Project Name: FRAMPTON LANDSCAPING DRB Number: DRB080377
Project Description:
Participants:
LANDSCAPE IMPROVEMENTS
OWNER FRAMPTON, SUSAN R.0 /O EAST W 08/21/2008
DRAWER 2770
AVON
CO 81620
APPLICANT LAND DESIGNS BY ELLISON 08/21/2008
PO BOX 2134
EAGLE
CO 81631
Project Address: 14 BEAVER DAM RD VAIL
Location:
Legal Description: Lot: 34 Block: 7 Subdivision: VAIL VILLAGE FILING 1
Parcel Number: 2101 - 071 - 1300 -1
Comments: SEE CONDITIONS
BOARD /STAFF ACTION
Motion By: Action: STAFFAPP
Second By:
Vote: Date of Approval: 09/19/2008
Conditions:
Cond: 8
(PLAN): No changes to these plans may be made without the written consent of Town of
Vail staff and /or the appropriate review committee(s).
Cond: 0
(PLAN): DRB approval does not constitute a permit for building. Please consult with
Town of Vail Building personnel prior to construction activities.
Cond: 201
(PLAN): DRB approval shall not become valid for 20 days following the date of
approval, pursuant to the Vail Town Code, Chapter 12 -3 -3: APPEALS.
Cond: 202
(PLAN): Approval of this project shall lapse and become void one (1) year following
the date of final approval, unless a building permit is issued and construction is
commenced and is diligently pursued toward completion.
Cond: CON0010324
THE APPLICANT SHALL BE HELD TO ALL CONDITIONS LISTED ON THE REVOCABLE RIGHT OF WAY
PERMIT THAT IS ASSOCIATED WITH THIS APPROVAL.
Planner: RACHEL FRIEDE DRB Fee Paid: $20.00
Development Review Coordinator
Community Development Department
75 South Frc _ _ _ --
tel :
Application for Design Review V, AUG 21 700B
Minor Exterior Alterations ��
General Information:
�'_ OF VAIL
This application is required for all proposals involving minor changes to buildings and site improvements, such as re-
roofing, painting, window additions, landscaping, fences, retaining walls, etc. Applicable Vail Town Code sections can be
reviewed on -line at www.vailgov.com under Vail Information – Town Code On -line. All projects requiring design review
must receive approval prior to submitting a building permit application. An application for Design Review cannot be
accepted until all required information is received by the Community Development Department, as outlined in the submittal
requirements. Design review approval expires one year from the date of approval, unless a building permit is issued and
construction commences.
Fee: $250 for Multi - Family /Commercial
$20 for Single Family /Duplex
Description of the Request:
a. e - A. 6�nrLA.b a.►-A
I_kS
Vpt3 L."A C .
_ Single Family I' Duplex Multi - Family r I I
Location of the Proposal: Lot: `f Block Subdivision: V I I k e_
Physical Address: 1ESe_0_Q eX Y ak' L- Co
Parcel No.: 2.1 C 1 d _�_ 1 1 b U (Contact Eagle Co. Assessor at 970 -328 -8640 for parcel no.)
Name(s) of Owner(s): t'1 ay rH 0.h I ra►- +1 ®
Mailing Address: Imo Sa ,- �'V0 � CC p 1(0 20
Phone: q 1_6 - H
Owner(s) Signature(s): L�
Name of Applicant: ► k —{=5t S
Mailing Address: 12 6 X 2�3
Phone: O (o
E -mail Address: Fax:
For Office Use Onlut ,1 i+ ,�//
Fee Paid: Check No.: By: �wnl llf� C P�✓`>
Meeting Date: DRB No.: Q J�
Planner: Project No.:
—61 i —
i
OCIVIfOIO:)'IIVA
OVOb WVCl'd3AV39 VT
9DNaGIS3d NOIdWVd=l
ro
OL
D
c
Ln
rn
—61 i —
i
D
T>
• 1 NIT
• • Zp
Ej
_ � yn .,HIW J��r,
v
Q-
•
i
ro
-r M
(U
CL
RL CL
co
0 CL
t;m Z<
CC)
x
rn
1-0
C) LL
U—
U)
ud .
CL
2
0.
Z,
a XUJ l3ed�IsdI dH Wdii =B 8002 16 tic
From:Land Designs by Ellison 970 328 6084 07131/2008 16:57 #280 P.0021002
s
' P '� UTILITY APPROVAL & VERIFICATION
This form serves to verify that the proposed improvements will not impact any existing or ,proposed utility services, and also to
verify service availability and location for new construction and should be used in conjunction with preparing your utility plan and
scheduling installations. A site plan, including grading plan, floor plan, and elevations, shall be submitted to the following utilities
for approval and verification. PLEASE ALLOW UP TO 2 WEEKS FOR APPROVAL OR COMMENTS' FROM THE UTILITY
COMPANIES. If you are unable to obtain comments within that timeframe please contact The Town of Vail.
Address: 10 L tLWM r' - 04m t- fGW Lot S-! Block - Subdivision: i/ft, i1;i0+4t_ `1LiN6 1
Wb l--' C G 1 b , 6 6 -- )
QW EST
970.468.6860(tel)
970.468.0672(fax)
Contacts: Sam Tooley
samuel.tooley a�gwest com
XCEL HIGH PRESSURE GAS
970,262,4076 (tel)
970.468.1401 (fax)
Contact: Rich Sisneros
richard.sisnerosgxcelenergy com
HOLY CROSS ENERGY
970.947.5425 (tel)
970.945.4081 (fax)
Contact: Diana Golis
dqolis@holycross.com
XCEL Energy
970.262.4038 (fax)
970.262.4024 (tei)
Contacts:
Kit Bogert
Kathry,n.Bogert@XCELENERGY.com
EAGLE RIVER WATER&
SANITATION DISTRICT
970.476.7480 (tel)
970.476.4089 (fax)
Contact: Fred Haslee
fhaslee @erwsd.org
COMCAST CABLE
970.418.8248 (tel)
970.949.9138 (fax)`
Contact Michael Johnson
michael _johnson @cable.comcast.com
Authorized Signature Comments Date
Q v�'C!T7 l.V i LL- IJ 0 "7 iE C
�Zei P -t rx, 4 t-E Fgf2- A
I t' 74f 7 (- A-r6^ - &NT
NOTES:
1. If the utility approval `& verification form has signatures from each of the utility companies; and no comments are made directly
on the form, or no action is taken within 2 weeks of the Utility's receipt of the form without explanation the Town will presume
that there are no problems and the development can proceed.
2. If a utility 'company has concerns with the proposed construction, the utility representative shall note directly on the utility
verification form that there is a- problem which needs to be resolved. The issue should then be detailed in an attached letter to the
Town of Vail. However, please keep in mind that it is the responsibility of the utility company and the applicant to resolve
identified problems:
3. These verifications' do not relieve the contractor of the responsibility to obtain a Public Way Permit from the Department of
Public Works at the Town of Vail. _Utility locations must be obtained before digging in any public right -of -way or easement
within the Town of Vail. A building permit is not a Public Way permit and must be obtained separate
4. The Developer is required and agrees to submit any revised drawings to the utilities for re- approval &. re- verification if the
submitted plans are al eredin anyway after the authorized signature date (unless otherwise specifically noted within the comment
area of this form),
Developer's Signature Date
Z d VOt00000St 'oN /OV : B ' 1S/ Lb : e aooz S L nnV (1 Nd) Z19OSSVOZG ANNOHLMMA1 1 S 1S3Mo NOMA
SILVERTHORNE HP Fax:19704681401 Huy 4 2008 6:06 P.02
* V iE TOWN UTILITY APPROVAL & VERIFICATION
This form serves to verify that the proposed improvements will not impact any existing or proposed utility services, and al to
verify service availability and location for new construction and should be used in conjunction with preparing your utility pan and
scheduling installations. A site plan, including grading plan, floor plan, and elevations, shall be submitted to the following !,utilities
for approval and verification. PLEASE ALLOW UP TO 2 WEEKS FOR APPROVAL OR COMMENTS FROM THE UTILITY
COMPANIES. If you are unable to obtain comments within that timeframe please contact The Town of Vail.
i
Address: I &- - J)V0t DAM 20V Lot �S Block _7 Subdivision: Uft (/tcf-i+e, = �1LIn1�
Authorized Signature Comments Date
UQWEST
970.468.6860(tel)
970.468.0672(fax)
Contacts: Sam Tooley q
sa u (.tool y gwest.com
XC HIGH PRESSURE GAS t ('p , � AUG 0 :4 2008
9 0.262.4076 (tel)
970.468.1401 (fax)
Contact: Rich Sisneros r(o (MPACT -yo lr Gam, (,A 4;�," Vt rd
richar . ssneros xcelener .com b2
HO CROSS ENERGY
R 97 .947.5425 (tel)
970.945.4081 (fax)
Contact: Diana Golis
i
dqolis@holycross.com
>- XCEL Energy
970.262.4038 (fax)''��`
970.262.4024 (tel)
Contacts:
Kit Bogert
Kathryn Bogert(d )XCELENERGY.com
— EAGLE RIVER WATER &
SANITATION DISTRICT
970.476.7480 (tel)
970.476.4089 (fax) F
Contact: Fred Haslee
fhaslee erws
MCAST CABLE
970.418.8248 (tel)
970.949.9138 (fax)
Contact: Michael Johnson
michael _johnson@cable.comcast.com
NOTES:
1. If the utility approval & verification form has signatures from each of the utility companies, and no comments are made directly
on the form, or no action is taken within 2 weeks of the Utility's receipt of the form without explanation the Town will; presume
that there are no problems and the development can proceed.
2. If a utility company has concerns with the proposed construction, the utility representative shall note directly on the utility
verification form that there is a problem which needs to be resolved. The issue should then be detailed in an attached letter to the
Town of Vail. However, please keep in mind that it is the responsibility of the utility company and the applicant to resolve
identified problems.
3. These verifications do not relieve the contractor of the responsibility to obtain a Public Way Permit from the Depalrtment of
Public Works at the Town of Vail. Utility locations must be obtained before digging in any public right -of -way or 'easement
within the Town of Vail. A building permit is not a Public Way permit and must be obtained separately
4. The Developer is required and agrees to submit any revised drawings to the utilities for re- approval & re- verification if the
submitted plans are al ered in any way after the authorized signature date (unless otherwise specifically noted within the' °comment
area of this form).
Developer's Signature ` Date
TOWN OF Vk ; UTILITY APPROVAL & VERIFICATION
This form serves to verify that the proposed improvements will not impact any existing or proposed utility services, and also to
verify service availability and location for new construction and should be used in conjunction with preparing your utility plan and
scheduling installations. A site plan, Including grading plan, floor plan, and elevations, shall be submitted to the following utilities
for approval and verification. PLEASE ALLOW UP TO 2 WEEKS FOR APPROVAL OR COMMENTS FROM THE UTILITY
COMPANIES. If you are unable to obtain comments within that timeframe please contact The Town of Vail.
Address: to GONCt'Z DJhvi 2 01}x} Lot 5`1 Block Subdivision: U ft UiLwgr ,r. OLIN1 ,
Authortzed Signature Comments Date
QW EST
970,468.6860(tel)
970.468.0672(fax)
Contacts: Sam Tooley
sa muel.tooleyCdgwest.corm
XCEL HIGH PRESSURE GAS
970.262.4076 (tel)
970.468.1401 (fax)
Contact: Rich Sisneros
richa rd.sisnerosPxcelenergy.coLn.
HOLY CROSS ENERGY
970.947.5425 (tel)
970.945.4081 (fax)
Contact: Diana Golis
dgoiisftolycross.com
XCEL Energy
970.262.4038 (fax)
970.262.4024 (tel)
Contacts:
Kit Bogert
Kathryn.�B Bert( XCELENERGY.com
EAGLE RIVER WATER &
SANITATION DISTRICT
970.476.7480 (tel)
970.476.4069 (fax)
Contact: Fred Haslee
fhaslee00erwsd.ora
COMCAST CABLE
970.418.8248 (tel)
970.949.9138 (fax)
Contact: Michael Johnson
michael- „Johnson @cable.comcast.com
NOTES:
1. If the utility approval & verification form has signatures from each of the utility companies, and no comments are made directly
on the form, or no action is taken within 2 weeks of the Utility's receipt of the form without explanation the Town will presume
that there are no problems and the development can proceed.
2. If a utility company has concerns with the proposed construction, the utility representative shall note directly on the utility
verification form that there is a problem which needs to be resolved. The issue should then be detailed in an attached letter to the
Town of Vail. However, please keep in mind that It is the responsibility of the utility company and the applicant to resolve
identified problems.
3. These verifications do not relieve the contractor of the responsibility to obtain a Public Way Permit from the Department of
Public Works at the Town of Vail. Utility locatigns must be obtained before digging in any public right -of -way or easement
within the Town of Vail. ,A building permit is not a Public Way permit and must be obtained separately
4. The Developer Is required and agrees to submit any revised drawings to the utilities for re- approval & re- verification if the
submitted plans are al eyed in any way after the authorized signature date (unless otherwise specifically noted within the comment
area of this form). V _ ! ^ v G
Developer's Signature Date
TOWN OF *ViAl
UTILITY APPROVAL & VERIFICATION
This form serves to verify that the proposed improvements will not impact any existing or proposed utility services, and also to
verify service availability and location for new construction and should be used in conjunction with preparing your utility plan and
scheduling installations. A site plan, including grading plan, floor plan, and elevations, shall be submitted to the following utilities
for approval and verification. PLEASE ALLOW UP TO 2 WEEKS FOR APPROVAL OR COMMENTS FROM THE UTILITY
COMPANIES. If you are unable to obtain comments within that timeframe please contact The Town of Vail.
Address: 1 1907 VOt Mm 7 OV, Lot �` 1 Block — 7 Subdivision: U; UtLL 0,,,t:7 a l lNh
y GU le)i(1
Authorized Signature Comments Date
QWEST
970.468.6860(tel)
970.468.0672(fax)
Contacts: Sam Tooley
sa muel.toolev @awest. com
XCEL HIGH PRESSURE GAS
970.262.4076 (tel)
970.468.1401 (fax)
Contact: Rich Sisneros
ri cha rd. sisn eras @xcel e n ergy.co m
HOLY CROSS ENERGY
970.947.5425 (tel)
970.945.4081 (fax)
Contact: Diana Golis
dgolis@holycross. com
XCEL Energy
970.262.4038 (fax)
970.262.4024 (tel)
Contacts:
Kit Bogert
Ka thry BoaertCNXCELEN ERGY. com
EAGLE RIVER WATER &
SANITATION DISTRICT
970.476.7480 (tel)
970.476.4089 (fax)
Contact: Fred Haslee
fhaslee@erwsd.org
COMCAST CABLE
970.418.8248 (tel)
970.949.9138 (fax)
Contact: Michael Johnson
michael-johnson@cable.comcast.com
� a k c
rn:1
NOTES:
1. If the utility approval & verification form has signatures from each of the utility companies, and no comments are made directly
on the form, or no action is taken within 2 weeks of the Utility's receipt of the form without explanation the Town will presume
that there are no problems and the development can proceed.
2. If a utility company has concerns with the proposed construction, the utility representative shall note directly on the utility
verification form that there is a problem which needs to be resolved. The issue should then be detailed in an attached letter to the
Town of Vail. However, please keep in mind that it is the responsibility of the utility company and the applicant to resolve
identified problems.
3. These verifications do not relieve the contractor of the responsibility to obtain a Public Way Permit from the Department of
Public Works at the Town of Vail. Utility locations must be obtained before digging in any public right -of -way or easement
within the Town of Vail. A building permit is not a Public Way permit and must be obtained separately.
4. The Developer is required and agrees to submit any revised drawings to the utilities for re- approval & re- verification if the
submitted plans are� tere zany way after the authorized signature date (unless otherwise specifically noted within the comment
area of this form), \ I
Developer's Signature - Date
O$ /04/2008 M 16:02 FAX 9709254106 COMCAST GABLE
®001 /002
r t
d
T Of
}((, UTILITY APPROVAL & VERIFICATION
This form serves to verify that the proposed improvemcnts will not impact any existing or proposed utility services, and also to
verify service availability and location for new construction and should be used in conjunction with preparing your utility plan and
scheduling Installations. A site plan, including grading plan, floor plan, and elevations, shall be submitted to the following utilities
for approval and verification, PLEASE ALLOW UP TO 2 'WEEKS FOR APPROVAL OR COMMENTS FROM THE UTILITY
COMPANIES. If you are unable to obtain comments within that timeframe please contact The "town of Vail.
Address: E 47IVO� DJty, ROD Lot Block 7_ Subdivision: U� -U_i.Lwg6L ::' .-5LiWI f
\ 41bL, cd ` lb 1
Authorized Signature Comments DatO
QWEST
970.466.6860(tel)
970.468.0672(fax)
Contacts: Sam Tooley
sarnuei.toaley�west.com
XCEL HIGH PRESSURE GAS
970.262.4076 (tel)
970.468.1401 (fax)
Contact: Rich Sisnero5
' ricftard .sisnerasCbl��elencrg�.rom
HOLY CROSS ENERGY
970.947.5425 (tel)
970.945,4081 (fax)
Contact: Diana Golis
dg�Iis,�h�
XCEL Energy
470.262.4038 (fax)
970.262.409 (tel)
Contacts':
Kit Bogert
{ t n.Boc e XCEI.ENE
EAGLE RtVll:k WATER &
SANITATION DTSTRICT
{ 970.476.74$0 (W)
970_476.4U89 (fax)
' Contact: Fred Haslee
fljaslaeCaerwsd_org
COMCAS°T CABLE
970.41$.8248 (tcl)
970.949.9138 (fax)
Contact: Michael Johnson
mlchael_ johnson(*oble.comcast.oam
NOTES%
1. If the utility approval & verification form has signatures from each of the utility companies, and no comments are made directly
on the form, or no action Is taken within 2 weeks of the Utility's receipt of the form without explanation the Town will presume
that there are no problems and the development can proceed.
2. If a utility company has concerns with the proposed construction, the utility representative shall note directly on the utility
verification form that there Is a problem which needs to be resolved. The issue should then be detailed in an attached letter to the
Town of wail. However, please keep in mind that it is the responsibility of the utility company and the applicant to resolve
identified problems.
3. These verifications do not relieve the contractor of the responsibility to obtain a Public Way permit from the Department of
Public Works at the Town of Vail, utility locations must be_optained before digging in any public right-of -way or easement
within the Town of Vail. A building hermit is not a Public Way pormit and must be g tawk senaratel1
4. The Developer is required and agrees to submit any revised drawings to the utilities for re- approval & re- verification if the
submitted plans area eyed :n any way after the authorized signature date (unless otherwise specifi - ally noted within the comment
area of this form).
Developer's Signature - Pate
TOWN OF VAIL, COLORADO Statement
Statement Number: R080001452 Amount: $20.00 08/21/200803:55 PM
Payment Method:Credit Crd Init: JLE
Notation: DANIELLE K
SELLERS
----------------------------------------------------------------------- - - - - --
Permit No: DRB080377 Type: DRB -Minor Alt,SFR /DUP
Parcel No: 2101 - 071 - 1300 -1
Site Address: 14 BEAVER DAM RD VAIL
Location:
Total Fees: $20.00
This Payment: $20.00 Total ALL Pmts: $20.00
Balance: $0.00
ACCOUNT ITEM LIST:
Account Code Description Current Pmts
-------------- - - - - -- ------------------------ - - - - -- ------ - - - - --
DR 00100003112200 DESIGN REVIEW FEES 20.00