HomeMy WebLinkAboutNorth Day Lot Meeting Minutes 062308Memorandum to File March 2, 2009 Planner: Warren Campbell The information contained in this file pertains to the discussion which occurred regarding the collocation of a transit center and employee housing on the North Day Lot. After several design iterations and multiple public reviews it was determined that the Town did not want to pursue anything more than skier drop-off and employee housing on the site, both of which were obligation of Vail resorts from the Arabelle project. These items are included with the approved plans for the North Day Lot simply to serve as a history for future inquiries regarding the North Day Lot. ARCHITECTURE ~~~~~ URBAN DESIGN ~ INTERIOR DESIGN PROJECT: North Day LOt NOTES BY: Brlan Lopez NEXT MEETING: ATTENDEES: Greg Hall Stan Zemler George Ruther Warren Campbell Will Hentschel Brian Lopez MEETING MINUTES DATE: June 23, 2008 PROJECT #: 17030.01 MEETING #: 3A FILE N: DISTRIBUTION: Attendees The aforementioned minutes constitute our understanding of the items discussed. If this is not an accurate written description of the intent and results of this meeting, please contact this office with comments. The minutes will stand as a record of the meeting unless corrections are received within seven (7) days after receipt. ITEM # DPCC'RIPTInN RFCDl1~ICI RII ITV 11FA nl ILIC 3A-1 Greg -overview of previous meetings discussion regarding Option 1 and Option 5. • Option 1 -Originally submitted in PEC Submittal #1 on 2.21.08 with east portion of site retained for future development. • Option 5 -Study of full transit development across entire site as directed by Vail Town Council. 3A-2 Will -explained Option 5 podium level. • This podium layout was taken from the Option 4 layout of a 120 bed EHU building and used for the pricing exercise by Swinerton including a structural feasibility study by SA Miro. 3A-3 George spoke about the Master Plan Amendment by the Vail Town Council. • Council directed the use of the entire parcel of land at the surface level for transit. This was agreed upon previous to the multiple transit study options. The exercise forward was meant to study what the best options were even if it meant not utilizing the entire site. 3A-4 Brian and Will presented the new Option 1 Alternative plan. ,, , DENVER BOULDER COLORADO sPHNGS LAS VEGAS LAKETAHOE BOULDER PHONE: 303449.8900 1805 29TH sTREET, SUITE 2054 FAX: 303.449.3886 BOULDER COLORAD080301 WWW.OZARCH.COM ARCHITECTURE ~~~~~~ URBAN DESIGN ® INTERIOR DESIGN ITEM # DESCRIPTION RESPONSIBILITY DEADLINE • This plan incorporated a shift of the hammerhead bus stop to the north similar to that of Option 5 to allow increased relief from Landmark and a potential enclosure along the southside of the transit center. • The above was accomplished by flipping the circulation cores for the building above. This allows the skier drop-off parking to shift to the northwest tucking under the berm. • Additional clarification of the existing utility locations is needed to evaluate the impact of this option along the northside. • This option increased the distance from the nearest bus to the property line from 14'-3" to 20'- 11 ". This could allow all pedestrian circulation to be under the podium above. • Stan raised a general concern of any additional cost that may come out of these options over the $19 million proposed. 3A-5 Any modifications to the stair and elevator cores for the building above will need to be approved by VRDC. 3A-6 Will presented the edge condition sketches for the various options. • Section studies were presented for Option A, A Alternate, and 5. • These sketches showed different solutions for pedestrian access and potential screening and snow retaining strategies along the southside of the transit level. Including Use by Right and Variance options. 3A-7 General studies to be addressed in near future once an Option is decided upon: • Evaluate ventilation strategies for the transit level, especially if an enclosed south wall is chosen, and the influence of this strategy as it pertains to an environmental review. • Evaluate all electrical, mechanical, BOULDER 1 BOS 29TH STREET, SURE 2054 DENVER BOULDER COLORADO SPRNGS LAS VEGAS LAKE TAHOE BOULDER COLORADO 80301 MEETING MINUTES PHONE: 303 449,8900 FAX: 303.449.3886 V/W W.OZARCH. COM ARCHITECTURE M~~~.~~ URBAN DESIGN ~ INTERIOR DESIGN ITEM # DESCRIPTION RESPONSIBILITY DEADLINE structural, civil, fire protection, and utility relocation costs associated with the option chosen. • Study % of open air/enclosure wall along south elevation of the transit level. • Additional plan studies for wall enclosure, pedestrian pathway, snow management, and landscaping along south edge. 3A-8 For TOV meeting with NDL neighbors at 1 pm OZ 06.24.08 on 06.24.08 - OZ to compose a package of at 12pm the current options and their associated pedestrian studies as reviewed in this meeting. DENVER BOULDER BOULDER 1805 29TH STREET, SURE 2054 COLORADO SPRNGS LAS VEG45 LAKE TAHOE BOULDER, COLORADO 80301 MEETING MINUTES PHONE: 303 449.8900 FAX: 303.449.3886 WWW.OZARCH.COM