ
1 ~ഀ
P ' Oഀ
1 +ഀ
• 1ഀ
O Iഀ
f 1ഀ
1ഀ
c~ഀ
rxഀ
Monroe & Newell Engineers, inc. Title : Vail's Front Door - Spa Job # 5500.02ഀ
1701 Wynkoop Street, Suite 200 Dsgnr: Arthur Ashworth, PE Date: 8:33AM, 3 APR 06ഀ
Denver, CO 80202 Description : Lodge Expansionഀ
5 i°..ഀ
303.623.4927 Scopeഀ
Fax: 303.623.6602ഀ
Rev: 580006 6ഀ
User: KW-0606238,Ver 5.8.0, 1-Dec-2003 Steel Beam Design Page 1ഀ
(0)1983-2003 ENERCALC Enqineerinq Software 5500.ecw:Revised Cadsഀ
Description Roof Beam - RB40ഀ
General Information Code Ref. AISC 9th ASD, 1997 UBC, 2003 IBC, 2003 NFPA 5000ഀ
Steel Section W8X10 Fy 50.00ksiഀ
Pinned-Pinned Load Duration Factor 1.00ഀ
Center Span 3.50 ft Bm Wt. Added to Loads Elastic Modulus 29,000.0 ksiഀ
Left Cant. 0.00 ft LL & ST Act Togetherഀ
Right Cant 0.00 ftഀ
Lu : Unbraced Length 3.50 ftഀ
Distributed Loads Note! Short Term ads Are WIND Loads.ഀ
#1 #2 #3 #4 #5 #6#7ഀ
DL 0.360 k/ftഀ
LL 1.200 k/ftഀ
ST k/ftഀ
Start Location ftഀ
End Location ftഀ
Summaryഀ
Beam OKഀ
Static Load Case Governs Stressഀ
Using: W8X10 section, Span= 3.50ft, Fy = 50.Oksiഀ
End Fixity = Pinned-Pinned, Lu = 3.50ft, LDF = 1.000ഀ
Actualഀ
Ak\/~,ableഀ
Moment 2.404 k-ftഀ
19.525 k-ftഀ
Max. Deflectionഀ
-0.006 inഀ
fb : Bending Stress 3.694 ksiഀ
30.000 ksiഀ
Length/DL DOഀ
30,025.4: 1ഀ
fb / Fb 0.123 : 1ഀ
Length/(DL+LL Defl)ഀ
7,076.8: 1ഀ
Shear 2.748 kഀ
26.826 kഀ
fv : Shear Stress 2.048 ksiഀ
20.000 ksiഀ
fv / Fv 0.102 : 1ഀ
Force & Stress Summaryഀ
<<--These columns are Dead + Live Load placed as noted »ഀ
DL LL LL+ST LL LL+STഀ
Maximum Only @ Center @ Center @ Cants @ Cantsഀ
Max. M + 2.40 k-ft 0.57 2.40 k-ftഀ
Max. M -ഀ
k-ftഀ
Max. M @ Leftഀ
k-ftഀ
Max. M @ Rightഀ
k-ftഀ
Shear @ Left 2.75 kഀ
0.65ഀ
2.75ഀ
kഀ
Shear @ Right 2.75 kഀ
0.65ഀ
2.75ഀ
kഀ
Center Defl. -0.006 inഀ
-C.CC1ഀ
-0.006ഀ
-0.006ഀ
0.000ഀ
0.000 inഀ
Left Cant DO 0.000inഀ
0.000ഀ
0.000ഀ
0.000ഀ
0.000ഀ
0.000 inഀ
Right Cant DO 0.000 inഀ
0.000ഀ
0.000ഀ
0.000ഀ
0.000ഀ
0.000 inഀ
...Query Defl @ 0.000 ftഀ
0.000ഀ
0.000ഀ
0.000ഀ
0.000ഀ
0.000 inഀ
Reaction @ Left 2.75ഀ
0.65ഀ
2.75ഀ
2.75ഀ
kഀ
Reaction @ Rt 2.75ഀ
0.65ഀ
2.75ഀ
2.75ഀ
kഀ
Fa calc'd per Eq. E2-1, K'L/r < Ccഀ
I Beam, Major Axis, L/rT < (102,000' Cb / Fy)ഀ
^.5, Fb = 0.6ഀ
Fy (F3)ഀ
Monroe & Newell Engineers, Inc. Title : Vail's Front Door - Spa Job # 5500.02ഀ
1701 Wynkoop Street, Suite 200 Dsgnr: Arthur Ashworth, PE Date: 8:33AM, 3 APR 06ഀ
Description :Lodge Expansionഀ
Deriver, CO 80202ഀ
303.623.4927 Scope:ഀ
Fax: 303.623.6602ഀ
Rev: 580006 Page 2 Aഀ
User: KW-0606238, Ver 5.8.0, 1-Dec-2003 Steel Beam Designഀ
(c)1983-2003 ENERCALC Enaineerina Software 5500.ecw:Revised Calcsഀ
Description Roof Beam - RB40ഀ
Section Propertiesഀ
W8X10ഀ
Depthഀ
7.890 inഀ
'Weightഀ
10.05 #/ftഀ
Web Thickഀ
0.170 inഀ
Ixxഀ
30.800 in4ഀ
Widthഀ
3.940 inഀ
lyyഀ
2.090 in4ഀ
Flange Thickഀ
0.205 inഀ
Sxxഀ
7.810 in3ഀ
Areaഀ
2.96 in2ഀ
Syyഀ
1.060 in3ഀ
Rtഀ
0.990 inഀ
R-xxഀ
3.220 inഀ
Values for LRFD Design.... R-yy 0.841 inഀ
1 0.040 in4 Zx 8.870 in3ഀ
Cw 30.90 in6 Zy 1.660 in3ഀ
K 0.505 inഀ
Sketch & Diagramഀ
2.40ഀ
1.92ഀ
- LG`8 iഀ
1 i~177i7i T7777T7T7iiTT1Ti 17 77777777 777T77Ti1i, 1.~a'klt 144ഀ
I .al 0.72ഀ
0.48ഀ
021:ഀ
0 O. i1 x.59 1.04 1.3? 1.74 21.09 2.45 21.20 3:15 3.5ഀ
i ~ E'i+.`It+1111+J t,'I411YBItiSഀ
Location (ft iഀ
O 3.6R D r tyഀ
Vmax = 2.4k-ft 1.33ഀ
Dmax = -0.006in 1.37ഀ
64ഀ
0.0ഀ
Rmax = 2.748k Rmax = 2.748kഀ
p n8ഀ
Vmax ®left = 2.748k Vmax B rt = 2.7 43ഀ
1 377ഀ
Vi -2.04ഀ
•2.73ഀ
B+,amഀ
-0.00ഀ
•0.00ഀ
-O.UOഀ
O.UOഀ
C -0.00ഀ
-0.C1ഀ
m -U.U1ഀ
uഀ
[1ef le+.~ഀ
Location fttlഀ
Location rft)ഀ
Monroe & Newell Engineers, Inc. Title : Vail's Front Door - Spaഀ
1701 Wynkoop Street, Suite 200 Dsgnr: Arthur Ashworth, PEഀ
Denver, CO $0202 Description : Lodge Expansionഀ
303.623.4927 Scope:ഀ
Fax: 303,623.6602ഀ
iഀ
Job # 5500.02ഀ
Date: 8:43AM, 3 APR 06ഀ
Rev: 580007ഀ
User: KW-0606238, Ver5.8.0, 1-Cec-2003 Multi-Span Steel Beam Page 1ഀ
(c)1983-2003 ENERCALC Engineering Softwareഀ
5500.ecv:Revised Calcs:ഀ
Description Roof Beam - RB41ഀ
General Informationഀ
Code Ref: AISC 9th ASD, 1997 UBC, 2003 IBC, 2003 NFPA 5000ഀ
Fy - Yield Stress 50.00 ksiഀ
Load Duration Factor 1.00ഀ
Spans Consideredഀ
Continuous Over Supportsഀ
Span Informationഀ
Descriptionഀ
Left Spanഀ
Right Spanഀ
Cantഀ
Spanഀ
ftഀ
4.00ഀ
4.00ഀ
6.50ഀ
Steel Sectionഀ
WSX15ഀ
waxesഀ
wsxleഀ
End Fixityഀ
Pin-Pinഀ
Pin-Pinഀ
Pin-Pinഀ
Unbraced Lengthഀ
ftഀ
4.00ഀ
4.00ഀ
4.00ഀ
Loadsഀ
E;ഀ
-ഀ
Live Load Used This Span ?ഀ
Yesഀ
Yesഀ
Yesഀ
Dead Loadഀ
k/ftഀ
0.060ഀ
0.060ഀ
0.060ഀ
Live Loadഀ
kiltഀ
0.200ഀ
0.200ഀ
0.200ഀ
F Resultsഀ
Mmax @ Cntrഀ
k-ttഀ
0.39ഀ
0.00ഀ
0ഀ
92ഀ
@ X =ഀ
ftഀ
1.73ഀ
0.00ഀ
.ഀ
3.86ഀ
Max @ Left Endഀ
k-ftiഀ
U0ഀ
-0.27ഀ
-i.00ഀ
Max @ Right Endഀ
k-ftiഀ
-0.27ഀ
-1.00ഀ
0.00ഀ
fb : Actualഀ
psi;ഀ
398.8ഀ
1,010.2ഀ
1,010.2ഀ
Fb : Allowableഀ
psiഀ
30,000.0ഀ
30,000.0ഀ
30,000.0ഀ
fv : Actualഀ
Sending OKഀ
Bending OKഀ
Bending OKഀ
psiഀ
295.8ഀ
353.0ഀ
502.4ഀ
Fv:Allowableഀ
psi,ഀ
20,000.0ഀ
20,000.0ഀ
20,000.0ഀ
Reactions & Deflectionsഀ
611ഀ
Shear @ Left kഀ
0.45ഀ
0.34-ഀ
~W 1.00ഀ
Shear @ Right kഀ
0.59ഀ
0.70ഀ
0.69ഀ
Reactions...ഀ
DL @ Left kഀ
0.10ഀ
0.21ഀ
0.39ഀ
LL @ Left kഀ
0.35ഀ
0.71ഀ
1.31ഀ
Total @ Left kഀ
0.45ഀ
0.93ഀ
1.70ഀ
DL @ Right kഀ
0.21ഀ
0.39ഀ
0.16ഀ
LL @ Right kഀ
0.7.1ഀ
1.31ഀ
0.53ഀ
Total @ Right kഀ
0.93ഀ
1.70ഀ
0.69ഀ
Max. Deflection inഀ
-0.001ഀ
0.001ഀ
-0.004ഀ
@ X = ftഀ
1.89ഀ
2.64ഀ
3.55ഀ
Span/Deflection Ratio Iഀ
64,621.8ഀ
86,859.8ഀ
18,200.5ഀ
Query Valuesഀ
Locationഀ
ft'ഀ
0.00ഀ
0.00ഀ
0.00ഀ
0.00ഀ
0.00ഀ
0.00ഀ
0.00ഀ
0.00ഀ
Shearഀ
kഀ
0.45ഀ
0.34ഀ
1.00ഀ
0.00ഀ
0.00ഀ
0.00ഀ
0.00ഀ
0.00ഀ
Momentഀ
k-ft ;ഀ
0.00ഀ
-0.27ഀ
-1.00ഀ
0.00ഀ
0.00ഀ
0.00ഀ
0.00ഀ
0ഀ
00ഀ
Max. Deflectionഀ
in jഀ
0.0000ഀ
0.0000ഀ
0.0000ഀ
0.0000ഀ
0.0000ഀ
0.0000ഀ
0.0000ഀ
.ഀ
0.0000ഀ
Monroe & Newellഀ
Engineers, Inc.ഀ
L.ഀ
PRODUCT 204-1 (Single Sheets) 205-1 (Padded)ഀ
JOB Ff'ഀ
SHEET NO.ഀ
CALCULATED BYഀ
CHECKED BY_ഀ
OFഀ
DATEഀ
DATEഀ
Monroe & Newellഀ
Engineers, Inc.ഀ
Aഀ
PRODUCT 204-1 (Single Sheets) 205-1 (Padded)ഀ
,Jഀ
JOBഀ
SHEET NOഀ
O Fഀ
CALCULATED BY 4>~ഀ
DATEഀ
CHECKED BYഀ
DATEഀ
Monroe & Newellഀ
Engineers, Inc.ഀ
SCALEഀ
ഀ
'i ".7 gഀ
.ഀ
ഀ
ഀ
as .ഀ
ഀ
d .ഀ
i.ഀ
.ഀ
ഀ
Ink/:ഀ
ഀ
rഀ
ഀ
ഀ
iഀ
ഀ
ഀ
ഀ
e _ഀ
( fഀ
ഀ
_rr. . .ഀ
.ഀ
.ഀ
C`ഀ
ഀ
: E..ഀ
2ഀ
.ഀ
.ഀ
_ഀ
iഀ
.ഀ
. _ഀ
dഀ
1 .ഀ
....i ..,-k`~..:.m'. t",.^;;,~,:ഀ
ഀ
-ഀ
ഀ
Iഀ
JOBഀ
SHEETഀ
OF 2-! 1'ഀ
CALCULATED BY- DATEഀ
CHECKED BY DATEഀ
Column Worksheetഀ
For Axial Compression and Bendingഀ
Job Name: Vail's Front Door - Spaഀ
M&N # 5500.02ഀ
Column Truss Columnsഀ
HSSഀ
[4x4x.25ഀ
Areaഀ
3.37ഀ
in^2ഀ
Ixഀ
7.8ഀ
in^4ഀ
lyഀ
7.8ഀ
in^4ഀ
Sxഀ
3.9ഀ
in^3ഀ
Syഀ
3.9ഀ
in^3ഀ
Axial Loadഀ
8 kipഀ
x-x Loadഀ
8ഀ
kipഀ
y-y Loadഀ
0.00ഀ
kipഀ
x-x Lenഀ
7.00ഀ
ftഀ
y-y Lenഀ
7.00ഀ
ftഀ
Cmxഀ
-1.00ഀ
Cmy,ഀ
1.00ഀ
Kxlx/rxഀ
55.26ഀ
Kyly/ryഀ
55.26ഀ
Faxഀ
21.97ഀ
ksiഀ
faxഀ
2.37ഀ
ksiഀ
Fbxഀ
30.36ഀ
ksiഀ
fbxഀ
4.10ഀ
ksiഀ
Fexഀ
48.90ഀ
ksiഀ
fa/Faxഀ
0.11ഀ
Use H1-3ഀ
H1-1ഀ
HI-2ഀ
H1-3ഀ
0.25 < 1.0ഀ
0.22 < 1.0ഀ
0.24 < 1.0ഀ
Column Size OKഀ
Fy 4.6 ksiഀ
rx 1.52 inഀ
ry 1.52 inഀ
x-x e 0.00 in 2.00 in Total exഀ
y-y e 0.00 in 2.00 in Total eyഀ
x-x K 1.0 16.00 kip-in M max x-xഀ
y-y K 1.0 0.00 kip-in M max y-yഀ
Cc 111.6 'ഀ
Fay 21.97 ksiഀ
fay 2.37 ksiഀ
Fby 30.36 ksiഀ
fby 0.00 ksiഀ
Fey 48.90 ksiഀ
fa/Fay 0.11ഀ
Use H1-3ഀ
Please note that there mayഀ
be differences in maximumഀ
capacity compared to ASDഀ
9th edition. This is dueഀ
to revised section proportiesഀ
shown in HSS Connections Manualഀ
Monroe & Newellഀ
/ Engineers, Inc.ഀ
JOBഀ
SHEETഀ
OF S'~- - iഀ
CALCULATED BY ! ~'N DATEഀ
CHECKED BYഀ
DATEഀ
SCALEഀ
ഀ
ഀ
.ഀ
ഀ
.ഀ
ഀ
G vഀ
Y ~~1ഀ
ഀ
ഀ
. iഀ
i _ഀ
.ഀ
ഀ
i aഀ
ഀ
_ഀ
~'rTഀ
ഀ
ഀ
;ഀ
1ഀ
Jഀ
. . sഀ
.ഀ
.ഀ
:ഀ
.ഀ
ഀ
ഀ
ഀ
ഀ
~iഀ
4ഀ
0ഀ
Xഀ
w..ഀ
ഀ
~iഀ
~Lഀ
~ (ഀ
ഀ
. .ഀ
ഀ
~ ~ ~ Lഀ
ഀ
ഀ
rഀ
!mac'.-'ഀ
ഀ
ഀ
19ഀ
IL sഀ
.....nഀ
It iഀ
.............................i_..........ഀ
7(15ഀ
.._i.............'............. :..............5._......._.;...........1..........J .ഀ
J,~~~ ~v-ഀ
ഀ
Cryഀ
ഀ
ഀ
.ഀ
ഀ
ഀ
.ഀ
ഀ
ഀ
.ഀ
ഀ
ഀ
PRODUCT 204-1 (Single Shees) 205-1(Padded)ഀ
i i`rrL LLഀ
r Monroe oe & Newell Joeഀ
f Il-' En~cers, Inc, s~e~,-~:a,_ഀ
CALCULATEDഀ
CHECXr:D BYഀ
~ ! SCk~Eഀ
iഀ
PAGE 64ഀ
OF T"ഀ
~P.TEഀ
DATA=ഀ
iഀ
rഀ
!ഀ
ഀ
~'aoouTaas.~ (siw.as~n,~rof~i [A+~nlഀ
11ഀ
ഀ
!ഀ